Permit Application Status

PRCOM20201668


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20201668
Building Permit - Commercial
Certificate of Occupancy
C82 MESA LLC
ALTERATION COMMERCIAL
ALTERATION OF EXISTING BUILDING TO PROVIDE 2 EMPTY SHELLS FOR FUTURE COFFEE SHOP AND MEDICAL OFFICES
06/19/2020
08/18/2020
02/17/2021
06/13/2023
Locations
Contacts
Midland General Contractors, Inc., Address:716 Windsor Road  
DONALDSON MECHANICAL INC, Address:934 SE 7TH TER, Unit B, Phone:(816) 246-9500  
RC ELECTRIC LLC, Address:10811 S WILDFLOWER DR, Phone:(816) 554-9135  
Mac Wilson LLC, Address:9100 STATE ROUTE A, Phone:(816) 768-0700  
CASCO CORP, Address:12 Sunnen Dr, Suite 100, Phone:(314) 821-1100  
C82 MESA LLC, Address:7015 SNIDER PLZ STE 203  
brent@midlandgeneralcontractors.com, Address:brent@midlandgeneralcontractors.com  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved 08/28/2020 08/26/2020
Joe Frogge
Fire Plan Review Approved with Conditions 08/28/2020 08/21/2020
Michael Weissenbach
Address numbers required
Corrective Action Required
08/21/2020

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Licensed Contractors Approved 08/21/2020 08/21/2020
Joe Frogge
Building Plan Review Approved 07/13/2020 08/18/2020
Joe Frogge
Final Development Plan
Resolved
07/20/2020

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 7/10/20 - not addressed
Miscellaneous Correction
Resolved
08/18/2020

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes. 7/10/20 - not addressed
Miscellaneous Correction
Resolved
07/10/2020

Inadequate information to complete review. Provide light pole base detail for relocated light poles.
Misc
Resolved
07/10/2020

Water meter appears to be oversized. Action required: Provide calculations to justify use of 2” water meter. If intended for irrigation, provide irrigation system design including location and method of backflow protection. 7/10/20 - not addressed
Licensed Contractors Approved 07/13/2020 08/17/2020
Joe Frogge
LC - MEP Subs
Resolved
08/17/2020

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 7/10/20 - not addressed
LC - General Contractor
Resolved
07/10/2020

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
Fire Plan Review Approved with Conditions 07/13/2020 07/07/2020
Michael Weissenbach
Address numbers required
Corrective Action Required
07/06/2020

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Building Plan Review Rejected 07/01/2020 06/26/2020
Joe Frogge
Final Development Plan
Corrective Action Required
07/20/2020

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Miscellaneous Correction
Corrective Action Required
06/23/2020

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
Miscellaneous Correction
Corrective Action Required
06/23/2020

Inadequate information to complete review. Provide light pole base detail for relocated light poles.
Misc
Corrective Action Required
06/23/2020

Water meter appears to be oversized. Action required: Provide calculations to justify use of 2” water meter. If intended for irrigation, provide irrigation system design including location and method of backflow protection.
Licensed Contractors Rejected 07/01/2020 06/23/2020
Joe Frogge
LC - MEP Subs
Corrective Action Required
06/23/2020

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
LC - General Contractor
Corrective Action Required
06/23/2020

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor.
Fire Plan Review Approved with Conditions 07/01/2020 06/23/2020
Michael Weissenbach
Address numbers required
Corrective Action Required
06/23/2020

