Permit Application Status

PRCOM20213681


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20213681
Building Permit - Commercial
Certificate of Occupancy
NEW MULTI-FAMILY
NEW APARTMENT BUILDING *Documents and plan reviews are in PRCOM20213548
07/16/2021
02/01/2022
09/26/2023
Locations
Contacts
BRINKMANN CONSTRUCTORS, Address:16650 CHESTERFIELD GROVE RD, Phone:(636) 537-9700  
nwintjen@brinkmannconstructors.com, Address:nwintjen@brinkmannconstructors.com  
WELKER HEATING & COOLING, Address:2221 N 147TH STREET, Phone:(913) 669-7555  
LYNN ELECTRIC & COMMUNICATIONS INC, Address:725 N 2ND ST STE K, Phone:(785) 843-5709  
MILLER PLUMBING CO, Address:PO BOX 393 , Phone:(913) 851-1333  
TRI Architects, Address:9812 Manchester rd, Phone:(314) 395-9750  
CFS ENGINEERS, Address:1421 EAST 104TH STREET STE 100, Phone:(816) 333-4477  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved with Conditions 02/01/2022
Joe Frogge
Fire Plan Review Approved with Conditions 02/01/2022
Joe Frogge
Final Development Plan Review Approved 02/01/2022
Joe Frogge
Special Inspections Review Approved 09/29/2021
Joe Frogge
Licensed Contractors Approved 09/29/2021
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Multi-Family $73,333.41 $73,333.41 Paid 02/01/2022
8331507-Sewer Connection Fee $3,000.00 $3,000.00 Paid 02/01/2022
7232302-Residential License Tax Fee $39,255.04 $39,255.04 Paid 02/01/2022
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 01/18/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 01/26/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 02/23/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 05/09/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
All Rough Inspection - Commercial Failed 2/15/2022 2/15/2022 02/15/2022
Corrective Action Required
02/15/2022
FIRST FLOOR
Corrective Action Required
02/15/2022
- 2/15/22 BLDG 2 AREA A SHEAR WALLS 1 & 2 PROVIDE NAILING PER SHEARWALL NAILING SCHEDULE ON PLANS -
SECOND FLOOR
Corrective Action Required
02/15/2022
THIRD FLOOR
Corrective Action Required
02/15/2022
Sewer Service Inspection Passed 4/21/2022 (8:00) 4/21/2022 04/21/2022
Misc
Informational
04/21/2022
Connection made with SDR 26 pipe and hardback Fernco’s. RP 4-21-22
Rated Assembly Inspection Partial 4/21/2022 4/21/2022 04/21/2022
Misc
Informational
04/21/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing
All Rough Inspection - Commercial Failed 6/3/2022 6/3/2022 06/03/2022
FIRST FLOOR
Corrective Action Required
02/15/2022
SECOND FLOOR
Corrective Action Required
02/15/2022
- 2/15/22 BLDG 2 AREA A SHEAR WALLS 1 & 2 PROVIDE NAILING PER SHEARWALL NAILING SCHEDULE ON PLANS -
THIRD FLOOR
Corrective Action Required
06/03/2022
Corridor-clarity draft stoping, support truss at corner of 338, 339- putty pack at metallic box at entry doorway, strap top plates lapped less than 48”, complete vent through roof, protect dwv at washer waste line, provide truss hanger near bathroom, protect sprinkler line at bedroom blocking, identify white current carrying conductors as current carrying conductors, midpoint strap at 2” and smaller dwv, 336-midpoint strap 2” and smaller dwv, missing H2.5’s at corner beds(4) jack trusses, nail all corner studs 12” oc, strap top plate lapped less than 48” at bathroom, bedroom,missing, lower Bocca plate at party wall master bath, strap pex vertical 32” oc max at master shower, 301-ok 331-seal top plate penetrations at master bath, strap top plates lapped less than 48”
All Rough Inspection - Commercial Partial 6/10/2022 06/10/2022
FIRST FLOOR
Corrective Action Required
06/03/2022
SECOND FLOOR
Corrective Action Required
06/03/2022
- 2/15/22 BLDG 2 AREA A SHEAR WALLS 1 & 2 PROVIDE NAILING PER SHEARWALL NAILING SCHEDULE ON PLANS -
THIRD FLOOR
Corrective Action Required
06/03/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
Above Ceiling Inspection Partial 6/10/2022 06/10/2022
All Rough Inspection - Commercial Partial 6/14/2022 6/14/2022 06/14/2022
FIRST FLOOR
Corrective Action Required
06/10/2022
SECOND FLOOR
Corrective Action Required
06/10/2022
AREA "A" UNITS AND CORRIDORS: 201-207- OK 235-secure sec, complete exhaust fan wiring 236-complete rated layer in laundry, Secure sec, complete exhaust fan wiring 237-ok 238-strap top plates at beam lapped less than 48" 240-strap exterior wall top plates lapped less than 48" 242-strap exterior corners and header, strap corridor wall at shower, protect dwv, fireblock ceiling line at corridor, remove bonding screw, 239- strap over bored top plate at bedroom/208, strap exterior corner, strap top plate at closet lapped less than 48"
THIRD FLOOR
Corrective Action Required
06/10/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
All Rough Inspection - Commercial Partial 6/17/2022 6/17/2022 06/17/2022
FIRST FLOOR
Corrective Action Required
06/14/2022
SECOND FLOOR
Corrective Action Required
06/14/2022
AREA "A" UNITS AND CORRIDORS: 201-207- OK 235-238- OK 240-OK 242-strap header 239- strap over bored top plate at bedroom/208,
THIRD FLOOR
Corrective Action Required
06/14/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
All Rough Inspection - Commercial Partial 8/23/2022 06/20/2022
FIRST FLOOR
Corrective Action Required
06/17/2022
SECOND FLOOR
Corrective Action Required
06/17/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
06/17/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
Rated Assembly Inspection Failed 6/20/2022 6/20/2022 06/20/2022
Miscellaneous Correction
Corrective Action Required
06/20/2022
-Support cut RC at boxes, duct work, etc., connect overlapping splices and other like connections with (2) framing screws
THIRD FLOOR
Corrective Action Required
06/20/2022
SECOND FLOOR
Corrective Action Required
06/20/2022
FIRST FLOOR
Corrective Action Required
06/20/2022
Rated Assembly Inspection Failed 6/22/2022 6/22/2022 06/22/2022
Misc
Informational
06/20/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing
THIRD FLOOR
Corrective Action Required
06/22/2022
Area "A" -Support rc channel throughout-max length unsupported 4"
All Rough Inspection - Commercial Partial 6/22/2022 6/22/2022 06/22/2022
FIRST FLOOR
Corrective Action Required
06/20/2022
SECOND FLOOR
Corrective Action Required
06/20/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
06/20/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B"- -H2.5s at exterior decks throughout -Protect dryer ducts 2" below plates throughout 345-joist hanger outside of entry door 349- strap top plates at back bedroom, correct crushed hvac, protect dryer vent, fireblock dead spaces, structural strap at stairwell wall 351- H2.5s on trusses outside of entry, protect dryer vent 353- complete deck 346-check on wall details tying exterior walls together 348- check engineered truss repair,check corner detail at deck beam of adjacent unit
STAIR TOWER 1
Corrective Action Required
06/22/2022
STAIR TOWER "A"
STAIR TOWER 2
Corrective Action Required
06/22/2022
STAIR TOWER "B"
STAIR TOWER 3
Corrective Action Required
06/22/2022
STAIR TOWER "C" -Provide structural strap at over bored top plate -Firblock dead space
Rated Assembly Inspection Partial 6/23/2022 6/23/2022 06/23/2022
Misc
Informational
06/22/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing
THIRD FLOOR
Corrective Action Required
06/22/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
06/23/2022
FIRST FLOOR
Corrective Action Required
06/23/2022
STAIR TOWER 1
Corrective Action Required
06/23/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 6/24/2022 6/24/2022 06/24/2022
FIRST FLOOR
Corrective Action Required
06/22/2022
SECOND FLOOR
Corrective Action Required
06/22/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
06/22/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
06/22/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
06/22/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
06/22/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 6/28/2022 6/28/2022 06/28/2022
Misc
Informational
06/23/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing
THIRD FLOOR
Corrective Action Required
06/23/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
06/23/2022
AREA “A” -RC CHANNEL AT UNITD AND CORRIDOR CEILINGS ONLY
FIRST FLOOR
Corrective Action Required
06/23/2022
STAIR TOWER 1
Corrective Action Required
06/23/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 6/28/2022 6/28/2022 06/28/2022
FIRST FLOOR
Corrective Action Required
06/24/2022
SECOND FLOOR
Corrective Action Required
