Permit Application Status

PRCOM20235208


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20235208
Building Permit - Commercial
Issued
RESIDENCES AT BLACKWELL LLC
NEW MULTI-FAMILY
RESIDENCES AT BLACKWELL - BUILDING #4 - 67 Units NEW APARTMENT BUILDING
10/10/2023
01/02/2025
Locations
Contacts
Jake Loveless, Address:21 SE 29TH TER  
Polar Aire Heating & Cooling Service, Address:400 S. Kansas Ave, Phone:(913) 782-8238  
KDM ELECTRICAL CONTRACTORS, Address:1103 NW CASEY BLVD STE C, Phone:(816) 443-5694  
BENCHMARK MECHANICAL LLC, Address:5 SW 4TH ST, Phone:(816) 524-5616  
NSPJ ARCHITECTS, Address:3515 W 75TH ST, SUITE 201, Phone:(913) 831-1415 Ext:278  
CFS ENGINEERS, Address:1421 EAST 104TH STREET STE 100, Phone:(816) 333-4477  
RESIDENCES AT BLACKWELL LLC, Address:21 SE 29TH TER  
Streamline General Contractors, Address:5 4TH ST SW  
Scott Runyan - Griffen Riley Property Group, Phone:(816) 500-5928  
Reviews
Review Type Outcome Est. Completion Date Completed
Alarm Plan Review Released for Construction 04/28/2025 04/28/2025
Craig Hill
Alarms connected to automatic sprinkler system
Informational
04/28/2025

2018 IFC 903.4.2- Alarms. Approved audible and visual devices shall be connected to every automatic sprinkler system. Such sprinkler water-flow alarm devices shall be activated by water flow equivalent to the flow of a single sprinkler of the smallest orifice size installed in the system. Listed alarm notification devices shall be provided on the exterior and interior of the building in an approved location. Where a fire alarm system is installed, actuation of the automatic sprinkler system shall actuate the building fire alarm system.
Alarm testing.
Informational
04/28/2025

2018 IFC 904.4.2- Alarm testing. Notification appliances, connections to fire alarm systems, and connections to approved supervising stations shall be tested in accordance with this section and Section 907 to verify proper operation. Call (816) 969-1300 24 hours in advance to schedule an alarm test. System must be monitored and pretested before scheduling.
Sprinkler Plan Review Released for Construction 02/27/2025
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Multi-Family $4,500.00 $4,500.00 Paid 04/10/2024
$40,475.00
Residential Excise Tax Fee $28,429.44 $28,429.44 Paid 12/18/2024
Valuation Fee for New Multi-Family $35,975.00 $35,975.00 Paid 12/18/2024
$40,475.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Alarm Test Pending
Piers/Caissons Inspection - Commercial Pending
Sewer Service Inspection Pending
Water Service Inspection Pending
Electrical Service Inspection Pending
Gas Piping Inspection - Commercial Pending
Gas Service Inspection - Commercial Pending
Underslab Electrical Inspection - Commercial Pending
Misc
Informational
10/15/2024
Underslab electrical raceways to electrical rm -underground electrical raceways to underslab electrical raceways.
Erosion Control Inspection Residential Pending
Misc
Corrective Action Required
10/16/2024
Erosion control installed along the street
Sprinkler - Hydrostatic Test Pending
Sprinkler - Flow Test Pending
Alarm Test Pending
Rated Assembly Inspection Pending
LOWER LEVEL
Corrective Action Required
03/11/2025
-Tub&shower walls screw pattern okay except 001 & 003 **Fc gap at top of shower wall (unit 008 and unit near middle corridor)
FIRST FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-mud and tape OK
SECOND FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls -mud&taped -screw pattern corridor ceiling -okay
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-mud&taped -Kitchen/corridor walls-screw OK --screw pattern corridor ceiling -okay **repair GB at unit 305 shower
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor wall-screw OK
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
-LL to 3rd floor, dwelling side 1st layer -4th floor, dwelling side 2nd layer
Above Ceiling Inspection Pending 7/28/2025
CORRIDORS
Corrective Action Required
07/24/2025
All Rough Inspection - Commercial Pending 8/11/2025 8/11/2025
Footing Inspection - Commercial Partial 5/16/2024 5/16/2024 03/30/2023
Misc
Corrective Action Required
04/23/2024
Footing OK to pour: -From A/4 to A.1/2 The rest of the footing from A/4 to L.5/4 have soil bearing issue that will need to be addressed by the engineer Grid line1 (4,building 4,concrete retaining wall) inspected up to grid line line L5 PASSED 5/16/24 AF
