Permit Application Status

PRCOMCOM20230057


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOMCOM20230057
Building Permit - Commercial
Certificate of Occupancy
NLV TOWNHOMES LLC
NEW MULTI-FAMILY
7 UNIT TOWNHOMES New Longview Development Agreement, Commercial, Phase II
01/05/2023
05/26/2023
10/18/2023
11/18/2024
Locations
Contacts
NLV TOWNHOMES LLC, Address:3152 SW GRANDSTAND CIR  
O'REILLY BUILD LLC, Address:5051 S NATIONAL AVE STE 4-110, Phone:(417) 862-9500  
Jacob Johnson - O'Reilly Build, Phone:(318) 413-2151  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
CLAYCO ELECTRIC COMPANY, Address:319 E 11TH AVE, Phone:(816) 221-0593  
MILLER PLUMBING CO, Address:PO BOX 393 , Phone:(913) 851-1333  
CLOCKWORK, Address:423 DELAWARE STREET #102, Phone:(816) 807-3787  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 02/06/2024 02/02/2024
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
01/30/2024

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Received stamped plans 1/30/2024. Indicate the contractor installing the system.
Installation acceptance testing
Corrective Action Required
01/30/2024

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule a hydrostatic test.
Miscellaneous Correction
Corrective Action Required
01/30/2024

It is the resposibility of the sprinkler installer and building contractor to ensure the system is adequately insulated and protected from freezing.
Sprinkler Plan Review Rejected 10/09/2023 10/09/2023
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
10/06/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action required- Unstamped plans received 9/29/2023. Provide PE stamped plans. Indicate the sprinkler contractor installing the system.
Installation acceptance testing
Corrective Action Required
10/09/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule a hydrostatic test.
Miscellaneous Correction
Corrective Action Required
10/09/2023

The 2016 Edition of NFPA 13 D is adopted as the referenced code per the 2018 Edition of the IFC. Call out any exceptions taken from the 2019 Edition and correct the code information.
Zoning Review Approved 07/07/2023 07/05/2023
Hector Soto Jr.
Misc
Corrective Action Required
06/29/2023

EXTERIOR MATERIAL. - The proposed change in exterior material from brick along the rear elevations of Buildings 1 and 2 depicted on Sheets A121 and A221 lists "Siding or Stucco". Which material will be used on the buildings? The elevations shall list the actual material to be used for staff review. - Label the color of the proposed material(s) to be used along the rear elevations for review. Also provide a color elevation.
Zoning Review Rejected 06/19/2023 06/21/2023
Hector Soto Jr.
Misc
Corrective Action Required
06/21/2023

EXTERIOR MATERIAL. - The proposed change in exterior material from brick along the rear elevations of Buildings 1 and 2 depicted on Sheets A121 and A221 lists "Siding or Stucco". Which material will be used on the buildings? The elevations shall list the actual material to be used for staff review. - Label the color of the proposed material(s) to be used along the rear elevations for review. Also provide a color elevation.
Fire Plan Review Approved with Conditions 06/19/2023 06/19/2023
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
06/12/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Submit sprinkler plans (13 D) for review and approval. Acknowledged deffered submittal on letter
Installation acceptance testing
Corrective Action Required
06/12/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Action Required: Call 816-969-1300 to schedule hydrostatic pressure test.
Building Plan Review Approved with Conditions 06/19/2023 06/15/2023
Joe Frogge
Engineered truss package
Corrective Action Required
06/12/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Comment is informational. Truss packages deferred per request. 2/1/2023 - acknowledged in letter.
Building Plan Review Approved with Conditions 02/06/2023 05/24/2023
Joe Frogge
Engineered truss package
Corrective Action Required
02/01/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Comment is informational. Truss packages deferred per request. 2/1/2023 - acknowledged in letter.
Project cost
Resolved
05/24/2023

The project cost, which is used to establish the permit fee, has not been provided. Action required: Provide construction cost breakdown for each structure. Townhomes attached to garages via covered walkway are considered a single structure. 2/1/2023 - acknowledged in letter.
IBC 706.1 Fire and Smoke Protection - General
Resolved
02/01/2023

2018 IRC 302.2 Townhouses. Action required: Provide complete UL details for separation walls. Must include nail/screw patterns.
IBC 706.6 Fire and Smoke Protection - Vertical Continuity
Resolved
02/01/2023

2018 IRC 302.2.3 Continuity. Action required: Amend designs to demonstrate compliance. Must be continuous through floor/ceiling assemblies. Unclear how to attach at roof deck.
IBC 706.1 Fire and Smoke Protection - General
Resolved
02/01/2023

2018 IRC 302.2.3 Parapets for townhouses. Action required: Amend drawings to demonstrate compliance. How is parapet exception being met?
Misc
Resolved
02/01/2023

2018 IRC 302.5 Dwelling-garage opening and penetration protection. thru 2018 IRC 302.7 Under-stair protection. Action required: Amend drawings to demonstrate compliance. Must address: - Mechanical rooms/door (where and how is separation accomplished? Back wall? Front wall with rated doors?) - Door ratings - Door closers - Garage ceilings (whether or not living space above)
IBC 1010.1.2 Door swing - direction of swing egress travel
Resolved
02/01/2023

2018 IRC 311.2 Egress door. Actions required: - Provide information as to how the doubled 3/6 doors comply. Floor and/or top jamb slide locks, or similar, will make these non-compliant. - Edit door label on sheet A111. (2/8 not allowed)
IPC 405.3.1 fixture clearance to obstruction
Resolved
02/01/2023

2018 IRC 307.1 Space required. Figure 307.1 Action required: Modifications required. All toilets require minimum 21" front clearance.
IBC 1030.2 Minimum size - emergency escape and rescue
Resolved
02/01/2023