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Alteration to Commercial $1,600.00 $1,600.00 Paid 08/04/2020
8331401-Water Tap Fee $11,937.00 $11,937.00 Paid 08/04/2020
8350015-Water Meter Fee $2,740.85 $2,740.85 Paid 08/04/2020
9110071-Site Grading Fee $360.00 $360.00 Paid 08/04/2020
9110081-Paved Surface Inspection Fee $1,950.00 $1,950.00 Paid 08/04/2020
91100C9-Water Insp Fee $150.00 $150.00 Paid 08/04/2020
9110068-Storm Fee $45.00 $45.00 Paid 08/04/2020
91100C8-Sanitary Sewer Insp Fees $150.00 $150.00 Paid 08/04/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Partial 9/18/2020 (8:00) 9/18/2020 09/18/2020
Miscellaneous Correction
Corrective Action Required
09/18/2020
-FOOTINGS FOR NEW BUILDING LINE ON EAST SIDE OF BUILDING AND DRIVE-THROUGH BUMP OUT ON SOUTH SIDE OF BUILDING
Foundation Inspection - Commercial Partial 9/23/2020 9/23/2020 09/23/2020
Misc
Informational
09/23/2020
-INSPECTED FOUNDATION FOR NEW BUILDING LINE ON EAST SIDE OF BUILDING AND DRIVE-THROUGH BUMP OUT ON SOUTH SIDE OF BUILDING
Underslab Electrical Inspection - Commercial Partial 10/6/2020 10/6/2020 10/06/2020
Misc
Informational
10/06/2020
- INSPECTED PARTIAL UNDERSLAB ELECTRICAL FROM TENTANT STARBUCKS SIDE AT SERVICE PANEL TO FUTURE TENANT SPACE STOPPING RIGHT BEHIND METERS ON EXTERIOR SIDE OF BUILD -
Underground Plumbing Inspection - Commercial Partial 10/6/2020 10/6/2020 10/06/2020
Misc
Informational
10/06/2020
- INSPECTED PARTIAL SEWER LINE FROM GREASE INTERCEPTOR EXIT ACROSS PARKING LOT TO SEWER END CONNECTION. WILL NEED REMAINDER INSPECTED INCLUDES - GREASE INTERCEPTOR, SEWER FROM BUILDING TO INTERCEPTOR, AND VENT PER PLANS
Rated Assembly Inspection Failed 10/6/2020 10/6/2020 10/06/2020
Misc
Corrective Action Required
10/06/2020
- REMOVE 2ND LAYER OF ROCK TO ALLOW FOR INSPECTION OF 1ST LAYER ROCK EAST SIDE. SCREW PATTERN PER UL LISTING SHOWN IN PLANS
Footing Inspection - Commercial Failed 10/6/2020 10/6/2020 10/06/2020
Miscellaneous Correction
Informational
10/06/2020
-FOOTINGS FOR NEW BUILDING LINE ON EAST SIDE OF BUILDING AND DRIVE-THROUGH BUMP OUT ON SOUTH SIDE OF BUILDING
Misc
Corrective Action Required
10/06/2020
- TRASH ENCLOSURE FOOTING POURED WITHOUT INSPECTION. SUBMIT ENGINEER REPORT CONCERNING FOOTING
Rated Assembly Inspection Partial 10/7/2020 10/7/2020 10/07/2020
Misc
Informational
10/07/2020
INSPECTED FIRST LAYER AT DEMISING WALL, PARTIAL INSPECTION, 1ST LAYER REQUIRED FOR LAST SHEET AT N WALL FRONT AND WILL NEED TO BE INSPECTED BEFORE COVER WITH 2ND LAYER, OK TO COVER REST WITH 2ND LAYER
Foundation Inspection - Commercial Failed 10/7/2020 10/7/2020 10/07/2020
Misc
Informational
09/23/2020
-INSPECTED FOUNDATION FOR NEW BUILDING LINE ON EAST SIDE OF BUILDING AND DRIVE-THROUGH BUMP OUT ON SOUTH SIDE OF BUILDING
Misc
Corrective Action Required
10/07/2020
SUBMIT ENGINEER REPORT ON FRONT N WALL FOUNDATION, REBAR SHOWING
Rated Assembly Inspection Partial 10/8/2020 10/8/2020 10/07/2020
Misc
Resolved
10/07/2020
INSPECTED FIRST LAYER AT DEMISING WALL, PARTIAL INSPECTION, 1ST LAYER REQUIRED FOR LAST SHEET AT N WALL FRONT AND WILL NEED TO BE INSPECTED BEFORE COVER WITH 2ND LAYER, OK TO COVER REST WITH 2ND LAYER
Miscellaneous Correction
Corrective Action Required
10/07/2020
-FIRST LAYER DEMISING WALL ROCK AND SCREW PATTERN COMPLETE
Piers/Caissons Inspection - Commercial Failed 10/7/2020 10/07/2020
Miscellaneous Correction
Corrective Action Required
10/07/2020
-POURED BEFORE INSPECTION- -TEAR OUT AND RECALL WHEN READY FOR INSPECTION
