Summary
PRCOM20235206
Building Permit - Commercial
Issued
RESIDENCES AT BLACKWELL LLC
NEW MULTI-FAMILY
RESIDENCES AT BLACKWELL - BUILDING #2 67 Units, NEW APARTMENT BUILDING
10/10/2023
05/15/2025
11/06/2023
Locations
Contacts
Jake Loveless, Address:21 SE 29TH TER  
Polar Aire Heating & Cooling Service, Address:400 S. Kansas Ave, Phone:(913) 782-8238  
KDM ELECTRICAL CONTRACTORS, Address:1103 NW CASEY BLVD STE C, Phone:(816) 443-5694  
BENCHMARK MECHANICAL LLC, Address:5 SW 4TH ST, Phone:(816) 524-5616  
NSPJ ARCHITECTS, Address:3515 W 75TH ST, SUITE 201, Phone:(913) 831-1415 Ext:278  
CFS ENGINEERS, Address:1421 EAST 104TH STREET STE 100, Phone:(816) 333-4477  
RESIDENCES AT BLACKWELL LLC, Address:21 SE 29TH TER  
Streamline General Contractors, Address:5 4TH ST SW  
Scott Runyan - Griffen Riley Property Group, Phone:(816) 500-5928  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 01/20/2026 01/20/2026
Craig Hill
Alarm Plan Review Released for Construction 04/28/2025 04/28/2025
Craig Hill
Alarms connected to automatic sprinkler system
Informational
04/28/2025

2018 IFC 903.4.2- Alarms. Approved audible and visual devices shall be connected to every automatic sprinkler system. Such sprinkler water-flow alarm devices shall be activated by water flow equivalent to the flow of a single sprinkler of the smallest orifice size installed in the system. Listed alarm notification devices shall be provided on the exterior and interior of the building in an approved location. Where a fire alarm system is installed, actuation of the automatic sprinkler system shall actuate the building fire alarm system.
Alarm testing.
Informational
04/28/2025

2018 IFC 904.4.2- Alarm testing. Notification appliances, connections to fire alarm systems, and connections to approved supervising stations shall be tested in accordance with this section and Section 907 to verify proper operation. Call (816) 969-1300 24 hours in advance to schedule an alarm test. System must be monitored and pretested before scheduling.
Fees
Paid Fees Amount Paid Owing Date Paid
Valuation Fee for New Multi-Family $4,500.00 $4,500.00 Paid 06/26/2024
$40,475.00
Residential Excise Tax Fee $28,429.44 $28,429.44 Paid 05/07/2025
Valuation Fee for New Multi-Family $35,975.00 $35,975.00 Paid 05/07/2025
$40,475.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Alarm Test Pending
Sprinkler - Hydrostatic Test Pending
Sprinkler - Flow Test Pending
Erosion Control Inspection Residential Pending
Piers/Caissons Inspection - Commercial Pending
Sewer Service Inspection Pending
Water Service Inspection Pending
Gas Piping Inspection - Commercial Pending
Gas Service Inspection - Commercial Pending
Above Ceiling Inspection Pending
Concrete Walls and Columns Inspection Pending
Misc
Corrective Action Required
08/16/2024
Foundation wall OK: -A/4 to G/4; cont. to M.3/7; rest of storm shelter f. wall -Elevator pit wall
Suspended Slab Inspection Pending
Misc
Informational
10/16/2024
Podium slab ok to pour pending approval of the on-site engineer
Underground Plumbing Inspection - Commercial Pending
Misc
Corrective Action Required
02/25/2025
-Domestic and fire sprinkler lines from ~ 10 ft outside to building
Alarm Test Pending
Erosion Control Inspection Pending
Underground Electrical Inspection - Commercial Pending
Misc
Corrective Action Required
08/27/2025
-Raceways from building 2 to junction point, site lighting, garage 2B, and future car port electric charging -Secondary between bldg 2&1
Sprinkler - Hydrostatic Test Pending
Water Line - Coliform Test 1 Pending
Rated Assembly Inspection Pending
STAIR TOWER 1
Corrective Action Required
03/30/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
STAIR TOWER 2
Corrective Action Required
03/30/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
ELEVATOR 1
Corrective Action Required
03/30/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -corridor side, 1st layer -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/30/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/30/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/30/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/30/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/30/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/30/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped -j channel in all rooms of this floor is in place. Ready for Sheetrock
FOURTH FLOOR
Corrective Action Required
03/30/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -GB install at 402&413 closet wall -RC ok -screw pattern in the main hall and ceiling is good
All Rough Inspection - Commercial Pending
Misc
Corrective Action Required
03/31/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/31/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/31/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok Corrective actions All units -Support and secure all wiring in ceiling space max spacing 4 1/2’ -provide minimum 1 1/2” Bearing for all trusses 101 -seal gaps in dead space at primary bedroom shower -protect wires at top plate primary bedroom entry -address damaged truss above dead space at primary bedroom shower 102 -missing receptacle in primary bedroom wall space greater than 2’ 103 -move fire sprinkler SE Bedroom -protect wire at top plate primary SW bath -provide bearing for trusses 1 1/2” minimum NE bedroom -seal draft stop penetrations S wall 104 -seal bottom plate penetration in mechanical closet -address trusses spaced greater than 24” OC 105 -strap top plate at coat closet -secure SE cable left of panel Corridor outside 105 -address cut load bearing stud pack garage side 106 -address electric SE primary bedroom 107 108 -provide protection for sprinkler line top and bottom plate at entry -secure stud at panel 109 -putty packs must cover entirety of box W wall -provide putty packs for outlets closer than 24” E wall multiple locations -furr wall at panel of electrical runs 110 -fireblock top of entire S wall -complete electrical in S bedroom -provide outlet at living room W wall -protect electrical in entry bath top plate
