Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Sewer Service Inspection
|
Passed
|
4/21/2022 (8:00)
|
4/21/2022
|
04/21/2022
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/18/2022
|
8/18/2022
|
08/18/2022
|
|
THIRD FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
8/19/2022
|
08/19/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
8/22/2022
|
8/22/2022
|
08/22/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
8/26/2022
|
8/26/2022
|
08/26/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
9/2/2022
|
9/2/2022
|
09/02/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Above Ceiling Inspection
|
Failed
|
9/13/2022
|
9/13/2022
|
09/13/2022
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/14/2022
|
9/14/2022
|
09/14/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/16/2022
|
9/16/2022
|
09/16/2022
|
|
FIRST FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
9/16/2022
|
9/16/2022
|
09/16/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/19/2022
|
9/19/2022
|
09/19/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
9/19/2022
|
9/19/2022
|
09/19/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/20/2022
|
9/20/2022
|
09/20/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
9/20/2022
|
9/20/2022
|
09/20/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/28/2022
|
9/28/2022
|
09/28/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
9/30/2022
|
9/30/2022
|
09/30/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/30/2022
|
9/30/2022
|
09/30/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
10/3/2022
|
10/3/2022
|
10/03/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/3/2022
|
10/3/2022
|
10/03/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/4/2022
|
10/4/2022
|
10/04/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/5/2022
|
10/5/2022
|
10/05/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/6/2022
|
10/6/2022
|
10/06/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/10/2022
|
10/10/2022
|
10/10/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/11/2022
|
10/11/2022
|
10/11/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
10/11/2022
|
10/11/2022
|
10/11/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/13/2022
|
10/13/2022
|
10/13/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/17/2022
|
10/17/2022
|
10/17/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/19/2022
|
10/19/2022
|
10/19/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
10/19/2022
|
10/19/2022
|
10/19/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/24/2022
|
10/24/2022
|
10/24/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
|
10/24/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/25/2022
|
10/25/2022
|
10/25/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
|
10/26/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/26/2022
|
10/26/2022
|
10/26/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
10/28/2022
|
10/28/2022
|
10/28/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/1/2022
|
11/1/2022
|
11/01/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
11/1/2022
|
11/1/2022
|
11/01/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
11/2/2022
|
11/2/2022
|
11/02/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
11/3/2022
|
11/3/2022
|
11/03/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
|
11/4/2022
|
11/04/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
11/4/2022
|
11/04/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
11/7/2022
|
11/7/2022
|
11/07/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
|
11/08/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
11/8/2022
|
11/8/2022
|
11/08/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/10/2022
|
11/10/2022
|
11/10/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
|
11/10/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Electrical Service Inspection
|
Failed
|
11/16/2022
|
11/16/2022
|
11/16/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
11/16/2022
|
11/16/2022
|
11/16/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/17/2022
|
11/17/2022
|
11/17/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/18/2022
|
11/18/2022
|
11/18/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/29/2022
|
11/29/2022
|
11/29/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Electrical Service Inspection
|
Partial
|
11/29/2022
|
11/29/2022
|
11/29/2022
|
|
Miscellaneous Correction
|
Above Ceiling Inspection
|
Passed
|
11/30/2022
|
11/30/2022
|
11/30/2022
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
11/30/2022
|
11/30/2022
|
11/30/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/30/2022
|
11/30/2022
|
11/30/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/1/2022
|
12/1/2022
|
12/01/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
12/2/2022
|
12/2/2022
|
12/02/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
12/5/2022
|
12/5/2022
|
12/05/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
12/6/2022
|