Piers/Caissons Inspection - Commercial Failed 10/8/2020 (3:00) 10/8/2020 10/08/2020
Miscellaneous Correction
Corrective Action Required
10/07/2020
- REBAR PER PLANS - SUSPEND REBAR FOR DIRT
Piers/Caissons Inspection - Commercial Partial 10/9/2020 10/09/2020
Miscellaneous Correction
Informational
10/09/2020
INSPECTED (4) LIGHT POLE BASES, (2) AT BACK OF BUILDING AT EAST AND WEST SIDE OF LOT AND (2) AT FRONT WEST AND SIDE FRONT LOT, REBAR PER PLANS, GROUNDING RODS INSPECTED
Underground Plumbing Inspection - Commercial Partial 10/9/2020 10/9/2020 10/09/2020
Misc
Informational
10/06/2020
- INSPECTED PARTIAL SEWER LINE FROM GREASE INTERCEPTOR EXIT ACROSS PARKING LOT TO SEWER END CONNECTION. -10/9- INSPECTED GREASE INTERCEPTOR, SEWER LINE AND VENT FROM GREASE INTERCEPTOR STOPPING AT ENTRANCE TO BUILDING. OK TO COVER PORTION INSPECTED
Underslab Electrical Inspection - Commercial Partial 10/9/2020 10/9/2020 10/09/2020
Misc
Informational
10/06/2020
- INSPECTED PARTIAL UNDERSLAB ELECTRICAL FROM TENTANT STARBUCKS SIDE AT SERVICE PANEL TO FUTURE TENANT SPACE STOPPING RIGHT BEHIND METERS ON EXTERIOR SIDE OF BUILD - -10/9-INSPECTED REMAINDER CONDUIT THAT STOPPED BEHIND METER ON INTERIOR EXITING FROM BUILDING
Underground Electrical Inspection - Commercial Partial 10/9/2020 10/9/2020 10/09/2020
Misc
Informational
10/09/2020
-INSPECTED PARTIAL UNDERGROUND CONDUIT ALONG BACK OF BUILDING THROUGH BACK PARKING LOT ON E SIDE BETWEEN TRANSFORMER AND LIGHT POLE
Underground Electrical Inspection - Commercial Partial 10/12/2020 10/12/2020 10/12/2020
Misc
Informational
10/09/2020
-INSPECTED PARTIAL UNDERGROUND CONDUIT ALONG BACK OF BUILDING THROUGH BACK PARKING LOT ON E SIDE BETWEEN TRANSFORMER AND LIGHT POLE - 10/12- INSPECTED CONDUIT BEHIND BUILDING RAN BETWEEN W AND E LIGHT POLES AND CONDUIT RAN AT FRONT OF BUILDING E SIDE LIGHT POLE ALONG FRONT OF LOT TO MONUMENT SIGN - OK TO COVER PORTION INSPECTED
Footing Inspection - Commercial Passed 10/30/2020 (2:45) 10/30/2020 10/12/2020
Miscellaneous Correction
Resolved
10/12/2020
Misc
Resolved
10/12/2020
Electrical Service Inspection Failed 10/13/2020 10/13/2020 10/13/2020
Corrective Action Required
10/13/2020
- TYPE OF CLAMP USED ON STEEL BEAM BOND, RATED FOR USE -SAND PAINT OFF BEAM AT BONDING CLAMP -BRING WATER BOND UP FROM BELOW GRADE -COMPLETE METER/DISCONNECT INSTALL -SUBMIT CURRENT LINE DRAWING, NOT CURRENTLY AS SHOWN IN PLANS
Underground Electrical Inspection - Commercial Partial 10/13/2020 10/13/2020
Misc
Informational
10/12/2020
-INSPECTED PARTIAL UNDERGROUND CONDUIT ALONG BACK OF BUILDING THROUGH BACK PARKING LOT ON E SIDE BETWEEN TRANSFORMER AND LIGHT POLE - 10/12- INSPECTED CONDUIT BEHIND BUILDING RAN BETWEEN W AND E LIGHT POLES AND CONDUIT RAN AT FRONT OF BUILDING E SIDE LIGHT POLE ALONG FRONT OF LOT TO MONUMENT SIGN - OK TO COVER PORTION INSPECTED -10/13 - INSPECTED CONDUIT FROM MONUMENT SIGN TO EXISTING LIGHT POLE ON WEST SIDE AT FRONT OF PARKING LOT. OK TO COVER PORTION INSPECTED
Rated Assembly Inspection Partial 10/15/2020 10/15/2020 10/15/2020
Miscellaneous Correction
Corrective Action Required
10/07/2020
-FIRST LAYER DEMISING WALL ROCK AND SCREW PATTERN COMPLETE, E SIDE -10/15 — INSPECTED 2ND LAYER ROCK AND SCREW PATTERN ON E SIDE OF DEMISING WALL
Underslab Electrical Inspection - Commercial Failed 10/16/2020 10/16/2020 10/16/2020
Misc
Resolved
10/16/2020