2018 IRC 310.1 Emergency escape and rescue opening required. Action required: Modify designs. All basements required to have egress direct to exterior. Some are missing, some have egress wells that lead to nowhere.
IBC 706.8.4.2 Fire and Smoke Protection - Fireblocks and Firestops
Resolved
02/01/2023

2018 IRC 302.12 Draftstopping. Action required: Specify draftstopping in floors and attics.
Misc
Resolved
02/01/2023

2018 IRC 302.2.2 Common walls. Action required: Revise plumbing drawings to comply. Piping not allowed in common walls.
IFGC 303.3 Prohibited locations for gas fired appliance
Resolved
02/01/2023

2018 IRC 1307.3 Elevation of ignition source. Action required: Amend drawings to demonstrate compliance at water heaters.
NEC Article 210.11 (C) (3) Bathroom branch circuits
Resolved
02/01/2023

2018 IRC 3703.4 Bathroom circuits. Action required: Bathroom circuits are required to be dedicated. This includes lighting and power.
IBC 915.1.1 Fire Protection - carbon monoxide detect
Resolved
02/01/2023

2018 IRC 315 Carbon Monoxide Alarms. 2018 IRC 315.2 Where required. 2018 IRC 315.3 Location. Action required: Provide carbon monoxide detection at all required locations.
NEC Article 250.50 Grounding electrode system
Resolved
02/01/2023

2018 IRC 3608.1 Grounding electrode system. Action required: Revise grounding detail to show connection to concrete-encased electrode per 3608.1.2.
NEC Article 230.2 Number of services
Resolved
02/01/2023

2018 IRC 3601.3 One building or other structure not to be supplied through another. Action required: SE cables are not to be routed through dwelling units. (each townhouse is considered a separate building at fire separation wall) To be field verified.
Licensed Contractors Approved 02/06/2023 05/08/2023
Joe Frogge
LC - General Contractor
Resolved
02/01/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Resolved
05/08/2023

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 2/1/2023 - acknowledged in letter.
Licensed Contractors Approved 01/20/2023 05/08/2023
Joe Frogge
LC - General Contractor
Resolved
05/08/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Resolved
05/08/2023

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved with Conditions 02/06/2023 02/01/2023
Ben Hicks
Construction documents - Fire protection systems
Corrective Action Required
02/01/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Submit sprinkler plans (13 D) for review and approval. Acknowledged deffered submittal on letter
Installation acceptance testing
Corrective Action Required
02/01/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Action Required: Call 816-969-1300 to schedule hydrostatic pressure test.
Building Plan Review Rejected 01/20/2023 01/18/2023
Joe Frogge
IBC 1103.1 Where required - accessibility
Resolved
01/24/2023

2018 IRC 320.1 Scope Accessibility. Where there are four or more dwelling units or sleeping units in a single structure, the provisions of Chapter 11 of the International Building Code for Group R-3 shall apply. 1107.6.3 Group R-3. In Group R-3 occupancies where there are four or more dwelling units or sleeping units intended to be occupied as a residence in a single structure, every dwelling unit and sleeping unit intended to be occupied as a residence shall be a Type B unit. Bedrooms within congregate living facilities, dormitories, sororities, fraternities, and boarding houses shall be counted as sleeping units for the purpose of determining the number of units. Exception: The number of Type B units is permitted to be reduced in accordance with Section 1107.7. Action required: Amend designs and code analysis to demonstrate compliance. 1/24/23 - per architect's analysis and review of commentary comment removed.
Engineered truss package
Corrective Action Required
01/18/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Comment is informational. Truss packages deferred per request.
Project cost
Corrective Action Required
01/18/2023

The project cost, which is used to establish the permit fee, has not been provided. Action required: Provide construction cost breakdown for each structure. Townhomes attached to garages via covered walkway are considered a single structure.
IBC 706.1 Fire and Smoke Protection - General
Corrective Action Required
01/18/2023

2018 IRC 302.2 Townhouses. Action required: Provide complete UL details for separation walls. Must include nail/screw patterns.
IBC 706.6 Fire and Smoke Protection - Vertical Continuity
Corrective Action Required
01/18/2023

2018 IRC 302.2.3 Continuity. Action required: Amend designs to demonstrate compliance. Must be continuous through floor/ceiling assemblies. Unclear how to attach at roof deck.
IBC 706.1 Fire and Smoke Protection - General
Corrective Action Required
01/18/2023

2018 IRC 302.2.3 Parapets for townhouses. Action required: Amend drawings to demonstrate compliance. How is parapet exception being met?
Misc
Corrective Action Required
01/18/2023

2018 IRC 302.5 Dwelling-garage opening and penetration protection. thru 2018 IRC 302.7 Under-stair protection. Action required: Amend drawings to demonstrate compliance. Must address: - Mechanical rooms/door (where and how is separation accomplished? Back wall? Front wall with rated doors?) - Door ratings - Door closers - Garage ceilings (whether or not living space above)
IBC 1010.1.2 Door swing - direction of swing egress travel
Corrective Action Required
01/18/2023

2018 IRC 311.2 Egress door. Actions required: - Provide information as to how the doubled 3/6 doors comply. Floor and/or top jamb slide locks, or similar, will make these non-compliant. - Edit door label on sheet A111. (2/8 not allowed)
IPC 405.3.1 fixture clearance to obstruction
Corrective Action Required
01/18/2023

2018 IRC 307.1 Space required. Figure 307.1 Action required: Modifications required. All toilets require minimum 21" front clearance.
IBC 1030.2 Minimum size - emergency escape and rescue
Corrective Action Required
01/18/2023

2018 IRC 310.1 Emergency escape and rescue opening required. Action required: Modify designs. All basements required to have egress direct to exterior. Some are missing, some have egress wells that lead to nowhere.
IBC 706.8.4.2 Fire and Smoke Protection - Fireblocks and Firestops
Corrective Action Required
01/18/2023

