Permit Application Status

PRCOM20215028


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20215028
Building Permit - Commercial
Certificate of Occupancy
MARION RIDGE SAFETY STORAGE LLC
NEW COMMERCIAL
Spec Building - Office/Warehouse Use STOP WORK ORDER removed on 01/19/2022 12:00 AM by username 'Adam Nacke'.
09/27/2021
01/26/2022
06/14/2022
11/18/2022
Locations
Contacts
MARION RIDGE SAFETY STORAGE LLC, Address:1120 NW EAGLE RIDGE BLVD  
WARD DEVELOPMENT & INVESTMENT CO, Address:1120 NW EAGLE RIDGE BLVD, Phone:(816) 229-8115  
david@safetyministorage.com  
F & G MECHANICAL SERVICES INC, Address:17219 BEL RAY PLACE, Phone:(816) 322-0810  
BLUE SPRINGS ELECTRICAL SERVICE, Address:3402 LAKE SHORE DR, Phone:(816) 224-9911  
R2 PLUMBING LLC, Address:1705 A SE COUNTY RD AA, Phone:(816) 215-8098  
ALPHA-OMEGA GEOTECH, Address:1701 STATE AVE, Phone:(913) 371-0000  
POWELL CWM INC, Address:3200 S STATE ROUTE 291 BLDG 1, Phone:(816) 373-4800  
Reviews
Review Type Outcome Est. Completion Date Completed
Alarm Plan Review Released for Construction 10/28/2022
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
05/27/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Revised plans received October 25, 2022.
Installation acceptance testing
Corrective Action Required
05/27/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule testing. The alarm system will be tested during the sprinkler flow test.
Sprinkler Plan Review Released for Construction 10/11/2021 05/27/2022
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
05/27/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Revised Plans received May 27, 2022 with all correction addressed. Ensure the alarm company moves the horn/stobe to the new location of the FDC.
Installation acceptance testing
Corrective Action Required
05/27/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule a hydrostatic and flow test.
Sprinkler Plan Review Rejected 05/26/2022
Jim Eden
Miscellaneous Correction
Corrective Action Required
05/26/2022

The FDC needs to be relocated to the southwest corner of the building. It will still be within 100 feet of a fire hydrant and would not require closing Independence Ave.to supply it.
Miscellaneous Correction
Corrective Action Required
05/26/2022

The safety margin is below the 5psi. standard required by the Lee's Summit Fire Department.
Building Plan Review Approved with Conditions 01/04/2022 01/26/2022
Joe Frogge
Final Development Plan
Resolved
01/26/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 12/16/21 - in plan review
Suite address
Resolved
12/27/2021

This structure has been assigned one address. All suites/apartments shall be assigned an address by the owner which can be numeric, alphabetic or a combination of both. If the building has multiple stories the suite/apartment number shall start with a number representing the floor on which the unit is located. 12/16/21 - Comment is for informational purposes. We have assigned address numbers from West to East - 2601, 2603, 2605, 2607, 2609, 2613, 2615, 2617 NE McBaine Dr for future tenants. There will be no other suite designations.
IBC 1704.2 Special Inspections
Resolved
12/27/2021

2018 IBC 1705.1 General. Special inspections and tests of elements and nonstructural components of buildings and structures shall meet the applicable requirements of this section. Action required: Expand list of required special inspections to include structural steel.
Planning - Screening of ground mounted equipment
Corrective Action Required
12/27/2021

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment (condensing units) will be screened from all 4 sides per referenced UDO section. 12/16/21 - not addressed 12/27/21 - accomplished with landscaping - to be field verified.
Final Development Plan Review Approved 01/07/2022 01/25/2022
Mike Weisenborn
Lot 10 I-470 Spec Building
Engineering Review Approved with Conditions 10/11/2021 12/29/2021
Mike Weisenborn
Fire Plan Review Approved with Conditions 01/04/2022 12/27/2021
Michael Weissenbach
Licensed Contractors Approved 12/27/2021 12/27/2021
Joe Frogge
LC - MEP Subs
Resolved
12/27/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (R-Z Plumbing not licensed) 12/15/21 - R-Z still not licensed
Building Plan Review Rejected 12/21/2021 12/16/2021
Joe Frogge
Final Development Plan
Corrective Action Required
12/14/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 12/16/21 - in plan review
Suite address
Corrective Action Required
12/14/2021

This structure has been assigned one address. All suites/apartments shall be assigned an address by the owner which can be numeric, alphabetic or a combination of both. If the building has multiple stories the suite/apartment number shall start with a number representing the floor on which the unit is located. 12/16/21 - Comment is for informational purposes. We have assigned address numbers from West to East - 2601, 2603, 2605, 2607, 2609, 2613, 2615, 2617 NE McBaine Dr for future tenants. There will be no other suite designations.
IBC 1803.1 General - geotech
Resolved
12/15/2021

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf.
IBC 1704.2 Special Inspections
Corrective Action Required
12/14/2021

2018 IBC 1705.1 General. Special inspections and tests of elements and nonstructural components of buildings and structures shall meet the applicable requirements of this section. Action required: Expand list of required special inspections to include structural steel.
Planning - Screening of ground mounted equipment
Corrective Action Required
12/14/2021

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment (condensing units) will be screened from all 4 sides per referenced UDO section. 12/16/21 - not addressed
Engineered truss package
Resolved
12/16/2021

Copies of the engineered steel building package were not provided at the time of permit application. Action required: Provide complete steel building package or request deferral. 12/16/21 - deferred per request
Licensed Contractors Rejected 12/21/2021 12/15/2021
Joe Frogge
LC - MEP Subs
Corrective Action Required
12/14/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (R-Z Plumbing not licensed) 12/15/21 - R-Z still not licensed
Fire Plan Review Approved with Conditions 12/21/2021 12/14/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
12/14/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
12/14/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection) Address all exterior doors.
Knox box required
Corrective Action Required
12/14/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knoxbox from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
12/14/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net Note: Class 1 Standpipes will be required at the rear exit doors in the warehouse spaces and the loading dock.
Installation acceptance testing
Corrective Action Required
12/14/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Portable fire extinguishers - conspicuous locations
Corrective Action Required
12/14/2021

2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel. (Action Required) Provide 1 2A10BC Fire Extinguisher in the office spaces and 1 2A10BC Fire Extinguisher in the warehouse spaces. 12/14/21 (Verified At Inspection)
Misc
Corrective Action Required
12/14/2021