SECOND FLOOR
Corrective Action Required
03/31/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies 210: -Complete fur out wall at 6” roof drain **install top lid 207: -Mud and fire tape elevator firewall. Close off excessive gaps and install fire tape
THIRD FLOOR
Corrective Action Required
03/31/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies -All units and corridor **Correction:
FOURTH FLOOR
Corrective Action Required
03/31/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor **Correction: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/31/2026
OK: -Pre-rock for top lid and wall
Footing Inspection - Commercial Partial 7/23/2024 7/23/2024 07/23/2024
Misc
Informational
07/23/2024
Exterior wall footing-OK
Concrete Walls and Columns Inspection Partial 7/25/2024 07/25/2024
Misc
Corrective Action Required
07/25/2024
Foundation wall OK: -G/4 to A/4 **Install electrical service grounding electrode conductor at north end of building. Call for inspection before pouring
Concrete Walls and Columns Inspection Partial 7/26/2024 07/26/2024
Misc
Corrective Action Required
07/25/2024
Foundation wall OK: -G/4 to A/4
Concrete Walls and Columns Inspection Partial 7/31/2024 07/31/2024
Misc
Corrective Action Required
07/26/2024
Foundation wall OK: -A/4 to G/4; cont. to M.3/7
Footing Inspection - Commercial Partial 8/7/2024 8/7/2024 08/07/2024
Misc
Informational
07/23/2024
Exterior wall footing-OK Column footing and elevator pit on building C. PASSED 8/7/24 AF
Concrete Walls and Columns Inspection Partial 8/13/2024 8/13/2024 08/13/2024
Misc
Corrective Action Required
07/31/2024
Foundation wall OK: -A/4 to G/4; cont. to M.3/7 **8/13-site locked up. Inspection canceled
Concrete Walls and Columns Inspection Partial 8/16/2024 08/16/2024
Misc
Corrective Action Required
08/13/2024
Foundation wall OK: -A/4 to G/4; cont. to M.3/7 -Elevator pit wall **correction: install corner rebars per 3/S3.00
Concrete Walls and Columns Inspection Partial 8/16/2024 08/16/2024
Misc
Corrective Action Required
08/16/2024
Foundation wall OK: -A/4 to G/4; cont. to M.3/7; rest of storm shelter f. wall -Elevator pit wall
Underslab Plumbing Inspection - Commercial Failed 8/30/2024 08/30/2024
Misc
Corrective Action Required
08/30/2024
Pressure not holding
Underslab Plumbing Inspection - Commercial Passed 9/4/2024 9/4/2024 09/04/2024
Misc
Resolved
09/04/2024
Pressure not holding
Footing Inspection - Commercial Partial 9/24/2024 9/25/2024 09/25/2024
Misc
Informational
08/07/2024
Lower level foundation: -Exterior wall footing; column footing and elevator pit -Interior footing
Suspended Slab Inspection Partial 10/16/2024 10/16/2024 10/16/2024
Misc
Informational
10/16/2024
Podium slab ok to pour pending approval of the on-site engineer
Underslab Plumbing Inspection - Commercial Passed 12/11/2024 12/11/2024 12/11/2024
Misc
Informational
12/11/2024
Upper floor underslab plumbing OK
Footing Inspection - Commercial Partial 12/12/2024 12/12/2024 12/12/2024
Misc
Informational
09/25/2024
Lower level foundation: -Exterior wall footing; storm shelter column footing and elevator pit -Interior footing Upper level foundation:
Misc
Informational
12/12/2024
Inspected Interior grade beams building 2
Footing Inspection - Commercial Partial 12/18/2024 12/18/2024
Misc
Informational
12/12/2024
Lower level foundation: -Exterior wall footing; storm shelter column footing and elevator pit -Interior footing Upper level foundation: -Interior garage footing -Exterior grade beam, except at garage 9 and garages north of north stair A
Misc
Resolved
12/18/2024
Inspected Interior grade beams building 2
Footing Inspection - Commercial Partial 12/23/2024 12/23/2024 12/23/2024
Misc
Informational
12/12/2024
Lower level foundation: -Exterior wall footing; storm shelter column footing and elevator pit -Interior footing Upper level foundation: -Interior garage footing -Exterior grade beam, except at garage 9 and garage 1
Underground Electrical Inspection - Commercial Partial 12/27/2024 12/27/2024
Misc
Corrective Action Required
12/27/2024
Building 2 level 1 electrical conduit from electrical room to out side of garage running south west ( incomplete)
Underground Plumbing Inspection - Commercial Partial 2/25/2025 2/25/2025 02/25/2025
Misc
Corrective Action Required
02/25/2025
-Domestic and fire sprinkler lines from ~ 10 ft outside to building
Footing Inspection - Commercial Passed 3/7/2025 3/7/2025 03/07/2025
Misc
Informational
12/23/2024
Lower level foundation: -Exterior wall footing; storm shelter column footing and elevator pit -Interior footing Upper level foundation: -Interior garage footing -Exterior grade beam
Footing Inspection - Commercial Passed 3/10/2025 3/10/2025 03/10/2025
Misc
Informational
12/23/2024
Lower level foundation: -Exterior wall footing; storm shelter column footing and elevator pit -Interior footing Upper level foundation: -Interior garage footing -Exterior grade beam -Garage stem walls
Underground Electrical Inspection - Commercial Partial 5/2/2025 5/2/2025 05/02/2025
Misc
Corrective Action Required
12/27/2024
In progress: raceways from building 2 to junction point, site lighting, garage 2B, and future car port electric charging
Underground Electrical Inspection - Commercial Partial 7/25/2025 07/25/2025
Misc
Corrective Action Required
05/02/2025
-Raceways from building 2 to junction point, site lighting, garage 2B, and future car port electric charging -Secondary between bldg 2&1 not ready
Rated Assembly Inspection Partial 8/4/2025 8/4/2025 08/04/2025
MISC
Corrective Action Required
08/04/2025
APPROVED AREAS - First layer of 2 on one wall of stairs tower in basement of both towers of Building 2
Rated Assembly Inspection Failed 8/5/2025 8/5/2025 08/05/2025
STAIR TOWER 1
Corrective Action Required
08/05/2025
1st layer sheetrock screw pattern-okay 2nd layer sheetrock- offset seams running horizontally.
STAIR TOWER 2
Corrective Action Required
08/05/2025
1st layer sheetrock screw pattern-okay 2nd layer sheetrock- offset seams running horizontally.