2018 IRC 302.12 Draftstopping. Action required: Specify draftstopping in floors and attics.
Misc
Corrective Action Required
01/18/2023

2018 IRC 302.2.2 Common walls. Action required: Revise plumbing drawings to comply. Piping not allowed in common walls.
IFGC 303.3 Prohibited locations for gas fired appliance
Corrective Action Required
01/18/2023

2018 IRC 1307.3 Elevation of ignition source. Action required: Amend drawings to demonstrate compliance at water heaters.
NEC Article 210.11 (C) (3) Bathroom branch circuits
Corrective Action Required
01/18/2023

2018 IRC 3703.4 Bathroom circuits. Action required: Bathroom circuits are required to be dedicated. This includes lighting and power.
IBC 915.1.1 Fire Protection - carbon monoxide detect
Corrective Action Required
01/18/2023

2018 IRC 315 Carbon Monoxide Alarms. 2018 IRC 315.2 Where required. 2018 IRC 315.3 Location. Action required: Provide carbon monoxide detection at all required locations.
NEC Article 250.50 Grounding electrode system
Corrective Action Required
01/18/2023

2018 IRC 3608.1 Grounding electrode system. Action required: Revise grounding detail to show connection to concrete-encased electrode per 3608.1.2.
NEC Article 230.2 Number of services
Corrective Action Required
01/18/2023