(Action Required) Show placement of FDC on building. FDC needs to be within 100 feet of a hydrant. (Suggestion) For ease of access to the fire sprinkler system, recommendation to add an exterior door to the fire sprinkler room. 12/14/21 (To be verified with sprinkler shop drawings)
Special Inspections Review Approved 10/19/2021
Joe Frogge
Building Plan Review Rejected 10/11/2021 10/07/2021
Joe Frogge
Final Development Plan
Corrective Action Required
10/07/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Suite address
Corrective Action Required
10/07/2021

This structure has been assigned one address. All suites/apartments shall be assigned an address by the owner which can be numeric, alphabetic or a combination of both. If the building has multiple stories the suite/apartment number shall start with a number representing the floor on which the unit is located.
IBC 1704.2 Special Inspections
Resolved
10/19/2021

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
IBC 1803.1 General - geotech
Corrective Action Required
10/07/2021

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf.
IBC 1704.2 Special Inspections
Corrective Action Required
10/07/2021

2018 IBC 1705.1 General. Special inspections and tests of elements and nonstructural components of buildings and structures shall meet the applicable requirements of this section. Action required: Expand list of required special inspections to include structural steel.
Planning - Screening of ground mounted equipment
Corrective Action Required
10/07/2021

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment (condensing units) will be screened from all 4 sides per referenced UDO section.
Engineered truss package
Corrective Action Required
10/07/2021

Copies of the engineered steel building package were not provided at the time of permit application. Action required: Provide complete steel building package or request deferral.
Licensed Contractors Rejected 10/11/2021 10/06/2021
Joe Frogge
LC - MEP Subs
Corrective Action Required
10/06/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. (R-Z Plumbing not licensed)
Fire Plan Review Rejected 10/11/2021 09/29/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
09/29/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
09/29/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection) Address all exterior doors.
Knox box required
Corrective Action Required
09/29/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knoxbox from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
09/29/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net Note: Class 1 Standpipes will be required at the rear exit doors in the warehouse spaces and the loading dock.
Installation acceptance testing
Corrective Action Required
09/29/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Portable fire extinguishers - conspicuous locations
Corrective Action Required
09/29/2021

2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel. (Action Required) Provide 1 2A10BC Fire Extinguisher in the office spaces and 1 2A10BC Fire Extinguisher in the warehouse spaces.
Misc
Corrective Action Required
09/29/2021

(Action Required) Show placement of FDC on building. FDC needs to be within 100 feet of a hydrant. (Suggestion) For ease of access to the fire sprinkler system, recommendation to add an exterior door to the fire sprinkler room.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $4,560.00 $4,560.00 Paid 01/26/2022
8331507-Sewer Connection Fee $480.00 $480.00 Paid 01/26/2022
7232302-Industrial/Warehouse License Tax Fee $4,310.00 $4,310.00 Paid 10/26/2021
8331401-Water Tap Fee $9,750.00 $9,750.00 Paid 12/29/2021
8350015-Water Meter Fee $820.29 $820.29 Paid 12/29/2021
9110068-Storm Fee $1,761.01 $1,761.01 Paid 12/29/2021
91100C9-Water Insp Fee $310.50 $310.50 Paid 12/29/2021
9110081-Paved Surface Inspection Fee $8,736.68 $8,736.68 Paid 12/29/2021
9110071-Site Grading Fee $349.19 $349.19 Paid 12/29/2021
91100C8-Sanitary Sewer Insp Fees $83.25 $83.25 Paid 12/29/2021
9110072-Water Test Fee $200.00 $200.00 Paid 12/29/2021
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 12/29/2021
9110079-After Hours Inspection (Building Codes)(Per Hour) $175.00 $175.00 Paid 03/10/2022
8331401-Water Tap Fee $6,095.00 $6,095.00 Paid 03/11/2022
$15,845.00
8350015-Water Meter Fee $529.29 $529.29 Paid 03/11/2022
$1,349.58
9110069-After Hours Inspections (Public Works)(Per Hour) $200.00 $200.00 Paid 11/04/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 11/07/2022
Outstanding Fees Amount Paid Owing Date Paid


