Permit Application Status

PRCOM20246376


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20246376
Building Permit - Commercial
Temporary Occupancy
LSMO TUDOR APARTMENTS LLC
NEW COMMERCIAL
EVREN - CLUBHOUSE AND LEASING OFICE FOR EVREN APARTMENT COMPLEX, PRIVATE SITE DEVELOPMENT **Approved plans are in PRCOM20244879** STOP WORK ORDER generated on 08/15/2025 12:00 AM by username 'Robb Popp'. STOP WORK ORDER removed on 08/15/2025 12:00 AM by username 'John Jackson'. STOP WORK ORDER generated on 01/12/2026 12:00 AM by username 'John Jackson'. STOP WORK ORDER removed on 01/13/2026 12:00 AM by username 'Ryan Heckman'.
12/12/2024
06/26/2025
07/22/2025
Locations
Contacts
CITYSCAPE CONSTRUCTION - TUDOR LLC, Address:10 W CARMEL DRIVE STE 200, Phone:(317) 574-1600  
Shawn Bartholomew, Address:114 DOUGLAS ST SE, Phone:(714) 944-0215  
STANDARD ELECTRIC TOO LLC, Address:2006 E PRAIRIE CIRCLE, Phone:(913) 782-5409  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
Mitsch Design, Address:200 S Rangeline Rd, Phone:(317) 805-1159  
LSMO TUDOR APARTMENTS LLC, Address:10 W CARMEL DR STE 200  
  
STANDARD HEATING & COOLING TOO LLC, Address:2006 E PRAIRIE CIRCLE , Phone:(913) 782-5409  
Reviews
Review Type Outcome Est. Completion Date Completed
Fire Plan Review Approved 02/12/2026 02/12/2026
Craig Hill
Hazardous material identification
Corrective Action Required
02/05/2026

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 2703.5. Action Required: Provide 704 placard for storage of pool chemicals.
Building Plan Review Approved with Conditions 12/30/2024 02/05/2026
Joe Frogge
Planning - Screening of ground mounted equipment
Corrective Action Required
02/05/2026

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (must be either masonry or approved evergreen plantings) 1/17/2025 - Designs are approvable assuming grass is at least as tall as the equipment to be screened. To be field verified during inspections.
Alarm Plan Review Rejected 01/27/2026 01/22/2026
Craig Hill
Miscellaneous Correction
Corrective Action Required
01/22/2026

Action Required: Please provide the code reference of the IFC and NFPA edition used.
Sprinkler Plan Review Rejected 08/27/2025 08/27/2025
Craig Hill
Miscellaneous Correction
Corrective Action Required
08/19/2025

Action Required: Safety Margins need to be 5 or greater. Page 38
Miscellaneous Correction
Corrective Action Required
08/19/2025

Action Required: Change fire department connection to a 4" storz with a 30 degree elbow.
Misc
Corrective Action Required
08/19/2025

Action Required: Ball drip is needed on the "type A, B. C, & D" riser.
Building Plan Review Approved with Conditions 02/05/2025 01/29/2025
Joe Frogge
Planning - Screening of ground mounted equipment
Corrective Action Required
01/29/2025

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (must be either masonry or approved evergreen plantings) 1/17/2025 - Designs are approvable assuming grass is at least as tall as the equipment to be screened. To be field verified during inspections.
IPC 604.9 Water hammer
Resolved
01/29/2025

2018 IPC 604.9 Water hammer. The flow velocity of the water distribution system shall be controlled to reduce the possibility of water hammer. A water-hammer arrestor shall be installed where quick-closing valves are utilized. Water-hammer arrestors shall be installed in accordance with the manufacturer’s instructions. Water-hammer arrestors shall conform to ASSE 1010. Action required: Air chambers not allowed. Remove general notes that give that option. 1/17/2025 - Not addressed. P-series sheets not found in uploads.
Fire Plan Review Approved with Conditions 02/05/2025 01/29/2025
Joe Frogge
Hazardous material identification
Corrective Action Required
01/29/2025

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 2703.5. Action Required: Provide 704 placard for storage of pool chemicals.
Licensed Contractors Approved 01/29/2025 01/29/2025
Joe Frogge
LC - MEP Subs
Resolved
01/29/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 1/17/2025 - Standard Electric is not currently licensed with us.
Fire Plan Review Approved with Conditions 01/23/2025 01/22/2025
Craig Hill
Hazardous material identification
Corrective Action Required
01/15/2025

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 2703.5. Action Required: Provide 704 placard for storage of pool chemicals.
Building Plan Review Rejected 01/23/2025 01/17/2025
Joe Frogge
Planning - Screening of ground mounted equipment
Corrective Action Required
01/15/2025

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (must be either masonry or approved evergreen plantings) 1/17/2025 - Designs are approvable assuming grass is at least as tall as the equipment to be screened. To be field verified during inspections.
IBC 1803.1 General - geotech
Resolved
01/17/2025

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf.
IPC 604.8 Water pressure reducing valve
Resolved
01/17/2025

2018 IPC 604.8 Water Pressure reducing valve or regulator. Where water pressure within a building exceeds 80 psi static, an approved water-pressure reducing valve conforming to ASSE 1003 or CSA B356 with strainer shall be installed to reduce the pressure in the building water distribution piping to not greater than 80 psi static. Action required: Provide pressure reducing valve at water entry. i.e. remove "if" statement from detail 5/MP101. (Our Water Department requires PRV installation in all locations regardless of pressure)
NEC Article 210.8 (B) Other than dwelling units GFCI
Resolved
01/17/2025

2017 NEC Article 210.8 (B) Other Than Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(B)(1) through (10) shall have ground-fault circuit-interrupter protection for personnel. (1) Bathrooms (2) Kitchens (3) Rooftops (4) Outdoors (5) Sinks - where receptacles are installed within 6 feet of the outside edge of the sink. (6) Indoor wet locations (7) Locker rooms with associated showering facilities (8) Garages, service bays, and similar areas other than vehicle exhibition halls and showrooms. (9) Crawl spaces – at or below grade level. (10) Unfinished portions or areas of the basement not intended as habitable rooms. (refer to code for exceptions) Action required: Provide GFCI protection at Kitchenette island.
NEC Article 250.66 Size of AC Grounding electrode conductor
Resolved
01/17/2025

2017 NEC Article 250.66 Size of Alternating-Current Grounding Electrode Conductor. The size of the grounding electrode conductor at the service, at each building or structure where supplied by a feeder(s) or branch circuit(s), or at a separately derived system of a grounded or ungrounded ac system shall not be less than given in Table 250.66, except as permitted in 250.66(A) through (C). Action required: Provide conductor sizes for entire grounding electrode system.
IPC 604.9 Water hammer
Corrective Action Required
01/29/2025

2018 IPC 604.9 Water hammer. The flow velocity of the water distribution system shall be controlled to reduce the possibility of water hammer. A water-hammer arrestor shall be installed where quick-closing valves are utilized. Water-hammer arrestors shall be installed in accordance with the manufacturer’s instructions. Water-hammer arrestors shall conform to ASSE 1010. Action required: Air chambers not allowed. Remove general notes that give that option. 1/17/2025 - Not addressed. P-series sheets not found in uploads.
Misc
Resolved
01/17/2025

Unable to verify pipe materials. Action required: Provide pipe material schedule for all water and sanitary systems.
Licensed Contractors Rejected 01/23/2025 01/17/2025
Joe Frogge
LC - MEP Subs
Corrective Action Required
01/17/2025

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 1/17/2025 - Standard Electric is not currently licensed with us.
Final Development Plan Review Approved 12/30/2024 01/02/2025
Daniel Fernandez
Fire Plan Review Approved with Conditions 12/30/2024 12/30/2024
Craig Hill
Hazardous material identification
Corrective Action Required
12/30/2024

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 2703.5. Action Required: Provide 704 placard for storage of pool chemicals.
Building Plan Review Rejected 12/30/2024 12/20/2024
Joe Frogge
Planning - Screening of ground mounted equipment
Corrective Action Required
12/19/2024

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. (must be either masonry or approved evergreen plantings)
IBC 1803.1 General - geotech
Corrective Action Required
12/19/2024

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf.
IPC 604.8 Water pressure reducing valve
Corrective Action Required
12/20/2024

2018 IPC 604.8 Water Pressure reducing valve or regulator. Where water pressure within a building exceeds 80 psi static, an approved water-pressure reducing valve conforming to ASSE 1003 or CSA B356 with strainer shall be installed to reduce the pressure in the building water distribution piping to not greater than 80 psi static. Action required: Provide pressure reducing valve at water entry. i.e. remove "if" statement from detail 5/MP101. (Our Water Department requires PRV installation in all locations regardless of pressure)
NEC Article 210.8 (B) Other than dwelling units GFCI
Corrective Action Required
12/20/2024

2017 NEC Article 210.8 (B) Other Than Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(B)(1) through (10) shall have ground-fault circuit-interrupter protection for personnel. (1) Bathrooms (2) Kitchens (3) Rooftops (4) Outdoors (5) Sinks - where receptacles are installed within 6 feet of the outside edge of the sink. (6) Indoor wet locations (7) Locker rooms with associated showering facilities (8) Garages, service bays, and similar areas other than vehicle exhibition halls and showrooms. (9) Crawl spaces – at or below grade level. (10) Unfinished portions or areas of the basement not intended as habitable rooms. (refer to code for exceptions) Action required: Provide GFCI protection at Kitchenette island.
NEC Article 250.66 Size of AC Grounding electrode conductor
Corrective Action Required
12/20/2024