Footing Inspection - Commercial Partial 4/23/2024 4/23/2024 04/23/2024
Misc
Corrective Action Required
04/23/2024
Footing OK to pour: -From A/4 to A.1/2 The rest of the footing from A/4 to L.5/4 have soil bearing issue that will need to be addressed by the engineer
Footing Inspection - Commercial Partial 5/17/2024 (10:00) 5/17/2024 05/17/2024
Misc
Corrective Action Required
05/16/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3
Footing Inspection - Commercial Partial 5/23/2024 5/23/2024 05/23/2024
Misc
Corrective Action Required
05/17/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3 -remaining storm shelter wall footing
Foundation Inspection - Commercial Partial 5/28/2024 05/28/2024
Misc
Informational
05/28/2024
Ok below: Front foundation wall from A to L.5; east stair f.wall
Footing Inspection - Commercial Partial 6/4/2024 6/4/2024 06/04/2024
Misc
Corrective Action Required
05/23/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing
Footing Inspection - Commercial Partial 6/5/2024 6/5/2024 06/05/2024
Misc
Corrective Action Required
06/04/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads; elevator footing pad
Footing Inspection - Commercial Partial 6/7/2024 6/7/2024 06/07/2024
Misc
Corrective Action Required
06/05/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall
Foundation Inspection - Commercial Partial 6/7/2024 6/7/2024 06/07/2024
Misc
Informational
05/28/2024
Ok below: -Front foundation wall from A to L.5; east stair f.wall -Completion of storm shelter foundation wall
Underslab Plumbing Inspection - Commercial Passed 7/23/2024 07/23/2024
Footing Inspection - Commercial Partial 8/5/2024 08/05/2024
Misc
Corrective Action Required
06/07/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall - building 4 footing and slab by SH
Footing Inspection - Commercial Partial 9/10/2024 09/10/2024
Misc
Corrective Action Required
08/05/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall - building 4 footing and slab by SH -Slab above storm shelter-bottom mat installed
Foundation Inspection - Commercial Partial 9/12/2024 9/12/2024 09/12/2024
Misc
Informational
06/07/2024
Ok below: -Front foundation wall from A to L.5; east stair f.wall -Completion of storm shelter foundation wall -Slab above storm shelter-OK to pour pending approval from engineer
Underslab Plumbing Inspection - Commercial Passed 10/9/2024 10/9/2024 10/09/2024
Informational
10/09/2024
Completion of the garage underslab plumbing
Underslab Electrical Inspection - Commercial Partial 10/11/2024 10/11/2024
Misc
Informational
10/11/2024
Underslab electrical raceways to electrical rm
Underslab Electrical Inspection - Commercial Partial 10/15/2024 10/15/2024 10/15/2024
Misc
Informational
10/11/2024
Underslab electrical raceways to electrical rm -underground electrical raceways to underslab electrical raceways.
Footing Inspection - Commercial Partial 10/16/2024 10/16/2024 10/16/2024
Misc
Corrective Action Required
09/10/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall - building 4 footing and slab by SH *upper level footing not ready
Erosion Control Inspection Residential Partial 10/16/2024 10/16/2024
Misc
Corrective Action Required
10/16/2024
Erosion control installed along the street
Footing Inspection - Commercial Failed 10/17/2024 10/17/2024
Misc
Corrective Action Required
10/16/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall - building 4 footing and slab by SH *upper level footing-Provide proper sleeves around the plumbing through the footing
Footing Inspection - Commercial Partial 10/22/2024 10/22/2024 10/22/2024
Misc
Corrective Action Required
10/17/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall -building 4 footing and slab by SH -upper level footing
Footing Inspection - Commercial Failed 11/20/2024 11/20/2024 11/20/2024
Misc
Corrective Action Required
10/22/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall -building 4 footing and slab by SH **upper level footing at west side mot ready
Footing Inspection - Commercial Partial 11/26/2024 11/26/2024 11/26/2024
Misc
Corrective Action Required
11/20/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall -building 4 footing and slab by SH **upper level footing at west side-water spilling out from damaged underground water line and needs to be fixed
Footing Inspection - Commercial Partial 12/23/2024 12/23/2024 12/23/2024
Misc
Corrective Action Required