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Complete 12/13/2021 12/13/2021 01/19/2022
Misc
Resolved
01/19/2022
12-10-21 AN Heartland Construction was out at the job site doing dirt work with out any permits or approved plans. Spoke with Calvin Randall and let him know that they had to stop all work until all plans were approved and they had the appropriate permits are in place.
Site Visit Complete 1/19/2022 1/19/2022 01/19/2022
Misc
Resolved
01/19/2022
12-10-21 AN Heartland Construction was out at the job site doing dirt work with out any permits or approved plans. Spoke with Calvin Randall and let him know that they had to stop all work until all plans were approved and they had the appropriate permits are in place.
Erosion Control Inspection Passed 1/19/2022 1/19/2022 01/19/2022
Misc
Informational
01/19/2022
1-19-22 AN silt fence and construction entrance are all in place
Grading/Excavation/Fill Inspection Partial 1/19/2022 1/19/2022 01/19/2022
Misc
Informational
01/19/2022
1-19-22 AN crew is working on grading the site and preparing a site pad
Grading/Excavation/Fill Inspection Partial 2/1/2022 2/1/2022 02/01/2022
Misc
Informational
01/19/2022
1-19-22 AN crew is working on grading the site and preparing a site pad
Misc
Informational
02/01/2022
2-1-22 AN it appears that the crew has finished the grading for the pad only and is covering it to keep it dry and for frost
Grading/Excavation/Fill Inspection Partial 02/07/2022
Misc
Informational
02/01/2022
1-19-22 AN crew is working on grading the site and preparing a site pad
Misc
Informational
02/01/2022
2-1-22 AN it appears that the crew has finished the grading for the pad only and is covering it to keep it dry and for frost
Misc
Informational
02/07/2022
2-7-22 AN no work is being done today
Grading/Excavation/Fill Inspection Partial 02/08/2022
Misc
Informational
02/07/2022
1-19-22 AN crew is working on grading the site and preparing a site pad
Misc
Informational
02/07/2022
2-1-22 AN it appears that the crew has finished the grading for the pad only and is covering it to keep it dry and for frost
Misc
Informational
02/07/2022
2-7-22 AN no work is being done today
Misc
Informational
02/08/2022
2-8-22 AN 9:10 pad site is complete and concrete crew is laying out the footings to start digging.
Grading/Excavation/Fill Inspection Partial 02/09/2022
Misc
Informational
02/08/2022
1-19-22 AN crew is working on grading the site and preparing a site pad
Misc
Informational
02/08/2022
2-1-22 AN it appears that the crew has finished the grading for the pad only and is covering it to keep it dry and for frost
Misc
Informational
02/08/2022
2-7-22 AN no work is being done today
Misc
Informational
02/08/2022
2-8-22 AN 9:10 pad site is complete and concrete crew is laying out the footings to start digging.
Misc
Informational
02/09/2022
2-9-22 AN concrete crew is digging the footings
Footing Inspection - Commercial Partial 2/9/2022 (11:30) 2/9/2022 02/09/2022
Misc
Informational
02/09/2022
Exterior footing per page S100-ok to pour
Site Visit Partial 02/10/2022
Misc
Informational
02/10/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Footing Inspection - Commercial Partial 2/10/2022 (11:00) 2/10/2022 02/10/2022
Misc
Informational
02/09/2022
Exterior footing per page S100-ok to pour -East side of footing (S101) changed from the approved plan. Submit change to the footing to the city. OK to pour
Fire Line Construction Inspection Partial 02/11/2022
Misc
Informational
02/11/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Underslab Plumbing Inspection - Commercial Partial 2/14/2022 2/14/2022 02/14/2022
Misc
Informational
02/14/2022
-Underslab SS building drain-OK
Fire Line Construction Inspection Partial 02/14/2022
Misc
Informational
02/11/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/14/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Fire Line Construction Inspection Partial 02/15/2022
Misc
Informational
02/14/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/14/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
02/15/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Fire Line Construction Inspection Partial 02/16/2022
Misc
Informational
02/15/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/15/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
02/15/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
02/16/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Fire Line Construction Inspection Partial 02/22/2022
Misc
Informational
02/16/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/16/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
02/16/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
02/16/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
02/22/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Fire Line Construction Inspection Partial 02/23/2022
Misc
Informational
02/22/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/22/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
02/22/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
02/22/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
02/22/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
02/23/2022
2-23-22 AN no work being done today
Fire Line Construction Inspection Partial 02/28/2022
Misc
Informational
02/23/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/23/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
02/23/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
02/23/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
02/23/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
02/23/2022
2-23-22 AN no work being done today
Misc
Informational
02/28/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Sanitary Sewer Construction Inspection Partial 03/01/2022
Misc
Informational
03/01/2022
3-1-22 AN crew is going to begin digging to expose the 12” sewer main . I let them know that they need to use a wye and max adapters
Fire Line Construction Inspection Partial 03/02/2022
Misc
Informational
02/28/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
02/28/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
02/28/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
02/28/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
02/28/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
02/28/2022
2-23-22 AN no work being done today
Misc
Informational
02/28/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/02/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Fire Line Construction Inspection Partial 03/02/2022
Misc
Informational
03/02/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/02/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/02/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/02/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/02/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/02/2022
2-23-22 AN no work being done today
Misc
Informational
03/02/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/02/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/02/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Fire Line Construction Inspection Partial 03/03/2022
Misc
Informational
03/02/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/02/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/02/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/02/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/02/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/02/2022
2-23-22 AN no work being done today
Misc
Informational
03/02/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/02/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/02/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/03/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Underslab Plumbing Inspection - Commercial Partial 3/7/2022 3/7/2022 03/07/2022
Misc
Informational
02/14/2022
-Underslab SS OK below: -4" building drain -2 west restrooms and sprinkler rm
Fire Line Construction Inspection Partial 03/09/2022
Misc
Informational
03/03/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/03/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/03/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/03/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/03/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/03/2022
2-23-22 AN no work being done today
Misc
Informational
03/03/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/03/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/03/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/03/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/09/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Fire Line Construction Inspection Partial 03/09/2022
Misc
Informational
03/09/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/09/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/09/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/09/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/09/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/09/2022
2-23-22 AN no work being done today
Misc
Informational
03/09/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/09/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/09/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/09/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/09/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/09/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Fire Line Construction Inspection Partial 03/09/2022
Misc
Informational
03/09/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/09/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/09/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/09/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/09/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/09/2022
2-23-22 AN no work being done today
Misc
Informational
03/09/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/09/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/09/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/09/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/09/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/09/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Fire Line Construction Inspection Partial 03/09/2022
Misc
Informational