2017 NEC Article 250.66 Size of Alternating-Current Grounding Electrode Conductor. The size of the grounding electrode conductor at the service, at each building or structure where supplied by a feeder(s) or branch circuit(s), or at a separately derived system of a grounded or ungrounded ac system shall not be less than given in Table 250.66, except as permitted in 250.66(A) through (C). Action required: Provide conductor sizes for entire grounding electrode system.
IPC 604.9 Water hammer
Corrective Action Required
12/20/2024

2018 IPC 604.9 Water hammer. The flow velocity of the water distribution system shall be controlled to reduce the possibility of water hammer. A water-hammer arrestor shall be installed where quick-closing valves are utilized. Water-hammer arrestors shall be installed in accordance with the manufacturer’s instructions. Water-hammer arrestors shall conform to ASSE 1010. Action required: Air chambers not allowed. Remove general notes that give that option.
Misc
Corrective Action Required
12/20/2024

Unable to verify pipe materials. Action required: Provide pipe material schedule for all water and sanitary systems.
Licensed Contractors Rejected 12/30/2024 12/19/2024
Joe Frogge
LC - General Contractor
Corrective Action Required
12/19/2024

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and the name, email address & phone number for the on-site contact.
LC - MEP Subs
Corrective Action Required
12/19/2024

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Alarm Plan Review Pending 01/30/2026
Zachary Nelson
Miscellaneous Correction
Corrective Action Required
01/23/2026

Action Required: Please provide the code reference of the IFC and NFPA edition used.
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Commercial $4,984.22 $4,984.22 Paid 02/27/2025
Water Tap Fee $10,595.00 $10,595.00 Paid 02/27/2025
Sanitary Sewer Development Fee $6,101.00 $6,101.00 Paid 02/27/2025
Water Meter Fee $1,066.76 $1,066.76 Paid 02/27/2025
Storm Sewer Inspection Fee $8,817.93 $8,817.93 Paid 12/31/2024
Site Grading Fee $14,367.75 $14,367.75 Paid 12/31/2024
Water Test Fee $400.00 $400.00 Paid 12/31/2024
Paved Surface Inspection Fee $42,645.33 $42,645.33 Paid 12/31/2024
Water Insp Fee $9,193.44 $9,193.44 Paid 12/31/2024
Sanitary Sewer Insp Fees $2,846.70 $2,846.70 Paid 12/31/2024
Right of Way Permit Fee $85.00 $85.00 Paid 12/31/2024
Not Ready Inspection Fee $75.00 $75.00 Paid 03/05/2026
Not Ready Inspection Fee $75.00 $75.00 Paid 03/05/2026
Not Ready Inspection Fee $75.00 $75.00 Paid 03/05/2026
Not Ready Inspection Fee $75.00 $75.00 Paid 03/05/2026
Temporary Occupancy Fee $50.00 $50.00 Paid 03/13/2026
Temporary Occupancy Fee $50.00 $50.00 Paid 03/19/2026
Outstanding Fees Amount Paid Owing Date Paid
After Hours Inspections (Public Works)(Per Hour) $50.00 $0.00 $50.00 Not Paid