06/24/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" 230 -235 OK 241-overbored stud at party wall , fireblock dead space at bathroo, seal top plate penetration, protect dryer duct 24-hvac4-protect dryer duct 243- 244-Protect dryer duct 245-complete hvac 247-protect dryer/structural strap 246-add stud at over bored stud in corridor outside of unit 249-complete rated layer at bath 248-complete pex at shower, Bocca plates at pex, protect dryer duct
THIRD FLOOR
Corrective Action Required
06/24/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
06/24/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
06/24/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
06/24/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 6/29/2022 6/29/2022 06/29/2022
FIRST FLOOR
Corrective Action Required
06/28/2022
SECOND FLOOR
Corrective Action Required
06/28/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
06/28/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
06/28/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
06/28/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
06/28/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 6/30/2022 6/30/2022 06/30/2022
Misc
Informational
06/28/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing
THIRD FLOOR
Corrective Action Required
06/28/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS
SECOND FLOOR
Corrective Action Required
06/28/2022
AREA “A” -RC CHANNEL AT UNITD AND CORRIDOR CEILINGS ONLY
FIRST FLOOR
Corrective Action Required
06/28/2022
STAIR TOWER 1
Corrective Action Required
06/28/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 7/6/2022 7/6/2022 07/06/2022
Misc
Informational
06/30/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -REPAIR RATED CEILING IN CORRIDOR OUTSIDE OF 338 -REPAIR RATED CEILING IN UNITS 338, 340, 341, 342 -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL
THIRD FLOOR
Corrective Action Required
06/30/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED IN CORRECTIONS
SECOND FLOOR
Corrective Action Required
06/30/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDOR CEILINGS ONLY -FIRST LAYER AT BATHROOMS
FIRST FLOOR
Corrective Action Required
06/30/2022
STAIR TOWER 1
Corrective Action Required
06/30/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Failed 7/7/2022 07/07/2022
Misc
Informational
07/06/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -REPAIR RATED CEILING IN CORRIDOR OUTSIDE OF 338 -REPAIR RATED CEILING IN UNITS 338, 340, 341, 342-CUT ROCK FROM MEMBER TO MEMBER AND REPLACE -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/06/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED IN CORRECTIONS
SECOND FLOOR
Corrective Action Required
07/06/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDOR CEILINGS ONLY -FIRST LAYER AT BATHROOMS
FIRST FLOOR
Corrective Action Required
07/06/2022
STAIR TOWER 1
Corrective Action Required
07/06/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Above Ceiling Inspection Partial 7/8/2022 7/8/2022 07/08/2022
FIRST FLOOR
Corrective Action Required
07/08/2022
-AREA "B" AMENITIES SPACE OK FOR PRE ROCK FOR SOFFITS
Rated Assembly Inspection Partial 7/8/2022 7/8/2022 07/08/2022
Misc
Informational
07/07/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/07/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
07/07/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS
FIRST FLOOR
Corrective Action Required
07/07/2022
STAIR TOWER 1
Corrective Action Required
07/07/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 7/11/2022 07/11/2022
Misc
Informational
07/08/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/08/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
07/08/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS
FIRST FLOOR
Corrective Action Required
07/08/2022
STAIR TOWER 1
Corrective Action Required
07/08/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 7/12/2022 7/12/2022 07/12/2022
FIRST FLOOR
Corrective Action Required
06/29/2022
AREA A: Nail structural straps and fire caulk alarm lines throughout 133-incomplete 136-fire caulk fire line and dwv, plate penetrations, nail corner studs, vertical fireblocking 10’ oc at party wall, 135-strap top plate bedroom, caulk plate penetrations bathroom 138-support sec cables, remove bonding screw, fire caulk dwv by panel 140- correct hangers above doorway, support se cable, remove bonding screw, 142-fire caulk pex penetration, complete,protect, pex, fire caulk dwv in bath 137 -complete pex, ire caulk and protect pex 102-103, 105, 106, ok 104 strap top plate, seal penetrations at fire wall 107- address over bored stud at bearing wall
SECOND FLOOR
Corrective Action Required
06/29/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
06/29/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
06/29/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
06/29/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
06/29/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 7/14/2022 7/14/2022 07/14/2022
FIRST FLOOR
Corrective Action Required
07/12/2022
AREA A: Nail structural straps and fire caulk alarm lines throughout 133-incomplete 135-OK 136-vertical fireblocking 10’ oc at party wall, 138-OK 140- support se cable, 142-fire caulk dwv in bath 137 OK 102-107 ok
SECOND FLOOR
Corrective Action Required
07/12/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/12/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/12/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/12/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/12/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 7/15/2022 7/15/2022 07/15/2022
FIRST FLOOR
Corrective Action Required
07/14/2022
AREA A: 133-incomplete 135-OK 136-vertical fireblocking 10’ oc at party wall- SEAL PENETRATIONS 138-OK 140- support se cable, 142-OK 137 OK 102-107 ok
SECOND FLOOR
Corrective Action Required
07/14/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/14/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/14/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/14/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/14/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 7/19/2022 7/19/2022 07/19/2022
Misc
Informational
07/11/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/11/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS
SECOND FLOOR
Corrective Action Required
07/11/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS
FIRST FLOOR
Corrective Action Required
07/11/2022
STAIR TOWER 1
Corrective Action Required
07/11/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 7/19/2022 07/19/2022
FIRST FLOOR
Corrective Action Required
07/15/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete
SECOND FLOOR
Corrective Action Required
07/15/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/15/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/15/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/15/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/15/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 7/20/2022 7/20/2022 07/20/2022
FIRST FLOOR
Corrective Action Required
07/19/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete
SECOND FLOOR
Corrective Action Required
07/19/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/19/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” 313 ok 355-fire block ceiling line at bed 357- fire block ceiling line at bed, 352-add stud in corridor wall-stud over bored 359-ok 354-ok 361-strap at dryer duct, fire caulk dead space, address broken truss at back bed exterior wall, h2.5 at master closet 356-secure sec at panel 363- fireblocking at ceiling line bedroom, add stud st corridor wall 315-ok 358-ok 316-ok 365-fireblock ceiling line at bed 317-ok 318-ok 360-seal gaps at vertical fireblocking, fireblock at ceiling line, h2.5s at load bearing wall 319-324-ok 367-strap at dryer vent,
STAIR TOWER 1
Corrective Action Required
07/19/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/19/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/19/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 7/21/2022 7/21/2022 07/21/2022
FIRST FLOOR
Corrective Action Required
07/20/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete
SECOND FLOOR
Corrective Action Required
07/20/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/20/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED BELOW: 361-strap at dryer duct, address broken truss in master, missing h2.5 in master closet 367-strap at dryer duct