2018 IRC 3601.3 One building or other structure not to be supplied through another. Action required: SE cables are not to be routed through dwelling units. (each townhouse is considered a separate building at fire separation wall) To be field verified.
Building Plan Review Rejected 01/20/2023 01/18/2023
Joe Frogge
Final Development Plan Review Approved 12/13/2022 01/18/2023
Scott Ready
NLV Townhomes
Fire Plan Review Approved with Conditions 01/20/2023 01/06/2023
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
01/06/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Submit sprinkler plans (13 D) for review and approval.
Fees
Paid Fees Amount Paid Owing Date Paid
7232302-Residential Excise Tax Fee $2,970.24 $2,970.24 Paid 05/26/2023
9110078-Valuation Fee for New Multi-Family $12,487.71 $12,487.71 Paid 05/26/2023
8331401-Water Tap Fee $26,110.00 $26,110.00 Paid 06/19/2023
8350015-Water Meter Fee $3,853.50 $3,853.50 Paid 06/19/2023
8331507-Sanitary Sewer Development Fee $9,688.00 $9,688.00 Paid 06/19/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 09/06/2024
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 10/31/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Failed 6/13/2023 06/13/2023
Misc
Corrective Action Required
06/13/2023
- repair silt fence where down - trim overgrown vegetation
Footing Inspection - Commercial Partial 6/16/2023 (8:00) 6/16/2023 06/16/2023
Misc
Corrective Action Required
06/16/2023
- Partial building 1: -- A1-A8, AA to AE approved
Footing Inspection - Commercial Partial 6/19/2023 06/19/2023
Misc
Corrective Action Required
06/16/2023
- Partial building 1: -- A1-A8, AA to AE approved - pier pads building 1 approved
Footing Inspection - Commercial Partial 6/20/2023 (9:30) 6/20/2023 06/20/2023
Misc
Corrective Action Required
06/19/2023
- Partial building 1: -- A1-A8, AA to AE approved - pier pads building 1 approved - building 1 footing garage side , Ok
Sewer Service Inspection Partial 6/20/2023 (1:00) 6/20/2023 06/20/2023
Misc
Corrective Action Required
06/20/2023
- partial stubbed up building 1
Footing Inspection - Commercial Partial 6/28/2023 (1:00) 6/28/2023 06/28/2023
Misc
Corrective Action Required
06/20/2023
- Partial building 1:Approved
Foundation Inspection - Commercial Passed 7/14/2023 07/14/2023
Footing Inspection - Commercial Passed 7/14/2023 (1:00) 7/14/2023 07/14/2023
Misc
Resolved
07/14/2023
- Partial building 1:Approved
Underslab Plumbing Inspection - Commercial Passed 7/25/2023 7/25/2023 07/25/2023
Misc
Informational
07/25/2023
Building (1) complete
Underslab Electrical Inspection - Commercial Passed 7/26/2023 07/26/2023
Misc
Informational
07/26/2023
Building 1
Miscellaneous Inspection Partial 9/7/2023 9/7/2023 09/07/2023
THE FOLLOWING AREAS ARE APPROVED
Informational
09/21/2023
SECOND FLOOR SIMPSON STRONG TIE ASSEMBLY OK
Miscellaneous Inspection Passed 9/21/2023 09/21/2023
THE FOLLOWING AREAS ARE APPROVED
Informational
09/21/2023
SECOND FLOOR SIMPSON STRONG TIE ASSEMBLY OK
Miscellaneous Inspection Passed 10/2/2023 10/2/2023 10/02/2023
Misc
Informational
10/02/2023
Discussed mechanical room and second floor chase framing next to demizing wall.
All Rough Inspection - Commercial Failed 11/29/2023 11/29/2023 11/29/2023
Misc
Corrective Action Required
11/29/2023
• Protect sprinkler system from freezing in attic space -Pull wire to panel , complete inside unit before sheet rock - Correct alike issues in the rest of the units before calling for all rough on other units. 441 R302.2.2 No plumbing allowed in demise wall ( plans P100-2 ) general notes plumbing scedule • address break in 2x6 at garage opening • provide anchor bolt within 12” inches of end of sill plate and back from end more than 5 times the diameter of bolt in garage exterior wall • Provide straps for portal frame • Fire block penetrations at top plate throughout garage • Fire block stud bays vertical to horizontal every 10’ on demise wall • Repair Puddy pads falling off boxes • Provide puddy pads in any boxes within 24” of each other • Fire block all penetrations at top plate first floor garage wall plumbing and gas line at front exterior wall • Fire block top plate at HAVAC chase to prevent fire to joist space in living room • Provide door off kitchen • Fire block DWV top plate in kitchen exterior wall • Fire block top plate at ceiling height change in pantry/bathroom wall 2 nd floor • Fire block penetrations top plate in pantry • Fire block penetrations top plate above refrigerator • Provide attic access • Fire block HAVAC chase at top plate • Sheet Rock required on underside of roof decking 4’ out from demising wall( plans A003 ) • Solid block all sheeting breaks at third floor soffits • Fire block top of windows fur out • Provide hold down for double girder truss in master bedroom • Provide missing window master bedroom • Fire block DWV penetrations laundry at top plate • Provide windows back 3 rd floor bedroom • Demise wall to extend to exterior wall • On third floor, strap top plate every where their is less than 24” overlap • Fire block floor penetrations at tub • Fire block DWV top plate bathroom demise wall • Fire block chase both sides of demise wall • Provide roof ventilation • Provide double stud pack under girder truss • Fire protection needed underneath stairs above soffit • Fire block top plate at master window bump outs • Provide attic access • Provide roof ventilation • 443 • Fire block penetrations top plate garage • Sheet rock damaged at ductwork into demise wall garage • Fire block top plate throughout • Complete hold down brackets at first floor • Support gas pipe every 10’ • Fire block top of HVAC chase second floor • 3 studs pack not continuous at demise wall near kitchen • Support water line for sprinkler in joist space • Protect outlets in demising wall • Provide all doors and windows • 2x4 s going into demise wall • Rock wool missing between demise walls • Fire block stud space pantry to exterior wall • Missing stud ceiling middle second floor • Fire block vertical to horizontal every 10’ at demise wall • Demise wall to extend to exterior wall • Protect roof out 4’ from demise wall • R302.2.2 No plumbing in demise wall • Top plate not continuous in master bedroom no 2’ overlap • Engineered to verify stair clearance to demise wall • Strap all DWV smaller than 2” on vertical runs over 8’ • 445 • fire block top plate at soffit in garage exterior wall • Fire block gap in top plates garage demise wall • Fire block all top plate penetrations throughout • Provide missing windows and doors • Fire block gap in stud space in pantry demise wall to exterior wall • Fire block HVAC chase at top plate second floor • R302.2.2 No plumbing in demise wall • Strap top plate everywhere there is less than 24” overlap • Fire block floor penetrations throughout • Provide attic access • Provide attic ventilation • Demise wall to extend to exterior wall in third floor • Protect roof 4’ out from demise wall on underside of decking • Protect sprinkler line in attic • Fire Protect underside of stairs above ceiling •