Erosion Control Inspection Partial 8/13/2025 08/13/2025
Underground Electrical Inspection - Commercial Partial 8/27/2025 8/27/2025 08/27/2025
Misc
Corrective Action Required
07/25/2025
-Raceways from building 2 to junction point, site lighting, garage 2B, and future car port electric charging -Secondary between bldg 2&1
All Rough Inspection - Commercial Failed 8/28/2025 8/28/2025 08/28/2025
Misc
Corrective Action Required
08/28/2025
Garage PHF portal walls framing: -Nail sheathing to header w/ 8d @ 3" grid pattern -Nail sheathing to intermediate studs w/ 8d @ 12' oc -Nail wall top plates to header with 2 rows of 16d nails @ 3" oc -2 king studs at end of portal wall -For the straight portal walls between the garages, have engineer address whether aditional hold down is required at each individual garage portal wall
Rated Assembly Inspection Partial 9/3/2025 9/3/2025 09/03/2025
STAIR TOWER 1
Corrective Action Required
08/05/2025
**NORTH STAIR ENCLOSURE** 1st layer sheetrock screw pattern-okay 2nd layer sheetrock- offset seams running horizontally. -lower level, stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
08/05/2025
**SOUTH STAIR ENCLOSURE** 1st layer sheetrock screw pattern-okay 2nd layer sheetrock- offset seams running horizontally. -lower level, stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
09/03/2025
Lower level: -stair side 2nd layer
All Rough Inspection - Commercial Failed 9/12/2025 09/12/2025
Misc
Corrective Action Required
08/28/2025
Garage PHF portal walls framing: -Nail wall top plates to header with 2 rows of 16d nails @ 3" oc -Make sure all strap nails go into the studs, not through the sheathing
All Rough Inspection - Commercial Failed 9/17/2025 9/17/2025 09/17/2025
Misc
Corrective Action Required
09/12/2025
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
Rated Assembly Inspection Partial 9/22/2025 9/22/2025 09/22/2025
STAIR TOWER 1
Corrective Action Required
09/03/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 1st layer
STAIR TOWER 2
Corrective Action Required
09/03/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 1st layer
ELEVATOR 1
Corrective Action Required
09/03/2025
Lower level: -stair side 2nd layer
Rated Assembly Inspection Partial 9/25/2025 9/25/2025 09/25/2025
STAIR TOWER 1
Corrective Action Required
09/22/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
09/22/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
09/22/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
09/22/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok
Rated Assembly Inspection Partial 10/1/2025 10/1/2025 10/01/2025
STAIR TOWER 1
Corrective Action Required
09/25/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped
STAIR TOWER 2
Corrective Action Required
09/25/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped
ELEVATOR 1
Corrective Action Required
09/25/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
09/25/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Rated Assembly Inspection Partial 11/14/2025 11/14/2025 11/14/2025
STAIR TOWER 1
Corrective Action Required
10/01/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 1st layer
STAIR TOWER 2
Corrective Action Required
10/01/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 1st layer
ELEVATOR 1
Corrective Action Required
10/01/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
10/01/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Rated Assembly Inspection Partial 11/17/2025 11/17/2025 11/17/2025
STAIR TOWER 1
Corrective Action Required
11/14/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer **Extend GB to roof deck
STAIR TOWER 2
Corrective Action Required
11/14/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer **Extend GB to roof deck
ELEVATOR 1
Corrective Action Required
11/14/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
11/14/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Rated Assembly Inspection Partial 11/20/2025 11/20/2025 11/20/2025
STAIR TOWER 1
Corrective Action Required
11/17/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck
STAIR TOWER 2
Corrective Action Required
11/17/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck
ELEVATOR 1
Corrective Action Required
11/17/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
11/17/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
All Rough Inspection - Commercial Failed 11/21/2025 11/21/2025 11/21/2025
Misc
Corrective Action Required
09/17/2025
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
11/21/2025
FIRST FLOOR
Corrective Action Required
11/21/2025
**Pre-rock at showers and tubs corrections: -Provide FlameBlock sheathing at exterior wall where required 107: -Strap over-bored top plate per plan 103: -Nail shear wall at bottom wall plate per scheduled
SECOND FLOOR
Corrective Action Required
11/21/2025
**Pre-rock at showers and tubs corrections: 205: -Nail shear wall at bottom wall plate per scheduled; nail shear wall behind tub per scheduled 211: -Nail shear wall at bottom wall plate per scheduled 212: -Nail shear wall behind shower per scheduled
THIRD FLOOR
Corrective Action Required
11/21/2025
FOURTH FLOOR
Corrective Action Required
11/21/2025
ELEVATOR 1
Corrective Action Required
11/21/2025
All Rough Inspection - Commercial Failed 11/21/2025
Misc
Corrective Action Required
11/21/2025
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
11/21/2025
Pre-rock at showers and tubs-ok
FIRST FLOOR
Corrective Action Required
11/21/2025
**Pre-rock at showers and tubs corrections: -Provide FlameBlock sheathing at exterior wall where required 107: -Strap over-bored top plate per plan 103: -Nail shear wall at bottom wall plate per scheduled
SECOND FLOOR
Corrective Action Required
11/21/2025
**Pre-rock at showers and tubs corrections: 205: -Nail shear wall at bottom wall plate per scheduled; nail shear wall behind tub per scheduled 211: -Nail shear wall at bottom wall plate per scheduled 212: -Nail shear wall behind shower per scheduled
THIRD FLOOR
Corrective Action Required
11/21/2025
FOURTH FLOOR
Corrective Action Required
11/21/2025
ELEVATOR 1
Corrective Action Required
11/21/2025
Rated Assembly Inspection Partial 12/1/2025 12/1/2025 12/01/2025
STAIR TOWER 1
Corrective Action Required
11/20/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 1st layer
STAIR TOWER 2
Corrective Action Required
11/20/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 1st layer
ELEVATOR 1
Corrective Action Required
11/20/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
11/20/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Rated Assembly Inspection Failed 12/3/2025 12/3/2025 12/03/2025
STAIR TOWER 1
Corrective Action Required
12/01/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 1st layer **2 layers required at landing; cut out the wood near door and install 2nd layer
STAIR TOWER 2
Corrective Action Required
12/01/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
12/01/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
12/01/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Rated Assembly Inspection Failed 12/10/2025 12/10/2025 12/10/2025
STAIR TOWER 1
Corrective Action Required
12/03/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 1st layer **2 layers required at landing; cut out the wood near door and install 2nd layer
STAIR TOWER 2
Corrective Action Required
12/03/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
12/03/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
12/03/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
12/10/2025
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
Rated Assembly Inspection Failed 12/15/2025 12/15/2025
STAIR TOWER 1
Corrective Action Required
12/10/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer **2 layers required at landing; cut out the wood near door and install 2nd layer
STAIR TOWER 2
Corrective Action Required
12/10/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
12/10/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
12/10/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
12/10/2025
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
Rated Assembly Inspection Failed 12/17/2025 12/17/2025 12/17/2025
STAIR TOWER 1
Corrective Action Required
12/15/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer, mud&taped **2 layers required at landing; cut out the wood near door and install 2nd layer
STAIR TOWER 2
Corrective Action Required
12/15/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer, , mud&taped
ELEVATOR 1
Corrective Action Required
12/15/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