STAIR TOWER 1
Corrective Action Required
07/20/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/20/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/20/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 7/21/2022 7/21/2022 07/21/2022
Misc
Informational
07/19/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/19/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS
SECOND FLOOR
Corrective Action Required
07/19/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED: 242- COMPLETE ROCK AND SCREW PATTERN AT CORRIDOR WALL 237-MISSING SCREWS AT CEILING IN LAUNDRY AND BATH AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS
FIRST FLOOR
Corrective Action Required
07/19/2022
AREA "A" -COMPLETE RC, SUPPORT RC AT ENDS, PROVIDE MISSING SCREWS
STAIR TOWER 1
Corrective Action Required
07/19/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 7/22/2022 7/22/2022 07/22/2022
Misc
Informational
07/21/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/21/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS
SECOND FLOOR
Corrective Action Required
07/21/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS
FIRST FLOOR
Corrective Action Required
07/21/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/21/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 7/26/2022 7/26/2022 07/26/2022
Misc
Informational
07/22/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/22/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
07/22/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN
FIRST FLOOR
Corrective Action Required
07/22/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/22/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 7/27/2022 7/27/2022 07/27/2022
FIRST FLOOR
Corrective Action Required
07/21/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete
SECOND FLOOR
Corrective Action Required
07/21/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/21/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/21/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/21/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/21/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 7/28/2022 7/28/2022 07/28/2022
FIRST FLOOR
Corrective Action Required
07/27/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete
SECOND FLOOR
Corrective Action Required
07/27/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” 210-Strap over bored load bearing walls, repair draft stop at separation wall 251-Fireblock ceiling line at dead space corner, fire caulk cop, 250-straps at over bored top plates, fireblocking at ceiling line, add stud at south wall bathroom 253-structural strap at over bored top plate in kitchen and laundry, add stud at bathroom wall 252-strap top plate, protect n, Bocca at hot water in bedroom 255-bonding screw and jumper in bath, add stud in bath, fire caulk dwv in dead space 254-strap over bored plate at laundry, add studs at bath 257-seal dead space at bath, stud at bath 256-strap top plate at closet, 259-strap over bored top plate at kitchen and laundry, quash block at bedroom, 258-strap top plate at kitchen,protect sprinkler pipe at laundry 215-ok 216-overbored top plate 216-ok 261-missing nails at joist hanger in bedroom by window, straps at over bored top plates at bathroom 218- strap plates lapped less than 48” 260- protect nm at kitchen/bed, strap top plates in bedrooms lapped less than 48”, fire caulk dead space, strap and stud at laundry wall over bored top plate 219,220,221,222,223,224-ok 263-Add stud at laundry and bath South corridor at stair d-fireblock ceiling line
THIRD FLOOR
Corrective Action Required
07/27/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/27/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/27/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/27/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 7/29/2022 7/29/2022 07/29/2022
Misc
Informational
07/26/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/26/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
07/26/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
FIRST FLOOR
Corrective Action Required
07/26/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/26/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 8/2/2022 8/2/2022 08/02/2022
Misc
Informational
07/29/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
07/29/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
07/29/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
FIRST FLOOR
Corrective Action Required
07/29/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN
STAIR TOWER 1
Corrective Action Required
07/29/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 8/2/2022 8/2/2022 08/02/2022
FIRST FLOOR
Corrective Action Required
07/28/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete
SECOND FLOOR
Corrective Action Required
07/28/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
07/28/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
07/28/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
07/28/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
07/28/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 8/5/2022 8/5/2022 08/05/2022
Misc
Informational
08/02/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
08/02/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
08/02/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
FIRST FLOOR
Corrective Action Required
08/02/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
STAIR TOWER 1
Corrective Action Required
08/02/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 8/8/2022 8/8/2022 08/08/2022
FIRST FLOOR
Corrective Action Required
08/02/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete AREA C -Correct penetrations in shaft wall -Seal draft stop penetrations at elevator -147-fireblock corner of laundry ceiling line, secure sec in laundry,seal plate at bed and shaft liner, address holes bored in truss at entry 150-secure nm at back of elevator, seal top plate penetrations at mechanical room wall, anchor bolts at exterior walls?, protect dryer duct at blocking, remove bonding screw, address studs over bored at laundry, 149-add nails at strap in laundry, strap top plates at patio corner, plate penetration at thermostat wire, 152-seal draft stop, remove bonding screw at laundry, strap top plates in bedroom, address constricted deflection duct in living room, 151-remove bonding screw, strap top plate at common wall bedroom 154-ok 153-ok 156-.protect pex at laundry, protect nm at bedroom, add stud at bathroom, secure pex at laundry 158-ok 157- fire caulk pex, protect dryer duct, 169-protect nm at corner in bed, nail hangers at stairwell wall, fireblocking ceiling line and draft stop in back bed, protect dryer duct 159 not ready 115-120- ok
SECOND FLOOR
Corrective Action Required
08/02/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/02/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/02/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
08/02/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
08/02/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 8/10/2022 8/10/2022 08/10/2022
Misc
Informational
08/05/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
08/05/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
08/05/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
FIRST FLOOR
Corrective Action Required
08/05/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
STAIR TOWER 1
Corrective Action Required
08/05/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 8/12/2022 8/12/2022 08/12/2022
Misc
Informational
08/10/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
08/10/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS
SECOND FLOOR
Corrective Action Required
08/10/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS
FIRST FLOOR
Corrective Action Required
08/10/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED
STAIR TOWER 1
Corrective Action Required
08/10/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 8/12/2022 8/12/2022 08/12/2022
FIRST FLOOR
Corrective Action Required
08/08/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall -147-fireblock corner of laundry ceiling line -159 not ready
SECOND FLOOR
Corrective Action Required
08/08/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/08/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/08/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