$50.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Gas Service Inspection - Commercial Pending
In-wall Inspection Pending
Above Ceiling Inspection Pending
Sanitary - Material Verification Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Install Street and Stop Signs Pending
Sidewalk Inspection Pending
Pavement-Stabilized Subgrade Pending
Misc
Informational
05/23/2025
05/23/25 Friday JMJ (CP Excavation/Sup. Kameron) Contractor installing geo-grid and (AB3/compressive rock) for driveway and parking lot upper subgrade. (Contractor was reminded that proof rolls will be performed on geo -grid and materials.)
Grading/Excavation/Fill Inspection Pending
Misc
Informational
08/07/2025
08/07/25 Thursday (Cityscape) Contractor connected sanitary with hard back fernco to stub on the private sanitary and a clean out.
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Miscellaneous Correction
Informational
02/06/2026
06/11/25 Wednesday JMJ (CP Construction) Contractor grading parking lots for asphalt. 06/12/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 asphalt for parking lot at 7:00AM. Superior Bowen delivered 35 trucks of KCMMB A3 base asphalt last truck arrived around 1:30PM. 08/06/25 Wednesday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 base asphalt Superior Bowen had to stop because of inclement weather around 11:30AM. 08/07/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor continued to lay KCMMB A3 base asphalt complete on section of parking lot that was proof roll tested. KAW was the third party inspection on job site. density test were performed on the base asphalt. 09/29/25 Monday JMJ (CP Excavation / Austin) Contractor grading and laying geo-grid.
Storm Sewer Construction Inspection Pending
Misc
Informational
08/15/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains. 06/30/25 Monday JMJ (Gen. Cityscape, CP Excavating) Underground roof drains finished for building #2 and continued installing roof underground drains on building #4. Collars were poured on storm structure throughout the project. 07/01/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) Contractor continues to install underground roof drains for building #4 and garage. 07/07/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor removed and abandon approximately 26' of existing storm that connected to old basin. The grading will be changed and the structure of the basin was change. 07/10/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains to garage #3. 08/15/25 Friday JMJ (Gen. Cityscape, CP Excavating-Austin) Contractor removed 35' of 15" HDPE storm pipe around building #4 because the conflict with the retaining wall.
Water Line - Coliform Test 1 Pending
Water Service Inspection Pending
Misc
Informational
09/29/2025
09/29/25 Monday (CP Excavation/ Austin) Contractor flush the chlorine from the fire line. Line was chlorinated on Friday.
Curb - Proof Roll Pending
Pavement-Proof Roll Pending
Misc
Informational
10/08/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location. Correction: 06/02/25 Monday proof roll for curb was passed and curbs were installed. 06/11/25 Wednesday JMJ Contractor passed the proof roll. Third party was Kaw Valley. There was some deflection in three different valley point in parking lot area, but no rutting. 07/29/25 Tuesday JMJ ( Cityscape, CP) Contractor passed proof roll for the East and Southside. 10/01/25 Tuesday JMJ (Gen. Cityscape, Sub. CP, Third Party Testing Kaw Valley) Contractor passed proof roll on the Southwest side of project. The storm box in the parking lot area of building #2. 10/08/25 Wednesday JMJ ( Gen. CityScape, Sub. CP Excavation, Third KAW Valley) Proof Roll passed and the KAW Valley inspector was present.
Pavement-Curb Construction Pending
Misc
Informational
10/10/2025
10/09/25 Thursday JMJ (Bedrock Construction) Contractor poured curbs for turn lanes. 10/10/25 Friday JMJ (Bedrock Construction) Curb poured turn lanes yesterday and apron and curbs off NW Commerce Road.
Miscellaneous Inspection Pending
Misc
Corrective Action Required
10/13/2025
Rated Assembly Inspection Pending
Misc
Corrective Action Required
11/07/2025
shear walls approved
Pool Steel/Bonding - Commercial Pending
Misc
Informational
11/21/2025
Components bonded: -(12) points at shell, (2) sets of handrail sleeves, (4) light niches
Water Line - Construction Inspection Pending
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Storm Sewer Construction Inspection Pending
Underground Electrical Inspection - Commercial Pending
Misc
Informational
02/10/2026
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: -Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6, (3) light poles east of building 4 -Conduit for 3 light pole od South East edge of lot -Conduit for (3) light poles S of building 2 and to garages at building 2 -Conduit for 4 lights on the East and West side of building 4 -From clubhouse to NW light pole -From clubhouse to SW (3) light poles -From building 5 to west light pole at north entry
Piers/Caissons Inspection - Commercial Pending
Misc
Informational
02/10/2026
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6 (4) east of building 4 (4) west of building 7 (1) north of building 2 (2) SW of club house (2) S of club house (3) SW of building 7 (1) NW of clubhouse
Occupancy Inspection - Planning Pending
Miscellaneous Correction
Corrective Action Required
03/12/2026
Awaiting final landscaping and vegetation. All site landscaping and vegetation will be reviewed under this permit.
Occupancy Inspection - Engineering Pending
Misc
Informational
03/12/2026
03/12/26 Thursday JMJ TCO given for Club House @3:30PM Punch LIst 1. Grading and Seeding or Sod. 2. Repairing sprinkler system head. 3. Installing cap over sanitary clean-out on general site.
Occupancy Inspection - Codes Commercial Pending
Misc
Corrective Action Required
03/16/2026
-Complete corrections for all other departments -Seal all exterior penetrations -Complete pool equipment room -Complete exit paths to courtyard and pool
Site Visit Pending
Misc
Informational
03/18/2026
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading 12/11/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor took the sample yesterday and today. 1-6-25 PS Made site visit, no activity for dev today 01/14/26 JMJ Concentration on site clean-up contractor has failed a number of erosion control inspection and give two days from 01/13/26 to clean up sediment spreading across parking lot, adjacent streets, and failed silt erosion control. 2/10/26 PS Made site visit, CP Excavating moving dirt and grading. 03/18/26 Wednesday JMJ (CityScape) Contractor performing general construction work on site, no inspection required at this time.
Pavement-Surface Pending
Misc
Informational
03/30/2026
06/10/25 Tuesday JMJ (Cityscape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach. Approach was poured, cured, and saw cut.
Misc
Informational
03/30/2026
10/09/25 Thursday JMJ (Gen. Cityscape, Sub. Seal-O-Matic, Third party KAW) Contractor laid KCMMB A3 1,286 ton 51 loads. Third party testing was on site KAW Valley. 10/10/25 Friday JMJ (Gen. Cityscape, Sub Bedrock Concrete) Contractor poured concrete of turning lane going Westbound. Curbs were poured yesterday. Approach was poured on for the entrances of NW Commerce Road. Sidewalk and ADA ramps were poured on Tudor Road. 1013/25 Monday JMJ ( Gen. CityScape, Sub Bedrock Concrete) Contractor poured drive approach on NW Commerce Road @ 6:30AM.
Misc
Informational
03/30/2026
03/30/26 Monday JMJ (Sub. Seal-O-Matic) Contractor laid KCMMB A2 656.79 Tons, 26 Loads of surface asphalt. The entrance off 25NE Tudor Rd, the parking lot area for two of apartment complexes.
Erosion Control Inspection Residential Pending
Misc
Informational
04/02/2026
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control. 03/25/26 Wednesday JMJ (CityScape) Erosion control appears to be functioning properly. 04/01/26 Wednesday JMJ (CityScape) Entrances and street on NW Commerce DR need to be clean from the mud and silt from project site. Also the curbs and gutter buddies need to check ensure the clear of debris. 04/02/26 Thursday JMJ (CityScape) Contractor appears to correct the mud and silt athe the entrances on NW Commerce Drive and the gutter buddies appeared fairly clear of obstruction.
Footing Inspection - Commercial Failed 4/17/2025 4/17/2025 04/17/2025
Misc
Corrective Action Required
04/17/2025
4/17/25 -Footings for building 5 scheduled on clubhouse permit. Obtain proper, issued permit
Water Line - Construction Inspection Partial 05/01/2025
Misc
Informational
05/01/2025
05/01/25 Thursday JMJ ( Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain maker on the North and South end boring on street.(04/30/25).
Water Line - Construction Inspection Partial 5/1/2025 5/1/2025 05/01/2025
Misc
Informational
05/01/2025
05/01/25 Thursday JMJ ( Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road.
Sanitary Sewer Construction Inspection Partial 5/1/2025 5/1/2025 05/01/2025
Misc
Informational
05/01/2025
05/01/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 49' of 6" SDR-26 sanitary pipe for building #7 & 147' of 6" SDR-26 sanitary pipe for building #8.
Storm Sewer Construction Inspection Partial 5/5/2025 5/5/2025 05/05/2025
Misc
Informational
05/05/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25.
Sanitary Sewer Construction Inspection Partial 5/5/2025 5/5/2025 05/05/2025
Misc
Informational
05/01/2025
05/01/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 49' of 6" SDR-26 sanitary pipe for building #7 & 147' of 6" SDR-26 sanitary pipe for building #8. 05/02/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 90' of 6" SDR-26 sanitary pipe for building #4, 94' of 6" SDR-26 sanitary pipe for Maintenance building as per project plans.
Storm Sewer Construction Inspection Partial 5/5/2025 5/5/2025 05/05/2025
Misc
Informational
05/05/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49.
Sanitary Sewer Construction Inspection Partial 5/7/2025 5/7/2025 05/07/2025
Misc
Informational
05/05/2025
05/01/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 49' of 6" SDR-26 sanitary pipe for building #7 & 147' of 6" SDR-26 sanitary pipe for building #8. 05/02/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 90' of 6" SDR-26 sanitary pipe for building #4, 94' of 6" SDR-26 sanitary pipe for Maintenance building as per project plans. 05/07/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary building #1 stub 54ft of 6" SDR-26 pipe.
Water Line - Construction Inspection Partial 5/6/2025 5/6/2025 05/07/2025
Misc
Informational
05/01/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends.
Erosion Control Inspection Residential Partial 5/7/2025 5/7/2025 05/08/2025
Misc
Informational
05/08/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly.
Underground Electrical Inspection - Commercial Partial 5/9/2025 5/9/2025 05/09/2025
Misc
Informational
05/09/2025
Conduit for (3) light poles South of building 5 and (1) SE of building 8
Footing Inspection - Commercial Failed 5/14/2025 5/14/2025 05/14/2025
Misc
Corrective Action Required
04/17/2025