12/15/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
12/15/2025
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
Rated Assembly Inspection Failed 12/24/2025 12/24/2025 12/24/2025
STAIR TOWER 1
Corrective Action Required
12/17/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
12/17/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
12/17/2025
Lower level: -stair side 2nd layer
STAIR TOWER 3
Corrective Action Required
12/17/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
12/17/2025
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
All Rough Inspection - Commercial Failed 12/31/2025 12/31/2025 12/31/2025
Misc
Corrective Action Required
11/21/2025
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
11/21/2025
Pre-rock at showers and tubs-ok
FIRST FLOOR
Corrective Action Required
11/21/2025
**Pre-rock at showers and tubs corrections: -Provide FlameBlock sheathing at exterior wall where required 107: -Strap over-bored top plate per plan 103: -Nail shear wall at bottom wall plate per scheduled
SECOND FLOOR
Corrective Action Required
11/21/2025
**Pre-rock at showers and tubs corrections: 205: -Nail shear wall at bottom wall plate per scheduled; nail shear wall behind tub per scheduled 211: -Nail shear wall at bottom wall plate per scheduled 212: -Nail shear wall behind shower per scheduled
THIRD FLOOR
Corrective Action Required
11/21/2025
OK: -Pre-rock for walls at showers and tubs
FOURTH FLOOR
Corrective Action Required
11/21/2025
OK: -Pre-rock for walls at showers and tubs
ELEVATOR 1
Corrective Action Required
11/21/2025
Rated Assembly Inspection Failed 12/31/2025 12/31/2025
STAIR TOWER 1
Corrective Action Required
12/24/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
12/24/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
12/24/2025
Lower level: -stair side 2nd layer 1st fl: 2nd fl: 3rd fl: -307&309 sides-1st layer 4th fl: -407&409 sides-1st layer
STAIR TOWER 3
Corrective Action Required
12/24/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
12/24/2025
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
Rated Assembly Inspection Failed 1/16/2026 1/16/2026 01/16/2026
STAIR TOWER 1
Corrective Action Required
12/31/2025
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
12/31/2025
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
12/31/2025
Lower level: -stair side 2nd layer 1st fl: 2nd fl: 3rd fl: -307&309 sides-1st layer 4th fl: -407&409 sides-1st layer
STAIR TOWER 3
Corrective Action Required
12/31/2025
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
12/31/2025
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
LOWER LEVEL
Corrective Action Required
01/16/2026
FIRST FLOOR
Corrective Action Required
01/16/2026
SECOND FLOOR
Corrective Action Required
01/16/2026
THIRD FLOOR
Corrective Action Required
01/16/2026
OK: -Walls at tubs & showers
FOURTH FLOOR
Corrective Action Required
01/16/2026
OK: -Walls at tubs & showers
Rated Assembly Inspection Failed 1/20/2026 1/20/2026 01/20/2026
STAIR TOWER 1
Corrective Action Required
01/16/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
01/16/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
01/16/2026
Lower level: -stair side 2nd layer 1st fl: 2nd fl: 3rd fl: -307&309 sides-2nd layer 4th fl: -407&409 sides-1st layer
STAIR TOWER 3
Corrective Action Required
01/16/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
01/16/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
LOWER LEVEL
Corrective Action Required
01/16/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
FIRST FLOOR
Corrective Action Required
01/16/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
SECOND FLOOR
Corrective Action Required
01/16/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
THIRD FLOOR
Corrective Action Required
01/16/2026
OK: -Walls at tubs & showers screw pattern
FOURTH FLOOR
Corrective Action Required
01/16/2026
OK: -Walls at tubs & showers screw pattern
Water Line - Hydrostatic Test Passed 1/21/2026 1/21/2026 01/21/2026
Misc
Informational
01/21/2026
1-21-26 Dustin A, Hydrostatic test performed for fire line for building 2. Tested for 2 hours at 200psi. pass
Rated Assembly Inspection Failed 1/22/2026 1/22/2026 01/22/2026
STAIR TOWER 1
Corrective Action Required
01/20/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
01/20/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
01/20/2026
Lower level: -stair side 2nd layer 1st fl: 2nd fl: 3rd fl: -307&309 sides-2nd layer 4th fl: -407&409 sides-2nd layer
STAIR TOWER 3
Corrective Action Required
01/20/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
01/20/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
LOWER LEVEL
Corrective Action Required
01/20/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
FIRST FLOOR
Corrective Action Required
01/20/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
SECOND FLOOR
Corrective Action Required
01/20/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
THIRD FLOOR
Corrective Action Required
01/20/2026
OK: -Walls at tubs & showers screw pattern
FOURTH FLOOR
Corrective Action Required
01/20/2026
OK: -Walls at tubs & showers screw pattern
All Rough Inspection - Commercial Failed 2/3/2026 2/3/2026 02/03/2026
Misc
Corrective Action Required
12/31/2025
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
12/31/2025
**Pre-rock at showers and tubs corrections: 001: -Install 2-ft strap at top plate lapped less than 4 ft 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
12/31/2025
**Pre-rock at showers and tubs corrections: 101: -Install 2-ft strap at top plate lapped less than 4 ft 103: -Nail shear wall at bottom wall plate per scheduled 107: -Strap over-bored top plate per plan
SECOND FLOOR
Corrective Action Required
12/31/2025
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 201: -Install 2-ft strap at top plate lapped less than 4 ft 202: -Install 2-ft strap at top plate lapped less than 4 ft 213: -Strap over-bored top plate per plan
THIRD FLOOR
Corrective Action Required
12/31/2025
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling
FOURTH FLOOR
Corrective Action Required
12/31/2025
OK: -Pre-rock for walls at showers and tubs
ELEVATOR 1
Corrective Action Required
12/31/2025
OK: -Pre-rock for top lid
Rated Assembly Inspection Failed 2/6/2026 02/06/2026
STAIR TOWER 1
Corrective Action Required
01/22/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
01/22/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
01/22/2026
Lower level: -stair side 2nd layer 1st fl: 2nd fl: 3rd fl: -307&309 sides-2nd layer, mud&taped 4th fl: -407&409 sides-2nd layer, mud&taped
STAIR TOWER 3
Corrective Action Required
01/22/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
01/22/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
LOWER LEVEL
Corrective Action Required
01/22/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
FIRST FLOOR
Corrective Action Required
01/22/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
SECOND FLOOR
Corrective Action Required
01/22/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
THIRD FLOOR
Corrective Action Required
01/22/2026
OK: -Walls at tubs & showers screw pattern, mud&taped
FOURTH FLOOR
Corrective Action Required
01/22/2026
OK: -Walls at tubs & showers screw pattern, mud&taped
Rated Assembly Inspection Failed 2/11/2026 2/11/2026 02/11/2026
STAIR TOWER 1
Corrective Action Required
02/06/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
02/06/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
02/06/2026
Lower level: -stair side 2nd layer 1st fl: 2nd fl: 3rd fl: -307&309 sides-2nd layer, mud&taped 4th fl: -407&409 sides-2nd layer, mud&taped
STAIR TOWER 3
Corrective Action Required
02/06/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
02/06/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building. Verify with architect
LOWER LEVEL
Corrective Action Required
02/06/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing -At end units, strap top plates lapped less than 4 ft -Fb top of fur-out wall space
FIRST FLOOR
Corrective Action Required
02/06/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (unit 107)
SECOND FLOOR
Corrective Action Required
02/06/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (unit 213) -Fb top of fur-out wall space (215)
THIRD FLOOR
Corrective Action Required
02/06/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
FOURTH FLOOR
Corrective Action Required
02/06/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
All Rough Inspection - Commercial Failed 2/12/2026 2/12/2026 02/12/2026
Misc
Corrective Action Required