- INSPECTED PARTIAL UNDERSLAB ELECTRICAL FROM TENTANT STARBUCKS SIDE AT SERVICE PANEL TO FUTURE TENANT SPACE STOPPING RIGHT BEHIND METERS ON EXTERIOR SIDE OF BUILD - -10/9-INSPECTED REMAINDER CONDUIT THAT STOPPED BEHIND METER ON INTERIOR EXITING FROM BUILDING
Misc
Corrective Action Required
10/16/2020
- JUNCTION BOX WITH SPLICE BELOW SERVICE PANEL ON E SIDE OF BUILDING. CANNOT HAVE SPLICE BELOW CONCRETE, BOX NOT RATED FOR BURIAL
Misc
Corrective Action Required
10/16/2020
- JUNCTION BOX WITH SPLICE BELOW SERVICE PANEL ON E SIDE OF BUILDING. CANNOT HAVE SPLICE BELOW CONCRETE, BOX NOT RATED FOR BURIAL
Misc
Resolved
10/16/2020
Electrical Service Inspection Failed 10/16/2020 10/16/2020 10/16/2020
Misc
Corrective Action Required
10/16/2020
- 1000 AMP DISCONNECT NOT INSTALLED AS PER PLANS, RESUBMIT REVISED PLAN WITH CHANGES BEFORE SCHEDULING REINSPECTION -TIGHTEN ALL LUGS, CONNECTIONS, BUSHINGS, AND JAMB NUTS IN METERS AND DISCONNECTS -EMT NOT RATED FOR OUTDOOR USE -CORRECT BONDING BUSHING -COLOR CODE NEUTRAL
Pavement-Proof Roll Passed 10/19/2020
Misc
Informational
10/19/2020
On Monday 10-19-2020. I performed a proof roll inspection on the sub-grade for geo-grid placement. Proof roll passed inspection.
In-wall Inspection Failed 10/19/2020 10/19/2020 10/19/2020
Misc
Corrective Action Required
10/19/2020
- INSPECTED E WALL, COMPLETE ALL MC RUNS, SECURE MC PER CODE
In-wall Inspection Partial 10/20/2020 10/20/2020
Misc
Corrective Action Required
10/19/2020
- INSPECTED IN WALL MC ON E, S, AND N WALLS ON E SIDE OF BUILDING. OK TO COVER PORTION INSPECTED
Gas Service Inspection - Commercial Passed 10/21/2020 10/21/2020 10/21/2020
Electrical Service Inspection Failed 10/21/2020 10/21/2020 10/21/2020
Misc
Corrective Action Required
10/16/2020
-EMT NOT RATED FOR OUTDOOR USE - COUPLER COMPRESSION FITTINGS AND RIGID EMT
Electrical Service Inspection Passed 10/22/2020 10/22/2020 10/22/2020
Misc
Resolved
10/22/2020
Site Visit Complete 10/30/2020
Misc
Informational
10/30/2020
On Friday, 10-30-2020. R&R Concrete poured (1) 8” commercial driveway and poured sidewalk pieces to finish all flat work on project. All concrete has been completed and passes inspection.
Misc
Informational
11/03/2020
On Tuesday, 11-03-2020. The contractor installed paint stripping for parking lot.
Footing Inspection - Commercial Partial 10/30/2020 10/30/2020 10/30/2020
Misc
Informational
10/30/2020
INSPECTED (6) FOOTINGS FOR EXIT SIGNS, ROOF CLEARANCE SIGNS, DRIVE THRU MENU SIGN, DO NOT ENTER SIGN, AND EXIT SIGNS
In-wall Inspection Failed 11/4/2020 11/4/2020 11/04/2020
Misc
Informational
11/04/2020
- INSPECTED IN WALL MC ON E, S, AND N WALLS ON E SIDE OF BUILDING. OK TO COVER PORTION INSPECTED
Misc
Corrective Action Required
11/04/2020
- 11/4 - INSPECTED LOWER IN WALL MC ON N WALL REMAINING, E SIDE TENANT, SECURE MC WITHIN 10” OF PENETRATION, ADD BOX TO LIGHT FIXTURE AND PUT MC IN BOX
In-wall Inspection Passed 11/6/2020 11/6/2020 11/06/2020
Misc
Resolved
11/06/2020
- INSPECTED IN WALL MC ON E, S, AND N WALLS ON E SIDE OF BUILDING. OK TO COVER PORTION INSPECTED
Misc
Resolved
11/06/2020
- 11/4 - INSPECTED LOWER IN WALL MC ON N WALL REMAINING, E SIDE TENANT, SECURE MC WITHIN 10” OF PENETRATION, ADD BOX TO LIGHT FIXTURE AND PUT MC IN BOX
Site Visit Complete 12/02/2020
Misc
Informational
10/30/2020
On Thursday, 10-29-2020. R&R Concrete formed and compacted and poured front entrance to building also poured reinforced concrete sidewalk next to commercial driveway across from MacDonalds. Contractor also saw cut pavement poured the day before.