08/08/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
08/08/2022
STAIR TOWER "C" -3RD FLOOR OK
All Rough Inspection - Commercial Partial 8/23/2022 8/23/2022 08/23/2022
FIRST FLOOR
Corrective Action Required
08/12/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall -147-fireblock corner of laundry ceiling line -159 not ready AREA B Outside of 148- nail stud shoes, missing hanger at entry, 148-seal plate penetration at dryer duct, support dwv, anchor sill plate, 145-seal draft stop, anchor sill plates, support sec, fire caulk pex in corridor, nail stud shoes 146-protect nm under bed window, anchor sill plate, seal top plate penetration in corridor 143-support sec throughout support/secure pex in attic spaces, anchor sill plates, protect nm at living room, 141-seal draft at corridor, anchor sill plate, seal penetration at sec, strap top plates, secure AC, support AC in joist space, seal penetrations and support pex at shower Amenities- midpoint strap dwv, nail hangers, anchor sill plate, seal gaps at mailboxes, complete pex at pet wash, seal top plate at storages, secure nm in ceilings within 12” of boxes, draft stop at bike storage, seal top plate at exit doors, address penetrations at shaft wall, plate penetrations at locker room and support dwv 144-Bocca plate at corridor, strap top plate in bedroom, seal penetrations at laundry
SECOND FLOOR
Corrective Action Required
08/12/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/12/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/12/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
08/12/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
08/12/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 8/24/2022 8/24/2022 08/24/2022
Misc
Informational
08/12/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
08/12/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT UNITS
SECOND FLOOR
Corrective Action Required
08/12/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS
FIRST FLOOR
Corrective Action Required
08/12/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS- MISSING PIECES AT CORRIDOR SPRINKLER HEADS AND AT UNITS BY MECHANICAL
STAIR TOWER 1
Corrective Action Required
08/12/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
Rated Assembly Inspection Partial 8/25/2022 8/25/2022 08/25/2022
Misc
Informational
08/24/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
08/24/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT UNITS
SECOND FLOOR
Corrective Action Required
08/24/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST LAYER AT UNITS
FIRST FLOOR
Corrective Action Required
08/24/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/24/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 8/25/2022 8/25/2022 08/25/2022
FIRST FLOOR
Corrective Action Required
08/23/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall -147-fireblock corner of laundry ceiling line -159 not ready AREA B 148-support dwv 145-support sec, corridor, nail stud shoes 146-OK 143-support sec, protect nm at living room, 141-seal penetration at sec, secure AC AND NM IN STUD SPACE Amenities- midpoint strap dwv, seal gaps at mailboxes, -Address penetrations at shaft wall, plate penetrations at locker room and support dwv 144-Bocca plate at corridor
SECOND FLOOR
Corrective Action Required
08/23/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/23/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/23/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
08/23/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
08/23/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 8/26/2022 8/26/2022 08/26/2022
Misc
Informational
08/25/2022
-3rd party inspector to verify and document nailing pattern at exterior sheathing -SUPPORT RC CHANNEL AT 2ND FLOOR CORRIDOR WALLS AT EACH END, PROTECT ALL DWV AND DRYER DUCT WITHIN 1.25" OF FACE OF RC CHANNEL-ALL LOCATIONS
THIRD FLOOR
Corrective Action Required
08/25/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
08/25/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
08/25/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/25/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 8/26/2022 8/26/2022 08/26/2022
FIRST FLOOR
Corrective Action Required
08/25/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS EXCEPT AS NOTED: 133-incomplete AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall -147-fireblock corner of laundry ceiling line -159 not ready AREA B -COMPLETE
SECOND FLOOR
Corrective Action Required
08/25/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/25/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/25/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
08/25/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
08/25/2022
STAIR TOWER "C" -3RD FLOOR OK
Rated Assembly Inspection Partial 8/31/2022 8/31/2022 08/31/2022
Misc
Informational
08/26/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
08/26/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
08/26/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
08/26/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN EXCEPT AS NOTED: *147- PATCH HOLES AT TOP PLATES *156- ROCK TO CONTINUE THROUGH ASSEMBLY
STAIR TOWER 1
Corrective Action Required
08/26/2022
STAIR TOWER "A" -RC CHANNEL AT CEILING AND THIRD FLOOR LANDING
All Rough Inspection - Commercial Partial 8/31/2022 8/31/2022 08/31/2022
FIRST FLOOR
Corrective Action Required
08/26/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall -147-fireblock corner of laundry ceiling line -159 not ready AREA B -COMPLETE
SECOND FLOOR
Corrective Action Required
08/26/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/26/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/26/2022
STAIR TOWER "A" -3RD FLOOR OK
STAIR TOWER 2
Corrective Action Required
08/26/2022
STAIR TOWER "B" -3RD FLOOR OK
STAIR TOWER 3
Corrective Action Required
08/26/2022
STAIR TOWER "C" -3RD FLOOR OK
Electrical Service Inspection Failed 9/1/2022 9/1/2022 09/01/2022
Misc
Corrective Action Required
09/01/2022
-Connect grounding electrode system to neutral -Connect water service pipe to grounding electrode system -Provide (2) 5/8" ground rods 6' apart -Provide address at disconnect and meters
Rated Assembly Inspection Partial 9/1/2022 9/1/2022 09/01/2022
Misc
Informational
08/31/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
08/31/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
08/31/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
08/31/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN
STAIR TOWER 1
Corrective Action Required
08/31/2022
STAIR TOWER "A" -Complete RC channel, add missing screws, seal gaps in vertical fire stopping, secure and protect condensate line at third floor landing, seal penetration at condensate line
STAIR TOWER 2
Corrective Action Required
09/01/2022
STAIR TOWER "B"
STAIR TOWER 3
Corrective Action Required
09/01/2022
STAIR TOWER "C"
All Rough Inspection - Commercial Partial 9/1/2022 9/1/2022 09/01/2022
FIRST FLOOR
Corrective Action Required
08/31/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall AREA B -COMPLETE
SECOND FLOOR
Corrective Action Required
08/31/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
08/31/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
08/31/2022
STAIR TOWER "A" -OK
STAIR TOWER 2
Corrective Action Required
08/31/2022
STAIR TOWER "B"
STAIR TOWER 3
Corrective Action Required
08/31/2022
STAIR TOWER "C"
Rated Assembly Inspection Partial 9/2/2022 9/2/2022 09/02/2022
Misc
Informational
09/01/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/01/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/01/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/01/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN - 9/2/22 2ND LAYER SCREW PATTERN UNITS 149,151,152,153,154,155,156,157,158,, 160 - AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR
STAIR TOWER 1
Corrective Action Required
09/01/2022
STAIR TOWER "A" - RC channel APPROVED -
STAIR TOWER 2
Corrective Action Required
09/01/2022
STAIR TOWER "B"
STAIR TOWER 3
Corrective Action Required
09/01/2022
STAIR TOWER "C"
Rated Assembly Inspection Partial 9/7/2022 09/07/2022
Misc
Informational
09/02/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/02/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/02/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/02/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN - 9/2/22 2ND LAYER SCREW PATTERN UNITS 149,151,152,153,154,155,156,157,158,, 160 - AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR
