Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Grading/Excavation/Fill Inspection
|
Pending
|
|
|
|
Sanitary - Material Verification
|
Pending
|
|
|
|
Install Street and Stop Signs
|
Pending
|
|
|
|
Retaining Wall Inspection
|
Pending
|
|
|
|
Install Street and Stop Signs
|
Pending
|
|
|
|
Storm Sewer Construction Inspection
|
Pending
|
|
|
|
Sanitary Sewer Construction Inspection
|
Pending
|
|
|
|
Install Street and Stop Signs
|
Pending
|
|
|
|
Storm Sewer Construction Inspection
|
Pending
|
|
|
|
Water Line - Construction Inspection
|
Pending
|
|
|
|
Water Line - Construction Inspection
|
Pending
|
|
|
|
Sanitary Sewer Construction Inspection
|
Pending
|
|
|
|
Install Street and Stop Signs
|
Pending
|
|
|
|
Storm Sewer Construction Inspection
|
Pending
|
|
|
|
Sanitary Sewer - Vacuum
|
Pending
|
|
|
|
|
Misc
|
Water Service Inspection
|
Pending
|
|
|
|
|
Misc
|
Pavement-Surface
|
Pending
|
|
|
|
Water Line - Hydrostatic Test
|
Pending
|
|
|
|
Sewer Service Inspection
|
Pending
|
|
|
|
Miscellaneous Inspection
|
Pending
|
|
|
|
Above Ceiling Inspection
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Piers/Caissons Inspection - Commercial
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Water Line - Construction Inspection
|
Pending
|
|
|
|
Sanitary Sewer Construction Inspection
|
Pending
|
|
|
|
Install Street and Stop Signs
|
Pending
|
|
|
|
Pavement-Stabilized Subgrade
|
Pending
|
|
|
|
Storm Sewer Construction Inspection
|
Pending
|
|
|
|
Water Line - Hydrostatic Test
|
Pending
|
|
|
|
Detention Basin
|
Pending
|
|
|
|
Sidewalk Inspection
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Pending
|
|
|
|
Occupancy Inspection - Planning
|
Pending
|
|
|
|
Erosion Control Inspection
|
Pending
|
|
|
|
|
Corrective Action Required
|
Erosion Control Inspection Residential
|
Pending
|
|
|
|
|
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Site Visit
|
Pending
|
|
|
|
|
Miscellaneous Correction
|
Gas Service Inspection - Commercial
|
Pending
|
|
|
|
|
Misc
|
Pavement-Proof Roll
|
Pending
|
|
|
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Pending
|
2/28/2024
|
|
|
|
Misc
|
All Rough Inspection - Commercial
|
Pending
|
6/27/2025
|
|
|
|
Misc
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
Occupancy Inspection - Fire
|
Pending
|
7/28/2025
|
7/28/2025
|
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection Residential
|
Partial
|
|
|
08/14/2023
|
|
Misc
|
Site Visit
|
Partial
|
|
|
09/12/2023
|
|
Misc
|
Site Visit
|
Partial
|
10/12/2023
|
10/12/2023
|
10/12/2023
|
|
Misc
|
Erosion Control Inspection Residential
|
Partial
|
10/23/2023
|
10/23/2023
|
11/16/2023
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
|
11/30/2023
|
11/30/2023
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
|
12/5/2023
|
12/05/2023
|
|
Misc
|
Footing Inspection - Commercial
|
Not Ready
|
12/13/2023 (2:00)
|
12/13/2023
|
12/13/2023
|
Footing Inspection - Commercial
|
Partial
|
|
12/14/2023
|
12/14/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
|
12/15/2023
|
12/15/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/21/2023
|
12/21/2023
|
12/21/2023
|
|
Misc
Corrective Action Required
|
Pavement-Aggregate Base
|
Partial
|
|
|
01/04/2024
|
|
Misc
|
Foundation Inspection - Commercial
|
Failed
|
|
1/10/2024
|
01/10/2024
|
|
Misc
Corrective Action Required
|
Foundation Inspection - Commercial
|
Partial
|
|
1/17/2024
|
01/17/2024
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