02/03/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
02/03/2026
**Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
02/03/2026
OK: -Pre-rock at showers and tubs
SECOND FLOOR
Corrective Action Required
02/03/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs
THIRD FLOOR
Corrective Action Required
02/03/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling
FOURTH FLOOR
Corrective Action Required
02/03/2026
OK: -Pre-rock for walls at showers and tubs
ELEVATOR 1
Corrective Action Required
02/03/2026
OK: -Pre-rock for top lid
All Rough Inspection - Commercial Failed 2/13/2026 2/13/2026 02/13/2026
Misc
Corrective Action Required
02/12/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
02/12/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
02/12/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs
SECOND FLOOR
Corrective Action Required
02/12/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs
THIRD FLOOR
Corrective Action Required
02/12/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling
FOURTH FLOOR
Corrective Action Required
02/12/2026
OK: -Pre-rock for walls at showers and tubs
ELEVATOR 1
Corrective Action Required
02/12/2026
OK: -Pre-rock for top lid
All Rough Inspection - Commercial Partial 2/18/2026 2/18/2026 02/18/2026
Misc
Corrective Action Required
02/13/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
02/13/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
02/13/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
02/13/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
02/13/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling - Balconies framing ok except: 316,312, 304, not built 316- no guard installed 301- provide joist hangers at beam 302- correct hanger on wall side for bearing
FOURTH FLOOR
Corrective Action Required
02/13/2026
OK: -Pre-rock for walls at showers and tubs -Balconies: 405- hanger missing nails 410- install guard rails All others framing ok
ELEVATOR 1
Corrective Action Required
02/13/2026
OK: -Pre-rock for top lid
Rated Assembly Inspection Failed 2/19/2026 2/19/2026 02/19/2026
STAIR TOWER 1
Corrective Action Required
02/11/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
02/11/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
02/11/2026
Lower level: -stair side 2nd layer 1st fl: -104 side, 1st layer 2nd fl: -207&209 sides, 1st layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped
STAIR TOWER 3
Corrective Action Required
02/11/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
02/11/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
02/11/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
02/11/2026
OK: -Pre-rock at tubs & showers walls -Walls at tubs & showers screw pattern
SECOND FLOOR
Corrective Action Required
02/11/2026
OK: -Pre-rock at tubs & showers walls -Walls at tubs & showers screw pattern
THIRD FLOOR
Corrective Action Required
02/11/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
FOURTH FLOOR
Corrective Action Required
02/11/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
Rated Assembly Inspection Failed 2/20/2026 2/20/2026 02/20/2026
STAIR TOWER 1
Corrective Action Required
02/19/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
02/19/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
02/19/2026
Lower level: -stair side 2nd layer 1st fl: -104 side, 1st layer 2nd fl: -207&209 sides, 1st layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped
STAIR TOWER 3
Corrective Action Required
02/19/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
02/19/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
02/19/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
02/19/2026
OK: -Pre-rock at tubs & showers walls -Walls at tubs & showers screw pattern
SECOND FLOOR
Corrective Action Required
02/19/2026
OK: -Pre-rock at tubs & showers walls -Walls at tubs & showers screw pattern, walls mud&taped
THIRD FLOOR
Corrective Action Required
02/19/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
FOURTH FLOOR
Corrective Action Required
02/19/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
Electrical Service Inspection Failed 2/23/2026 2/23/2026 02/23/2026
Misc
Corrective Action Required
02/23/2026
-Provide address -grounding does not match plans.
Rated Assembly Inspection Failed 2/24/2026 2/24/2026 02/24/2026
STAIR TOWER 1
Corrective Action Required
02/20/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
02/20/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
02/20/2026
Lower level: -stair side 2nd layer 1st fl: -104 side, 1st layer 2nd fl: -207&209 sides, 1st layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped
STAIR TOWER 3
Corrective Action Required
02/20/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
02/20/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
02/20/2026
Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
02/20/2026
OK: -Walls at tubs & showers screw pattern
SECOND FLOOR
Corrective Action Required
02/20/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling
THIRD FLOOR
Corrective Action Required
02/20/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling
FOURTH FLOOR
Corrective Action Required
02/20/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
Rated Assembly Inspection Failed 2/27/2026 2/27/2026 02/27/2026
STAIR TOWER 1
Corrective Action Required
02/24/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
02/24/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
02/24/2026
Lower level: -stair side 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -ceiling, 1st layer
STAIR TOWER 3
Corrective Action Required
02/24/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
02/24/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
02/24/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
02/24/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
02/24/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
02/24/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
02/24/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
Rated Assembly Inspection Failed 3/3/2026 3/3/2026 03/03/2026
STAIR TOWER 1
Corrective Action Required
02/27/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
02/27/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
02/27/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -ceiling, 1st layer
STAIR TOWER 3
Corrective Action Required
02/27/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
02/27/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
02/27/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
02/27/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
02/27/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
02/27/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
02/27/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
Electrical Service Inspection Passed 3/3/2026 3/3/2026 03/03/2026
Misc
Resolved
03/03/2026
-Provide address -grounding does not match plans.
Rated Assembly Inspection Failed 3/5/2026 3/5/2026 03/05/2026
STAIR TOWER 1
Corrective Action Required
03/03/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
03/03/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
03/03/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/03/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/03/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/03/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/03/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/03/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/03/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
03/03/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped
All Rough Inspection - Commercial Failed 3/5/2026 3/5/2026 03/05/2026
Misc
Corrective Action Required
02/18/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
02/18/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
02/18/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
02/18/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
02/18/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling - Balconies framing ok except: 316,312, 304, not built 316- no guard installed 301- provide joist hangers at beam 302- correct hanger on wall side for bearing
FOURTH FLOOR
Corrective Action Required
02/18/2026