STAIR TOWER 1
Corrective Action Required
09/02/2022
STAIR TOWER "A" - RC channel APPROVED -
STAIR TOWER 2
Corrective Action Required
09/02/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/02/2022
STAIR TOWER "C" RC CHANNEL APPROVED
All Rough Inspection - Commercial Failed 9/7/2022 9/7/2022 09/07/2022
FIRST FLOOR
Corrective Action Required
09/01/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall AREA B -COMPLETE
SECOND FLOOR
Corrective Action Required
09/01/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
09/01/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
09/01/2022
STAIR TOWER "A" -OK
STAIR TOWER 2
Corrective Action Required
09/01/2022
STAIR TOWER "B" 1ST FLOOR NAIL HANGER NW CORNER FIRE CAULK CONDUCTORS BOTH SIDES BETWEEN DOOR & STAIRS NAIL JOIST HANGER UNDER STAIR LANDING
STAIR TOWER 3
Corrective Action Required
09/01/2022
STAIR TOWER "C" 2ND FLOOR LANDING NAIL JOIST HANGER 3RD FLOOR NAIL H2.5 SE CORNER
Electrical Service Inspection Failed 9/7/2022 9/7/2022 09/07/2022
Misc
Informational
09/07/2022
-Provide address at disconnect and meters - PANEL H22 HAS TWO METERS LABELED # 157 PANEL H2A HOUSE,MAINTENANCE,133,135,136,137,138,140, 142,235,236,237,238,239,240,336,338,339,340,341,342,343, PANEL H22 HOUSE, 135,149,151,152,155,156,157, ?157? 158,160, 252,253,255,257,259,261,263,256,258,260, ,352,354,356,357,358,359,360,361,363,365,367,
Rated Assembly Inspection Partial 9/9/2022 9/9/2022 09/09/2022
Misc
Informational
09/07/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/07/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/07/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/07/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN - 9/2/22 2ND LAYER SCREW PATTERN UNITS 149,151,152,153,154,155,156,157,158,, 160 - AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR
STAIR TOWER 1
Corrective Action Required
09/07/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/07/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/07/2022
STAIR TOWER "C" RC CHANNEL APPROVED
STAIR TOWER 4
Corrective Action Required
09/09/2022
STAIR "D"
All Rough Inspection - Commercial Failed 9/9/2022 9/9/2022 09/09/2022
FIRST FLOOR
Corrective Action Required
09/07/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall AREA B -COMPLETE
SECOND FLOOR
Corrective Action Required
09/07/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
09/07/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
09/07/2022
STAIR TOWER "A" -OK
STAIR TOWER 2
Corrective Action Required
09/07/2022
STAIR TOWER "B" ALL ROUGH APPROVED
STAIR TOWER 3
Corrective Action Required
09/07/2022
STAIR TOWER "C" ALL ROUGH APPROVED
STAIR TOWER 4
Corrective Action Required
09/09/2022
STAIR TOWER "D" PROVIDE H2.5S OR TRUSS LOK SCREWS @ EXTERIOR WALL
Electrical Service Inspection Partial 9/9/2022 9/9/2022 09/09/2022
Misc
Informational
09/07/2022
-Provide address at disconnect and meters PARTIAL PASS ONE MORE METER BANK TO COMPLETE PANEL H2A HOUSE,MAINTENANCE,133,135,136,137,138,140, 142,235,236,237,238,239,240,254,336,338,339,340,341,342,343, PANEL H22 HOUSE, 135,149,151,152,153,154,155,156,157, 158,159,160, 252,253,255,257,259,261,263,256,258,260, ,352,354,356,357,358,359,360,361,363,365,367,
Rated Assembly Inspection Partial 9/12/2022 9/12/2022 09/12/2022
Misc
Informational
09/09/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/09/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/09/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/09/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS - 9/2/22 2ND LAYER SCREW PATTERN UNITS 149,151,152,153,154,155,156,157,158,, 160 - AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR
STAIR TOWER 1
Corrective Action Required
09/09/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/09/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/09/2022
STAIR TOWER "C" RC CHANNEL APPROVED
STAIR TOWER 4
Corrective Action Required
09/09/2022
STAIR "D"
All Rough Inspection - Commercial Partial 9/13/2022 9/13/2022 09/13/2022
FIRST FLOOR
Corrective Action Required
09/09/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall AREA B -COMPLETE
SECOND FLOOR
Corrective Action Required
09/09/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Corrective Action Required
09/09/2022
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Corrective Action Required
09/09/2022
STAIR TOWER "A" -OK
STAIR TOWER 2
Corrective Action Required
09/09/2022
STAIR TOWER "B" ALL ROUGH APPROVED
STAIR TOWER 3
Corrective Action Required
09/09/2022
STAIR TOWER "C" ALL ROUGH APPROVED
STAIR TOWER 4
Corrective Action Required
09/09/2022
STAIR TOWER "D" ALL ROUGH APPROVED
Rated Assembly Inspection Partial 9/13/2022 9/13/2022 09/13/2022
Misc
Informational
09/12/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/12/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/12/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/12/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS - 9/2/22 2ND LAYER SCREW PATTERN UNITS 149,151,152,153,154,155,156,157,158,, 160 - AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR -FIRST LAYER SCREW PATTERN
STAIR TOWER 1
Corrective Action Required
09/12/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/12/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/12/2022
STAIR TOWER "C" RC CHANNEL APPROVED FIRST LAYER SCREW PATTERN OK AT WALLS -COMPLETE FIRST LAYER AT ROOF ACCESS LADDER
STAIR TOWER 4
Corrective Action Required
09/12/2022
STAIR "D" RC CHANNEL APPROVED
Rated Assembly Inspection Partial 09/15/2022
Misc
Informational
09/13/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/13/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/13/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/13/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED: LOBBY, 109A, 109B INCOMPLETE
STAIR TOWER 1
Corrective Action Required
09/13/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/13/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/13/2022
STAIR TOWER "C" RC CHANNEL APPROVED FIRST, SECOND LAYER SCREW PATTERN OK AT WALLS -COMPLETE FIRST LAYER AT ROOF ACCESS LADDER
STAIR TOWER 4
Corrective Action Required
09/13/2022
STAIR "D" RC CHANNEL APPROVED
Rated Assembly Inspection Partial 9/27/2022 9/27/2022 09/27/2022
Misc
Informational
09/15/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/15/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/15/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/15/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED: LOBBY, 109A, 109B INCOMPLETE
STAIR TOWER 1
Corrective Action Required
09/15/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/15/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/15/2022
STAIR TOWER "C" RC CHANNEL APPROVED FIRST, SECOND LAYER SCREW PATTERN OK AT WALLS -COMPLETE FIRST LAYER AT ROOF ACCESS LADDER
STAIR TOWER 4
Corrective Action Required
09/15/2022
STAIR "D" RC CHANNEL APPROVED
Electrical Service Inspection Failed 9/27/2022 9/27/2022 09/27/2022
Misc
Informational
09/09/2022
-Provide address at disconnect and meters PARTIAL PASS ONE MORE METER BANK TO COMPLETE PANEL H2A HOUSE,MAINTENANCE,133,135,136,137,138,140, 142,235,236,237,238,239,240,254,336,338,339,340,341,342,343, PANEL H22 HOUSE, 135,149,151,152,153,154,155,156,157, 158,159,160, 252,253,255,257,259,261,263,256,258,260, ,352,354,356,357,358,359,360,361,363,365,367,
Misc
Corrective Action Required
09/27/2022
H2 B- -CONNECT METALLIC WATER PIPING TO GROUNDING ELECTRODE SYSTEM -PROVIDE PROPER, LISTED CLAMP FOR UFER
Rated Assembly Inspection Failed 9/28/2022 9/28/2022 09/28/2022
Misc
Informational
09/27/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/27/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/27/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/27/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED: LOBBY, 109A, 109B INCOMPLETE
STAIR TOWER 1
Corrective Action Required
09/27/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/27/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/27/2022
STAIR TOWER "C" RC CHANNEL APPROVED FIRST, SECOND LAYER SCREW PATTERN OK AT WALLS -COMPLETE FIRST LAYER AT ROOF ACCESS LADDER
STAIR TOWER 4
Corrective Action Required
09/27/2022
STAIR "D" RC CHANNEL APPROVED -9/28/22 SCREW PATTERN INCOMPLETE
Rated Assembly Inspection Partial 9/29/2022 9/29/2022 09/29/2022
Misc
Informational