2/13/2024
|
2/13/2024
|
02/13/2024
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
|
2/23/2024
|
02/23/2024
|
Footing Inspection - Commercial
|
Partial
|
2/27/2024
|
2/27/2024
|
02/27/2024
|
|
Misc
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Passed
|
|
2/28/2024
|
02/28/2024
|
Footing Inspection - Commercial
|
Passed
|
3/1/2024
|
3/1/2024
|
03/01/2024
|
|
Misc
|
Water Line - Hydrostatic Test
|
Passed
|
|
|
03/14/2024
|
|
Misc
|
Water Line - Coliform Test 1
|
Passed
|
|
|
03/22/2024
|
|
Misc
|
Water Line - Coliform Test 2
|
Passed
|
|
|
03/22/2024
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
4/11/2024 (1:00)
|
4/11/2024
|
04/11/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
|
04/12/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
|
04/12/2024
|
|
Misc
|
Detention Basin
|
Partial
|
|
|
04/16/2024
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
4/25/2024
|
4/25/2024
|
04/25/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
|
04/26/2024
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
5/23/2024
|
5/23/2024
|
05/23/2024
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
06/05/2024
|
|
Misc
|
Miscellaneous Inspection
|
Partial
|
6/7/2024
|
6/7/2024
|
06/07/2024
|
|
Misc
|
Miscellaneous Inspection
|
Partial
|
7/25/2024
|
7/25/2024
|
07/25/2024
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Failed
|
7/26/2024
|
7/26/2024
|
07/26/2024
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
8/2/2024
|
08/02/2024
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
8/13/2024
|
8/14/2024
|
08/14/2024
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
|
8/15/2024
|
08/15/2024
|
|
Misc
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Failed
|
8/20/2024
|
8/20/2024
|
08/20/2024
|
|
Misc
Corrective Action Required
|
|
FIRST FLOOR
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
8/23/2024
|
8/23/2024
|
08/23/2024
|
|
Misc
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
Foundation Inspection - Commercial
|
Partial
|
|
9/4/2024
|
09/04/2024
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
9/5/2024
|
9/5/2024
|
09/05/2024
|
|
Misc
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
9/5/2024
|
9/5/2024
|
09/05/2024
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
9/5/2024
|
9/5/2024
|
09/05/2024
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
|
9/10/2024
|
09/10/2024
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
10/7/2024
|
10/7/2024
|
10/07/2024
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
10/7/2024
|
10/07/2024
|
|
Misc
Corrective Action Required
|
|
LOWER LEVEL
Corrective Action Required
|
Sanitary Sewer - Mandrel
|
Partial
|
10/9/2024
|
10/9/2024
|
10/09/2024
|
|
Misc
|
Sanitary Sewer - Vacuum
|
Partial
|
10/8/2024
|
10/8/2024
|
10/09/2024
|
|
Misc
|
Sanitary Sewer - Air Test
|
Partial
|
10/8/2024
|
10/8/2024
|
10/09/2024
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
10/11/2024
|
10/11/2024
|
10/11/2024
|
|
Misc
Corrective Action Required
|
Water Service Inspection
|
Partial
|
10/11/2024
|
10/11/2024
|
10/11/2024
|
|
Misc
|
Retaining Wall Inspection
|
Partial
|
10/15/2024
|
10/15/2024
|
10/15/2024
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
10/15/2024
|
10/15/2024
|
10/15/2024
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
10/28/2024
|
10/28/2024
|
10/28/2024
|
|
Misc
Corrective Action Required
|
Site Visit
|
Partial
|
10/29/2024
|
10/29/2024