03/09/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/09/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/09/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/09/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/09/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/09/2022
2-23-22 AN no work being done today
Misc
Informational
03/09/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/09/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/09/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/09/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/09/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/09/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/09/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Fire Line Construction Inspection Partial 03/14/2022
Misc
Informational
03/09/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/09/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/09/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/09/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/09/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/09/2022
2-23-22 AN no work being done today
Misc
Informational
03/09/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/09/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/09/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/09/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/09/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/09/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/09/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Misc
Informational
03/14/2022
3-14-22 AN. Crew flushed out the chlorinated fire line and taking 1st sample tomorrow
Water Line - Fire Hydrant Partial 03/15/2022
Misc
Informational
03/15/2022
3-15-22 AN crew has fully dug up to expose the water main for the hydrant install.. waiting on parts
Water Service Inspection Partial 03/16/2022
Misc
Informational
03/16/2022
3-16-22 AN water department did the tap on the main and the meter pit is also installed.
Fire Line Construction Inspection Partial 03/16/2022
Misc
Informational
03/14/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/14/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/14/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/14/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/14/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/14/2022
2-23-22 AN no work being done today
Misc
Informational
03/14/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/14/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/14/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/14/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/14/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/14/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/14/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Misc
Informational
03/14/2022
3-14-22 AN. Crew flushed out the chlorinated fire line and taking 1st sample tomorrow
Misc
Informational
03/16/2022
3-16-22 did first bac-t test at 12pm on 3-15-22
Fire Line Construction Inspection Partial 03/16/2022
Misc
Informational
03/16/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/16/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/16/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/16/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/16/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/16/2022
2-23-22 AN no work being done today
Misc
Informational
03/16/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/16/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/16/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/16/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/16/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/16/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/16/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Misc
Informational
03/16/2022
3-14-22 AN. Crew flushed out the chlorinated fire line and taking 1st sample tomorrow
Misc
Informational
03/16/2022
3-16-22 did first bac-t test at 12pm on 3-15-22
Water Line - Coliform Test 1 Partial 03/16/2022
Misc
Informational
03/16/2022
3-16-22 AN did first bac-t test on 3-15-22 at 12pm
Water Line - Coliform Test 2 Partial 03/16/2022
Misc
Informational
03/16/2022
12-16-22 AN 2nd bac-t test taken at 11:55am . Still waiting on the results of the 1st one
Water Line - Fire Hydrant Partial 03/21/2022
Misc
Informational
03/15/2022
3-15-22 AN crew has fully dug up to expose the water main for the hydrant install.. waiting on parts
Misc
Informational
03/21/2022
3-18-22 & 3-21-22 AN no work being done
Site Visit Partial 03/22/2022
Misc
Informational
02/10/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
03/22/2022
3-22-22 AN no work being done today. Rained
Water Line - Coliform Test 1 Passed 03/22/2022
Misc
Informational
03/16/2022
3-16-22 AN did first bac-t test on 3-15-22 at 12pm
Misc
Informational
03/22/2022
3-22-22 AN first water sample passed. Doc attached
Water Line - Coliform Test 2 Passed 03/22/2022
Misc
Informational
03/22/2022
3-22-22 AN second water sample passed. Doc attached
Water Line - Coliform Test 2 Passed 03/22/2022
Misc
Informational
03/16/2022
12-16-22 AN 2nd bac-t test taken at 11:55am . Still waiting on the results of the 1st one
Misc
Informational
03/22/2022
3-22-22 AN second water sample passed. Doc attached
Fire Line Construction Inspection Partial 03/23/2022
Misc
Informational
03/16/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/16/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/16/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/16/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/16/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/16/2022
2-23-22 AN no work being done today
Misc
Informational
03/16/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/16/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/16/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/16/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/16/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/16/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/16/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Misc
Informational
03/16/2022
3-14-22 AN. Crew flushed out the chlorinated fire line and taking 1st sample tomorrow
Misc
Informational
03/16/2022
3-16-22 did first bac-t test at 12pm on 3-15-22
Misc
Informational
03/23/2022
3-23-22 AN second water sample was taken on 3-16-22
Misc
Informational
03/23/2022
3-23-22 AN Both water samples passed and pressure test passed. Fire line should be completely done.
Fire Line Construction Inspection Partial 03/23/2022
Misc
Informational
03/23/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/23/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/23/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/23/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/23/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/23/2022
2-23-22 AN no work being done today
Misc
Informational
03/23/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/23/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/23/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/23/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/23/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/23/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/23/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Misc
Informational
03/23/2022
3-14-22 AN. Crew flushed out the chlorinated fire line and taking 1st sample tomorrow
Misc
Informational
03/23/2022
3-16-22 did first bac-t test at 12pm on 3-15-22
Misc
Informational
03/23/2022
3-23-22 AN second water sample was taken on 3-16-22
Misc
Informational
03/23/2022
3-23-22 AN Both water samples passed and pressure test passed. Fire line should be completely done. Water samples are in Docs and also sent to water department
Fire Line Construction Inspection Passed 03/23/2022
Misc
Informational
03/23/2022
2-11-22 AN the plumber call be to talk about the design of the fire line . Plans call for a 6” tap but i told him that a T had to be installed
Misc
Informational
03/23/2022
2-14-22 AN meet with the plumber about the fire line on what we expected for the shut down, fittings and testing of the line . Bac t and pressure test. Helped fine the valves and sent a request for a test shut down . One business will be affected,
Misc
Informational
03/23/2022
2-15-22 AN went and talked to the two customers that would be affected by the water shut down and they rely on the water for business. Notified the plumber that they would have to do the water tie-in before 8 or after 5
Misc
Informational
03/23/2022
2-16-22 AN crew got all the parts needed for the tie-in and also began digging to find the main
Misc
Informational
03/23/2022
2-22-22 AN crew is digging and in encountering a lot of rock . So it will be a couple of days before its all excavated
Misc
Informational
03/23/2022
2-23-22 AN no work being done today
Misc
Informational
03/23/2022
2-28-22 AN plumber is going to do the water tie-in for the fire line on wed mar 2 and have it done before 8am. 2 businesses will be affected and they have been given 48hr notice
Misc
Informational
03/23/2022
3-2-22 AN water tie-in has been changed to 5pm and the customer has been notified
Misc
Informational
03/23/2022
3-2-22 AN water tie-in is complete and was 5pm to 7pm. No leaks . Arrived at 4pm
Misc
Informational
03/23/2022
3-3-22 AN Spoke with plumber about wrapping the valves, fitting with plastic also getting the thrust blocks done.
Misc
Informational
03/23/2022
3-8-22 AN crew was doing the pressure test on the fire line and forgot to install the all thread rod connecting their joints and to dig it up and fix. 1st test failed.
Misc
Informational
03/23/2022
3-9-22 AN second pressure test fail and they think they are getting air in the line
Misc
Informational
03/23/2022
3-9-22 AN pressure test on the fire line passed . 200psi for 2hr
Misc
Informational
03/23/2022
3-14-22 AN. Crew flushed out the chlorinated fire line and taking 1st sample tomorrow
Misc
Informational
03/23/2022
3-16-22 did first bac-t test at 12pm on 3-15-22
Misc
Informational
03/23/2022
3-23-22 AN second water sample was taken on 3-16-22
Misc
Informational
03/23/2022
3-23-22 AN Both water samples passed and pressure test passed. Fire line should be completely done. Water samples are in Docs and also sent to water department
Site Visit Partial 03/25/2022
Misc
Informational
03/22/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