Post site address before requesting inspections
Piers/Caissons Inspection - Commercial Partial 5/14/2025 5/14/2025 05/14/2025
Misc
Informational
05/14/2025
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (1) southeast of building 8
Water Line - Construction Inspection Partial 05/15/2025
Misc
Informational
05/07/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.
Storm Sewer Construction Inspection Partial 05/15/2025
Misc
Informational
05/05/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A.
Storm Sewer Construction Inspection Partial 05/15/2025
Misc
Informational
05/15/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A.
Storm Sewer Construction Inspection Partial 05/21/2025
Misc
Informational
05/15/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing.
Storm Sewer Construction Inspection Partial 5/21/2025 5/21/2025 05/21/2025
Misc
Informational
05/21/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2.
Pavement-Proof Roll Passed 5/22/2025 5/22/2025 05/22/2025
Misc
Informational
05/22/2025
05/22/25 Thursday JMJ (Gen. Titians Construction, Sub. Hanrranh Pavement, UES Geotech) Proof Roll passed geo grid was installed.
Storm Sewer Construction Inspection Partial 05/22/2025
Misc
Informational
05/21/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E.
Pavement-Stabilized Subgrade Partial 5/23/2025 5/23/2025 05/23/2025
Misc
Informational
05/23/2025
05/23/25 Friday JMJ (CP Excavation/Sup. Kameron) Contractor installing geo-grid and (AB3/compressive rock) for driveway and parking lot upper subgrade. (Contractor was reminded that proof rolls will be performed on geo -grid and materials.)
Water Line - Construction Inspection Partial 05/27/2025
Misc
Informational
05/15/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'.
Erosion Control Inspection Residential Partial 05/27/2025
Misc
Informational
05/08/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ Erosion control appears to be functioning properly.
Storm Sewer Construction Inspection Partial 5/27/2025 5/27/2025 05/27/2025
Misc
Informational
05/22/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6.
Footing Inspection - Commercial Partial 5/28/2025 5/28/2025 05/28/2025
Misc
Informational
05/28/2025
Lines B, C, D, 6 and 7 complete. Line 1 complete from B to E
Water Line - Construction Inspection Partial 5/28/2025 5/28/2025 05/28/2025
Misc
Informational
05/27/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6.
Pavement-Curb Construction Partial 06/02/2025
Misc
Informational
06/02/2025
06/02/25 Monday JMJ (Bedrock Concrete) Contractor poured approximately 40yds of concrete for private curbs.
Water Line - Construction Inspection Partial 06/02/2025
Misc
Informational
05/28/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4.
Storm Sewer Construction Inspection Partial 06/02/2025
Misc
Informational
05/27/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.
Erosion Control Inspection Residential Failed 6/4/2025 6/4/2025 06/04/2025
Misc
Informational
05/27/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive.
Water Line - Construction Inspection Partial 6/6/2025 6/6/2025 06/06/2025
Misc
Informational
06/02/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant.
Pavement-Proof Roll Partial 6/6/2025 6/6/2025 06/06/2025
Misc
Informational
06/06/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location.
Pavement-Proof Roll Partial 06/06/2025
Misc
Informational
06/06/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location. Correction: 06/02/25 Monday proof roll for curb was passed and curbs were installed
Pavement-Surface Partial 6/10/2025 6/10/2025 06/10/2025
Misc
Informational
06/10/2025
06/10/25 Tuesday JMJ (CityScape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach.
Storm Sewer Construction Inspection Partial 6/10/2025 6/10/2025 06/10/2025
Misc
Informational
06/02/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday.
Water Line - Construction Inspection Partial 6/10/2025 6/10/2025 06/10/2025
Misc
Informational
06/06/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building #7.
Storm Sewer Construction Inspection Partial 06/10/2025
Misc
Informational
06/10/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today.
Pavement-Surface Partial 06/10/2025
Misc
Informational
06/10/2025
06/10/25 Tuesday JMJ (Cityscape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach. Approach was poured, cured, and saw cut.
Pavement-Aggregate Base Partial 6/11/2025 6/11/2025 06/11/2025
Misc
Informational
06/11/2025
06/11/25 Wednesday JMJ (CP Construction) Contractor grading parking lots for asphalt.
Footing Inspection - Commercial Passed 6/11/2025 6/11/2025 06/11/2025
Misc
Resolved
06/11/2025
Lines B, C, D, 6 and 7 complete. Line 1 complete from B to E
Pavement-Proof Roll Partial 6/11/2025 6/11/2025 06/11/2025
Misc
Informational
06/06/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location. Correction: 06/02/25 Monday proof roll for curb was passed and curbs were installed. 06/11/25 Wednesday JMJ Contractor passed the proof roll. Third party was Kaw Valley. There was some deflection in three different valley point in parking lot area, but no rutting.
Storm Sewer Construction Inspection Partial 6/11/2025 6/11/2025 06/11/2025
Misc
Informational
06/10/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B.
Site Visit Partial 6/11/2025 6/11/2025 06/11/2025
Misc
Informational
06/11/2025
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site.
Water Line - Construction Inspection Partial 6/10/2025 6/10/2025 06/12/2025
Misc
Informational
06/10/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building
Water Line - Construction Inspection Partial 06/12/2025
Misc
Informational
06/12/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans.
Storm Sewer Construction Inspection Partial 6/12/2025 6/12/2025 06/12/2025
Misc
Informational
06/11/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7.
Pavement-Aggregate Base Partial 6/12/2025 6/12/2025 06/12/2025
Misc
Informational
06/11/2025
06/11/25 Wednesday JMJ (CP Construction) Contractor grading parking lots for asphalt. 06/12/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 asphalt for parking lot at 7:00AM. Superior Bowen delivered 35 trucks of KCMMB A3 base asphalt last truck arrived around 1:30PM.
Erosion Control Inspection Partial 6/13/2025 6/13/2025 06/13/2025
Misc
Informational
06/13/2025
06/13/25 Friday JMJ (Cityscape, CP Excavating) Talked with contractor about cleaning up the street of soil track on adjacent streets of project Tudor Rd & NW Commerce Drive. The contractor is power washing NW Commerce Drive due to the dump trucks hauling dirt to approved site.
Water Line - Construction Inspection Partial 6/16/2025 6/16/2025 06/16/2025
Misc
Informational
06/12/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day.
Water Line - Construction Inspection Partial 6/17/2025 6/17/2025 06/17/2025
Misc
Informational
06/16/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains.
Underslab Plumbing Inspection - Commercial Passed 6/17/2025 6/17/2025 06/17/2025
Underground Electrical Inspection - Commercial Partial 6/17/2025 06/17/2025
Misc
Informational
05/09/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: Conduit for (3) light poles South of building 5 and (1) SE of building 8
Underslab Electrical Inspection - Commercial Passed 6/18/2025 6/18/2025 06/18/2025
Underground Electrical Inspection - Commercial Partial 6/20/2025 06/20/2025
Misc
Informational
06/17/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6
Piers/Caissons Inspection - Commercial Partial 6/23/2025 6/23/2025 06/20/2025
Misc
Informational
05/14/2025
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6
Underslab Electrical Inspection - Commercial Passed 6/23/2025 6/23/2025 06/23/2025
Sanitary Sewer Construction Inspection Partial 6/18/2025 6/18/2025 06/23/2025
Misc
Informational
05/07/2025
05/01/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 49' of 6" SDR-26 sanitary pipe for building #7 & 147' of 6" SDR-26 sanitary pipe for building #8. 05/02/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 90' of 6" SDR-26 sanitary pipe for building #4, 94' of 6" SDR-26 sanitary pipe for Maintenance building as per project plans. 05/07/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary building #1 stub 54ft of 6" SDR-26 pipe. 06/18/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary for Club House.
PW-Sanitary Sewer Testing
Informational
07/14/2025
07/14/25 Monday JMJ (Gen. Cityscape, CP Excavating) Sanitary air test A-7 to A-6 07/11/, A-6 to A-5, A-5 to A-4, A-4 to A3, & A-2 to A-1 passed 07/14/25 Monday. Sanitary air test A-3 to A-2 failed 07/14/25 . Contractor will retest (A-3 to A-2) line on 07/15/25 Tuesday will test tomorrow. Mandrel A-7 to A-6, A-6 to A-5, A-5 to A-4, A-4 to A-3, & A-3 to A-2 passed 07/14/25 Monday. Vacuum Pressure Manhole A-4, A-5, & A-6 passed 07/14/25 Monday.
Storm Sewer Construction Inspection Partial 6/18/2025 6/18/2025 06/23/2025
Misc
Informational
06/12/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building.
Water Line - Construction Inspection Partial 6/20/2025 6/20/2025 06/23/2025
Misc
Informational
06/17/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later.
Underground Electrical Inspection - Commercial Partial 6/23/2025 6/23/2025 06/23/2025
Misc
Informational
06/20/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6
Piers/Caissons Inspection - Commercial Partial 6/23/2025 6/23/2025 06/23/2025
Misc
Informational
06/20/2025
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6 (1) east of building 4
Water Line - Construction Inspection Partial 6/24/2025 6/24/2025 06/24/2025
Misc
Informational
06/23/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose.
Water Line - Construction Inspection Partial 6/26/2025 6/26/2025 06/26/2025
Misc
Informational
06/24/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3.
Underground Electrical Inspection - Commercial Partial 6/27/2025 06/27/2025
Misc
Informational
06/23/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6, (3) light poles east of building 4
Storm Sewer Construction Inspection Partial 6/27/2025 6/27/2025 06/27/2025
Misc
Informational
06/23/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains.
Underground Electrical Inspection - Commercial Partial 6/30/2025 6/30/2025 06/30/2025
Misc
Informational
06/27/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6, (3) light poles east of building 4 Conduit for 3 light pole od South East edge of lot Conduit for 4 lights on the East and West side of building 4
Storm Sewer Construction Inspection Partial 6/30/2025 6/30/2025 07/01/2025
Misc
Informational
06/27/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains. 06/3025 Monday JMJ (Gen. Cityscape, CP Excavating) Underground roof drains finished for building #2 and continued installing roof underground drains on #4. Collars were poured on storm structure throughout the project.
Water Line - Construction Inspection Partial 6/30/2025 6/30/2025 07/01/2025
Misc
Informational
06/26/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project.
Storm Sewer Construction Inspection Partial 7/1/2025 7/1/2025 07/01/2025