Miscellaneous Inspection Passed 1/12/2024 01/12/2024
Misc
Informational
01/12/2024
LOOKED AT 441 ROOF DECH CMR APPLICATION, TAPE AND MUD INCOMPLETE.
All Rough Inspection - Commercial Failed 1/22/2024 1/23/2024 01/23/2024
Misc
Resolved
01/23/2024
Misc
Corrective Action Required
01/23/2024
• Protect sprinkler system from freezing in attic space - Correct alike issues in the rest of the units before calling for all rough on other units. - units 447,449,452,554 not ready 441 • Fire block top plate at HAVAC chase to prevent fire to joist space in living room • Fire protection needed underneath stairs above soffit - 3rd floor demise wall must extend to exterior wall. And use approved materials. 443 • Fire block penetrations top plate garage • Sheet rock damaged at ductwork into demise wall garage - solid block stud bays at mechanical room at soffit of garage • Fire block top plate throughout • Complete hold down brackets at first floor • Fire block top of HVAC chase second floor • 3 studs pack not continuous at demise wall near kitchen • Support water line for sprinkler in joist space • 2x4 s going into demise wall • Rock wool missing between demise walls • Fire block stud space pantry to exterior wall • Missing stud ceiling middle second floor • Fire block vertical to horizontal every 10’ at demise wall • Demise wall to extend to exterior wall • damaged rock master toilet • Top plate not continuous in master bedroom no 2’ overlap • Engineered to verify stair clearance to demise wall • Strap all DWV smaller than 2” on vertical runs over 8’ • provide attic access 445 • fire block top plate at soffit in garage exterior wall • Fire block gap in top plates garage demise wall • Fire block all top plate penetrations throughout • Fire block gap in stud space in pantry demise wall to exterior wall • Strap top plate everywhere there is less than 24” overlap • Fire block floor penetrations throughout • Provide attic access • Demise wall to extend to exterior wall in third floor ( not adequate) • Protect sprinkler line in attic • Fire Protect underside of stairs above ceiling
All Rough Inspection - Commercial Failed 1/30/2024 1/30/2024 01/30/2024
Misc
Corrective Action Required
01/23/2024
441 - OK to insulate 443 • OK to insulate 445 • OK to isolate 447 - Missing insulation in gap demising wall third floor back bathroom also master bathroom - 449 - Missing rock wool at 1” gap of demising wall top plate third floor multiple locations - 451 - Extend demising wall to exterior wall second floor pantry - Missing rock wool third floor demising wall top plate back bathroom - 453 - Fire block HVAC chase ( Finnish) all openings and gaps top on second floor ( stop vertical to horizontal fire and gasses into joists space - Continue demising wall to exterior wall at second floor pantry - Address top plate master bedroom third floor ( blocks)
Gas Service Inspection - Commercial Passed 2/2/2024 02/02/2024
Misc
Informational
02/02/2024
OK: 441,443,445,447,446,451,453
All Rough Inspection - Commercial Failed 2/2/2024 2/2/2024 02/02/2024
Misc
Corrective Action Required
01/30/2024
DO NOT SHEET ROCK Will Check at occupy : All front stoops 32” code is 36” Tempered windows Garage landing 441 - OK to insulate 2/2 - Boca plates first floor sill plate - Fire block mechanical chase to prevent flame into joist space - Protect stair stringers at garage above mechanical room 443 • OK to insulate 2/2 - window at second floor stairs landing to be Tempered - Fire block top of mechanical chase at second floor 445 • OK to insulate 2/2 - landing for garage stairs under 36” - Protect stair stringers at garage above mechanical room 447 2/2 - window at bottom of stairs second floor to be Tempered - Fire caulk penetration above third floor back toilet in attic space - 449 2/2 - window at second floor stairs landing to be Tempered - 451 - Missing rock wool third floor demising wall top plate back bathroom closet 2/2 - window at second floor stairs landing to be Tempered - 453 2/2 - protect stair stringers above mechanical room garage DI NOT SHEET ROCK
Erosion Control Inspection Residential Failed 2/2/2024 02/02/2024
Misc
Corrective Action Required
06/13/2023
- REMOVE TRASH FROM STORM INLETS.
Rated Assembly Inspection Partial 2/22/2024 02/22/2024
Misc
Corrective Action Required
02/22/2024
**UNIT SCREW PATTERN ON DEMISE WALLS 441 OK 443 OK 445 OK 447 NOT COMPLETE 449 NOT COMPLETE 451 NOT COMPLETE 453 NOT COMPLETE
Rated Assembly Inspection Partial 2/23/2024 02/23/2024
Misc
Corrective Action Required
02/22/2024
**UNIT SCREW PATTERN ON DEMISE WALLS 441 OK 443 OK 445 OK 447 OK 449 - more screws needed at kitchen stove wall - add screws second to third floor stairs 451 NOT COMPLETE 453 NOT COMPLETE
Rated Assembly Inspection Partial 2/26/2024 02/26/2024
Misc
Corrective Action Required
02/23/2024
**UNIT SCREW PATTERN ON DEMISE WALLS 441 OK 443 OK 445 OK 447 OK 449 OK 451 OK 453 OK OK TO MUD
Gas Piping Inspection - Commercial Passed 4/10/2024 04/10/2024
Misc
Informational
04/10/2024
FOR UNITS 441,443,445,447,449,451,453
Electrical Service Inspection Failed 4/10/2024 4/10/2024 04/10/2024
E110.22 Identification of disconnection means
Corrective Action Required
04/10/2024
Each disconnecting means shall be legibly marked to indicate its purpose unless located and arranged so the purpose os evident. The marking shall be of sufficient durability to withstand the environment involved. Where circuit breakers or fuses are applied in compliance with the series combination ratings marked on the equipment by the manufacturer, the equipment enclosure(s) shall bbe marked in the field to indicate the equipment has been applied with a series combination rating. The marking shall be readily visible and state the following: CAUTION-SERIES COMBINATION SYSTEM RATED ___AMPERES. IDENTIFIED REPLACEMENT COMPONENTS REQUIRED. EACH UNIT