09/28/2022
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Corrective Action Required
09/28/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Corrective Action Required
09/28/2022
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Corrective Action Required
09/28/2022
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED: LOBBY, 109A, 109B INCOMPLETE
STAIR TOWER 1
Corrective Action Required
09/28/2022
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Corrective Action Required
09/28/2022
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Corrective Action Required
09/28/2022
STAIR TOWER "C" RC CHANNEL APPROVED FIRST, SECOND LAYER SCREW PATTERN OK AT WALLS -COMPLETE FIRST LAYER AT ROOF ACCESS LADDER
STAIR TOWER 4
Corrective Action Required
09/28/2022
STAIR "D" RC CHANNEL APPROVED SCREW PATTERN
Electrical Service Inspection Failed 9/30/2022 9/30/2022 09/30/2022
Misc
Informational
09/27/2022
-Provide address at disconnect and meters PARTIAL PASS ONE MORE METER BANK TO COMPLETE PANEL H2A HOUSE,MAINTENANCE,133,135,136,137,138,140, 142,235,236,237,238,239,240,254,336,338,339,340,341,342,343, PANEL H22 HOUSE, 135,149,151,152,153,154,155,156,157, 158,159,160, 252,253,255,257,259,261,263,256,258,260, ,352,354,356,357,358,359,360,361,363,365,367,
Misc
Corrective Action Required
09/27/2022
Clarify repeating unit numbers : PANEL H2B HOUSE, 141,143,144,145,146,148,149**,150, 241,243,244,245,246,24,248,249,250,253 343**,344,345,346,348,349,350,351,353,355
Electrical Service Inspection Passed 10/3/2022 10/3/2022 10/03/2022
Misc
Informational
09/30/2022
3 SERVICES FOR BUILDING 2150 PANEL H2A HOUSE,MAINTENANCE,133,135,136,137,138,140,142 235,236,237,238,239,240,254 336,338,339,340,341,342,343, PANEL H22 HOUSE, 135,149,151,152,153,154,155,156,157,158,159,160, 252,253,255,256,257,258,259,261,260,263 352,354,356,357,358,359,360,361,363,365,367 PANEL H2B HOUSE, 141,143,144,145,146,148,150, 241,243,244,245,246,247,248,249,250,251,253 344,345,346,347,348,349,350,351,353,355
Misc
Resolved
10/03/2022
Miscellaneous Inspection Failed 12/13/2022 12/13/2022 12/13/2022
Misc
Corrective Action Required
12/13/2022
***Pre Final units 1A —Throughout: -Remove covers and install all sprinkler escutcheons interior and exterior -Ensure secondary lock at SGDs is operable -Extend box at master bath mirrors to within 1/4” of finish -Seal all gaps and penetrations at mechanical room ceilings 12/13/22 units inspected: 133-complete throughout items, provide panel schedule 136-Complete throughout items, latches at SGD 135-Throughout items, secondary latch at SGD, loose receptacle at bath
Miscellaneous Inspection Partial 12/20/2022 12/20/2022 12/20/2022
Misc
Corrective Action Required
12/13/2022
***Pre Final units 1A —Throughout: -Remove covers and install all sprinkler escutcheons interior and exterior -Ensure secondary lock at SGDs is operable -Extend box at master bath mirrors to within 1/4” of finish -Seal all gaps and penetrations at mechanical room ceilings 12/13/22 units inspected: 133-complete throughout items, provide panel schedule 136-Complete throughout items, latches at SGD 135-Throughout items, secondary latch at SGD, loose receptacle at bath 12/20/22 3 Floor building A-B Units only Provide combo smoke/co detector outside of second bedrooms throughout 336-Seal penetration at mechanical, spark ring at mirror, lockout for water heater 339- seal penetration at mechanical, spark ring at mirror, lockout at water heater breaker 341-open box/ gfci at island, correct flange at mechanical ceiling 338-ok 340 342-spark ring at mirror,sprinkler head/escutcheon 343-spark ring at mirror, sprinkler head/ escutcheon at deck, seal duct penetration in mechanical B (partial) 345-breaker 11 won’t trip, spark ring at mirror, complete exterior 344-Correct duct flange at mechanical, spark ring at mirror, 347-anti tip device at range, spark ring at mirror 349-seal penetrations, spark ring at mirrors 351-spark rings at mirror
Miscellaneous Inspection Failed 12/21/2022 12/21/2022 12/21/2022
Misc
Corrective Action Required
12/20/2022
***Pre Final units 1A —Throughout: -Remove covers and install all sprinkler escutcheons interior and exterior -Ensure secondary lock at SGDs is operable -Extend box at master bath mirrors to within 1/4” of finish -Seal all gaps and penetrations at mechanical room ceilings 12/13/22 units inspected: 133-complete throughout items, provide panel schedule 136-Complete throughout items, latches at SGD 135-Throughout items, secondary latch at SGD, loose receptacle at bath 12/20/22 3 Floor building A-B Units only Provide combo smoke/co detector outside of second bedrooms throughout 336-Seal penetration at mechanical, spark ring at mirror, lockout for water heater 339- seal penetration at mechanical, spark ring at mirror, lockout at water heater breaker 341-open box/ gfci at island, correct flange at mechanical ceiling 338-ok 340 342-spark ring at mirror,sprinkler head/escutcheon 343-spark ring at mirror, sprinkler head/ escutcheon at deck, seal duct penetration in mechanical B (partial) 345-breaker 11 won’t trip, spark ring at mirror, complete exterior 344-Correct duct flange at mechanical, spark ring at mirror, 347-anti tip device at range, spark ring at mirror 349-seal penetrations, spark ring at mirrors 351-spark rings at mirror
SECOND FLOOR
Corrective Action Required
12/21/2022
All units need GFCI at laundry wall receptacle South side 250,253- ,252- ,255- ,253-,254-,257,256, 259, 262,263, 261-not ready. North of fire doors. 248- 245 not ready 243,51,50, 244 lockout for breaker. ,39,40,42,47, 241- 246 locked 236,6,7,8,40, No lag bolts at deck ledgers
Miscellaneous Inspection Partial 12/30/2022 12/30/2022 12/30/2022
Misc
Corrective Action Required
12/21/2022
***Pre Final units 1A —Throughout: -Remove covers and install all sprinkler escutcheons interior and exterior -Ensure secondary lock at SGDs is operable -Extend box at master bath mirrors to within 1/4” of finish -Seal all gaps and penetrations at mechanical room ceilings -Provide smoke detector outside of second bedrooms throughout 12/13/22 units inspected: 133-complete throughout items, provide panel schedule 136-Complete throughout items, latches at SGD 135-Throughout items, secondary latch at SGD, loose receptacle at bath 2ND FLOOR: A 236-ok 235-ok 237-GfCI at laundry 238-GFCI at laundry 240-GFCI at laundry 242-GFCI at laundry, 239-GFCi at laundry B 241-GFCI at laundry 244-ok 243-GFCI at laundry 245-ok 247-GFCI at laundry, caulk behind hvac 246-GFCI at laundry, sprinkler escutcheon at bedroom 249-GFCI at laundry, 248-OK 3 Floor building A-B Units only A 336-Seal penetration at mechanical, spark ring at mirror, lockout for water heater 339- seal penetration at mechanical, spark ring at mirror, lockout at water heater breaker 341-open box/ gfci at island, correct flange at mechanical ceiling 338-ok 340 342-spark ring at mirror,sprinkler head/escutcheon 343-spark ring at mirror, sprinkler head/ escutcheon at deck, seal duct penetration in mechanical B (partial) 345-breaker 11 won’t trip, spark ring at mirror, complete exterior 344-Correct duct flange at mechanical, spark ring at mirror, 347-anti tip device at range, spark ring at mirror 349-seal penetrations, spark ring at mirrors 351-spark rings at mirror
SECOND FLOOR
Resolved
12/30/2022
Miscellaneous Inspection Partial 1/3/2023 1/3/2023 01/03/2023
Misc
Corrective Action Required
12/30/2022
***Pre Final units only 1A —Throughout: -Remove covers and install all sprinkler escutcheons interior and exterior -Ensure secondary lock at SGDs is operable -Extend box at master bath mirrors to within 1/4” of finish -Seal all gaps and penetrations at mechanical room ceilings -Provide smoke detector outside of second bedrooms throughout 12/13/22 units inspected: 133-complete throughout items, provide panel schedule 136-Complete throughout items, latches at SGD 135-Throughout items, secondary latch at SGD, loose receptacle at bath 2ND FLOOR: A -OK B 247-caulk behind hvac 3rd Floor A -OK B 347-anti tip device at range 353-GFCI at exterior 348-GFCI at exterior
Miscellaneous Inspection Partial 1/4/2023 1/4/2023 01/04/2023
Misc
Corrective Action Required
01/03/2023