|
10/29/2024
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
|
10/30/2024
|
10/30/2024
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Failed
|
12/6/2024
|
12/9/2024
|
12/09/2024
|
|
Misc
Corrective Action Required
|
Fire Line Construction Inspection
|
Partial
|
12/9/2024
|
12/9/2024
|
12/09/2024
|
|
Misc
|
Pavement-Proof Roll
|
Partial
|
12/17/2024
|
12/17/2024
|
12/17/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
12/18/2024
|
12/18/2024
|
12/18/2024
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
11/20/2024
|
12/19/2024
|
12/19/2024
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
1/9/2025
|
1/9/2025
|
01/09/2025
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Failed
|
1/9/2025
|
1/9/2025
|
01/09/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
1/14/2025
|
1/14/2025
|
01/14/2025
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
1/14/2025
|
1/14/2025
|
01/14/2025
|
|
Misc
Corrective Action Required
|
Fire Line - Hydrostatic Test
|
Passed
|
1/15/2025
|
1/15/2025
|
01/15/2025
|
|
Misc
|
Water Line - Construction Inspection
|
Passed
|
11/8/2024
|
11/8/2024
|
01/15/2025
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
1/22/2025
|
1/22/2025
|
01/22/2025
|
|
Misc
Corrective Action Required
|
Fire Line - Hydrostatic Test
|
Passed
|
1/27/2025
|
1/27/2025
|
01/27/2025
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
1/28/2025
|
01/28/2025
|
|
Misc
Corrective Action Required
|
Storm Sewer Construction Inspection
|
Partial
|
2/3/2025
|
2/3/2025
|
02/04/2025
|
|
Misc
|
Electrical Service Inspection
|
Passed
|
2/10/2025
|
2/11/2025
|
02/11/2025
|
Rated Assembly Inspection
|
Partial
|
2/13/2025
|
2/13/2025
|
02/13/2025
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Failed
|
|
3/12/2025
|
03/12/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
|
3/12/2025
|
03/12/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
3/13/2025
|
3/13/2025
|
03/13/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
3/14/2025
|
3/14/2025
|
03/14/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
3/17/2025
|
3/17/2025
|
03/17/2025
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
3/26/2025
|
3/26/2025
|
03/26/2025
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
|
3/31/2025
|
03/31/2025
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection Residential
|
Partial
|
4/8/2025
|
4/8/2025
|
04/08/2025
|
|
Misc
Corrective Action Required
|
Pavement-Stabilized Subgrade
|
Partial
|
4/8/2025
|
4/8/2025
|
04/08/2025
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
4/17/2025
|
4/17/2025
|
04/17/2025
|
|
Misc
Corrective Action Required
|
Pavement-Curb Construction
|
Partial
|
4/23/2025
|
4/23/2025
|
04/23/2025
|
|
Misc
|
Erosion Control Inspection Residential
|
Partial
|
|
|
04/28/2025
|
|
Misc
|
Erosion Control Inspection Residential
|
Failed
|
|
|
04/29/2025
|
|
Misc
|
|
Misc
Corrective Action Required
|
Pavement-Proof Roll
|
Failed
|
5/5/2025
|
5/5/2025
|
05/07/2025
|
|
Misc
|
Sewer Service Inspection
|
Partial
|
5/29/2025
|
5/29/2025
|
05/29/2025
|
|
Misc
|
Sanitary Sewer - Air Test
|
Passed
|
|
|
05/29/2025
|
|
Misc
|
Sanitary Sewer - Mandrel
|
Passed
|
5/29/2025
|
5/29/2025
|
05/29/2025
|
|
Misc
|
Rated Assembly Inspection
|
Failed
|
6/9/2025
|
6/9/2025
|
06/09/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
6/16/2025
|
6/16/2025
|
06/16/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
6/16/2025
|
6/16/2025
|
06/16/2025
|
|