12/6/2022
|
12/06/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/8/2022
|
12/8/2022
|
12/08/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/9/2022
|
12/9/2022
|
12/09/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
Electrical Service Inspection
|
Failed
|
12/14/2022
|
12/14/2022
|
12/14/2022
|
|
Miscellaneous Correction
|
Rated Assembly Inspection
|
Partial
|
|
|
12/14/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
12/15/2022
|
12/15/2022
|
12/15/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/15/2022
|
12/15/2022
|
12/15/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
12/21/2022
|
12/21/2022
|
12/21/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
12/28/2022
|
12/28/2022
|
12/28/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
|
12/30/2022
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Piers/Caissons Inspection - Commercial
|
Failed
|
12/30/2022
|
12/30/2022
|
12/30/2022
|
Rated Assembly Inspection
|
Partial
|
1/4/2023
|
1/4/2023
|
01/04/2023
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
1/17/2023
|
1/17/2023
|
01/17/2023
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
Corrective Action Required
|
|
STAIR TOWER 2
Corrective Action Required
|
|
STAIR TOWER 3
Corrective Action Required
|
|
STAIR TOWER 4
Corrective Action Required
|
Electrical Service Inspection
|
Partial
|
1/17/2023
|
1/17/2023
|
01/17/2023
|
|
Miscellaneous Correction
|
Electrical Service Inspection
|
Passed
|
2/3/2023
|
2/3/2023
|
02/03/2023
|
|
Miscellaneous Correction
|
All Rough Inspection - Commercial
|
Passed
|
|
|
03/02/2023
|
|
THIRD FLOOR
|
|
SECOND FLOOR
|
|
FIRST FLOOR
|
|
ELEVATOR 1
Corrective Action Required
|
|
STAIR TOWER 1
|
|
STAIR TOWER 2
|
|
STAIR TOWER 3
|
|
STAIR TOWER 4
|
Rated Assembly Inspection
|
Passed
|
|
|
03/02/2023
|
|
THIRD FLOOR
|
|
SECOND FLOOR
|
|
FIRST FLOOR
|
|
STAIR TOWER 1
|
Miscellaneous Inspection
|
Failed
|
3/2/2023
|
3/2/2023
|
03/02/2023
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Partial
|
3/3/2023
|
3/3/2023
|
03/03/2023
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Partial
|
3/6/2023
|
3/6/2023
|
03/06/2023
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Partial
|
3/7/2023
|
3/7/2023
|
03/07/2023
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Failed
|
3/9/2023
|
3/9/2023
|
03/09/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
Miscellaneous Inspection
|
Partial
|
|
3/10/2023
|
03/10/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Failed
|
3/14/2023
|
3/14/2023
|
03/14/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Miscellaneous Inspection
|
Failed
|
|
3/14/2023
|
03/14/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Miscellaneous Inspection
|
Failed
|
3/16/2023
|
3/16/2023
|
03/16/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Miscellaneous Inspection
|
Failed
|
|
3/16/2023
|
03/16/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Miscellaneous Inspection
|
Passed
|
3/20/2023
|
3/20/2023
|
03/20/2023
|
|
Misc
Corrective Action Required
|
|
THIRD FLOOR
Corrective Action Required
|
|
SECOND FLOOR
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
Miscellaneous Inspection
|
Partial
|
3/21/2023
|
3/21/2023
|
03/21/2023
|
|
Misc
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
3/21/2023
|
03/21/2023
|
Miscellaneous Inspection
|
Passed
|
3/22/2023
|
3/22/2023
|
03/22/2023
|
|
Misc
|
Sprinkler - Flow Test
|
Passed
|
|
3/22/2023
|
03/22/2023
|
Alarm Test
|
Passed
|
|
3/22/2023
|
03/22/2023
|
Occupancy Inspection - Planning
|
Temporary C of O
|
3/24/2023
|
3/24/2023
|
03/24/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Passed
|
|
|
03/24/2023
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
|
|
03/24/2023
|
Occupancy Inspection - Codes Commercial
|
Failed
|
3/24/2023
|
3/24/2023
|
03/24/2023
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
|
3/24/2023
|
03/24/2023
|
|
Misc
|
Occupancy Inspection - Fire
|
Failed
|
|
3/24/2023
|
03/26/2023
|
Alarm Test
|
Passed
|
|
3/22/2023
|
03/27/2023
|
Occupancy Inspection - Water Utilities
|
Passed
|
|
3/28/2023
|
03/28/2023
|
Occupancy Inspection - Codes Commercial
|
Ready for Temp CO
|
3/28/2023
|
3/28/2023
|
03/28/2023
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Ready for Temp CO
|
|
4/27/2023
|
04/27/2023
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Partial
|
4/27/2023
|
4/27/2023
|
04/27/2023
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Fire
|
Passed
|
5/5/2023
|
3/28/2023
|
05/05/2023
|
Occupancy Inspection - Codes Commercial
|
Failed
|
5/5/2023
|
5/5/2023
|
05/05/2023
|
|
Misc
Corrective Action Required
|
Miscellaneous Inspection
|
Passed
|
|
|
05/08/2023
|
Occupancy Inspection - Engineering
|
Passed
|
5/5/2023
|
5/5/2023
|
05/08/2023
|
|
Misc
|
|
Misc
|
Occupancy Inspection - Planning
|
Passed
|
5/5/2023
|
5/5/2023
|
05/08/2023
|
|
Misc
|
Occupancy Inspection - Fire
|
Passed
|
5/8/2023
|
5/8/2023
|
05/08/2023
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
5/8/2023
|
5/8/2023
|
05/08/2023
|
|
Misc
|