Commercial Curb Inspection Passed 12/02/2020
Misc
Informational
10/23/2020
On Friday, 10-23-2020. R&R Concrete is pouring CG-1 curbing up along the interior of the building. All forms and sub-grade met spec’s to pour concrete. Contractor is told they needed to get and use thermal blankets. Anticipated temp. For the low is 30 degrees.
Pavement-Surface Passed 12/02/2020
Misc
Informational
12/02/2020
On Monday 11-02-2020. Asphaltic Surfaces Layed asphalt base coarse early morning, Then completed Surface in afternoon.
Occupancy Inspection - Fire Passed 12/2/2020 12/2/2020 12/02/2020
Commercial Curb Inspection Passed 12/02/2020
Water Service Inspection Passed 10/19/2020 (3:30) 10/19/2020 12/02/2020
Occupancy Inspection - Engineering Temporary C of O 12/2/2020 12/02/2020
Misc
Corrective Action Required
12/02/2020
1. Establish vegetation on the south side of the building where the water meter was installed. 2. Clean up all trash and debris.
Occupancy Inspection - Codes Commercial Failed 12/2/2020 12/2/2020 12/02/2020
Misc
Corrective Action Required
12/02/2020
-LABEL MAIN DISCONNECT -LABEL GAS METERS -INSTALL CORRECT PANEL COVERS ON PANELS IN ROOF ACCESS ROOM. - INSTALL CORRECT CONDUIT IN ROOF ACCESS ROOM. -INSTALL HANDI-CAP SIGNAGE FRONT PARKING LOT. -COMPLETE PARKING LOT LIGHT POLES, INSPECT ELECTRICAL AT RE-INSPECTION. - SOD, FINAL GRADE, CUT SEWER CLEANOUT ON WEST SIDE OF LOT TO FLUSH WITH GRADE. -- AS PER A101 UL DESIGN U419 2 LAYERS IS REQUIRED ON BOTH SIDES OF WALL TO CLOSE THIS PERMIT. INCLUDING THE LABELING OF THE WALL.
Occupancy Inspection - Planning Failed 12/2/2020 12/02/2020
Corrective Action Required
12/02/2020
The wall mounted lighting above the rear doors does not meet the minimum UDO standards. Sec. 8.260.B requires all wall-mounted lights to utilize full cut-off fixtures.
Corrective Action Required
12/02/2020
The required ADA parking signage was not installed at the time of inspection.
Sewer Service Inspection Passed 10/9/2020 (4:00) 12/02/2020
Gas Piping Inspection - Commercial Passed 12/3/2020 12/03/2020
Foundation Inspection - Commercial Passed 12/3/2020 12/03/2020
Misc
Resolved
12/03/2020
-INSPECTED FOUNDATION FOR NEW BUILDING LINE ON EAST SIDE OF BUILDING AND DRIVE-THROUGH BUMP OUT ON SOUTH SIDE OF BUILDING
Misc
Resolved
12/03/2020
SUBMIT ENGINEER REPORT ON FRONT N WALL FOUNDATION, REBAR SHOWING
Piers/Caissons Inspection - Commercial Passed 12/3/2020 12/03/2020
Miscellaneous Correction
Resolved
12/03/2020
INSPECTED (4) LIGHT POLE BASES, (2) AT BACK OF BUILDING AT EAST AND WEST SIDE OF LOT AND (2) AT FRONT WEST AND SIDE FRONT LOT, REBAR PER PLANS, GROUNDING RODS INSPECTED
Underground Plumbing Inspection - Commercial Passed 10/12/2020 12/3/2020 12/03/2020
Misc
Resolved
12/03/2020
- INSPECTED PARTIAL SEWER LINE FROM GREASE INTERCEPTOR EXIT ACROSS PARKING LOT TO SEWER END CONNECTION. -10/9- INSPECTED GREASE INTERCEPTOR, SEWER LINE AND VENT FROM GREASE INTERCEPTOR STOPPING AT ENTRANCE TO BUILDING. OK TO COVER PORTION INSPECTED
Underground Electrical Inspection - Commercial Passed 12/3/2020 12/03/2020
Misc
Resolved
12/03/2020
-INSPECTED PARTIAL UNDERGROUND CONDUIT ALONG BACK OF BUILDING THROUGH BACK PARKING LOT ON E SIDE BETWEEN TRANSFORMER AND LIGHT POLE - 10/12- INSPECTED CONDUIT BEHIND BUILDING RAN BETWEEN W AND E LIGHT POLES AND CONDUIT RAN AT FRONT OF BUILDING E SIDE LIGHT POLE ALONG FRONT OF LOT TO MONUMENT SIGN - OK TO COVER PORTION INSPECTED -10/13 - INSPECTED CONDUIT FROM MONUMENT SIGN TO EXISTING LIGHT POLE ON WEST SIDE AT FRONT OF PARKING LOT. OK TO COVER PORTION INSPECTED