Misc
Informational
07/01/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains. 06/30/25 Monday JMJ (Gen. Cityscape, CP Excavating) Underground roof drains finished for building #2 and continued installing roof underground drains on building #4. Collars were poured on storm structure throughout the project. 07/01/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) Contractor continues to install underground roof drains for building #4 and garage.
Water Line - Construction Inspection Partial 7/2/2025 7/2/2025 07/02/2025
Misc
Informational
07/01/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans.
Piers/Caissons Inspection - Commercial Partial 7/2/2025 7/2/2025 07/02/2025
Misc
Informational
06/23/2025
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6 (4) east of building 4 (4) west of building 7
Water Line - Construction Inspection Partial 7/3/2025 7/3/2025 07/03/2025
Misc
Informational
07/02/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project.
Erosion Control Inspection Residential Partial 7/3/2025 7/3/2025 07/03/2025
Misc
Informational
06/04/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly.
Storm Sewer Construction Inspection Partial 7/7/2025 7/7/2025 07/07/2025
Misc
Informational
07/01/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains. 06/30/25 Monday JMJ (Gen. Cityscape, CP Excavating) Underground roof drains finished for building #2 and continued installing roof underground drains on building #4. Collars were poured on storm structure throughout the project. 07/01/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) Contractor continues to install underground roof drains for building #4 and garage. 07/07/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor removed and abandon approximately 26' of existing storm that connected to old basin. The grading will be changed and the structure of the basin was change.
Water Line - Construction Inspection Partial 7/8/2025 7/8/2025 07/08/2025
Misc
Informational
07/03/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project. Contractor also poured back block and straddle blocks throughout the project. 07/08/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install fire line around the proposed pool structure.
Storm Sewer Construction Inspection Partial 7/10/2025 7/10/2025 07/10/2025
Misc
Informational
07/07/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains. 06/30/25 Monday JMJ (Gen. Cityscape, CP Excavating) Underground roof drains finished for building #2 and continued installing roof underground drains on building #4. Collars were poured on storm structure throughout the project. 07/01/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) Contractor continues to install underground roof drains for building #4 and garage. 07/07/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor removed and abandon approximately 26' of existing storm that connected to old basin. The grading will be changed and the structure of the basin was change. 07/10/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains to garage #3.
Water Line - Construction Inspection Partial 7/10/2025 7/10/2025 07/10/2025
Misc
Informational
07/08/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project. Contractor also poured back block and straddle blocks throughout the project. 07/08/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install fire line around the proposed pool structure. 07/10/25 Thursday JMJ (CP Excavation Kameron) Installed hydrant at the garage #3.
Sanitary Sewer Construction Inspection Partial 7/16/2025 7/16/2025 07/16/2025
Misc
Informational
06/23/2025
05/01/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 49' of 6" SDR-26 sanitary pipe for building #7 & 147' of 6" SDR-26 sanitary pipe for building #8. 05/02/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 90' of 6" SDR-26 sanitary pipe for building #4, 94' of 6" SDR-26 sanitary pipe for Maintenance building as per project plans. 05/07/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary building #1 stub 54ft of 6" SDR-26 pipe. 05/18/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary for Club House. 07/16/25 Wednesday JMJ (Gen. Cityscape, Garrison Const.) Contractor connect to the sanitary outlet to the clean out @ Building #5, 8, & 6.
Water Line - Construction Inspection Partial 7/16/2025 7/16/2025 07/16/2025
Misc
Informational
07/10/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project. Contractor also poured back block and straddle blocks throughout the project. 07/08/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install fire line around the proposed pool structure. 07/10/25 Thursday JMJ (CP Excavation Kameron) Installed hydrant at the garage #3. 07/16/25 Wednesday JMJ (CP Excavation - Kameron) Contractor began to install backflow vault.
Water Line - Construction Inspection Partial 7/22/2025 7/22/2025 07/22/2025
Misc
Informational
07/16/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project. Contractor also poured back block and straddle blocks throughout the project. 07/08/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install fire line around the proposed pool structure. 07/10/25 Thursday JMJ (CP Excavation Kameron) Installed hydrant at the garage #3. 07/16/25 Wednesday JMJ (CP Excavation - Kameron) Contractor began to install backflow vault. 07/22/25 Tuesday JMJ (CP Excavation - Kameron) Contractor installed 8X12X12 Tee and pipe 8" pipe, fittings,45 bend on 8", 3/valves for backflow vault. Contractor set backflow and began construction on vault floor. 2/12" butterfly on the public water main.
Pavement-Proof Roll Partial 7/29/2025 7/29/2025 07/29/2025
Misc
Informational
06/11/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location. Correction: 06/02/25 Monday proof roll for curb was passed and curbs were installed. 06/11/25 Wednesday JMJ Contractor passed the proof roll. Third party was Kaw Valley. There was some deflection in three different valley point in parking lot area, but no rutting. 07/29/25 Tuesday JMJ ( Cityscape, CP) Contractor passed proof roll for the East and Southside.
Water Line - Construction Inspection Partial 7/31/2025 7/31/2025 07/31/2025
Misc
Informational
07/22/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project. Contractor also poured back block and straddle blocks throughout the project. 07/08/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install fire line around the proposed pool structure. 07/10/25 Thursday JMJ (CP Excavation Kameron) Installed hydrant at the garage #3. 07/16/25 Wednesday JMJ (CP Excavation - Kameron) Contractor began to install backflow vault. 07/22/25 Tuesday JMJ (CP Excavation - Kameron) Contractor installed 8X12X12 Tee and pipe 8" pipe, fittings,45 bend on 8", 3/valves for backflow vault. Contractor set backflow and began construction on vault floor. 2/12" butterfly on the public water main. 07/31/25 Thursday JMJ (CP Excavating - Austin) Contractor installed approximately 140' of 8" PVC water pipe yesterday and today going Eastward out of the backflow vault on NW Commerce Drive. As per project plans.
Grading/Excavation/Fill Inspection Partial 08/07/2025
Misc
Informational
08/07/2025
08/07/25 Thursday (Cityscape) Contractor connected sanitary with hard back fernco to stub on the private sanitary and a clean out.
Pavement-Aggregate Base Partial 8/8/2025 8/8/2025 08/08/2025
Misc
Informational
06/12/2025
06/11/25 Wednesday JMJ (CP Construction) Contractor grading parking lots for asphalt. 06/12/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 asphalt for parking lot at 7:00AM. Superior Bowen delivered 35 trucks of KCMMB A3 base asphalt last truck arrived around 1:30PM. 08/06/25 Wednesday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 base asphalt Superior Bowen had to stop because of inclement weather around 11:30AM. 08/07/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor continued to lay KCMMB A3 base asphalt complete on section of parking lot that was proof roll tested. KAW was the third party inspection on job site. density test were performed on the base asphalt.
Miscellaneous Inspection Failed - Stop Work 08/15/2025
Misc
Corrective Action Required
08/15/2025
VERTICAL CONSTRUCTION HAS NOT BEEN APPROVED, PERMIT IS IN PARTIAL ISSUED STATUS. STOP WORK ISSUED.
Storm Sewer Construction Inspection Partial 8/15/2025 8/15/2025 08/15/2025
Misc
Informational
07/10/2025
05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 60' of 24" HDPE storm pipe & cored into existing storm structure 05/02/25. 05/05/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collars and installed encasement of storm pipe as per project. Concrete block was poured at out going nyoplast structure to prevent floatation C49. 05/13/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) From Monday to Tuesday contractor installed approximately 183' of 30" HDPE storm line on #2 . Starting from the basin @ Sta 0+00 to 1+83 including storm structures 2A & 2B. 05/15/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed approximately 175' of 15" HDPE storm line on #4 with the storm structure 4A. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 2C & 2D on Friday and Monday. Inspector was not at work on 5/16 and 5/19 inspection were completed by fellow inspector. Contractor installed approximately 144' of 30" HDPE. Today contractor has already installed approximately 25' of 24" HDPE and continuing. 05/21/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor poured collar, invert, on storm line and toe wall on line #2. 05/21/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed from Manhole 2D to Drain Basin 2E, 121' of 24" HDPE storm pipe & approximately 80' of 18" HDPE storm pipe after storm structure 2E. 05/27/25 Tuesday (Gen. Cityscape, CP Excavating) Contractor installed approximately 80' of 8" roof drain off of building #6. 06/02/25 Monday (Gen. Cityscape, CP Excavating) Contractor continues to install roof drain for building #6.\ 06/10/25 Tuesday ( Gen. Cityscape, CP Excavating) Contractor completed the of storm in front of building #4 on 06/09/25 Monday. Roof drain 1A and roof drain 1B structure plus stub offs installed today. 06/11/25 Wednesday ( Gen. Cityscape, CP Excavating) Contractor installed approximately 200' of 15" HPDE storm pipe. Starting at curb inlet H1, thru, curb inlet 5A & 5B. 06/12/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor install 6" HPDE storm roof drains pipe underground roof drain extensions on building #7. Also contractor poured inverts and collars on structure and storm line #6 that are connected to building #7. 06/18/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains the maintenance/ pool building. 06/27/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor continued the install of roof drain around building #3 and incerta tees on building #1. 2nd crew installed underground detach roof drains. 06/30/25 Monday JMJ (Gen. Cityscape, CP Excavating) Underground roof drains finished for building #2 and continued installing roof underground drains on building #4. Collars were poured on storm structure throughout the project. 07/01/25 Tuesday JMJ (Gen. Cityscape, CP Excavating) Contractor continues to install underground roof drains for building #4 and garage. 07/07/25 Monday JMJ (Gen. Cityscape, CP Excavating) Contractor removed and abandon approximately 26' of existing storm that connected to old basin. The grading will be changed and the structure of the basin was change. 07/10/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed underground roof drains to garage #3. 08/15/25 Friday JMJ (Gen. Cityscape, CP Excavating-Austin) Contractor removed 35' of 15" HDPE storm pipe around building #4 because the conflict with the retaining wall.