11/26/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall -building 4 footing and slab by SH **garage 1 footing at west side not ready
Footing Inspection - Commercial Partial 12/30/2024 12/30/2024 12/30/2024
Misc
Corrective Action Required
11/26/2024
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall -building 4 upper footing and slab by SH -remaining upper footing
Foundation Inspection - Commercial Passed 1/3/2025 1/3/2025 01/03/2025
Misc
Informational
09/12/2024
Ok below: -Front foundation wall from A to L.5; east stair f.wall -Completion of storm shelter foundation wall -Slab above storm shelter-OK to pour pending approval from engineer -Garage curb walls
Footing Inspection - Commercial Passed 3/11/2025 03/11/2025
Misc
Resolved
03/11/2025
Footing OK to pour: -ext. footing from A/4 to A.1/2 -A/4 to L.5/5 (5/16/24-AF) -ext. footing from L.5/5 to M.9/3; complete rear footing from N to A -remaining storm shelter wall footing -4 storm shelter column pads and columns; elevator footing pad and wall -building 4 upper footing and slab by SH -remaining upper footing
Rated Assembly Inspection Partial 3/11/2025 03/11/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 1st layer 1st floor: 2nd floor:
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 1st layer 1st floor: 2nd floor:
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 1st layer
ELEVATOR 1
Corrective Action Required
03/11/2025
Rated Assembly Inspection Partial 3/14/2025 03/14/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: 2nd floor:
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: 2nd floor:
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
Rated Assembly Inspection Partial 3/26/2025 3/26/2025 03/26/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 1st layer 2nd floor:
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: 2nd floor:
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
FOURTH FLOOR
Corrective Action Required
03/26/2025
Rated Assembly Inspection Partial 3/26/2025 3/31/2025 03/31/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor:
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor:
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
FOURTH FLOOR
Corrective Action Required
03/26/2025
Rated Assembly Inspection Partial 3/26/2025 4/7/2025 04/07/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
FOURTH FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 1st layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 1st layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
Rated Assembly Inspection Partial 3/26/2025 4/8/2025 04/08/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
FOURTH FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor:
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor:
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
All Rough Inspection - Commercial Partial 4/8/2025 04/08/2025
LOWER LEVEL
Corrective Action Required
04/08/2025
FIRST FLOOR
Corrective Action Required
04/08/2025
SECOND FLOOR
Corrective Action Required
04/08/2025
THIRD FLOOR
Corrective Action Required
04/08/2025
FOURTH FLOOR
Corrective Action Required
04/08/2025
STAIR TOWER 1
Corrective Action Required
04/08/2025
STAIR TOWER 2
Corrective Action Required
04/08/2025
STAIR TOWER 3
Corrective Action Required
04/08/2025
ELEVATOR 1
Corrective Action Required
04/08/2025
Misc
Corrective Action Required
04/08/2025
Interior and exterior sheathed shear walls: -Lower floor, 1st, 2nd fl
Rated Assembly Inspection Partial 4/17/2025 4/17/2025 04/17/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
FOURTH FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor:
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 1st layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
Rated Assembly Inspection Partial 4/17/2025 4/22/2025 04/22/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
FOURTH FLOOR
Corrective Action Required
03/11/2025
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
Rated Assembly Inspection Partial 4/17/2025 6/5/2025 06/05/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-pre-rock OK **Corrections: -Kitchen/corridor walls-screw GB to bottom wall plates
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-pre-rock OK **Corrections: -Kitchen/corridor walls-screw GB to bottom wall plates
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