Electrical Service Inspection Passed 4/16/2024 4/16/2024 04/16/2024
E110.22 Identification of disconnection means
Resolved
04/16/2024
Each disconnecting means shall be legibly marked to indicate its purpose unless located and arranged so the purpose os evident. The marking shall be of sufficient durability to withstand the environment involved. Where circuit breakers or fuses are applied in compliance with the series combination ratings marked on the equipment by the manufacturer, the equipment enclosure(s) shall bbe marked in the field to indicate the equipment has been applied with a series combination rating. The marking shall be readily visible and state the following: CAUTION-SERIES COMBINATION SYSTEM RATED ___AMPERES. IDENTIFIED REPLACEMENT COMPONENTS REQUIRED. EACH UNIT
Miscellaneous Inspection Failed 7/16/2024 7/16/2024 07/16/2024
Misc
Corrective Action Required
07/16/2024
441 - provide security screws at front door (2 per hinge and 2 in strike plate) - Garage entry door to be self closing and latch - Draft stop penetrations in mechanical room at top @ line set and gas line - G2408.2 Elevation of ignition source @ water heater to be 18” above garage floor - Garage risers over 7 3/4” - Riser variance not within 3/8” at garage stairs - Provide spark rings at all outlets and switches on kitchen counter - Provide cover for attic access
Miscellaneous Inspection Passed 7/19/2024 7/19/2024 07/19/2024
Misc
Resolved
07/19/2024
441 - provide security screws at front door (2 per hinge and 2 in strike plate) - Garage entry door to be self c
Rated Assembly Inspection Passed 8/8/2024 08/08/2024
Misc
Resolved
08/08/2024
**UNIT SCREW PATTERN ON DEMISE WALLS 441 OK 443 OK 445 OK 447 OK 449 OK 451 OK 453 OK OK TO MUD
All Rough Inspection - Commercial Passed 8/8/2024 08/08/2024
Misc
Resolved
08/08/2024
DO NOT SHEET ROCK Will Check at occupy : All front stoops 32” code is 36” Tempered windows Garage landing 441 - OK to insulate 2/2 - Boca plates first floor sill plate - Fire block mechanical chase to prevent flame into joist space - Protect stair stringers at garage above mechanical room 443 • OK to insulate 2/2 - window at second floor stairs landing to be Tempered - Fire block top of mechanical chase at second floor 445 • OK to insulate 2/2 - landing for garage stairs under 36” - Protect stair stringers at garage above mechanical room 447 2/2 - window at bottom of stairs second floor to be Tempered - Fire caulk penetration above third floor back toilet in attic space - 449 2/2 - window at second floor stairs landing to be Tempered - 451 - Missing rock wool third floor demising wall top plate back bathroom closet 2/2 - window at second floor stairs landing to be Tempered - 453 2/2 - protect stair stringers above mechanical room garage DI NOT SHEET ROCK
Occupancy Inspection - Codes Commercial Failed 8/9/2024 8/9/2024 08/09/2024
Misc
Corrective Action Required
08/09/2024
Common items entire building - post address - Paint exterior gas piping - Final grading and sod - Provide anti tamper caps at A/C compressors - Gutters and down spouts and splash pads to divert water 36” away from foundation - Electrical outlet at garage mechanical room to be single and labeled non- gfci or GFCI protected - Secure water piping in mechanical room - Water heaters to be stubbed 18” before pex 441 - Post address - Add gravel to water meter pit - Land sewer trace wire at grade 443 - post address - Land sewer trace wire at grade - Man door from garage to be self closing and latch - no GFCI protection for dishwasher - Complete faucets in bathrooms - Open sewer in bathrooms - Window at second floor stairs landing front of building required to be tempered glass - Provide lock outs at electrical panel where required - 445 - post address - gravel required in water meter pit to grade - Land sewer trace wire at grade - Provide lock outs at electrical panel where required - Stairs landing into garage only 32 1/2”, 36” minimum - Open sewer in bathrooms - Missing switch cover at furnace - Provide back flow preventer at spigot in mechanical room - Handrail at main floor stairs needs to 34-38” above tread nosing - Window at second floor bathroom at back of building is required to be tempered 447 - Handrail to be 34-38” above riser treads nosing at bottom of first floor stairs - Provide lockouts at electrical panel where required - Provide back flow preventer at spigot in mechanical room - Garage stairs have more than 3/8” variance in riser height - Stairs from first floor to second have over a 3/8” variance - Tempered glass required at second level stairs landing - No rails at deck - No GFCI protection for dishwasher - Deck receptacle nor complete - Handrail from second floor to third to be 34-38” above nosing of riser - 449 - Provide back flow preventer at spigot in mechanical room - Missing box cover at switch at mechanical room - Stairs at garage over 7 3/4” rise and out of 3/8” variance - Handrails both stairs to be 34-38” above tread nosing - Open sewer in bathrooms - Install fixtures - Deck missing railings - Complete outlet at deck - Window at second floor landing to be tempered - Provide lockouts in electrical panel 451 - Stairs from first floor to second is over the 3/8” variance allowed - Provide back flow preventer at spigot in mechanical room - Stairs at garage over 3/8” variance of tread height - Handrails both stairs to be 34-38” above tread nosing - Open sewer in bathrooms - Install fixtures - Deck missing railings - Complete outlet at deck - Window at second floor landing to be tempered 454 - uncover water meter check height and gravel - Provide back flow preventer at spigot in mechanical room - Stairs at garage over 7 3/4” rise and out of 3/8” variance - Handrails both stairs to be 34-38” above tread nosing - Window in second floor bathroom at back of building to be tempered - Deck missing railings - Complete outlet at deck - Provide lockouts at electrical panel *** No Occupancy until all city departments have approved
Erosion Control Inspection Residential Failed 8/9/2024 08/09/2024
Misc
Resolved
08/09/2024
- REMOVE TRASH FROM STORM INLETS.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/09/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. REMOVE GRAVEL AND DEBRIS FROM T
Occupancy Inspection - Engineering Failed 8/9/2024 (10:00) 8/9/2024 08/09/2024