Water Line - Construction Inspection Partial 08/21/2025
Misc
Informational
07/31/2025
05/01/25 Thursday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor bored installed casing under South NW Commerce Dr. for the Combination water meter & backflow valve vault. Contractor waited on locator to help explain markings on the North and South end boring on street. 50' casing was completed on the South end going running East to West, and the Eastside of the road was backfilled. The contractor may start to bore the North end along NW Commerce & Tudor Road. 05/06/25 Wednesday JMJ (Gen. Cityscape, Sub. CP Excavation) Contractor installed approximate 60' of private water with 2-45 deg bends. 05/15/25 Thursday JMJ (Sub. CP Excavation) Contractor installed approximately 80' of 12" PVC water line from Sta 13+00 to 12+20 public water main.05/27/25 Tuesday JMJ (Contractor-McCown Gordon / Sub-Site Rite) Contractor installed 3 tees as per project plans (C53) building #6 & 6" valve approximately 30'. 05/28/25 Wednesday JMJ (CP Excavation Kameron) Contractor installed approximately 160' of 6" PVC Fire Line, 160' of 4" Fire suppression line, 160' of 2" domestic water for building #6. 06/02/25 Monday JMJ (CP Excavation Kameron) Contractor working on installing water line to building #4. 06/06/25 Thursday 195' of fire main for building #4 to #7 (2/45bends, 2/tees, and 15' of 6" and valve for fire hydrant. 06/09/25 Monday JMJ (CP Excavation Kameron) Contractor installed 160ft of 8" water main. 2/45 bends, 2/tees in front of building 06/12/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to install 2" domestic & 4" water line for building #7. Contractor also poured backing blocks for bends as-per project plans. 06/16/25 Monday JMJ (CP Excavation Kameron) Contractor continue to install Fire line approximately 265' of 8" PVC/ with a 8"X6" tee for hydrant on line B. Contractor ran to rock near the end of the day. 06/17/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install 8" fire line approximately 140'. Contractor backfilled excavation due to threating rains. 06/20/25 Friday JMJ (CP Excavation Kameron) Inspector was off duty, but 100' of 6" fire line was installed for building #2 and 10' for Building #4 both with fire hydrant stub for hydrant to be installed later. 06/24/25 Tuesday JMJ (CP Excavation Kameron) Contractor continue to install fire line around building #2 and Pool Hose. 06/25/25 Wednesday JMJ (CP Excavation Kameron) Contractor continue to install fire line approximately 100' around building #3. 06/30/25 Friday JMJ (CP Excavation Kameron) Contractor poured kickers / backing blocks on bends and fittings throughout the project. 07/02/25 Wednesday JMJ (CP Excavation Kameron) Contractor installing fire line #A going West toward NW Commerce DR. as-per project plans. 07/03/25 Thursday JMJ (CP Excavation Kameron) Contractor continued to installed fire line contractor also install fire throughout the project. Contractor also poured back block and straddle blocks throughout the project. 07/08/25 Tuesday JMJ (CP Excavation Kameron) Contractor continued to install fire line around the proposed pool structure. 07/10/25 Thursday JMJ (CP Excavation Kameron) Installed hydrant at the garage #3. 07/16/25 Wednesday JMJ (CP Excavation - Kameron) Contractor began to install backflow vault. 07/22/25 Tuesday JMJ (CP Excavation - Kameron) Contractor installed 8X12X12 Tee and pipe 8" pipe, fittings,45 bend on 8", 3/valves for backflow vault. Contractor set backflow and began construction on vault floor. 2/12" butterfly on the public water main. 07/31/25 Thursday JMJ (CP Excavating - Austin) Contractor installed approximately 140' of 8" PVC water pipe yesterday and today going Eastward out of the backflow vault on NW Commerce Drive. As per project plans. 08/21/25 Thursday JMJ (CP Excavating - Austin) Contractor continued to work on the construction meters to the water main.
Water Line - Construction Inspection Partial 8/22/2025 8/22/2025 08/22/2025
Misc
Informational
08/22/2025
08/22/25 Friday JMJ Meters were set installed building #5, #6, & #8.
Erosion Control Inspection Residential Partial 09/02/2025
Misc
Informational
07/03/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 09/02/25 Tuesday JMJ Erosion control appears to be functioning properly.
Sanitary Sewer Construction Inspection Partial 8/7/2025 09/12/2025
Misc
Informational
07/16/2025
05/01/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 49' of 6" SDR-26 sanitary pipe for building #7 & 147' of 6" SDR-26 sanitary pipe for building #8. 05/02/25 Friday JMJ (Gen. Cityscape, CP Excavating) Contractor installed 90' of 6" SDR-26 sanitary pipe for building #4, 94' of 6" SDR-26 sanitary pipe for Maintenance building as per project plans. 05/07/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary building #1 stub 54ft of 6" SDR-26 pipe. 05/18/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Private sanitary for Club House. 07/16/25 Wednesday JMJ (Gen. Cityscape, CP Excavating) Contractor connect to the sanitary outlet to the clean out @ Building #5, 8, & 6. 09/12/25 Friday JMJ (Gen. Cityscape, Garrison Plumbing) Contractor connected to the sanitary outlet to clean out @ Building #7
Underground Electrical Inspection - Commercial Partial 9/16/2025 9/16/2025 09/16/2025
Misc
Informational
06/30/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: -Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6, (3) light poles east of building 4 -Conduit for 3 light pole od South East edge of lot -Conduit for (3) light poles S of building 2 and to garages at building 2 -Conduit for 4 lights on the East and West side of building 4
Piers/Caissons Inspection - Commercial Partial 9/17/2025 9/17/2025 09/17/2025
Misc
Informational
07/02/2025
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6 (4) east of building 4 (4) west of building 7 (1) north of building 2
Water Line - Hydrostatic Test Passed 9/25/2025 9/25/2025 09/25/2025
Misc
Informational
09/25/2025
9-25-25 PS Hydrostatic test passed, 200 psi for 2 hours
Water Service Inspection Partial 9/29/2025 9/29/2025 09/29/2025
Misc
Informational
09/29/2025
09/29/25 Monday (CP Excavation/ Austin) Contractor flush the chlorine from the fire line. Line was chlorinated on Friday.
Pavement-Aggregate Base Partial 9/29/2025 9/29/2025 09/29/2025
Misc
Informational
08/08/2025
06/11/25 Wednesday JMJ (CP Construction) Contractor grading parking lots for asphalt. 06/12/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 asphalt for parking lot at 7:00AM. Superior Bowen delivered 35 trucks of KCMMB A3 base asphalt last truck arrived around 1:30PM. 08/06/25 Wednesday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor began laying KCMMB A3 base asphalt Superior Bowen had to stop because of inclement weather around 11:30AM. 08/07/25 Thursday JMJ (Sub. Seal-O-Matic-- Foreman Scott Osborne) Contractor continued to lay KCMMB A3 base asphalt complete on section of parking lot that was proof roll tested. KAW was the third party inspection on job site. density test were performed on the base asphalt. 09/29/25 Monday JMJ (CP Excavation / Austin) Contractor grading and laying geo-grid.
Pavement-Proof Roll Partial 10/1/2025 10/1/2025 10/01/2025
Misc
Informational
07/29/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location. Correction: 06/02/25 Monday proof roll for curb was passed and curbs were installed. 06/11/25 Wednesday JMJ Contractor passed the proof roll. Third party was Kaw Valley. There was some deflection in three different valley point in parking lot area, but no rutting. 07/29/25 Tuesday JMJ ( Cityscape, CP) Contractor passed proof roll for the East and Southside. 10/01/25 Tuesday JMJ (Gen. Cityscape, Sub. CP, Third Party Testing Kaw Valley) Contractor passed proof roll on the Southwest side of project. The storm box in the parking lot area of building #2.
Pavement-Curb Construction Partial 10/3/2025 10/3/2025 10/03/2025
Misc
Informational
06/02/2025
06/02/25 Monday JMJ (Bedrock Concrete) Contractor poured approximately 40yds of concrete for private curbs. 10/03/25 Friday JMJ (Bedrock Concrete) Contractor poured 30yds of curbs yesterday and plans to pour 50yds today. White cure was used curbs. Talked with contractor to repair some areas with excess honey come in the curbs mainly around curb bends. West of Clubhouse and around building #2.
Pavement-Proof Roll Partial 10/8/2025 10/8/2025 10/08/2025
Misc
Informational
10/01/2025
06/06/25 Friday JMJ (Cityscape, CP) Contractor passed proof roll for parking lot area Northeast section of project. Last week proof was was done passed for curbs that were installed on job location. Correction: 06/02/25 Monday proof roll for curb was passed and curbs were installed. 06/11/25 Wednesday JMJ Contractor passed the proof roll. Third party was Kaw Valley. There was some deflection in three different valley point in parking lot area, but no rutting. 07/29/25 Tuesday JMJ ( Cityscape, CP) Contractor passed proof roll for the East and Southside. 10/01/25 Tuesday JMJ (Gen. Cityscape, Sub. CP, Third Party Testing Kaw Valley) Contractor passed proof roll on the Southwest side of project. The storm box in the parking lot area of building #2. 10/08/25 Wednesday JMJ ( Gen. CityScape, Sub. CP Excavation, Third KAW Valley) Proof Roll passed and the KAW Valley inspector was present.
Pavement-Surface Partial 10/9/2025 10/9/2025 10/09/2025
Misc
Informational
06/10/2025
06/10/25 Tuesday JMJ (Cityscape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach. Approach was poured, cured, and saw cut.
Misc
Informational
10/09/2025
10/09/26 Thursday JMJ (Gen. Cityscape, Sub. Seal-O-Matic, Third party KAW) Contractor laid KCMMB A3 1,286 ton 51 loads. Third party testing was on site KAW Valley.
Pavement-Curb Construction Partial 10/9/2025 10/9/2025 10/09/2025
Misc
Informational
10/09/2025
10/09/25 Thursday JMJ (Bedrock Construction) Contractor poured curbs for turn lanes.
Pavement-Surface Partial 10/10/2025 10/10/2025 10/10/2025
Misc
Informational
10/09/2025
06/10/25 Tuesday JMJ (Cityscape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach. Approach was poured, cured, and saw cut.
Misc
Informational
10/09/2025
10/09/26 Thursday JMJ (Gen. Cityscape, Sub. Seal-O-Matic, Third party KAW) Contractor laid KCMMB A3 1,286 ton 51 loads. Third party testing was on site KAW Valley. 10/10/25 Friday JMJ (Gen. Cityscape, Sub Bedrock Concrete) Contractor poured concrete of turning lane going Westbound. Curbs were poured yesterday. Approach was poured on for the entrances of NW Commerce Road. Sidewalk and ADA ramps were poured on Tudor Road.