OK: -Pre-rock for walls at showers and tubs -Balconies Common deficiencies: -Fc all wall plate holes and penetrations -Secure SE cable within 12” of panel -Tape ungrounded conductor with proper color -Provide vertical fire blockings at max ten ft intervals -Strap bearing wall top plates where lapped less than 4 ft -Fc penetrations of elevator wall 401: 402: -Seal floor at tub trap 404: -Add another h clip at beam 403: -Install long screws and red screws at truss girder support stud pack -Fc penetration above alarm; secure alarm box to stud -Tie down window header to wall 406: 405: -Balcony hanger missing nails 408: -Move refrigerator water line to inside wall -Protect range wiring at bottom wall plate -Staple wiring near bathroom receptacle box 407: -Fc all wall plate holes and penetrations -Complete electrical to bedroom receptacle -Complete alarm wiring to box -Install truss hanger above shower 410: 409: -Protect fire sprinkler pipe at refrigerator -Complete soffit around roof drain 412: -Protect fire sprinkler pipe near balcony door 413: -Protect fire sprinkler pipe near entry door -Protect 3” pvc at laundry per code 411: -Protect wiring at laundry wall top plate
ELEVATOR 1
Corrective Action Required
02/18/2026
OK: -Pre-rock for top lid
Rated Assembly Inspection Failed 3/9/2026 3/9/2026 03/09/2026
STAIR TOWER 1
Corrective Action Required
03/05/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
03/05/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
03/05/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/05/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/05/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/05/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/05/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/05/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/05/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
03/05/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -GB install at 402&413 closet wall
All Rough Inspection - Commercial Failed 3/9/2026 3/9/2026 03/09/2026
Misc
Corrective Action Required
03/05/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/05/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/05/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/05/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
03/05/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling - Balconies framing ok except: 316,312, 304, not built 316- no guard installed 301- provide joist hangers at beam 302- correct hanger on wall side for bearing
FOURTH FLOOR
Corrective Action Required
03/05/2026
OK: -Pre-rock for walls at showers and tubs -Balconies Common deficiencies: -Secure SE cable within 12” of panel -Tape ungrounded conductor with proper color -Fc penetrations of elevator wall 401: 402: 404: 403: 406: 405: 408: -Move refrigerator water line to inside wall -Protect range wiring at bottom wall plate -Staple wiring near bathroom sink receptacle box 407: -Complete electrical to bedroom receptacle 410: 409: -Complete soffit around roof drain 412: 413: 411: -Protect wiring at laundry wall top plate
ELEVATOR 1
Corrective Action Required
03/05/2026
OK: -Pre-rock for top lid
All Rough Inspection - Commercial Failed 3/10/2026 3/10/2026 03/10/2026
Misc
Corrective Action Required
03/09/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/09/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/09/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/09/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
03/09/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling - Balconies framing ok except: 316,312, 304, not built 316- no guard installed 301- provide joist hangers at beam 302- correct hanger on wall side for bearing
FOURTH FLOOR
Corrective Action Required
03/09/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor Common deficiencies: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/09/2026
OK: -Pre-rock for top lid
All Rough Inspection - Commercial Failed 3/13/2026 3/13/2026 03/13/2026
Misc
Corrective Action Required
03/10/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/10/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/10/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/10/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
03/10/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling - Balconies framing ok except: 316,312, 304, not built 316- no guard installed 301- provide joist hangers at beam 302- correct hanger on wall side for bearing
FOURTH FLOOR
Corrective Action Required
03/10/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor Common deficiencies: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/10/2026
OK: -Pre-rock for top lid **Corrections: -Fc top plate penetrations
All Rough Inspection - Commercial Failed 3/16/2026 3/16/2026 03/16/2026
Misc
Corrective Action Required
03/13/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/13/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/13/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/13/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
03/13/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling -Balconies Common deficiencies: -Secure all wirings within 12” of panels -Tape ungrounded conductor with proper color -Fc wall plate holes and penetrations throughout -Draft stop all penetrations above demise walls -Fire caulk at 4” or bigger roof drain penetrations of subfloor -Kickers framing not per plan -Install squash blocks above bathroom where required -Protect wiring at top plates where within 1.25” of nailing surface in bedrooms 318: -Protect wiring at back side of panel -Fc hole at closet/kitchen bottom wall plate -Support dryer duct every 4 ft 317: -Fc wall plate penetrations; fc penetration above and hole below panel 315: -Fc holes at bottom wall plate 316: -Fc membrane penetration behind media panel -Protect wiring at balcony switch 314: -Protect sprinkler pipe in closet -Squash block above doorway -Protect wiring below media panel 311: -Install floor-floor screw at rear window -Move sprinkler head min 3 ft from fan 312: -Protect wiring at top plates where within 1.25” of nailing surface 309: 310: -Fc around elevator wall -Install squash block; strap top plates below -Provide access to roof space -Hanger above laundry not installed properly 307: -Fc around elevator wall 308: -Provide stud support for lvl beam at kitchen/demising wall 305: -Protect wiring at top plates where within 1.25” of nailing surface in bedrooms -Repair damaged truss -Install squash block above bathroom 306: 304: 303: -Protect wiring at top plates where within 1.25” of nailing surface in bedrooms 301: -Move sprinkler head to ceiling level -Complete the fresh air ducting 302: -Fb wall space from roof space
FOURTH FLOOR
Corrective Action Required
03/13/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor Common deficiencies: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/13/2026
OK: -Pre-rock for top lid **Corrections: -Fc top plate penetrations
Rated Assembly Inspection Failed 3/17/2026 3/17/2026 03/17/2026
STAIR TOWER 1
Corrective Action Required
03/09/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
STAIR TOWER 2
Corrective Action Required
03/09/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped **Extend GB to roof deck 3rd floor: -stair side, 2nd layer
ELEVATOR 1
Corrective Action Required
03/09/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/09/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/09/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/09/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/09/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/09/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/09/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
03/09/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -GB install at 402&413 closet wall -RC ok, except below **Corrections: -above bedroom windows, 401 -laundry and bedroom, 405
Rated Assembly Inspection Failed 3/17/2026 03/17/2026
STAIR TOWER 1
Corrective Action Required
03/17/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
STAIR TOWER 2
Corrective Action Required
03/17/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
ELEVATOR 1
Corrective Action Required
03/17/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -corridor side, 1st layer -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/17/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/17/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -GB install at 402&413 closet wall -RC ok, except below **Corrections: -above bedroom windows, 401 -laundry and bedroom, 405
Rated Assembly Inspection Failed 3/18/2026 3/18/2026 03/18/2026
STAIR TOWER 1
Corrective Action Required
03/17/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
STAIR TOWER 2
Corrective Action Required
03/17/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