03/22/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
03/25/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Site Visit Partial 03/28/2022
Misc
Informational
03/25/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
03/25/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
03/25/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
03/28/2022
3-28-22 AN no work being done today
Site Visit Partial 04/05/2022
Misc
Informational
03/28/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
03/28/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
03/28/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
03/28/2022
3-28-22 AN no work being done today
Misc
Informational
04/05/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Site Visit Partial 04/07/2022
Misc
Informational
04/05/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
04/05/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
04/05/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
04/05/2022
3-28-22 AN no work being done today
Misc
Informational
04/05/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
04/07/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Site Visit Partial 04/13/2022
Misc
Informational
04/07/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
04/07/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
04/07/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
04/07/2022
3-28-22 AN no work being done today
Misc
Informational
04/07/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
04/07/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
04/13/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES
Site Visit Partial 04/14/2022
Misc
Informational
04/13/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
04/13/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
04/13/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
04/13/2022
3-28-22 AN no work being done today
Misc
Informational
04/13/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
04/13/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
04/13/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES
Water Line - Fire Hydrant Partial 04/15/2022
Misc
Informational
03/21/2022
3-15-22 AN crew has fully dug up to expose the water main for the hydrant install.. waiting on parts
Misc
Informational
03/21/2022
3-18-22 & 3-21-22 AN no work being done
Misc
Informational
04/15/2022
Crew was on-site working on assembling hydrant and valve assembly. 4/15/22 ES
Site Visit Partial 04/15/2022
Misc
Informational
04/14/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
04/14/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
04/14/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
04/14/2022
3-28-22 AN no work being done today
Misc
Informational
04/14/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
04/14/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
04/14/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Site Visit Partial 05/06/2022
Misc
Informational
04/15/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
04/15/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
04/15/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
04/15/2022
3-28-22 AN no work being done today
Misc
Informational
04/15/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
04/15/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
04/15/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
05/06/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
05/06/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Sewer Service Inspection Partial 05/09/2022
Misc
Informational
05/09/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Site Visit Partial 05/09/2022
Misc
Informational
05/06/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
05/06/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
05/06/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
05/06/2022
3-28-22 AN no work being done today
Misc
Informational
05/06/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
05/06/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
05/06/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
05/06/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
05/06/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
05/09/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Site Visit Partial 05/09/2022
Misc
Informational
05/09/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
05/09/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
05/09/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
05/09/2022
3-28-22 AN no work being done today
Misc
Informational
05/09/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
05/09/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
05/09/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
05/09/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
05/09/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
05/09/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
05/09/2022
Building work taking place, no utility work being done. 5/9/22 ES
Sanitary Sewer Construction Inspection Partial 05/10/2022
Misc
Informational
03/01/2022
3-1-22 AN crew is going to begin digging to expose the 12” sewer main . I let them know that they need to use a wye and max adapters
Misc
Informational
05/10/2022
5-10-22 AN. Plumber has began digging to expose the sewer main and are waiting on a trench box to safely get down in the hole
Water Service Inspection Passed 05/11/2022
Misc
Informational
03/16/2022
3-16-22 AN water department did the tap on the main and the meter pit is also installed.
Misc
Informational
05/11/2022
5-11-22 AN water service is completed
Sewer Service Inspection Partial 05/11/2022
Misc
Informational
05/09/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Misc
Informational
05/11/2022
5-11-22 AN crew is working on tie-in to the sewer main
Sewer Service Inspection Partial 05/11/2022
Misc
Informational
05/11/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Misc
Informational
05/11/2022
5-11-22 AN crew is working on tie-in to the sewer main
Misc
Informational
05/11/2022
5-11-22 AN crew was digging and cracked the sewer main. I called water utilities and they came out and cammed the line and found that the pipe had cracked around 12ft of sewer main
Sewer Service Inspection Partial 05/12/2022
Misc
Informational
05/11/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Misc
Informational
05/11/2022
5-11-22 AN crew is working on tie-in to the sewer main
Misc
Informational
05/11/2022
5-11-22 AN crew was digging and cracked the sewer main. I called water utilities and they came out and cammed the line and found that the pipe had cracked around 12ft of sewer main
Misc
Informational
05/12/2022
5-12-22 AN crew still working on fixing sewer main
Sewer Service Inspection Partial 05/12/2022
Misc
Informational
05/12/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Misc
Informational
05/12/2022
5-11-22 AN crew is working on tie-in to the sewer main
Misc
Informational
05/12/2022
5-11-22 AN crew was digging and cracked the sewer main. I called water utilities and they came out and cammed the line and found that the pipe had cracked around 12ft of sewer main
Misc
Informational
05/12/2022
5-12-22 AN crew still working on fixing sewer main
Misc
Informational
05/12/2022
5-12-22 AN crew replaced all the broken sewer main and all so installed the wye . Water also came out and cammed the line and said it was good. They do need to jet the line to get a broken piece of pipe out and gravel. 5 pics attached
Sewer Service Inspection Partial 05/18/2022
Misc
Informational
05/12/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Misc
Informational
05/12/2022
5-11-22 AN crew is working on tie-in to the sewer main
Misc
Informational
05/12/2022
5-11-22 AN crew was digging and cracked the sewer main. I called water utilities and they came out and cammed the line and found that the pipe had cracked around 12ft of sewer main
Misc
Informational
05/12/2022
5-12-22 AN crew still working on fixing sewer main
Misc
Informational
05/12/2022
5-12-22 AN crew replaced all the broken sewer main and all so installed the wye . Water also came out and cammed the line and said it was good. They do need to jet the line to get a broken piece of pipe out and gravel. 5 pics attached 5-18-22 AN jet truck was coming to jet the line at 8am and WU will meet them. Waiting to here back from WU to make sure all debris was take out of sewer main .
Sanitary Sewer Construction Inspection Passed 06/01/2022
Misc
Informational
05/10/2022
3-1-22 AN crew is going to begin digging to expose the 12” sewer main . I let them know that they need to use a wye and max adapters
Misc
Informational
05/10/2022
5-10-22 AN. Plumber has began digging to expose the sewer main and are waiting on a trench box to safely get down in the hole
Misc
Informational
06/01/2022
6-1-22 AN sewer tie-in form the main to the building is complete
Sewer Service Inspection Passed 06/01/2022
Misc
Informational
05/18/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. 5/9/22 ES
Misc
Informational
05/18/2022
5-11-22 AN crew is working on tie-in to the sewer main
Misc
Informational
05/18/2022
5-11-22 AN crew was digging and cracked the sewer main. I called water utilities and they came out and cammed the line and found that the pipe had cracked around 12ft of sewer main
Misc
Informational
05/18/2022
5-12-22 AN crew still working on fixing sewer main
Misc
Informational
05/18/2022
5-12-22 AN crew replaced all the broken sewer main and all so installed the wye . Water also came out and cammed the line and said it was good. They do need to jet the line to get a broken piece of pipe out and gravel. 5 pics attached 5-18-22 AN jet truck was coming to jet the line at 8am and WU will meet them. Waiting to here back from WU to make sure all debris was take out of sewer main . 6-1-22 AN sewer tie-in form the main to the building is complete
Water Line - Fire Hydrant Partial 06/01/2022
Misc
Informational
04/15/2022
3-15-22 AN crew has fully dug up to expose the water main for the hydrant install.. waiting on parts
Misc
Informational
04/15/2022
3-18-22 & 3-21-22 AN no work being done
Misc
Informational
04/15/2022
Crew was on-site working on assembling hydrant and valve assembly. 4/15/22 ES 6-1-22 AN fire hydrant is still not completed. Hydrant is assembled and there is a open hole but have not heard form plumber on when it will be installed