Underslab Electrical Inspection - Commercial Passed 12/3/2020 12/03/2020
Misc
Resolved
12/03/2020
- JUNCTION BOX WITH SPLICE BELOW SERVICE PANEL ON E SIDE OF BUILDING. CANNOT HAVE SPLICE BELOW CONCRETE, BOX NOT RATED FOR BURIAL
Misc
Resolved
12/03/2020
- JUNCTION BOX WITH SPLICE BELOW SERVICE PANEL ON E SIDE OF BUILDING. CANNOT HAVE SPLICE BELOW CONCRETE, BOX NOT RATED FOR BURIAL
Rough Electrical Inspection - Commercial Passed 10/19/2020 12/3/2020 12/03/2020
Footing Inspection - Commercial Passed 12/3/2020 12/03/2020
Misc
Resolved
12/03/2020
INSPECTED (6) FOOTINGS FOR EXIT SIGNS, ROOF CLEARANCE SIGNS, DRIVE THRU MENU SIGN, DO NOT ENTER SIGN, AND EXIT SIGNS
Occupancy Inspection - Codes Commercial Failed 12/4/2020 12/4/2020 12/04/2020
Misc
Corrective Action Required
12/02/2020
- INSTALL CORRECT PANEL COVERS ON PANELS IN ROOF ACCESS ROOM. - INSTALL CORRECT CONDUIT IN ROOF ACCESS ROOM. -COMPLETE PARKING LOT LIGHT POLES, INSPECT ELECTRICAL AT RE-INSPECTION. - SOD, FINAL GRADE -- AS PER A101 UL DESIGN U419 2 LAYERS IS REQUIRED ON BOTH SIDES OF WALL TO CLOSE THIS PERMIT. INCLUDING THE LABELING OF THE WALL.
Occupancy Inspection - Codes Commercial Failed 12/21/2020 12/21/2020 12/21/2020
Misc
Corrective Action Required
12/04/2020
- SOD, FINAL GRADE -- AS PER A101 UL DESIGN U419 2 LAYERS IS REQUIRED ON BOTH SIDES OF WALL TO CLOSE THIS PERMIT. INCLUDING THE LABELING OF THE WALL.
Occupancy Inspection - Engineering Temporary C of O 1/13/2021 01/12/2021
Misc
Corrective Action Required
12/02/2020
1. Establish vegetation on the south side of the building where the water meter was installed. 2. Clean up all trash and debris. 3. Backfill is needed at the light pole and curb at the northwest side of the project.
Occupancy Inspection - Planning Temporary C of O 1/13/2021 01/12/2021
Corrective Action Required
01/12/2021
The wall mounted lighting above the rear doors does not meet the minimum UDO standards. Sec. 8.260.B requires all wall-mounted lights to utilize full cut-off fixtures.
Occupancy Inspection - Codes Commercial Temporary C of O 1/13/2021 01/13/2021
Misc
Corrective Action Required
12/21/2020
- SOD, FINAL GRADE - COMPLETE OUTSTANDING ITEMS FOR PLANNING AND FIELD ENGINEERING
Miscellaneous Correction
Resolved
01/13/2021
-- AS PER A101 UL DESIGN U419 2 LAYERS IS REQUIRED ON BOTH SIDES OF WALL TO CLOSE THIS PERMIT. INCLUDING THE LABELING OF THE WALL. Mike Weisenborn 01/13/2021 2:28 PM --- the arechitect of record provided a letter indicating the west side of the wall will be completed on the future tenant infill.
Occupancy Inspection - Codes Commercial Failed 1/27/2021 1/27/2021 01/27/2021
Misc
Corrective Action Required
01/13/2021
- SOD, FINAL GRADE - REMOVE ELECTRIC GFCI RECEPTACLE AND WIRING THAT HAS BEEN INSTALLED IN WATER METER WELL -
Miscellaneous Correction
Corrective Action Required
01/13/2021
-- AS PER A101 UL DESIGN U419 2 LAYERS IS REQUIRED ON BOTH SIDES OF WALL TO CLOSE THIS PERMIT. INCLUDING THE LABELING OF THE WALL. Mike Weisenborn 01/13/2021 2:28 PM --- the arechitect of record provided a letter indicating the west side of the wall will be completed on the future tenant infill.
Rated Assembly Inspection Passed 08/24/2021
Miscellaneous Correction
Resolved
08/24/2021
-FIRST LAYER DEMISING WALL ROCK AND SCREW PATTERN COMPLETE, E SIDE -10/15 — INSPECTED 2ND LAYER ROCK AND SCREW PATTERN ON E SIDE OF DEMISING WALL