ELEVATOR 1
Corrective Action Required
03/17/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -corridor side, 1st layer -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/17/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/17/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
FOURTH FLOOR
Corrective Action Required
03/17/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -GB install at 402&413 closet wall -RC ok
All Rough Inspection - Commercial Failed 3/19/2026 3/19/2026 03/19/2026
Misc
Corrective Action Required
03/16/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/16/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/16/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/16/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
03/16/2026
OK: -Pre-rock for walls at showers and tubs -Pre-rock for corridor ceiling -Balconies Common deficiencies: -Tape ungrounded conductor with proper color -Fire caulk at 4” or bigger roof drain penetrations of subfloor -Protect wiring at top plates where within 1.25” of nailing surface 318: 317: 315: -Secure all wirings within 12” of panels 313: -Fc wall plate holes and penetrations 316: 314: 311: -Protect wiring at top plates where within 1.25” of nailing surface 312: -Protect wiring at top plates where within 1.25” of nailing surface 309: -Fc bedroom wall plate penetrations by fire alarm cables 310: -Provide access to roof space 307: 308: 305: -Protect wiring at top plates where within 1.25” of nailing surface in bedrooms (SE and other wiring) -Repair damaged truss 306: 304: 303: 301: -Strap wall in bedroom 302: -Fc hole at kitchen wall top plate
FOURTH FLOOR
Corrective Action Required
03/16/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor Common deficiencies: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/16/2026
OK: -Pre-rock for top lid **Corrections: -Fc top plate penetrations
All Rough Inspection - Commercial Failed 3/20/2026 3/20/2026 03/20/2026
Misc
Corrective Action Required
03/19/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/19/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/19/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/19/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs - Balconies 204,216,217 not built others framing ok
THIRD FLOOR
Corrective Action Required
03/19/2026
-Protect wiring at top plates where within 1.25” of nailing surface
FOURTH FLOOR
Corrective Action Required
03/19/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor Common deficiencies: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/19/2026
OK: -Pre-rock for top lid and wall
All Rough Inspection - Commercial Failed 3/23/2026 3/23/2026 03/23/2026
Misc
Corrective Action Required
03/20/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/20/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/20/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/20/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies Common deficiencies: -Fc 4” or bigger roof drain penetrations at subfloor -Protect ducts at balcony -Check all box puddy pad fully cover around boxes 218: -Protect back-back boxes -Provide hanger support for trusses where bearing is less than 1.5” of bearing -Secure SE within 12” of panel -Strap top plates lapped less than 4 ft at laundry 217: -Protect SE at top plate 215: 213: 216: -Protect water lines above kitchen sink -Fb fur out wall in bedroom 214: -Protect back-back boxes; secure wiring near box -Protect wiring at top plate in closet 211: -Protect wiring below media box -Move sprinkler head min 3 ft away from fan -Secure receptacle in master bathroom 212: 209: -Fc penetration below media -Fb fur out wall in bedroom; fb gap between wall top plates 210: -Complete fur out wall at 6” roof drain -Fc wiring penetration in close -Receptacle spacing at rear wall exceed 12 ft 207: -Provide hanger support for trusses where bearing is less than 1.5” of bearing -Fc water line penetration of wall plate -Mud and fire tape elevator firewall 208: -Move sprinkler head min 3 ft away from fan 205: -Protect wiring at top plate near SE cable 206: -Protect back-back boxes -Screw down the floor-floor screw in bedroom 204: -Protect wiring at kitchen top plate; below balcony light switch -Fc holes and penetrations of stair wall plate 203: -Protect wiring at top plate in bedroom -Secure MC cable near panel -Protect fire sprinkler at top wall plate in closet 201: 200: -Provide hanger support for trusses where bearing is less than 1.5” of bearing -Protect sprinkler pipe in bedroom
THIRD FLOOR
Corrective Action Required
03/20/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies **Correction: -Protect wiring at top plates where within 1.25” of nailing surface
FOURTH FLOOR
Corrective Action Required
03/20/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor **Correction: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/20/2026
OK: -Pre-rock for top lid and wall
All Rough Inspection - Commercial Failed 3/25/2026 3/25/2026 03/25/2026
Misc
Corrective Action Required
03/23/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/23/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/23/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/23/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies Common deficiencies: -Fc 4” or bigger roof drain penetrations at subfloor 218: 217: 215: 213: 216: 214: -Protect back-back boxes near laundry standpipe; secure wiring near box 211: 212: 209: -Fb fur out wall in bedroom; fb gap between wall top plates 210: -Complete fur out wall at 6” roof drain **install top lid 207: -Mud and fire tape elevator firewall. Close off excessive gaps and install fire tape 208: 205: -Protect wiring at top plate near SE cable 206: -Protect back-back boxes -Screw down the floor-floor screw in bedroom 204: -Protect wiring at kitchen top plate -Fc holes at stair wall plate **holes about 3-3.5 ft left of mechanical closet door 203: -Protect fire sprinkler at top wall plate in closet 201: 200: -Provide hanger support for trusses where bearing is less than 1.5” of bearing **above master bathroom -Protect sprinkler pipe in bedroom **at top plate
THIRD FLOOR
Corrective Action Required
03/23/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies **Correction: -Protect wiring at top plates where within 1.25” of nailing surface
FOURTH FLOOR
Corrective Action Required
03/23/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor **Correction: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/23/2026
OK: -Pre-rock for top lid and wall
All Rough Inspection - Commercial Failed 3/27/2026 3/27/2026 03/27/2026
Misc
Corrective Action Required
03/25/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/25/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/25/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok
SECOND FLOOR
Corrective Action Required
03/25/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies 210: -Complete fur out wall at 6” roof drain **install top lid 207: -Mud and fire tape elevator firewall. Close off excessive gaps and install fire tape
THIRD FLOOR
Corrective Action Required
03/25/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies -All units and corridor **Correction:
FOURTH FLOOR
Corrective Action Required
03/25/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor **Correction: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/25/2026
OK: -Pre-rock for top lid and wall
Rated Assembly Inspection Partial 3/30/2026 3/30/2026 03/30/2026
STAIR TOWER 1
Corrective Action Required
03/18/2026
**NORTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
STAIR TOWER 2
Corrective Action Required
03/18/2026
**SOUTH STAIR ENCLOSURE** Lower level: -stair side, 2nd layer First floor: -stair side, 2nd layer, mud&taped 2nd floor: -stair side, 2nd layer, mud&taped 3rd floor: -stair side, 2nd layer 4th floor: -corridor and unit sides, 1st layer
ELEVATOR 1
Corrective Action Required
03/18/2026
Lower level: -stair side, 2nd layer -004 side, 2nd layer 1st fl: -104 side, 1st layer **correction: remove the 2nd layer. Cannot cut out 2nd layer around the hangers. Need full 2 layers behind hangers 2nd fl: -207&209 sides, 2nd layer 3rd fl: -307&309 sides, 2nd layer, mud&taped 4th fl: -407&409 sides, 2nd layer, mud&taped -corridor side, 1st layer -ceiling, 2nd layer of 4 layers
STAIR TOWER 3
Corrective Action Required
03/18/2026
**REAR STAIR ENCLOSURE** -wall adjacent to stair-ok, mud&taped
Misc
Corrective Action Required
03/18/2026
-Exterior wall protected with 1-hr FlameBlock sheathing 12 ft from NE corner of building.