Pavement-Curb Construction Partial 10/10/2025 10/10/2025 10/10/2025
Misc
Informational
10/09/2025
10/09/25 Thursday JMJ (Bedrock Construction) Contractor poured curbs for turn lanes. 10/10/25 Friday JMJ (Bedrock Construction) Curb poured turn lanes yesterday and apron and curbs off NW Commerce Road. 11/10/25 Monday JMJ (Bedrock Construction) Contractor restarted pouring curbs throughout the project.
All Rough Inspection - Commercial Failed 10/13/2025 10/13/2025
Misc
Corrective Action Required
10/13/2025
Inspection denied Complete all fire blocking for inspection
Miscellaneous Inspection Failed 10/13/2025 10/13/2025 10/13/2025
Misc
Corrective Action Required
08/15/2025
VERTICAL CONSTRUCTION HAS NOT BEEN APPROVED, PERMIT IS IN PARTIAL ISSUED STATUS. STOP WORK ISSUED.
Pavement-Surface Partial 10/13/2025 10/13/2025 10/13/2025
Misc
Informational
10/10/2025
06/10/25 Tuesday JMJ (Cityscape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach. Approach was poured, cured, and saw cut.
Misc
Informational
10/10/2025
10/09/26 Thursday JMJ (Gen. Cityscape, Sub. Seal-O-Matic, Third party KAW) Contractor laid KCMMB A3 1,286 ton 51 loads. Third party testing was on site KAW Valley. 10/10/25 Friday JMJ (Gen. Cityscape, Sub Bedrock Concrete) Contractor poured concrete of turning lane going Westbound. Curbs were poured yesterday. Approach was poured on for the entrances of NW Commerce Road. Sidewalk and ADA ramps were poured on Tudor Road. 1013/25 Monday JMJ ( Gen. CityScape, Sub Bedrock Concrete) Contractor poured drive approach on NW Commerce Road @ 6:30AM.
All Rough Inspection - Commercial Failed 10/15/2025 10/15/2025 10/15/2025
Misc
Corrective Action Required
10/13/2025
-Complete all fire blocking -Seal plate penetrations -Install missing roof boots -Protect DWV within 1.25" to face of framing -Provide truss plans for inspection -Conductors at panel not permitted to be bundled greater than 24" **Not ready, inspection incomplete
All Rough Inspection - Commercial Not Ready 10/16/2025 10/16/2025 10/16/2025
Misc
Corrective Action Required
10/15/2025
-Complete all fire blocking-not done -Seal plate penetrations-not done -Install missing roof boots-not done -Protect DWV within 1.25" to face of framing-not done -Provide truss plans for inspection -Conductors at panel not permitted to be bundled greater than 24" -Strap load bearing wall top plates lapped less than 48" -Complete framing for 2 hour wall shown to go to deck **Not ready, inspection incomplete
All Rough Inspection - Commercial Failed 10/17/2025 10/17/2025 10/17/2025
Misc
Corrective Action Required
10/16/2025
-Complete all fire blocking at dead spaces and ceiling lines -Seal plate penetrations-not done -Install missing roof boots-not done -Provide truss plans for inspection-complete all truss bracing -Install missing lateral bracing and repair cut bracing at East side-to be 48” oc max -Secure electrical in attic space -Provide engineered correction for cut stud act exterior corner of theater and at ceiling joists drilled closer than 2” -Install joist hangers at joists over 48” *OK to insulate exterior walls only
All Rough Inspection - Commercial Failed 10/22/2025 10/22/2025 10/22/2025
Misc
Corrective Action Required
10/17/2025
-Complete all fire blocking at dead spaces and ceiling lines -Provide truss plans for inspection-complete all truss bracing -Secure electrical in attic space -Provide engineered correction at ceiling joists drilled closer than 2” -Install joist hangers at joists over 48” *OK to insulate exterior walls only
Sprinkler - Hydrostatic Test Passed 10/22/2025 10/23/2025
All Rough Inspection - Commercial Not Ready 10/23/2025 10/23/2025 10/23/2025
Misc
Corrective Action Required
10/22/2025
-Complete all fire blocking at dead spaces and ceiling lines-NOT DONE -Provide truss plans for inspection-complete all truss bracing-NOT DONE -Provide engineered correction at ceiling joists drilled closer than 2”-NOT DONE -Install joist hangers at joists over 48”-NOT DONE *OK to insulate exterior walls only
All Rough Inspection - Commercial Partial 10/27/2025 10/27/2025 10/27/2025
Misc
Corrective Action Required
10/23/2025
-Complete all fire blocking at dead spaces and ceiling lines-NOT DONE -Provide engineered correction at ceiling joists drilled closer than 2”-NOT DONE *DI NOT COVER INSPECTION ITEMS
Erosion Control Inspection Partial 9/2/2025 9/2/2025 10/28/2025
Misc
Informational
06/13/2025
06/13/25 Friday JMJ (Cityscape, CP Excavating) Talked with contractor about cleaning up the street of soil track on adjacent streets of project Tudor Rd & NW Commerce Drive. The contractor is power washing NW Commerce Drive due to the dump trucks hauling dirt to approved site. 10/28/25 Tueday JMJ (Gen. CityScape) Contractor continue to maintain the erosion control devices.
All Rough Inspection - Commercial Not Ready 10/29/2025 10/29/2025 10/29/2025
Misc
Corrective Action Required
10/27/2025
-Complete all fire blocking at dead spaces and ceiling lines-NOT DONE -Provide engineered correction at ceiling joists drilled closer than 2”-NOT DONE 10/29/25 NOT READY *DI NOT COVER INSPECTION ITEMS
All Rough Inspection - Commercial Not Ready 10/30/2025 10/30/2025 10/30/2025
Misc
Corrective Action Required
10/29/2025
-Complete all fire blocking at dead spaces and ceiling lines-NOT DONE -Provide engineered correction at ceiling joists drilled closer than 2”-NOT DONE 10/29/25 NOT READY 10/30/25 NOT READY *DI NOT COVER INSPECTION ITEMS
All Rough Inspection - Commercial Passed 11/3/2025 11/3/2025 11/03/2025
Misc
Resolved
11/03/2025
-Complete all fire blocking at dead spaces and ceiling lines-NOT DONE -Provide engineered correction at ceiling joists drilled closer than 2”-NOT DONE 10/29/25 NOT READY 10/30/25 NOT READY *DI NOT COVER INSPECTION ITEMS
Site Visit Partial 11/3/2025 11/3/2025 11/03/2025
Misc
Informational
06/11/2025
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading
Rated Assembly Inspection Partial 11/7/2025 11/7/2025 11/07/2025
Misc
Corrective Action Required
11/07/2025
shear walls approved
Pool Steel/Bonding - Commercial Partial 11/21/2025 11/21/2025 11/21/2025
Misc
Informational
11/21/2025
Components bonded: -(12) points at shell, (2) sets of handrail sleeves, (4) light niches
Site Visit Partial 12/11/2025 12/11/2025 12/11/2025
Misc
Informational
11/03/2025
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading 12/11/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor took the sample yesterday and today.
Erosion Control Inspection Residential Partial 12/29/2025 12/29/2025 12/29/2025
Misc
Informational
09/02/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control.
Erosion Control Inspection Residential Partial 12/29/2025
Misc
Informational
12/29/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control.
Site Visit Partial 1/6/2026 1/6/2026 01/06/2026
Misc
Informational
12/11/2025
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading 12/11/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor took the sample yesterday and today. 1-6-25 PS Made site visit, no activity for dev today
Erosion Control Inspection Residential Failed - Stop Work 1/12/2026 1/12/2026 01/12/2026
Misc
Informational
12/29/2025
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control.
Erosion Control Inspection Partial 01/13/2026
Misc
Informational
10/28/2025
06/13/25 Friday JMJ (Cityscape, CP Excavating) Talked with contractor about cleaning up the street of soil track on adjacent streets of project Tudor Rd & NW Commerce Drive. The contractor is power washing NW Commerce Drive due to the dump trucks hauling dirt to approved site. 10/28/25 Tueday JMJ (Gen. CityScape) Contractor continue to maintain the erosion control devices. 1-13-25 RH. Erosion control measures on site did not meet required standards and the site failed inspection. Trash was present throughout the site and adjacent field. Several field inlets were not properly protected, with some having fill material piled directly in front of them. Silt fence was down in multiple locations; although repairs were underway, the deficiencies were still causing issues. Additionally, aggregate piles located in the roadway/hard surface were not protected, and sediment was observed leaving the site entrance and tracking into the roadway. All erosion control deficiencies must be corrected and the site brought into full compliance by Thursday afternoon, 1/15/26. Failure to do so will result in a stop work order being issued, and all work on the jobsite will be halted until corrected.
Erosion Control Inspection Failed 01/13/2026
Misc
Informational
01/13/2026
06/13/25 Friday JMJ (Cityscape, CP Excavating) Talked with contractor about cleaning up the street of soil track on adjacent streets of project Tudor Rd & NW Commerce Drive. The contractor is power washing NW Commerce Drive due to the dump trucks hauling dirt to approved site. 10/28/25 Tueday JMJ (Gen. CityScape) Contractor continue to maintain the erosion control devices. 1-13-25 RH. Erosion control measures on site did not meet required standards and the site failed inspection. Trash was present throughout the site and adjacent field. Several field inlets were not properly protected, with some having fill material piled directly in front of them. Silt fence was down in multiple locations; although repairs were underway, the deficiencies were still causing issues. Additionally, aggregate piles located in the roadway/hard surface were not protected, and sediment was observed leaving the site entrance and tracking into the roadway. All erosion control deficiencies must be corrected and the site brought into full compliance by Thursday afternoon, 1/15/26. Failure to do so will result in a stop work order being issued, and all work on the jobsite will be halted until corrected.
Site Visit Partial 1/14/2026 1/14/2026 01/14/2026
Misc
Informational
01/06/2026
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading 12/11/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor took the sample yesterday and today. 1-6-25 PS Made site visit, no activity for dev today 01/14/26 JMJ Concentration on site clean-up contractor has failed a number of erosion control inspection and give two days from 01/13/26 to clean up sediment spreading across parking lot, adjacent streets, and failed silt erosion control.
Erosion Control Inspection Partial 1/15/2026 1/15/2026 01/15/2026
Misc
Informational
01/13/2026