Site Visit Partial 06/17/2022
Misc
Informational
05/09/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
05/09/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
05/09/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
05/09/2022
3-28-22 AN no work being done today
Misc
Informational
05/09/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
05/09/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
05/09/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
05/09/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
05/09/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
05/09/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
05/09/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
06/17/2022
6-17-22 AN still waiting on the plumber to do the FH
Erosion Control Inspection Residential Partial 06/20/2022
Misc
Informational
06/20/2022
6-20-22 AN silt fence is looking good
Site Visit Partial 06/20/2022
Misc
Informational
06/17/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
06/17/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
06/17/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
06/17/2022
3-28-22 AN no work being done today
Misc
Informational
06/17/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
06/17/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
06/17/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
06/17/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
06/17/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
06/17/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
06/17/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
06/17/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development
Site Visit Partial 06/21/2022
Misc
Informational
06/20/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
06/20/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
06/20/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
06/20/2022
3-28-22 AN no work being done today
Misc
Informational
06/20/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
06/20/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
06/20/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
06/20/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
06/20/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
06/20/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
06/20/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
06/20/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development
Site Visit Partial 06/28/2022
Misc
Informational
06/21/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
06/21/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
06/21/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
06/21/2022
3-28-22 AN no work being done today
Misc
Informational
06/21/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
06/21/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
06/21/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
06/21/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
06/21/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
06/21/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
06/21/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
06/21/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed
Site Visit Partial 06/30/2022
Misc
Informational
06/28/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
06/28/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
06/28/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
06/28/2022
3-28-22 AN no work being done today
Misc
Informational
06/28/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
06/28/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
06/28/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
06/28/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
06/28/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
06/28/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
06/28/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
06/28/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled
In-wall Inspection Partial 7/1/2022 07/01/2022
Misc
Informational
07/01/2022
DEMISING WALL-OK TO COVER, EXCEPT AT OPENING AT SOUTH END OF WALL
Water Line - Fire Hydrant Passed 07/03/2022
Misc
Informational
06/01/2022
3-15-22 AN crew has fully dug up to expose the water main for the hydrant install.. waiting on parts
Misc
Informational
06/01/2022
3-18-22 & 3-21-22 AN no work being done
Misc
Informational
06/01/2022
Crew was on-site working on assembling hydrant and valve assembly. 4/15/22 ES 6-1-22 AN fire hydrant is still not completed. Hydrant is assembled and there is a open hole but have not heard form plumber on when it will be installed 7-1-22 AN fire hydrant is now installed. Flushed water main for around 10 mins
Site Visit Partial 07/07/2022
Misc
Informational
06/30/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
06/30/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
06/30/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
06/30/2022
3-28-22 AN no work being done today
Misc
Informational
06/30/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
06/30/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
06/30/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
06/30/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
06/30/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
06/30/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
06/30/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
06/30/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant.
Erosion Control Inspection Residential Partial 07/07/2022
Misc
Informational
06/20/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order.
Rated Assembly Inspection Failed 7/7/2022 07/07/2022
Misc
Corrective Action Required
07/07/2022
DEMISING WALL AT LINE 8, EAST SIDE-SCREW TOP AND BOTTOM TRACK @ 8" OC
Site Visit Partial 07/08/2022
Misc
Informational
07/07/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/07/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/07/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/07/2022
3-28-22 AN no work being done today
Misc
Informational
07/07/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/07/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/07/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/07/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/07/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/07/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/07/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/07/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today.
Water Line - Fire Hydrant Failed 07/11/2022
Miscellaneous Correction
Corrective Action Required
07/11/2022
7-11-22 RH. Fire Hydrant needs to be turned so it is facing the road.
In-wall Inspection Partial 7/11/2022 07/11/2022
Misc
Informational
07/01/2022
IN-WALL-OK TO COVER BELOW: -OFFICE AND RESTROOM -DEMISING WALL-OK TO COVER, EXCEPT AT OPENING AT SOUTH END OF WALL
Rated Assembly Inspection Partial 7/11/2022 07/11/2022
Misc
Corrective Action Required
07/07/2022
DEMISING WALL AT LINE 8-SCREW PATTERN OK, EXCEPT THE OPENING AT THE SOUTH END OF DEMISING WALL
Water Line - Fire Hydrant Passed 07/11/2022
Miscellaneous Correction
Corrective Action Required
07/11/2022
7-11-22 RH. Fire Hydrant needs to be turned so it is facing the road. 7-11-22 RH. Fire Hydrant was rotated correctly.
Site Visit Partial 07/12/2022
Misc
Informational
07/08/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/08/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/08/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/08/2022
3-28-22 AN no work being done today
Misc
Informational
07/08/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/08/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/08/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/08/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/08/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/08/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/08/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/08/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today.
Erosion Control Inspection Residential Partial 07/12/2022
Misc
Informational
07/07/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order.
Site Visit Partial 07/14/2022
Misc
Informational
07/12/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/12/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/12/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/12/2022
3-28-22 AN no work being done today
Misc
Informational
07/12/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/12/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/12/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/12/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/12/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/12/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/12/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/12/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building
Grading/Excavation/Fill Inspection Partial 07/14/2022
Misc
Informational
07/14/2022
7-14-22 AN KAT excavation is removing excess dirt from the site and taking it to another lot down the street that does have a LD permit
Grading/Excavation/Fill Inspection Partial 07/15/2022
Misc
Informational
02/09/2022
1-19-22 AN crew is working on grading the site and preparing a site pad
Misc
Informational
02/09/2022
2-1-22 AN it appears that the crew has finished the grading for the pad only and is covering it to keep it dry and for frost
Misc
Informational
02/09/2022
2-7-22 AN no work is being done today
Misc
Informational
02/09/2022
2-8-22 AN 9:10 pad site is complete and concrete crew is laying out the footings to start digging.
Misc
Informational
02/09/2022
2-9-22 AN concrete crew is digging the footings
Misc
Informational
07/15/2022
7-15-22 RH. Crew continues to load dump trucks with fill to be moved off site.
Underground Electrical Inspection - Commercial Partial 7/18/2022 7/18/2022 07/18/2022
Misc
Informational
07/18/2022
-UNDERGROUND ELECTRICAL FROM TRANSFORMER TO BUILDING-OK
Site Visit Partial 07/18/2022
Misc
Informational