LOWER LEVEL
Corrective Action Required
03/18/2026
OK: -Walls at tubs & showers screw pattern, except at 007 -Corridor ceiling screw pattern **Pre-rock at tubs & showers walls corrections: -Strap across top plates bored more than 50% at 3" plumbing (007)
FIRST FLOOR
Corrective Action Required
03/18/2026
OK: -Walls at tubs & showers screw pattern, mud&taped -Corridor ceiling screw pattern
SECOND FLOOR
Corrective Action Required
03/18/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped
THIRD FLOOR
Corrective Action Required
03/18/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -Corridor ceiling, mud&taped -j channel in all rooms of this floor is in place. Ready for Sheetrock
FOURTH FLOOR
Corrective Action Required
03/18/2026
OK: -Walls at tubs & showers screw pattern, walls mud&taped -GB install at 402&413 closet wall -RC ok -screw pattern in the corridors and all units and ceiling is good
ELEVATOR 1
Corrective Action Required
03/30/2026
-elevator shaft inside first layer all floors is good on the screw pattern
All Rough Inspection - Commercial Failed 3/31/2026 3/31/2026 03/31/2026
Misc
Corrective Action Required
03/27/2026
Garage PHF portal walls framing-OK to cover **install blockings under window jack and kings studs
LOWER LEVEL
Corrective Action Required
03/27/2026
OK: -Pre-rock for corridor ceiling **Pre-rock at showers and tubs corrections: 007: -Strap over-bored top plate per plan
FIRST FLOOR
Corrective Action Required
03/27/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies- 106, Rafter has no bearing at top at middle of soffit All others framing ok Corrective actions All units -Support and secure all wiring in ceiling space max spacing 4 1/2’ -provide minimum 1 1/2” Bearing for all trusses 101 -seal gaps in dead space at primary bedroom shower -protect wires at top plate primary bedroom entry -address damaged truss above dead space at primary bedroom shower 102 -missing receptacle in primary bedroom wall space greater than 2’ 103 -move fire sprinkler SE Bedroom -protect wire at top plate primary SW bath -provide bearing for trusses 1 1/2” minimum NE bedroom -seal draft stop penetrations S wall 104 -seal bottom plate penetration in mechanical closet -address trusses spaced greater than 24” OC 105 -strap top plate at coat closet -secure SE cable left of panel Corridor outside 105 -address cut load bearing stud pack garage side 106 -address electric SE primary bedroom 107 108 -provide protection for sprinkler line top and bottom plate at entry -secure stud at panel 109 -putty packs must cover entirety of box W wall -provide putty packs for outlets closer than 24” E wall multiple locations -furr wall at panel of electrical runs 110 -fireblock top of entire S wall -complete electrical in S bedroom -provide outlet at living room W wall -protect electrical in entry bath top plate
SECOND FLOOR
Corrective Action Required
03/27/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies 210: -Complete fur out wall at 6” roof drain **install top lid 207: -Mud and fire tape elevator firewall. Close off excessive gaps and install fire tape
THIRD FLOOR
Corrective Action Required
03/27/2026
OK: -Pre-rock for corridor ceiling -Pre-rock at showers and tubs -Balconies -All units and corridor **Correction:
FOURTH FLOOR
Corrective Action Required
03/27/2026
OK: -Pre-rock for walls at showers and tubs -Balconies -Units, corridor **Correction: -Install GB at ceiling of dead space adjacent to storage space. Fire-stop penetration
ELEVATOR 1
Corrective Action Required
03/27/2026
OK: -Pre-rock for top lid and wall
Documents & Images
Date Uploaded File Type Document Name
06/26/2024 Receipt Receipt for transaction:2024-005225
06/27/2024 Letter DS Building Permit
07/23/2024 Letter INSPECTION SUMMARY
07/25/2024 Letter INSPECTION SUMMARY
07/26/2024 Letter INSPECTION SUMMARY
07/31/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/13/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter INSPECTION SUMMARY
08/16/2024 Letter INSPECTION SUMMARY
08/30/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/25/2024 Letter INSPECTION SUMMARY
12/11/2024 Letter INSPECTION SUMMARY
12/12/2024 Letter INSPECTION SUMMARY
12/12/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
12/23/2024 Letter INSPECTION SUMMARY
12/27/2024 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
03/07/2025 Letter INSPECTION SUMMARY
03/10/2025 Letter INSPECTION SUMMARY
04/21/2025 Plans Alarm plans
04/21/2025 24050258 Blackwell Apt 2-FA-set SEALED
04/28/2025 24050258 Blackwell Apt 2-FA-set SEALED RFC
04/28/2025 Letter Fire (Alarm) Plan Review Notice
05/02/2025 Letter INSPECTION SUMMARY
05/07/2025 Receipt Receipt for transaction:2025-002959
05/15/2025 Letter DS Building Permit
06/09/2025 Alliance Fire Protection Combined FP drawings 8-7-24
06/09/2025 RB-0B_LH-Calc-06-18-2024
06/09/2025 RB-04-13RCalc-06-11-2024
06/09/2025 RB-04-13RCalc-06-18-2024
07/25/2025 Letter INSPECTION SUMMARY
07/13/2023 Approved Plans approved - volume 1
07/13/2023 Approved Plans approved - volume 2
08/04/2025 Letter INSPECTION SUMMARY
08/05/2025 Letter INSPECTION SUMMARY
08/13/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
08/28/2025 Letter INSPECTION SUMMARY
09/03/2025 Letter INSPECTION SUMMARY
09/12/2025 Letter INSPECTION SUMMARY
09/17/2025 Letter INSPECTION SUMMARY
09/22/2025 Letter INSPECTION SUMMARY
09/25/2025 Letter INSPECTION SUMMARY
10/01/2025 Letter INSPECTION SUMMARY
11/14/2025 Letter Blackwell Code Modification Request2
11/14/2025 Letter INSPECTION SUMMARY
11/17/2025 Letter INSPECTION SUMMARY
11/20/2025 Letter INSPECTION SUMMARY
11/21/2025 Letter INSPECTION SUMMARY
11/21/2025 Letter INSPECTION SUMMARY
12/01/2025 Letter INSPECTION SUMMARY
12/03/2025 Letter INSPECTION SUMMARY
12/10/2025 Letter INSPECTION SUMMARY
12/15/2025 Letter INSPECTION SUMMARY
12/17/2025 Letter INSPECTION SUMMARY
12/24/2025 Letter INSPECTION SUMMARY
12/31/2025 Letter INSPECTION SUMMARY
12/31/2025 Letter INSPECTION SUMMARY
01/06/2026 Alliance Fire Protection Combined FP drawings 8-7-24
01/06/2026 RB-0B_LH-Calc-06-18-2024 Stamped
01/06/2026 RB-04-13RCalc-06-18-2024 Stamped
01/06/2026 RB-ST-Calc-06-18-2024 Stamped
01/16/2026 Letter INSPECTION SUMMARY
01/20/2026 Letter INSPECTION SUMMARY
01/20/2026 Alliance Fire Protection Combined FP drawings 8-7-25 RFC
01/20/2026 Letter Fire (Sprinkler) Plan Review
01/21/2026 Letter INSPECTION SUMMARY
01/22/2026 Letter INSPECTION SUMMARY
02/03/2026 Letter INSPECTION SUMMARY
02/06/2026 Letter INSPECTION SUMMARY
02/11/2026 Letter INSPECTION SUMMARY
02/12/2026 Letter INSPECTION SUMMARY
02/13/2026 Letter INSPECTION SUMMARY
02/18/2026 Letter INSPECTION SUMMARY
02/20/2026 Letter INSPECTION SUMMARY
02/23/2026 Letter INSPECTION SUMMARY
02/23/2026 Letter INSPECTION SUMMARY
02/24/2026 Letter INSPECTION SUMMARY
02/27/2026 Letter INSPECTION SUMMARY
03/03/2026 Letter INSPECTION SUMMARY
03/03/2026 Letter INSPECTION SUMMARY
03/05/2026 Letter INSPECTION SUMMARY
03/05/2026 Letter INSPECTION SUMMARY
03/09/2026 Letter INSPECTION SUMMARY
03/09/2026 Letter INSPECTION SUMMARY
03/10/2026 Letter INSPECTION SUMMARY
03/13/2026 Letter INSPECTION SUMMARY
03/16/2026 Letter INSPECTION SUMMARY
03/17/2026 Letter INSPECTION SUMMARY
03/17/2026 Letter INSPECTION SUMMARY
03/18/2026 Letter INSPECTION SUMMARY
03/19/2026 Letter INSPECTION SUMMARY
03/20/2026 Letter INSPECTION SUMMARY
03/23/2026 Letter INSPECTION SUMMARY
03/25/2026 Letter INSPECTION SUMMARY
03/27/2026 Letter INSPECTION SUMMARY
03/31/2026 Letter INSPECTION SUMMARY
03/31/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home