06/13/25 Friday JMJ (Cityscape, CP Excavating) Talked with contractor about cleaning up the street of soil track on adjacent streets of project Tudor Rd & NW Commerce Drive. The contractor is power washing NW Commerce Drive due to the dump trucks hauling dirt to approved site. 10/28/25 Tueday JMJ (Gen. CityScape) Contractor continue to maintain the erosion control devices. 1-13-25 RH. Erosion control measures on site did not meet required standards and the site failed inspection. Trash was present throughout the site and adjacent field. Several field inlets were not properly protected, with some having fill material piled directly in front of them. Silt fence was down in multiple locations; although repairs were underway, the deficiencies were still causing issues. Additionally, aggregate piles located in the roadway/hard surface were not protected, and sediment was observed leaving the site entrance and tracking into the roadway. All erosion control deficiencies must be corrected and the site brought into full compliance by Thursday afternoon, 1/15/26. Failure to do so will result in a stop work order being issued, and all work on the jobsite will be halted until corrected. 01/15/26 Thursday JMJ (Gen. CityScape) Contractor continued to work clean site to the required standards. Gutter buddies along street curb inlet were clean. Contractor was repairing silt fencing along the street of Tudor Road & NW Commerce Road. Street Sweeper was active on site. Contractor needs to continued strong efforts to clean site of excess soil on base asphalt.
Electrical Service Inspection Failed 1/16/2026 1/16/2026 01/16/2026
Misc
Corrective Action Required
01/16/2026
-Ground service per code at main disconnect -Land service conductors
Piers/Caissons Inspection - Commercial Partial 1/21/2026 1/21/2026 01/21/2026
Misc
Informational
09/17/2025
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6 (4) east of building 4 (4) west of building 7 (1) north of building 2 (2) SW of club house (2) S of club house (3) SW of building 7
Electrical Service Inspection Passed 1/26/2026 1/26/2026 01/26/2026
Misc
Resolved
01/26/2026
-Ground service per code at main disconnect -Land service conductors
Underground Electrical Inspection - Commercial Partial 2/10/2026 2/10/2026 02/10/2026
Misc
Informational
09/16/2025
-Secondary and communications conduit from transformer location 25 to building 8 and building 6 -Secondary and comms conduit from transformer 24 60' north Light poles: -Conduit for (3) light poles South of building 5, (2) SE of building 8, (3) South of building 6, (3) light poles east of building 4 -Conduit for 3 light pole od South East edge of lot -Conduit for (3) light poles S of building 2 and to garages at building 2 -Conduit for 4 lights on the East and West side of building 4 -From clubhouse to NW light pole -From clubhouse to SW (3) light poles -From building 5 to west light pole at north entry
Piers/Caissons Inspection - Commercial Partial 2/10/2026 2/10/2026 02/10/2026
Misc
Informational
01/21/2026
Light pole bases and ground rods at: /1) east of building 5 (2) south building 5 (2) southeast of building 8 (3) south of building 6 (4) east of building 4 (4) west of building 7 (1) north of building 2 (2) SW of club house (2) S of club house (3) SW of building 7 (1) NW of clubhouse
Site Visit Partial 2/10/2026 2/10/2026 02/10/2026
Misc
Informational
01/14/2026
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading 12/11/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor took the sample yesterday and today. 1-6-25 PS Made site visit, no activity for dev today 01/14/26 JMJ Concentration on site clean-up contractor has failed a number of erosion control inspection and give two days from 01/13/26 to clean up sediment spreading across parking lot, adjacent streets, and failed silt erosion control. 2/10/26 PS Made site visit, CP Excavating moving dirt and grading.
Sidewalk Inspection Partial 2/26/2026 2/26/2026 02/26/2026
Misc
Informational
02/26/2026
2/26/26 PS Pre pour inspection for replacement sidewalk panels at corners of Commerce at Tudor road. East side of Commerce includes section of curb being replaced that was damaged from construction. Approved to pour replacement panels
Sidewalk Inspection Partial 2/26/2026 2/26/2026 02/26/2026
Misc
Informational
02/26/2026
02/26/26 Thursday JMJ contractor has installed ADA and sidewalk on the Southwest and East conner of NW Tudor Rd & NW Commerce Dr.
Sprinkler - Flow Test Passed 3/3/2026 03/04/2026
Alarm Test Passed 3/3/2026 03/04/2026
Occupancy Inspection - Planning Temporary C of O 3/12/2026 03/12/2026
Miscellaneous Correction
Corrective Action Required
03/12/2026
Awaiting final landscaping and vegetation. All site landscaping and vegetation will be reviewed under this permit.
Occupancy Inspection - Water Utilities Passed 3/12/2026 03/12/2026
Occupancy Inspection - Codes Commercial Failed 3/12/2026 03/12/2026
Misc
Corrective Action Required
03/12/2026
-Complete corrections for all other departments -Seal all exterior penetrations -Complete pool equipment room -Complete exit paths to courtyard and pool
Occupancy Inspection - Fire Failed 3/12/2026 03/12/2026
Occupancy Inspection - Engineering Temporary C of O 3/12/2026 03/12/2026
Misc
Informational
03/12/2026
03/12/26 Thursday JMJ TCO given for Club House @3:30PM Punch LIst 1. Grading and Seeding or Sod. 2. Repairing sprinkler system head. 3. Installing cap over sanitary clean-out on general site.
Occupancy Inspection - Fire Passed 3/13/2026 03/13/2026
Erosion Control Inspection Passed 3/17/2026 3/17/2026 03/17/2026
Misc
Informational
01/15/2026
06/13/25 Friday JMJ (Cityscape, CP Excavating) Talked with contractor about cleaning up the street of soil track on adjacent streets of project Tudor Rd & NW Commerce Drive. The contractor is power washing NW Commerce Drive due to the dump trucks hauling dirt to approved site. 10/28/25 Tueday JMJ (Gen. CityScape) Contractor continue to maintain the erosion control devices. 1-13-25 RH. Erosion control measures on site did not meet required standards and the site failed inspection. Trash was present throughout the site and adjacent field. Several field inlets were not properly protected, with some having fill material piled directly in front of them. Silt fence was down in multiple locations; although repairs were underway, the deficiencies were still causing issues. Additionally, aggregate piles located in the roadway/hard surface were not protected, and sediment was observed leaving the site entrance and tracking into the roadway. All erosion control deficiencies must be corrected and the site brought into full compliance by Thursday afternoon, 1/15/26. Failure to do so will result in a stop work order being issued, and all work on the jobsite will be halted until corrected. 01/15/26 Thursday JMJ (Gen. CityScape) Contractor continued to work clean site to the required standards. Gutter buddies along street curb inlet were clean. Contractor was repairing silt fencing along the street of Tudor Road & NW Commerce Road. Street Sweeper was active on site. Contractor needs to continued strong efforts to clean site of excess soil on base asphalt. 03/17/26 Tuesday JMJ (Gen. Cityscape) Contractor continue to maintain site.
Occupancy Inspection - Codes Commercial Ready for Temp CO 3/13/2026 03/17/2026
Misc
Corrective Action Required
03/12/2026
-Complete corrections for all other departments -Seal all exterior penetrations -Complete pool equipment room -Complete exit paths to courtyard and pool
Site Visit Partial 3/18/2026 3/18/2026 03/18/2026
Misc
Informational
02/10/2026
06/11/25 Wednesday JMJ ( Gen. Cityscape, CP Excavating) Contractor pour backing block and invert, collars & other needed structure throughout job site. 11-3-25 PS CP Excavating crew working on site cleanup and grading 12/11/25 Thursday JMJ (Gen. Cityscape, CP Excavating) Contractor took the sample yesterday and today. 1-6-25 PS Made site visit, no activity for dev today 01/14/26 JMJ Concentration on site clean-up contractor has failed a number of erosion control inspection and give two days from 01/13/26 to clean up sediment spreading across parking lot, adjacent streets, and failed silt erosion control. 2/10/26 PS Made site visit, CP Excavating moving dirt and grading. 03/18/26 Wednesday JMJ (CityScape) Contractor performing general construction work on site, no inspection required at this time.
Erosion Control Inspection Residential Partial 3/25/2026 3/25/2026 03/25/2026
Misc
Informational
01/12/2026
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control. 03/25/26 Wednesday JMJ (CityScape) Erosion control appears to be functioning properly.
Pavement-Surface Partial 3/30/2026 3/30/2026 03/30/2026
Misc
Informational
10/13/2025
06/10/25 Tuesday JMJ (Cityscape, CP Const., Bedrock Const.) Contractor will pour the approach off Tudor Road on the North entrance of project. Contractor installed smooth epoxy dowels in the new poured curbs that will connect to the approach. Approach was poured, cured, and saw cut.
Misc
Informational
10/13/2025
10/09/25 Thursday JMJ (Gen. Cityscape, Sub. Seal-O-Matic, Third party KAW) Contractor laid KCMMB A3 1,286 ton 51 loads. Third party testing was on site KAW Valley. 10/10/25 Friday JMJ (Gen. Cityscape, Sub Bedrock Concrete) Contractor poured concrete of turning lane going Westbound. Curbs were poured yesterday. Approach was poured on for the entrances of NW Commerce Road. Sidewalk and ADA ramps were poured on Tudor Road. 1013/25 Monday JMJ ( Gen. CityScape, Sub Bedrock Concrete) Contractor poured drive approach on NW Commerce Road @ 6:30AM.
Misc
Informational
03/30/2026
03/30/26 Monday JMJ (Sub. Seal-O-Matic) Contractor laid KCMMB A2 656.79 Tons, 26 Loads of surface asphalt. The entrance off 25NE Tudor Rd, the parking lot area for two of apartment complexes.
Erosion Control Inspection Residential Failed 4/1/2026 4/1/2026 04/01/2026
Misc
Informational
03/25/2026
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control. 03/25/26 Wednesday JMJ (CityScape) Erosion control appears to be functioning properly. 04/01/26 Wednesday JMJ (CityScape) Entrances and street on NW Commerce DR need to be clean from the mud and silt from project site. Also the curbs and gutter buddies need to check ensure the clear of debris.
Erosion Control Inspection Residential Partial 4/2/2026 4/2/2026 04/02/2026
Misc
Informational
04/01/2026
05/07/25 Wednesday JMJ Erosion control appears to be functioning properly. 05/27/25 Tuesday JMJ 06/04/25 Wednesday JMJ Erosion control appears to be functioning properly. Erosion control has failed along NW Commerce Drive mud at the entrance clogged gutter buddies along NW Commerce Drive. 07/03/25 Thursday JMJ Erosion control appears to be functioning properly. 12/29/25 Monday JMJ (CityScape) Erosion control appears to mainly functioning. Entrances and interior of the project needs a street sweeper and clean-up. Silt fence needs to be removed or re-staked contractor can moved to other methods of erosion control. 03/25/26 Wednesday JMJ (CityScape) Erosion control appears to be functioning properly. 04/01/26 Wednesday JMJ (CityScape) Entrances and street on NW Commerce DR need to be clean from the mud and silt from project site. Also the curbs and gutter buddies need to check ensure the clear of debris. 04/02/26 Thursday JMJ (CityScape) Contractor appears to correct the mud and silt athe the entrances on NW Commerce Drive and the gutter buddies appeared fairly clear of obstruction.
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home

*PLEASE NOTE - You must be logged in with your registered user account to view any documents related to your permit