Misc
Corrective Action Required
|
Site Visit
|
Partial
|
6/24/2025
|
6/24/2025
|
06/24/2025
|
|
Misc
|
Miscellaneous Inspection
|
Partial
|
6/24/2025
|
6/24/2025
|
06/25/2025
|
|
Misc
|
|
Misc
|
Water Line - Coliform Test 1
|
Passed
|
|
|
06/25/2025
|
|
Misc
|
Water Line - Coliform Test 2
|
Passed
|
|
|
06/25/2025
|
Water Line - Coliform Test 2
|
Passed
|
|
|
06/25/2025
|
|
Misc
|
Water Line - Coliform Test 2
|
Passed
|
|
|
06/25/2025
|
Water Line - Construction Inspection
|
Partial
|
6/25/2025
|
6/25/2025
|
06/25/2025
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
7/1/2025
|
7/1/2025
|
07/01/2025
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
|
7/1/2025
|
07/01/2025
|
|
Misc
Corrective Action Required
|
Alarm Test
|
Passed
|
|
|
07/02/2025
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
|
07/02/2025
|
Sprinkler - Flow Test
|
Passed
|
|
|
07/02/2025
|
Piers/Caissons Inspection - Commercial
|
Partial
|
7/3/2025
|
7/3/2025
|
07/03/2025
|
|
Misc
Corrective Action Required
|
Foundation Inspection - Commercial
|
Passed
|
|
|
07/08/2025
|
|
Misc
|
Footing Inspection - Commercial
|
Passed
|
|
|
07/08/2025
|
|
Misc
|
Water Line - Construction Inspection
|
Passed
|
|
|
07/09/2025
|
Pavement-Proof Roll
|
Failed
|
|
|
07/09/2025
|
|
Misc
|
Pavement-Aggregate Base
|
Passed
|
|
|
07/09/2025
|
Pavement-Curb Construction
|
Passed
|
|
|
07/09/2025
|
Pavement-Curb Construction
|
Passed
|
|
|
07/09/2025
|
Erosion Control Inspection
|
Failed
|
7/8/2025
|
7/8/2025
|
07/09/2025
|
|
Misc
Corrective Action Required
|
Detention Basin
|
Failed
|
7/9/2025
|
7/9/2025
|
07/09/2025
|
|
Misc
|
Pavement-Stabilized Subgrade
|
Passed
|
|
|
07/09/2025
|
Fire Line Construction Inspection
|
Passed
|
|
|
07/09/2025
|
|
Misc
|
Pavement-Stabilized Subgrade
|
Passed
|
|
|
07/09/2025
|
Pavement-Stabilized Subgrade
|
Passed
|
|
|
07/09/2025
|
Sidewalk Inspection
|
Failed
|
7/9/2025
|
7/9/2025
|
07/09/2025
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Not Ready
|
|
7/9/2025
|
07/09/2025
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Failed
|
|
7/9/2025
|
07/09/2025
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Water Utilities
|
Passed
|
|
7/9/2025
|
07/09/2025
|
Occupancy Inspection - Planning
|
Failed
|
|
7/9/2025
|
07/09/2025
|
|
Corrective Action Required
|
Site Visit
|
Partial
|
|
|
07/14/2025
|
|
Miscellaneous Correction
|
Occupancy Inspection - Fire
|
Failed
|
|
|
07/17/2025
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection Residential
|
Failed
|
7/17/2025
|
7/17/2025
|
07/17/2025
|
|
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
|
Erosion Control Inspection Residential
|
Failed
|
|
|
07/23/2025
|
|
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
7/24/2025
|
7/24/2025
|
07/24/2025
|
Erosion Control Inspection Residential
|
Partial
|
7/25/2025
|
7/25/2025
|
07/25/2025
|
|
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Failed
|
7/28/2025
|
7/28/2025
|
07/28/2025
|
|
Misc
Corrective Action Required
|
Site Visit
|
Partial
|
|
|
07/30/2025
|
|
Miscellaneous Correction
|
Pavement-Proof Roll
|
Partial
|
|
|
08/01/2025
|
|
Misc
|
Gas Service Inspection - Commercial
|
Failed
|
8/6/2025
|
8/6/2025
|
08/06/2025
|
|
Misc
Corrective Action Required
|
Site Visit
|
Partial
|
|
|
08/06/2025
|
|
Miscellaneous Correction
|
Gas Service Inspection - Commercial
|
Partial
|
8/7/2025
|
8/7/2025
|
08/07/2025
|
|
Misc
|
Pavement-Proof Roll
|
Partial
|
|
|
08/08/2025
|
|
Misc
|