Miscellaneous Correction
Corrective Action Required
08/09/2024
Punch list 1. Clean trash and put up erosion control. 2. Remove dirt and rock piles 3. Vegetation needed. 4. Top asphalt coat needed, And repair asphalt by stop sign. 5. Clean parking lot and sidewalks 6. Put in approach for driveway please have this done by 9-9-24
Occupancy Inspection - Codes Commercial Failed 9/5/2024 9/5/2024 09/05/2024
Misc
Resolved
09/05/2024
Common items entire building - post address - Paint exterior gas piping - Final grading and sod - Provide anti tamper caps at A/C compressors - Gutters and down spouts and splash pads to divert water 36” away from foundation - Electrical outlet at garage mechanical room to be single and labeled non- gfci or GFCI protected - Secure water piping in mechanical room - Water heaters to be stubbed 18” before pex 441 - Post address - Add gravel to water meter pit - Land sewer trace wire at grade 443 - post address - Land sewer trace wire at grade - Man door from garage to be self closing and latch - no GFCI protection for dishwasher - Complete faucets in bathrooms - Open sewer in bathrooms - Window at second floor stairs landing front of building required to be tempered glass - Provide lock outs at electrical panel where required - 445 - post address - gravel required in water meter pit to grade - Land sewer trace wire at grade - Provide lock outs at electrical panel where required - Stairs landing into garage only 32 1/2”, 36” minimum - Open sewer in bathrooms - Missing switch cover at furnace - Provide back flow preventer at spigot in mechanical room - Handrail at main floor stairs needs to 34-38” above tread nosing - Window at second floor bathroom at back of building is required to be tempered 447 - Handrail to be 34-38” above riser treads nosing at bottom of first floor stairs - Provide lockouts at electrical panel where required - Provide back flow preventer at spigot in mechanical room - Garage stairs have more than 3/8” variance in riser height - Stairs from first floor to second have over a 3/8” variance - Tempered glass required at second level stairs landing - No rails at deck - No GFCI protection for dishwasher - Deck receptacle nor complete - Handrail from second floor to third to be 34-38” above nosing of riser - 449 - Provide back flow preventer at spigot in mechanical room - Missing box cover at switch at mechanical room - Stairs at garage over 7 3/4” rise and out of 3/8” variance - Handrails both stairs to be 34-38” above tread nosing - Open sewer in bathrooms - Install fixtures - Deck missing railings - Complete outlet at deck - Window at second floor landing to be tempered - Provide lockouts in electrical panel 451 - Stairs from first floor to second is over the 3/8” variance allowed - Provide back flow preventer at spigot in mechanical room - Stairs at garage over 3/8” variance of tread height - Handrails both stairs to be 34-38” above tread nosing - Open sewer in bathrooms - Install fixtures - Deck missing railings - Complete outlet at deck - Window at second floor landing to be tempered 454 - uncover water meter check height and gravel - Provide back flow preventer at spigot in mechanical room - Stairs at garage over 7 3/4” rise and out of 3/8” variance - Handrails both stairs to be 34-38” above tread nosing - Window in second floor bathroom at back of building to be tempered - Deck missing railings - Complete outlet at deck - Provide lockouts at electrical panel *** No Occupancy until all city departments have approved
Misc
Corrective Action Required
09/05/2024
441 sw Longview Common items entire building - Final grading and sod - Provide anti tamper caps at A/C compressors - Gutters and down spouts and splash pads to divert water 36” away from foundation 441 -ok 443 -ok 445 - Handrail at main floor stairs needs to 34-38” above tread nosing ( at bottom) - Window at second floor bathroom at back of building is required to be tempered 447 - ok 449 - Window at second floor landing to be tempered 451 - Window at second floor landing to be tempered 454 - Window in second floor bathroom at back of building to be tempered *** No Occupancy until all city departments have approved
Occupancy Inspection - Engineering Temporary C of O 9/6/2024 9/6/2024 09/06/2024
Miscellaneous Correction
Corrective Action Required
08/09/2024
Punch list 1. Clean trash and put up erosion control. 2. Remove dirt and rock piles 3. Vegetation needed. 4. Top asphalt coat needed, And repair asphalt by stop sign. 5. Clean parking lot and sidewalks 6. Put in approach for driveway please have this done by 9-9-24
Misc
Informational
09/06/2024
Updated punch list- 1. Keep areas cleaned up 2. Clean entire private site and roads, address silt fence in areas where needed. 3. Remove dumpsters, porta johns, fencing 4. establish 70% vegetation 5. fix 2 sections of broken curb. Completed from previous punch list-- 1. Surface Asphalt completed From Longview to SW Brummel Rd. 2. approach for alleyway. ********TCO approved for Buildings 1 and 2********
Occupancy Inspection - Planning Failed 8/9/2024 8/9/2024 09/06/2024
Misc
Corrective Action Required
09/06/2024
Complete landscaping per the approved plan.
Corrective Action Required
09/06/2024
PARKING. The site currently does not meet minimum parking requirements. Building 1 (and Building 2 that is still under construction) rely on 22 diagonally-striped parking spaces in the parking area at the front of the buildings to comply with the City's parking requirements. Said parking area appears to have relatively recently been re-paved, but has not been striped. Temporary occupancy of Building 1 cannot be issued until the parking area is striped per the approved plan.
Occupancy Inspection - Codes Commercial Failed 9/6/2024 09/06/2024
Misc
Corrective Action Required
09/06/2024
441 sw Longview UNits 441,443,445,447,449,451,454 Common items entire building - Gutters and down spouts and splash pads to divert water 36” away from foundation 445,454 BOTH - Window in second floor bathroom at back of building to be tempered ( covered with plexiglass) *** No Occupancy until all city departments have approved; see planning comments on seperate cover.
Occupancy Inspection - Planning Temporary C of O 9/11/2024 09/11/2024
Corrective Action Required
09/11/2024
LANDSCAPING. Staff will confirm compliance with the approved landscape plan prior to the issuance of Final Occupancy.