07/14/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/14/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/14/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/14/2022
3-28-22 AN no work being done today
Misc
Informational
07/14/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/14/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/14/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/14/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/14/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/14/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/14/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/14/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building
Erosion Control Inspection Residential Partial 07/20/2022
Misc
Informational
07/12/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order
Site Visit Partial 07/20/2022
Misc
Informational
07/18/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/18/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/18/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/18/2022
3-28-22 AN no work being done today
Misc
Informational
07/18/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/18/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/18/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/18/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/18/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/18/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/18/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/18/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building
Site Visit Partial 07/21/2022
Misc
Informational
07/20/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/20/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/20/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/20/2022
3-28-22 AN no work being done today
Misc
Informational
07/20/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/20/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/20/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/20/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/20/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/20/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/20/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/20/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building
Storm Sewer Construction Inspection Partial 07/26/2022
Misc
Informational
07/26/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe
Erosion Control Inspection Residential Partial 07/26/2022
Misc
Informational
07/20/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order
Site Visit Partial 07/26/2022
Misc
Informational
07/21/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/21/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/21/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/21/2022
3-28-22 AN no work being done today
Misc
Informational
07/21/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/21/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/21/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/21/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/21/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/21/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/21/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/21/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building
Storm Sewer Construction Inspection Partial 07/28/2022
Misc
Informational
07/26/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe 7-27-22 AN. KAT was continuing to install storm pipe 7-28-22 AN Kat was going to work but it has Ben raining all morning
Storm Sewer Construction Inspection Partial 07/28/2022
Misc
Informational
07/28/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe 7-27-22 AN. KAT was continuing to install storm pipe 7-28-22 AN Kat was going to work but it has Ben raining all morning
Storm Sewer Construction Inspection Partial 07/29/2022
Misc
Informational
07/28/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe 7-27-22 AN. KAT was continuing to install storm pipe 7-28-22 AN Kat was going to work but it has Ben raining all morning 7-29-22 AN KAT is trying to locate the fire line so they can install the storm pipe.
Storm Sewer Construction Inspection Partial 08/01/2022
Misc
Informational
07/29/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe 7-27-22 AN. KAT was continuing to install storm pipe 7-28-22 AN Kat was going to work but it has Ben raining all morning 7-29-22 AN KAT is trying to locate the fire line so they can install the storm pipe. 8-1-22 AN crew is continuing to install storm pipe
Storm Sewer Construction Inspection Partial 08/02/2022
Misc
Informational
08/01/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe 7-27-22 AN. KAT was continuing to install storm pipe 7-28-22 AN Kat was going to work but it has Ben raining all morning 7-29-22 AN KAT is trying to locate the fire line so they can install the storm pipe. 8-1-22 AN crew is continuing to install storm pipe 8-2-22 AN crew still working on the storm 2 pics attached
Install Street and Stop Signs Partial 08/04/2022
Misc
Informational
08/04/2022
No street signs on this job
Install Street and Stop Signs Passed 08/04/2022
Misc
Informational
08/04/2022
No street signs on this job
Site Visit Partial 08/04/2022
Misc
Informational
07/26/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
07/26/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
07/26/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
07/26/2022
3-28-22 AN no work being done today
Misc
Informational
07/26/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
07/26/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
07/26/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
07/26/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
07/26/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
07/26/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
07/26/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
07/26/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building
Erosion Control Inspection Residential Partial 08/04/2022
Misc
Informational
07/26/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order 8-4-22 AN silt fence looks good
Site Visit Partial 08/08/2022
Misc
Informational
08/04/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/04/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/04/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/04/2022
3-28-22 AN no work being done today
Misc
Informational
08/04/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/04/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/04/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/04/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/04/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/04/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/04/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/04/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building
Site Visit Partial 08/09/2022
Misc
Informational
08/08/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/08/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/08/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/08/2022
3-28-22 AN no work being done today
Misc
Informational
08/08/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/08/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/08/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/08/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/08/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/08/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/08/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/08/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development.
Site Visit Partial 08/11/2022
Misc
Informational
08/09/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/09/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/09/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/09/2022
3-28-22 AN no work being done today
Misc
Informational
08/09/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/09/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/09/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/09/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/09/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/09/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/09/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/09/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today
Erosion Control Inspection Residential Partial 08/11/2022
Misc
Informational
08/04/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order 8-4-22 AN silt fence looks good 8-11-22 AN no erosion issues
Grading/Excavation/Fill Inspection Partial 08/12/2022
Misc
Informational
07/15/2022
7-14-22 AN KAT excavation is removing excess dirt from the site and taking it to another lot down the street that does have a LD permit 8-12-22 AN survey stacks are in place for the grading of the parking lot
Pavement-Aggregate Base Partial 08/12/2022
Misc
Informational
08/12/2022
8-12-22 AN survey stacks are in place to begin grading of the parking lot
Erosion Control Inspection Residential Partial 08/15/2022
Misc
Informational
08/11/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order 8-4-22 AN silt fence looks good 8-11-22 AN no erosion issues 8-15-22 AN no erosion issues
Site Visit Partial 08/15/2022
Misc
Informational
08/11/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/11/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/11/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/11/2022
3-28-22 AN no work being done today
Misc
Informational
08/11/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/11/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/11/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/11/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/11/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/11/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/11/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/11/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building
Site Visit Partial 08/17/2022
Misc
Informational
08/15/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/15/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/15/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/15/2022
3-28-22 AN no work being done today
Misc
Informational