Rated Assembly Inspection Partial 4/17/2025 6/11/2025 06/11/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-pre-rock OK **Corrections: -Kitchen/corridor walls-screw GB to bottom wall plates
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor wall-screw OK
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
**Correction: 4th floor, outer side 1st layer-screw GB above ceiling
Rated Assembly Inspection Partial 6/12/2025 6/12/2025 06/12/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
FIRST FLOOR
Corrective Action Required
03/11/2025
SECOND FLOOR
Corrective Action Required
03/11/2025
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor walls-screw OK
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor wall-screw OK
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
-4th floor, dwelling side 1st layer
All Rough Inspection - Commercial Partial 6/16/2025 06/16/2025
LOWER LEVEL
Corrective Action Required
04/08/2025
FIRST FLOOR
Corrective Action Required
04/08/2025
SECOND FLOOR
Corrective Action Required
04/08/2025
THIRD FLOOR
Corrective Action Required
04/08/2025
FOURTH FLOOR
Corrective Action Required
04/08/2025
**Check all -Fc along edge of drywall inside tub/corridor space; Fc penetrations of drywall -Complete panel SE connection -Check framing detail of balcony ceiling support -Terminate wiring inside ceiling boxes -Nail elevator drywall above ceiling -Nail together girder truss -Fc gap at top of dead spaces at both ends of corridor -Redo floor-floor screw in dead space at north end of corridor 401: -Fc plate penetrations at exterior wall -Nail together girder truss -Terminate wiring inside ceiling boxes 402: -Complete laundry plumbing -Fc top of laundry and tub wall; penetration by MC and fire alarm cable -Strap top plates at rear exterior balcony wall 404: 403: -Nail corner studs -Strap down header above rear windows -Strap closet wall top plates lapped less than 2 ft 406: -Strap at bored wall top plates at 3” waste&vent stack 405: -Protect wiring outside entry door -Complete soffit at laundry -Fc wall plate penetration -Re-nail kitchen/corridor wall stud to plate 407: -Protect fire sprinkler line at laundry wall 410: 409: -Repair damaged truss 412: 413: -Fc gap at top of double stud wall -Strap top plates at rear exterior balcony wall 411: -Protect refrigerator water line -Protect wiring below master bedroom window -Fc floor penetrations behind tub. Add min 1/2” bead of caulk at 4” pipe
STAIR TOWER 1
Corrective Action Required
04/08/2025
STAIR TOWER 2
Corrective Action Required
04/08/2025
STAIR TOWER 3
Corrective Action Required
04/08/2025
ELEVATOR 1
Corrective Action Required
04/08/2025
Misc
Corrective Action Required
04/08/2025
Interior and exterior sheathed shear walls: -Lower floor, 1st, 2nd fl
All Rough Inspection - Commercial Failed 7/2/2025 7/2/2025 07/02/2025
LOWER LEVEL
Corrective Action Required
04/08/2025
FIRST FLOOR
Corrective Action Required
04/08/2025
SECOND FLOOR
Corrective Action Required
04/08/2025
THIRD FLOOR
Corrective Action Required
04/08/2025
FOURTH FLOOR
Corrective Action Required
04/08/2025
**Check all -Check framing detail of balcony ceiling support -Terminate wiring inside ceiling boxes -Redo floor-floor screw in dead space at north end of corridor -Strap down lvl header at corridor near elevator -3-studs packs at truss girder supports -Check bracing of end of trusses 401: 402: -Complete laundry plumbing; install stud shoe at over-bored stud; protect plumbing -Fire stop top of laundry wall 404: 403: -Nail corner studs -Strap down header above rear windows -Terminate wiring inside ceiling boxes -Missing stud at bath/closet wall 406: -Strap at bored wall top plates at 3” waste&vent stack -Nail girder truss stud pack together; nail the Simpson hold down device -Secure wiring within 12” of corridor light box 405: -Protect wiring outside entry door -Complete soffit at laundry and fb as required -Fc wall plate penetration -Re-nail kitchen/corridor wall stud to plate 408: -Strap window header down to wall 407: 410: 409: -Repair damaged truss per engineer -Missing stud at laundry 412: -Strap down beam at rear 413: 411: -Protect wiring below master bedroom window
STAIR TOWER 1
Corrective Action Required
04/08/2025
STAIR TOWER 2
Corrective Action Required
04/08/2025
STAIR TOWER 3
Corrective Action Required
04/08/2025
ELEVATOR 1
Corrective Action Required
04/08/2025
Misc
Corrective Action Required
04/08/2025