Erosion Control Inspection Residential Passed 9/12/2024 09/12/2024
DCM2 ESC DEFICIENT INSTALLATION
Resolved
09/12/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. REMOVE GRAVEL AND DEBRIS FROM T
Occupancy Inspection - Codes Commercial Temporary C of O 9/12/2024 09/12/2024
Misc
Corrective Action Required
09/06/2024
441 sw Longview UNits 441,443,445,447,449,451,454 Common items entire building - Gutters and down spouts and splash pads to divert water 36” away from foundation 445,454 BOTH - Window in second floor bathroom at back of building to be tempered ( covered with plexiglass) *** No Occupancy until all city departments have approved; see planning comments on seperate cover.
Occupancy Inspection - Codes Commercial Ready for Temp CO 10/23/2024 10/23/2024 10/23/2024
Misc
Corrective Action Required
09/12/2024
441 sw Longview UNits 441,443,445,447,449,451,454 *** No Occupancy until all city departments have approved; see planning comments on seperate cover.
Sewer Service Inspection Passed 10/31/2024 10/31/2024 10/31/2024
Misc
Corrective Action Required
06/20/2023
- partial stubbed up building 1 10-31-24 DP. All sewer services have been installed with passing tests.
Water Service Inspection Passed 10/31/2024 10/31/2024 10/31/2024
Misc
Informational
10/31/2024
10-31-24 DP. All water services have been installed, issues have been repaired. Passed
Occupancy Inspection - Engineering Passed 10/31/2024
Miscellaneous Correction
Corrective Action Required
08/09/2024
Punch list 1. Clean trash and put up erosion control. 2. Remove dirt and rock piles 3. Vegetation needed. 4. Top asphalt coat needed, And repair asphalt by stop sign. 5. Clean parking lot and sidewalks 6. Put in approach for driveway please have this done by 9-9-24 10-31-24 DP. Punch list items have been complete.
Occupancy Inspection - Codes Commercial Full C of O 11/18/2024 11/18/2024 11/18/2024
Misc
Resolved
11/18/2024
441 sw Longview UNits 441,443,445,447,449,451,454
Documents & Images
Date Uploaded File Type Document Name
01/05/2023 Application Form APPLICATION
01/05/2023 Plans 20221223 NLV Townhomes - Permit Set
01/05/2023 Engineer Report/Study 22-1212 NLV Townhomes_Struct Calc Book
01/06/2023 Letter Fire Building Plan Review
01/18/2023 Letter DS P/R Corrections Document
01/27/2023 Plans 20230126 NLV Townhomes - Permit Resubmittal
01/27/2023 Letter DS P_R Corrections Document - RESPONSE Letter
02/01/2023 Letter Fire Building Plan Review
02/09/2023 Plans 20230126 NLV Townhomes - Permit Resubmittal Full Set
02/09/2023 Approved Plans approved - NLV Townhomes - Permit Resubmittal Full Set
05/25/2023 Email building identification
05/26/2023 Receipt Receipt for transaction:2023-003701
05/26/2023 Letter DS Building Permit
06/12/2023 Plans 20230427 NLV Townhomes - Current Set
06/13/2023 Letter INSPECTION SUMMARY
06/16/2023 Letter INSPECTION SUMMARY
06/19/2023 Receipt Receipt for transaction:2023-004560
06/19/2023 Letter INSPECTION SUMMARY
06/20/2023 Letter INSPECTION SUMMARY
06/20/2023 Letter Fire Building Plan Review
06/20/2023 Letter Fire Building Plan Review
06/20/2023 Letter Fire Building Plan Review
06/20/2023 Letter INSPECTION SUMMARY
06/28/2023 Letter INSPECTION SUMMARY
06/29/2023 Drawing 20230627 NLV Townhomes - A121
06/29/2023 Drawing 20230627 NLV Townhomes - A221
06/29/2023 Drawing 20230627 A06 - Building 1 Elevations
06/29/2023 Drawing 20230627 A07 - Building 2 Elevations
07/14/2023 Letter INSPECTION SUMMARY
07/14/2023 Letter INSPECTION SUMMARY
07/25/2023 Letter INSPECTION SUMMARY
07/26/2023 Letter INSPECTION SUMMARY
09/07/2023 Letter INSPECTION SUMMARY
09/07/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Approved Plans approved fire sep detail
09/29/2023 Plans 22-01004-35 Fire Suppression Buildings 1&2
09/29/2023 Plans 22-01004-35 Fire Suppression Buildings 3&4
10/02/2023 Letter INSPECTION SUMMARY
10/02/2023 Letter INSPECTION SUMMARY
10/09/2023 Letter Fire (Sprinkler) Plan Review
11/29/2023 Letter INSPECTION SUMMARY
12/20/2023 Code Mod Request Code Modification Request RESIDENTIAL - NLV Townhomes - R302.2.4
12/22/2023 rejected CMR
01/12/2024 Letter Fire Building Plan Review
01/12/2024 Letter INSPECTION SUMMARY
01/23/2024 Letter INSPECTION SUMMARY
01/30/2024 Plans 44424F 001 NLV Devlopment - Longview & Kessler - Fire, Unit A1_1_SEALED
01/30/2024 Plans 44424F 002 NLV Devlopment - Longview & Kessler - Fire, Unit B1_1_SEALED
01/30/2024 Plans 44424F 003 NLV Devlopment - Longview & Kessler - Fire, Unit E1_1_SEALED
01/30/2024 Plans 44424F 004 NLV Devlopment - Longview & Kessler - Fire, Unit F1_1_SEALED
01/30/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/02/2024 Approved Plans 44424F 001 NLV Devlopment - Longview & Kessler - Fire, Unit A1_1_SEALED APPROVED
02/02/2024 Approved Plans 44424F 002 NLV Devlopment - Longview & Kessler - Fire, Unit B1_1_SEALED APPROVED
02/02/2024 Approved Plans 44424F 003 NLV Devlopment - Longview & Kessler - Fire, Unit E1_1_SEALED APPROVED
02/02/2024 Approved Plans 44424F 004 NLV Devlopment - Longview & Kessler - Fire, Unit F1_1_SEALED APPROVED
02/02/2024 Letter INSPECTION SUMMARY
02/22/2024 Letter INSPECTION SUMMARY
02/23/2024 Letter INSPECTION SUMMARY
02/26/2024 Letter INSPECTION SUMMARY
04/10/2024 Letter INSPECTION SUMMARY
04/10/2024 Letter INSPECTION SUMMARY
04/16/2024 Letter INSPECTION SUMMARY
07/16/2024 Letter INSPECTION SUMMARY
07/18/2024 Specifications WATER HEATER DOC
07/19/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/08/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter Fire (Sprinkler) Plan Review
08/09/2024 Letter Fire (Sprinkler) Plan Review
08/09/2024 Letter Fire (Sprinkler) Plan Review
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter Fire (Sprinkler) Plan Review
08/09/2024 Letter INSPECTION SUMMARY
09/05/2024 Letter INSPECTION SUMMARY
09/06/2024 Letter INSPECTION SUMMARY
09/06/2024 Receipt Receipt for transaction:2024-007505
09/06/2024 Letter INSPECTION SUMMARY
09/12/2024 Letter INSPECTION SUMMARY
09/12/2024 Letter INSPECTION SUMMARY
09/12/2024 Letter INSPECTION SUMMARY
09/12/2024 Certificate/License Codes Temporary Certificate of Occupancy
10/31/2024 Letter INSPECTION SUMMARY
10/31/2024 Letter INSPECTION SUMMARY
10/31/2024 Letter INSPECTION SUMMARY
10/31/2024 Certificate/License Codes Temporary Certificate of Occupancy
10/31/2024 Receipt Receipt for transaction:2024-008702
11/18/2024 Letter Field Certificate of Occupancy
11/18/2024 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home