Occupancy Inspection - Planning Temporary C of O 08/24/2021
Corrective Action Required
08/24/2021
The wall mounted lighting above the rear doors and west wall do not meet the minimum UDO standards. Sec. 8.260.B requires all wall-mounted lights to utilize full cut-off fixtures.
Occupancy Inspection - Codes Commercial Failed 8/25/2021 8/25/2021 08/25/2021
Misc
Resolved
08/25/2021
Miscellaneous Correction
Corrective Action Required
08/25/2021
CODES ISSUES RESOLVED RESOLVE OUTSTANDING CORRECTIONS WITH PLANNING AND ENGINEERING
Occupancy Inspection - Codes Commercial Full C of O 06/13/2023
Misc
Resolved
06/13/2023
Documents & Images
Date Uploaded File Type Document Name
06/19/2020 Application Form CASCO application
06/19/2020 A001 Arch Site Plan
06/19/2020 old - A101 Floor Plan
06/19/2020 A301 Sections
06/19/2020 old - A201 Exterior Elevations
06/19/2020 A202 Exterior Elevations
06/19/2020 A501 Exterior Details
06/19/2020 A502 Misc Details
06/19/2020 A302 Wall Sections
06/19/2020 A504A Drive Thru Details
06/19/2020 A504B Drive Thru Details
06/19/2020 A505 Site Details
06/19/2020 A601 Window and Door Schedules
06/19/2020 C0_0 Cover
06/19/2020 C1_0 Demolition Plan
06/19/2020 C2_0 Site & Utility Plan
06/19/2020 C3_0 Grading Plan
06/19/2020 C4_0 Site Details
06/19/2020 C5_0 Erosion & Sediment Control Plan
06/19/2020 C5_1 Erosion & Seidment Control Details
06/19/2020 D101 Demo Plan
06/19/2020 old - E101 elec site plan
06/19/2020 E201 elec int plan
06/19/2020 E301 Elec Riser & Details
06/19/2020 E102 site photometrics
06/19/2020 E302 Elec Panel Schedule
06/19/2020 E401 Specifications
06/19/2020 G010 Specifications
06/19/2020 G011 Specifications
06/19/2020 G012 Specifications
06/19/2020 G013 Specifications
06/19/2020 A506 Site Details
06/19/2020 L100 Landscape Plan
06/19/2020 G100 Fire Rated Assemblies
06/19/2020 M101 Mechanical Plan And Specifications
06/19/2020 M201 Mechanical Schedules And Details
06/19/2020 P101 Plumbing Plan
06/19/2020 S001 General Notes
06/19/2020 S101 Foundation Plan
06/19/2020 old - S201 Roof Framing Plan
06/19/2020 S301 Foundation Details
06/19/2020 old - S401 Elevation and Roof Framing Details
06/19/2020 S402 Roof top Unit Support Plan and Details
06/19/2020 T100 Title Sheet
06/19/2020 A102 Roof Plan
06/23/2020 Letter Fire Building Plan Review
06/26/2020 Letter DS P/R Corrections Document
07/06/2020 Letter BuildingPermitPlanResponseLetter200706
07/06/2020 Letter Lee's Summit Business License
07/06/2020 Plans 488_A201 Exterior Elevations-A201
07/06/2020 Plans 488_A101 Floor Plan-A101
07/06/2020 Plans 488_E101 elec site plan-E101
07/06/2020 Plans 488_S401-S401
07/06/2020 Plans 488_S201-S201
07/07/2020 Letter Fire Building Plan Review
08/04/2020 Receipt Receipt for transaction: 2020-004967
08/17/2020 Approved Plans Starbucks Shell Plans
08/18/2020 Application Form City of Lee's Summit Excise Tax Form
08/18/2020 Letter DS Building Permit
08/21/2020 Drawing 488_A102 Roof Plan-A102
08/21/2020 Drawing 488_A101 Floor Plan-A101
08/21/2020 Drawing 488_A001 Arch Site Plan-A001
08/21/2020 Drawing 488_A504A-B Drive Thru Details-A504B
08/21/2020 Drawing 488_A201 Exterior Elevations-A201
08/21/2020 Drawing 488_A202 Exterior Elevations-A202
08/21/2020 Drawing 488_A601 Window and Door Schedules-A601
08/21/2020 Drawing 488_C1_0 Demolition
08/21/2020 Drawing 488_C3_0 Grading Plan
08/21/2020 Drawing 488_C2_0 Site & Utility Plan
08/21/2020 Drawing 488_C0_0 Cover