Interior and exterior sheathed shear walls: -Lower floor, 1st, 2nd fl
Rated Assembly Inspection Partial 6/12/2025 7/10/2025 07/10/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
-Tub&shower walls pre-rock OK **Fc gap at top of shower wall (unit 008 and unit near middle corridor)
FIRST FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls pre-rock-OK
SECOND FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls pre-rock OK **screw SW 3-3 and 3-5 GB @ 4/4 **extend elevator GB through 207 demising wall
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-mud&taped -Kitchen/corridor walls-screw OK **repair GB at unit 305 shower
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor wall-screw OK
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
-4th floor, dwelling side 1st layer
All Rough Inspection - Commercial Failed 7/2/2025 7/22/2025 07/22/2025
LOWER LEVEL
Corrective Action Required
04/08/2025
FIRST FLOOR
Corrective Action Required
04/08/2025
SECOND FLOOR
Corrective Action Required
04/08/2025
THIRD FLOOR
Corrective Action Required
04/08/2025
FOURTH FLOOR
Corrective Action Required
04/08/2025
**Check all -Framing of balcony ceiling not per plan -Redo floor-floor screw in dead space at north end of corridor. Screw outside of the plate 401: 402: -Complete laundry plumbing; install stud shoe at over-bored stud; protect plumbing 404: 403: -Missing studs at bath and laundry walls 406: 405: -3-studs packs at truss girder support (corridor) 408: 407: -Missing studs at laundry wall 410: 409: -Missing stud at laundry 412: 413: 411:
STAIR TOWER 1
Corrective Action Required
04/08/2025
STAIR TOWER 2
Corrective Action Required
04/08/2025
STAIR TOWER 3
Corrective Action Required
04/08/2025
ELEVATOR 1
Corrective Action Required
04/08/2025
Misc
Corrective Action Required
04/08/2025
Interior and exterior sheathed shear walls: -Lower floor, 1st, 2nd fl
Above Ceiling Inspection Failed 7/24/2025 7/24/2025 07/24/2025
CORRIDORS
Corrective Action Required
07/24/2025
2 and 3rd floors corridor ceiling pre-rock-Install proper size hangers
All Rough Inspection - Commercial Failed 7/28/2025 7/28/2025 07/28/2025
LOWER LEVEL
Corrective Action Required
04/08/2025
FIRST FLOOR
Corrective Action Required
04/08/2025
SECOND FLOOR
Corrective Action Required
04/08/2025
Pre-rock for corridor ceiling-OK
THIRD FLOOR
Corrective Action Required
04/08/2025
Pre-rock for corridor ceiling-OK
FOURTH FLOOR
Corrective Action Required
04/08/2025
**Check all -Framing of balcony ceiling not per plan -Complete corridor electrical 401: 402: -Complete laundry plumbing; install stud shoe at over-bored stud; protect plumbing 404: 403: -Missing studs at bath and laundry walls 406: 405: 408: 407: 410: 409: 412: 413: 411:
STAIR TOWER 1
Corrective Action Required
04/08/2025
STAIR TOWER 2
Corrective Action Required
04/08/2025
STAIR TOWER 3
Corrective Action Required
04/08/2025
ELEVATOR 1
Corrective Action Required
04/08/2025
Misc
Corrective Action Required
04/08/2025
Interior and exterior sheathed shear walls: -Lower floor, 1st, 2nd fl
Rated Assembly Inspection Partial 7/30/2025 7/30/2025 07/30/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
-Tub&shower walls pre-rock OK **Fc gap at top of shower wall (unit 008 and unit near middle corridor)
FIRST FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK
SECOND FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-mud&taped -Kitchen/corridor walls-screw OK **repair GB at unit 305 shower
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor wall-screw OK
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
-4th floor, dwelling side 2nd layer
Rated Assembly Inspection Partial 7/30/2025 7/31/2025 07/31/2025
LOWER LEVEL
Corrective Action Required
03/11/2025
-Tub&shower walls pre-rock OK **Fc gap at top of shower wall (unit 008 and unit near middle corridor)
FIRST FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK
SECOND FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls -mud&taped
THIRD FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-mud&taped -Kitchen/corridor walls-screw OK **repair GB at unit 305 shower
FOURTH FLOOR
Corrective Action Required
03/11/2025
-Tub&shower walls-screw OK -Kitchen/corridor wall-screw OK
STAIR TOWER 1
Corrective Action Required
03/11/2025
**THIS IS NORTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 2
Corrective Action Required
03/11/2025