***Pre Final units only 1A —Throughout: -Remove covers and install all sprinkler escutcheons interior and exterior -Ensure secondary lock at SGDs is operable -Extend box at master bath mirrors to within 1/4” of finish -Seal all gaps and penetrations at mechanical room ceilings -Provide smoke detector outside of second bedrooms throughout 12/13/22 units inspected: 133-complete throughout items, provide panel schedule 136-Complete throughout items, latches at SGD 135-Throughout items, secondary latch at SGD, loose receptacle at bath 2ND FLOOR: A -OK B -OK 3rd Floor A -OK B 347-anti tip device at range C 355-Correct collar at hvac 354-Anti tip device at range, correct collar at hvac, seal penetration, exterior GFCI 356-Seal hvac penetration
Miscellaneous Inspection Partial 1/5/2023 1/5/2023 01/05/2023
Misc
Corrective Action Required
01/04/2023
***Pre Final units only 1st Floor: A —Throughout: ADDRESS EXTERIOR LIGHTING PER SECURITY CODE 141-Repair rated assembly at ceiling and stairwell B 148-Clarify unit type A or B for accessible unit, provide adjustable height hand shower 2ND FLOOR: A -OK B -OK 3rd Floor A -OK B 347-anti tip device at range C 355-Correct collar at hvac 354-Anti tip device at range, correct collar at hvac, seal penetration, exterior GFCI 356-Seal hvac penetration
Piers/Caissons Inspection - Commercial Passed 1/6/2023 01/06/2023
Miscellaneous Inspection Partial 1/6/2023 1/6/2023 01/06/2023
Misc
Corrective Action Required
01/05/2023
***Pre Final units only 1st Floor: A 141-Repair rated assembly at ceiling and stairwell B 148-provide adjustable height hand shower and grab bars at ADA bath C 153-GFCI at patio 150-Anti tip device at range 152-Hanger nails at deck 154-Smoke detector cover, exterior GFCI 156-Hanger nails at deck 158-Anti tip device at range 2ND FLOOR: A -OK B -OK C 251-Exterior GFCI 252-Hanger nails at deck 256-Seal penetration at line set through floor 257-Seal hvac penetration 261-Complete electrical 3rd Floor A -OK B 347-anti tip device at range C 355-Correct collar at hvac 354-Anti tip device at range, correct collar at hvac, seal penetration, exterior GFCI 356-Seal hvac penetration
Alarm Test Not Ready 1/10/2023 01/11/2023
Sprinkler - Flow Test Passed 1/10/2023 01/11/2023
Sprinkler - Hydrostatic Test Passed 7/5/2022 01/11/2023
Miscellaneous Inspection Partial 1/17/2023 1/17/2023 01/17/2023
Misc
Corrective Action Required
01/06/2023
***Pre Final units only 1st Floor: A 141-Repair rated assembly at ceiling and stairwell B 148-provide adjustable height hand shower and grab bars at ADA bath C 153-GFCI at patio 150-Anti tip device at range 152-Hanger nails at deck 154-Smoke detector cover, exterior GFCI 156-Hanger nails at deck 158-Anti tip device at range 2ND FLOOR: A -OK B -OK C 251-Exterior GFCI 252-Hanger nails at deck 256-Seal penetration at line set through floor 257-Seal hvac penetration 261-Complete electrical 3rd Floor A -OK B 347-anti tip device at range C 355-Correct collar at hvac 354-Anti tip device at range, correct collar at hvac, seal penetration, exterior GFCI 356-Seal hvac penetration ROOFTOP- -Remove cap from vent pipes -Label all disconnects -Secure all electrical per code -Remove trash and materials
Miscellaneous Inspection Passed 1/18/2023 1/18/2023 01/18/2023
Rated Assembly Inspection Passed 01/18/2023
Misc
Resolved
01/18/2023
-SEAL THROUGH PENETRATIONS AT CORRIDORS WITH APPROVED METHODS AT FIRST FLOOR SHAFT WALLS
THIRD FLOOR
Resolved
01/18/2023
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -1ST LAYER AT BATHROOM WALLS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "B" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST,SECOND LAYER AT STAIRWELL UNIT SIDE AND BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS AREA "C" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
SECOND FLOOR
Resolved
01/18/2023
AREA “A” -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER AT BATHROOMS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA " B": -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C": -RC AT UNITS AND CORRIDORS -FIRST, SECOND LAYER AT UNITS AND CORRIDOR
FIRST FLOOR
Resolved
01/18/2023
AREA "A" -RC CHANNEL AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "C" -RC AT UNITS AND CORRIDORS -FIRST LAYER SCREW PATTERN ALL UNITS -SCREW PATTERN AT UNITS AND CORRIDORS APPROVED AREA "B" RC UNITS 141,143,144,145,146,148,153 PET WASH, LOBBY,BICYCLE STORAGE,STORAGE LOCKERS,CORRIDOR -FIRST LAYER SCREW PATTERN -SCREW PATTERN AT UNITS AND CORRIDORS EXCEPT AS NOTED: LOBBY, 109A, 109B INCOMPLETE
STAIR TOWER 1
Resolved
01/18/2023
STAIR TOWER "A" - RC channel APPROVED - - 1ST, 2ND LAYER TYPE X SCREW PATTERN APPROVED
STAIR TOWER 2
Resolved
01/18/2023
STAIR TOWER "B" RC CHANNEL APPROVED
STAIR TOWER 3
Resolved
01/18/2023
STAIR TOWER "C" RC CHANNEL APPROVED FIRST, SECOND LAYER SCREW PATTERN OK AT WALLS -COMPLETE FIRST LAYER AT ROOF ACCESS LADDER
STAIR TOWER 4
Resolved
01/18/2023
STAIR "D" RC CHANNEL APPROVED SCREW PATTERN
Above Ceiling Inspection Passed 01/18/2023
FIRST FLOOR
Resolved
01/18/2023
-AREA "B" AMENITIES SPACE OK FOR PRE ROCK FOR SOFFITS
All Rough Inspection - Commercial Passed 01/18/2023
FIRST FLOOR
Resolved
01/18/2023
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA C UNITS AND CORRIDORS APPROVED EXCEPT AS NOTED -Correct penetrations in shaft wall AREA B -COMPLETE
SECOND FLOOR
Resolved
01/18/2023
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
THIRD FLOOR
Resolved
01/18/2023
THE FOLLOWING AREAS ARE APPROVED: AREA "A" UNITS AND CORRIDORS AREA "B" UNITS AND CORRIDORS AREA “C” UNITS AND CORRIDORS
STAIR TOWER 1
Resolved
01/18/2023
STAIR TOWER "A" -OK
STAIR TOWER 2
Resolved
01/18/2023
STAIR TOWER "B" ALL ROUGH APPROVED
STAIR TOWER 3
Resolved
01/18/2023
STAIR TOWER "C" ALL ROUGH APPROVED
STAIR TOWER 4
Resolved
01/18/2023
STAIR TOWER "D" ALL ROUGH APPROVED
Alarm Test Passed 1/18/2023 01/18/2023
Corrective Action Required
01/18/2023
Add strobe sunder bases to ADA rooms. Item to be checked on final.
Occupancy Inspection - Planning Temporary C of O 1/23/2023 1/23/2023 01/23/2023
Misc
Corrective Action Required
01/23/2023
Complete parking lot lighting installation per approved plan.
Misc
Corrective Action Required
01/23/2023
Complete landscaping per approved plan.
Misc
Corrective Action Required
01/23/2023
Install ADA parking space signs at the head of each space (in landscape area) per the approved plans.
Occupancy Inspection - Engineering Failed 01/23/2023
Misc
Corrective Action Required
01/23/2023
1-23-23 AN Needed for Occupancy at building 2.. This punch list will be on going since the whole lot is not completed and building 1 1. Not all of the sidewalks , ADA ramps and entrances are completed. 2. Two spots of the retaining wall on the east side of the building is caving in 3. roof drains need to be properly connected 4. water valve risers need to be lowered 5. sewer clean outs need to be lowered 6. grading and backfill 7. fire hydrant next to the dumpster area may need to raised after grading is completed
Occupancy Inspection - Fire Failed 1/23/2023 1/23/2023 01/23/2023
01/23/2023
Miscellaneous Correction
Corrective Action Required
01/23/2023
Covered head, storage room, third-floor 342 367 sprinkler head deflector on the deck Stand pipe caps Elevator key Storage 1st floor south 159 rscutcheon on sprinkler missing
Occupancy Inspection - Codes Commercial Failed 1/23/2023 1/23/2023 01/23/2023
Miscellaneous Correction
Corrective Action Required
01/23/2023
-Complete corrections for all other departments -Provide building Addresses -Seal penetrations at all electrical/ mechanical rooms as well as Riser room -Ensure all panels are labeled and contain panel schedules -Seal penetration in Stair A 1st floor corridor wall -Complete Dog Wash room -Complete common restrooms -Complete receptacles at lobby countertop space -Seal penetrations, label disconncect, missing cover plate at MDF -Provide permanent labels at all exterior meter banks and disconnects, drive ground rods to grade, and label services 1 or 3, 2 of 3 etc. -Provide barrier under stairs where height less than 80" per A117.1 307.4 -Complete floor finishes at stair landings-height variance greater than 1/4" Exterior: -Complete roof drains -Complete site lighting -Provide bonding jumpers at exterior entry of area B and complete electrical -Complete HVAC covers at North -Cut cleanouts to grade -Complete sidewalks -Mount hose bib at South -Cover plate at open box at West **OK FOR FURNITURE
Occupancy Inspection - Water Utilities Passed 01/24/2023
Occupancy Inspection - Fire Passed 1/26/2023 1/26/2023 01/26/2023
Corrective Action Required
01/26/2023
All life safety was appropriate. Okay to occupy with approval from codes.