08/21/2020 Drawing 488_D101 Demo Plan-D101
08/21/2020 Drawing 488_C4_2 Site Details
08/21/2020 Drawing 488_E101 elec site plan-E101
08/21/2020 Drawing 488_C4_1 Site Details
08/21/2020 Drawing 488_E201 elec int plan-E201
08/21/2020 Drawing 488_E102 site photometrics-E102
08/21/2020 Drawing 488_M101-Mechanical Plan And Specifications
08/21/2020 Drawing 488_E301 Elec Riser & Details-E301
08/21/2020 Drawing 488_M201-Mechanical Schedules And Details
08/21/2020 Drawing 488_E302 Elec Panel Schedule-E302
08/21/2020 Drawing 488_P101-Plumbing Plan
08/21/2020 Drawing 488_S101-Foundation Plan
08/21/2020 Drawing 488_S201-Roof Framing Plan
08/21/2020 Drawing 488_T100-T1_0
08/21/2020 Letter BuildingPermitSummaryofChangesLtr-08202020
08/21/2020 Letter Fire Building Plan Review
08/26/2020 Approved Plans approved - starbucks revisions
08/27/2020 Letter Letter from Architect
09/01/2020 Approved Plans Aproved 155 SW M 150 Hwy
09/18/2020 Letter INSPECTION SUMMARY
09/23/2020 Letter INSPECTION SUMMARY
10/06/2020 Letter INSPECTION SUMMARY
10/06/2020 Letter INSPECTION SUMMARY
10/06/2020 Letter INSPECTION SUMMARY
10/06/2020 Letter INSPECTION SUMMARY
10/07/2020 Letter INSPECTION SUMMARY
10/07/2020 Letter INSPECTION SUMMARY
10/07/2020 Letter INSPECTION SUMMARY
10/07/2020 Letter INSPECTION SUMMARY
10/07/2020 Letter INSPECTION SUMMARY
10/08/2020 Letter INSPECTION SUMMARY
10/09/2020 Letter INSPECTION SUMMARY
10/09/2020 Letter INSPECTION SUMMARY
10/09/2020 Letter INSPECTION SUMMARY
10/09/2020 Letter INSPECTION SUMMARY
10/12/2020 Letter INSPECTION SUMMARY
10/12/2020 Letter INSPECTION SUMMARY
10/13/2020 Letter INSPECTION SUMMARY
10/13/2020 Letter INSPECTION SUMMARY
10/13/2020 Engineer Report/Study RFI 4 Response
10/15/2020 Letter INSPECTION SUMMARY
10/16/2020 Letter INSPECTION SUMMARY
10/16/2020 Letter INSPECTION SUMMARY
10/19/2020 Letter INSPECTION SUMMARY
10/19/2020 Drawing 488_M101-Mechanical Plan And Specifications
10/19/2020 Plot Plan Rev 8 - 10 16 2020
10/19/2020 Approved Plans Approved - M101 revision
10/19/2020 Letter Rev 9 - 10 19 2020
10/19/2020 Drawing 488E301
10/19/2020 Approved Plans approved - E301
10/20/2020 Letter INSPECTION SUMMARY
10/21/2020 Letter INSPECTION SUMMARY
10/21/2020 Letter INSPECTION SUMMARY
10/22/2020 Letter INSPECTION SUMMARY
10/30/2020 Letter INSPECTION SUMMARY
11/04/2020 Letter INSPECTION SUMMARY
11/06/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter Fire Loss Reduction Form
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter Codes Temporary Certificate of Occupancy
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter INSPECTION SUMMARY
12/02/2020 Letter Codes Temporary Certificate of Occupancy
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/04/2020 Letter INSPECTION SUMMARY
12/21/2020 Letter INSPECTION SUMMARY
12/21/2020 Letter INSPECTION SUMMARY
01/12/2021 Letter DE-Daily Inspection Summary
01/12/2021 Letter DE-Certificate of Substantial Completion Single Lot
01/12/2021 Letter DE-Punch List
01/12/2021 Letter INSPECTION SUMMARY
01/13/2021 Letter Rated assembly letter
01/13/2021 Letter INSPECTION SUMMARY
01/13/2021 Letter INSPECTION SUMMARY
01/25/2021 Letter Codes Temporary Certificate of Occupancy
01/27/2021 Letter INSPECTION SUMMARY
08/24/2021 Letter INSPECTION SUMMARY
08/24/2021 Letter INSPECTION SUMMARY
08/25/2021 Letter INSPECTION SUMMARY
08/25/2021 Letter INSPECTION SUMMARY
06/12/2023 Letter Codes 140 Day Letter
06/13/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home