**THIS IS SOUTH STAIR A** Lower floor: -stair side 2nd layer 1st floor: -stair side 2nd layer 2nd floor: -stair side 2nd layer 3rd floor: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
03/11/2025
**THIS IS REAR STAIR B** Lower floor: -elevator/stair wall-stair side 2nd layer
ELEVATOR 1
Corrective Action Required
03/11/2025
-4th floor, dwelling side 2nd layer
All Rough Inspection - Commercial Partial 8/8/2025 8/8/2025 08/08/2025
LOWER LEVEL
Corrective Action Required
04/08/2025
FIRST FLOOR
Corrective Action Required
04/08/2025
SECOND FLOOR
Corrective Action Required
04/08/2025
Pre-rock for corridor ceiling-OK
THIRD FLOOR
Corrective Action Required
04/08/2025
Pre-rock for corridor ceiling-OK Incomplete inspection, check throughout for deficiencies 302 -Install all wall kickers per S3.31 -Bond all metallic boxes -Land service entry cables -remove bonding screw from panel -Protect sprinkler pipes 2” above bottom plate -Nail all exterior corners 12” oc -Seal top plate by deck -Seal penetrations in draft stops stairwell -Missing bocca plates at mechanical closet -protect pex in wall in mechanical closet -Protect back to back boxes at separation walls -Draft stop between units -Missing nails at stud shoes -Label white current carrying conductors -Protect electrical at island 6” above floor -missing Simpson SDWC screws in multiple areas throughout
FOURTH FLOOR
Corrective Action Required
04/08/2025
**Check all -Framing of balcony ceiling not per plan -Complete corridor electrical. Fc all penetrations 401: 402: 404: 403: 406: 405: 408: 407: 410: 409: 412: 413: 411:
STAIR TOWER 1
Corrective Action Required
04/08/2025
STAIR TOWER 2
Corrective Action Required
04/08/2025
STAIR TOWER 3
Corrective Action Required
04/08/2025
ELEVATOR 1
Corrective Action Required
04/08/2025
Misc
Corrective Action Required
04/08/2025
Interior and exterior sheathed shear walls: -Lower floor, 1st, 2nd fl
Documents & Images
Date Uploaded File Type Document Name
04/10/2024 Receipt Receipt for transaction:2024-002292
04/11/2024 Letter DS Building Permit
04/23/2024 Letter INSPECTION SUMMARY
05/16/2024 Letter INSPECTION SUMMARY
05/17/2024 Letter INSPECTION SUMMARY
05/17/2024 Letter INSPECTION SUMMARY
05/23/2024 Letter INSPECTION SUMMARY
05/28/2024 Letter INSPECTION SUMMARY
06/04/2024 Letter INSPECTION SUMMARY
06/05/2024 Letter INSPECTION SUMMARY
06/07/2024 Letter INSPECTION SUMMARY
06/07/2024 Letter INSPECTION SUMMARY
07/23/2024 Letter INSPECTION SUMMARY
08/05/2024 Letter INSPECTION SUMMARY
09/10/2024 Letter INSPECTION SUMMARY
09/12/2024 Letter INSPECTION SUMMARY
10/09/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/15/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/22/2024 Letter INSPECTION SUMMARY
11/20/2024 Letter INSPECTION SUMMARY
11/26/2024 Letter INSPECTION SUMMARY
12/18/2024 Receipt Receipt for transaction:2024-009584
12/23/2024 Letter INSPECTION SUMMARY
12/30/2024 Letter INSPECTION SUMMARY
01/02/2025 Letter DS Building Permit
01/03/2025 Letter INSPECTION SUMMARY
03/11/2025 Letter INSPECTION SUMMARY
03/14/2025 Letter INSPECTION SUMMARY
03/25/2025 Letter INSPECTION SUMMARY
03/31/2025 Letter INSPECTION SUMMARY
04/07/2025 Letter INSPECTION SUMMARY
04/08/2025 Letter INSPECTION SUMMARY
04/08/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
04/17/2025 Letter INSPECTION SUMMARY
04/21/2025 Plans 24050258 Blackwell Apt 4-FA-set SEALED
04/21/2025 24050258 Blackwell Apt 4-FA-set SEALED
04/21/2025 24050258 Blackwell Apt 4-FA-set SEALED
04/22/2025 Letter INSPECTION SUMMARY
04/28/2025 24050258 Blackwell Apt 4-FA-set SEALED1 RFC
04/28/2025 Letter Fire (Alarm) Plan Review Notice
06/05/2025 Letter INSPECTION SUMMARY
06/12/2025 Letter INSPECTION SUMMARY
06/16/2025 Letter INSPECTION SUMMARY
07/02/2025 Letter INSPECTION SUMMARY
07/03/2025 Building 4 Unit 409 Truss Repair
07/10/2025 Letter INSPECTION SUMMARY
07/22/2025 Letter INSPECTION SUMMARY
07/22/2025 Letter INSPECTION SUMMARY
07/22/2025 Letter INSPECTION SUMMARY
07/22/2025 Letter INSPECTION SUMMARY
07/22/2025 Letter INSPECTION SUMMARY
07/28/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/30/2025 Letter INSPECTION SUMMARY
07/31/2025 Letter INSPECTION SUMMARY
07/13/2023 Approved Plans approved - volume 1
07/13/2023 Approved Plans approved - volume 2
08/01/2025 Letter INSPECTION SUMMARY
08/01/2025 Letter INSPECTION SUMMARY
08/05/2025 Letter INSPECTION SUMMARY
08/08/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home