Occupancy Inspection - Codes Commercial Ready for Temp CO 1/26/2023 1/26/2023 01/26/2023
Miscellaneous Correction
Corrective Action Required
01/23/2023
-Complete corrections for all other departments-See individual reports for corrections Exterior: -Complete roof drains -Cut cleanouts to grade
Footing Inspection - Commercial Passed 01/26/2023
Miscellaneous Inspection Passed 1/20/2023 01/26/2023
Occupancy Inspection - Engineering Passed 1/26/2023 1/26/2023 01/26/2023
Misc
Corrective Action Required
01/23/2023
1-23-23 AN Needed for Occupancy at building 2.. This punch list will be on going since the whole lot is not completed and building 1 1. Not all of the sidewalks , ADA ramps and entrances are completed. 2. Two spots of the retaining wall on the east side of the building is caving in 3. roof drains need to be properly connected 4. water valve risers need to be lowered 5. sewer clean outs need to be lowered 6. grading and backfill 7. fire hydrant next to the dumpster area may need to raised after grading is completed
Misc
Informational
01/26/2023
1-26-23 DP. TCO passed. For punch list Items we will hold accountability on the last building they have to finish. Punch list building 2- vegetation, backfill and grading, lowering of sewer clean outs and valve risers to grade, fix retaining wall in both spots that it's failing. Make sure blankets are removed off of new concrete poured and enternances are opened up per plan with fire department.
Underslab Plumbing Inspection - Commercial Passed 02/23/2023
Occupancy Inspection - Codes Commercial Ready for Temp CO 3/25/2023 05/02/2023
Miscellaneous Correction
Corrective Action Required
02/23/2023
-Complete corrections for all other departments-See individual reports for corrections Exterior: -Complete roof drains -Cut cleanouts to grade
Occupancy Inspection - Codes Commercial Full C of O 5/5/2023 5/5/2023 05/05/2023
Miscellaneous Correction
Resolved
05/05/2023
-Complete corrections for all other departments-See individual reports for corrections Exterior: -Complete roof drains -Cut cleanouts to grade
Occupancy Inspection - Engineering Passed 5/5/2023 5/5/2023 05/08/2023
Misc
Corrective Action Required
01/23/2023
1-23-23 AN Needed for Occupancy at building 2.. This punch list will be on going since the whole lot is not completed and building 1 1. Not all of the sidewalks , ADA ramps and entrances are completed. 2. Two spots of the retaining wall on the east side of the building is caving in 3. roof drains need to be properly connected 4. water valve risers need to be lowered 5. sewer clean outs need to be lowered 6. grading and backfill 7. fire hydrant next to the dumpster area may need to raised after grading is completed
Documents & Images
Date Uploaded File Type Document Name
07/22/2021 Letter License Tax Bill
02/01/2022 Receipt Receipt for transaction: 2022-000564
02/01/2022 Letter DS Building Permit
02/15/2022 Letter INSPECTION SUMMARY
04/21/2022 Letter INSPECTION SUMMARY
04/21/2022 Sanitary connection
04/21/2022 Letter INSPECTION SUMMARY
06/03/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/17/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/22/2022 Letter INSPECTION SUMMARY
06/22/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
06/24/2022 Letter INSPECTION SUMMARY
06/24/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
06/29/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
07/06/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/08/2022 Letter INSPECTION SUMMARY
07/08/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter INSPECTION SUMMARY
07/14/2022 Letter INSPECTION SUMMARY
07/15/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/22/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/27/2022 Letter INSPECTION SUMMARY
07/28/2022 Letter INSPECTION SUMMARY
07/29/2022 Letter INSPECTION SUMMARY
08/02/2022 Letter INSPECTION SUMMARY
08/02/2022 Letter INSPECTION SUMMARY
08/05/2022 Letter INSPECTION SUMMARY
08/08/2022 Letter INSPECTION SUMMARY
08/10/2022 Letter INSPECTION SUMMARY
08/12/2022 Letter INSPECTION SUMMARY
08/12/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/31/2022 Letter INSPECTION SUMMARY
08/31/2022 Letter INSPECTION SUMMARY
09/01/2022 Letter INSPECTION SUMMARY
09/01/2022 Letter INSPECTION SUMMARY
09/01/2022 Letter INSPECTION SUMMARY
09/02/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/12/2022 Letter INSPECTION SUMMARY
09/12/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/29/2022 Letter INSPECTION SUMMARY
09/30/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
12/13/2022 Letter INSPECTION SUMMARY
12/20/2022 Letter INSPECTION SUMMARY
12/21/2022 Letter INSPECTION SUMMARY
12/30/2022 Letter INSPECTION SUMMARY
01/03/2023 Letter INSPECTION SUMMARY
01/04/2023 Letter INSPECTION SUMMARY
01/05/2023 Letter INSPECTION SUMMARY
01/06/2023 Letter INSPECTION SUMMARY
01/06/2023 Letter INSPECTION SUMMARY
01/11/2023 Letter Fire Loss Reduction Form
01/17/2023 Letter INSPECTION SUMMARY
01/18/2023 Letter INSPECTION SUMMARY
01/18/2023 Letter INSPECTION SUMMARY
01/18/2023 Letter INSPECTION SUMMARY
01/18/2023 Letter INSPECTION SUMMARY
01/18/2023 Letter Fire Loss Reduction Form
01/18/2023 Receipt Receipt for transaction:2023-000327
01/23/2023 Letter INSPECTION SUMMARY
01/23/2023 Letter INSPECTION SUMMARY
01/23/2023 Letter Fire Loss Reduction Form
01/26/2023 Letter INSPECTION SUMMARY
01/26/2023 Letter INSPECTION SUMMARY
01/26/2023 Letter INSPECTION SUMMARY
01/26/2023 Letter INSPECTION SUMMARY
01/26/2023 Certificate/License Codes Temporary Certificate of Occupancy
01/26/2023 Receipt Receipt for transaction:2023-000523
01/26/2023 Letter Fire Loss Reduction Form
02/22/2023 Substantial Completion and TCO Extension Request_prcom20213681
02/23/2023 Letter INSPECTION SUMMARY
02/23/2023 Letter INSPECTION SUMMARY
02/23/2023 Certificate/License Codes Temporary Certificate of Occupancy
02/23/2023 Receipt Receipt for transaction:2023-001058
03/27/2023 Substantial Completion and TCO Extension Request_prcom20213681 3_27_23
05/05/2023 Letter Codes Final Certificate of Occupancy
05/05/2023 Letter Field Certificate of Occupancy
05/09/2023 Receipt Receipt for transaction:2023-003011
12/20/2023 Codes Temporary Certificate of Occupancy104
12/20/2023 Codes Temporary Certificate of Occupancy83
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home