08/15/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/15/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/15/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/15/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/15/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/15/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/15/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/15/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building 8-16-22 AN raining no work
Site Visit Partial 08/17/2022
Misc
Informational
08/17/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/17/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/17/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/17/2022
3-28-22 AN no work being done today
Misc
Informational
08/17/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/17/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/17/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/17/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/17/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/17/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/17/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/17/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building 8-16-22 AN raining no work 8-17-22 AN crew just working on the building
Site Visit Partial 08/19/2022
Misc
Informational
08/17/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/17/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/17/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/17/2022
3-28-22 AN no work being done today
Misc
Informational
08/17/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/17/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/17/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/17/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/17/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/17/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/17/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/17/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building 8-16-22 AN raining no work 8-17-22 AN crew just working on the building 8-18-22 AN working on the building
Site Visit Partial 08/19/2022
Misc
Informational
08/19/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/19/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/19/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/19/2022
3-28-22 AN no work being done today
Misc
Informational
08/19/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/19/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/19/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/19/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/19/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/19/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/19/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/19/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building 8-16-22 AN raining no work 8-17-22 AN crew just working on the building 8-18-22 AN working on the building 8-19-22 AN working on the building
Erosion Control Inspection Residential Partial 08/22/2022
Misc
Informational
08/15/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order 8-4-22 AN silt fence looks good 8-11-22 AN no erosion issues 8-15-22 AN no erosion issues 8-22-22 AN no erosion control issues
Grading/Excavation/Fill Inspection Partial 08/23/2022
Misc
Informational
08/12/2022
7-14-22 AN KAT excavation is removing excess dirt from the site and taking it to another lot down the street that does have a LD permit 8-12-22 AN survey stacks are in place for the grading of the parking lot 8-23-22 AN Kat is grading for the parking lot area
Grading/Excavation/Fill Inspection Partial 08/24/2022
Misc
Informational
08/23/2022
7-14-22 AN KAT excavation is removing excess dirt from the site and taking it to another lot down the street that does have a LD permit 8-12-22 AN survey stacks are in place for the grading of the parking lot 8-23-22 AN Kat is grading for the parking lot area 8-24-22 AN Kat is going to finish the grading today and do a proof roll in the afternoon
Electrical Service Inspection Failed 8/24/2022 8/24/2022 08/24/2022
Misc
Corrective Action Required
08/24/2022
-Submit revised plan to match service -Please recheck all conductors sizing. Ex; 4/0 Alum GEC for (3)400 kcmil SE conductors, etc
Pavement-Proof Roll Partial 08/25/2022
Misc
Informational
08/25/2022
5-24-22 AN. Crew did a proof roll and there was on bad spot.
Pavement-Proof Roll Partial 08/25/2022
Misc
Informational
08/25/2022
8-24-22 AN. Crew did a proof roll and there was one bad spot. 8-25-22 AN. Crew dug up the bad spot 15’ x 10’ x 4’ deep and is filling it with type5
Pavement-Aggregate Base Partial 08/26/2022
Misc
Informational
08/26/2022
8-26-22 AN. Kat is putting down their type 5 base
Electrical Service Inspection Passed 8/26/2022 08/26/2022
Misc
Resolved
08/26/2022
-Submit revised plan to match service -Please recheck all conductors sizing. Ex; 4/0 Alum GEC for (3)400 kcmil SE conductors, etc
Rated Assembly Inspection Partial 8/26/2022 8/26/2022 08/26/2022
Misc
Corrective Action Required
07/11/2022
DEMISING WALL AT LINE 8-SCREW PATTERN INSPECTION FOR THE REMAINING PORTION OF WALL AT SOUTH END
Rated Assembly Inspection Passed 8/30/2022 8/30/2022 08/30/2022
Misc
Resolved
08/30/2022
DEMISING WALL AT LINE 8-SCREW PATTERN INSPECTION FOR THE REMAINING PORTION OF WALL AT SOUTH END
Site Visit Partial 08/30/2022
Misc
Informational
08/19/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/19/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/19/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/19/2022
3-28-22 AN no work being done today
Misc
Informational
08/19/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/19/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/19/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/19/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/19/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/19/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/19/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/19/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building 8-16-22 AN raining no work 8-17-22 AN crew just working on the building 8-18-22 AN working on the building 8-19-22 AN working on the building No utility or grading work being done. Building work only. 8/30/22 ES
Pavement-Proof Roll Partial 09/06/2022
Misc
Informational
08/25/2022
8-24-22 AN. Crew did a proof roll and there was one bad spot. 8-25-22 AN. Crew dug up the bad spot 15’ x 10’ x 4’ deep and is filling it with type5 8-31-22 AN JJ did a proof roll and there was a couple bad spots that needed to dry out
Pavement-Stabilized Subgrade Partial 09/06/2022
Misc
Informational
09/06/2022
9-6-22 AN aggregate base is type 5 and it is 6” deep
Pavement-Aggregate Base Partial 09/06/2022
Misc
Informational
08/26/2022
8-26-22 AN. Kat is putting down their type 5 base
Pavement-Curb Construction Partial 09/08/2022
Misc
Informational
09/08/2022
9-8-22 AN string line is laid out so they can begin curbs
Pavement-Curb Construction Partial 09/09/2022
Misc
Informational
09/08/2022
9-8-22 AN string line is laid out so they can begin curbs 9-9-22 AN crew has began to pour curbs
Erosion Control Inspection Residential Partial 09/09/2022
Misc
Informational
08/22/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order 8-4-22 AN silt fence looks good 8-11-22 AN no erosion issues 8-15-22 AN no erosion issues 8-22-22 AN no erosion control issues 9-9-22 AN no erosion control issues
Pavement-Curb Construction Partial 09/12/2022
Misc
Informational
09/09/2022
9-8-22 AN string line is laid out so they can begin curbs 9-9-22 AN crew has began to pour curbs 9-12-22 AN crew is continuing to work on the the curbs
Above Ceiling Inspection Passed 9/13/2022 9/13/2022 09/13/2022
Gas Service Inspection - Commercial Failed 9/13/2022 9/13/2022 09/13/2022
Misc
Corrective Action Required
09/13/2022
Provide updated plan for change to gas piping size. Pressure test holds for min ten minutes
Pavement-Proof Roll Partial 09/14/2022
Misc
Informational
09/06/2022
8-24-22 AN. Crew did a proof roll and there was one bad spot. 8-25-22 AN. Crew dug up the bad spot 15’ x 10’ x 4’ deep and is filling it with type5 8-31-22 AN JJ did a proof roll and there was a couple bad spots that needed to dry out 9-14-22 AN there was no need to do a proof roll for the parking lot because there has been no rain since the curb proof roll
Pavement-Surface Partial 09/14/2022
Misc
Informational
09/14/2022
9-14-22 AN crew started to do the concrete parking lot. They only did a couple small pours
Gas Service Inspection - Commercial Passed 9/22/2022 09/22/2022
Misc
Resolved
09/22/2022
Provide updated plan for change to gas piping size. Pressure test holds for min ten minutes
Pavement-Proof Roll Passed 09/27/2022
Misc
Informational
09/14/2022
8-24-22 AN. Crew did a proof roll and there was one bad spot. 8-25-22 AN. Crew dug up the bad spot 15’ x 10’ x 4’ deep and is filling it with type5 8-31-22 AN JJ did a proof roll and there was a couple bad spots that needed to dry out 9-14-22 AN there was no need to do a proof roll for the parking lot because there has been no rain since the curb proof roll 9-27-22 AN. Parking lot is complete
Pavement-Aggregate Base Passed 09/27/2022
Misc
Informational
09/06/2022
8-26-22 AN. Kat is putting down their type 5 base 9-27-22 AN parking lot is complete
Pavement-Stabilized Subgrade Passed 09/27/2022
Misc
Informational
09/06/2022
9-6-22 AN aggregate base is type 5 and it is 6” deep 9-27-22 AN parking lot is complete
Sidewalk Inspection Partial 09/27/2022
Misc
Informational
09/27/2022
9-27-22 AN crew has sidewalks framed up and ready to go
Pavement-Curb Construction Passed 09/28/2022
Misc
Informational
09/12/2022
9-8-22 AN string line is laid out so they can begin curbs 9-9-22 AN crew has began to pour curbs 9-12-22 AN crew is continuing to work on the the curbs 9-28-22 AN all of the curbs are done and look good
Pavement-Surface Passed 09/28/2022
Misc
Informational
09/14/2022
9-14-22 AN crew started to do the concrete parking lot. They only did a couple small pours 9-28-22 AN. The rest of the parking lot is completed
Storm Sewer Construction Inspection Passed 09/28/2022
Misc
Informational
08/02/2022
7-26-22 AN KAT has began uncovering a existing storm box and are also going to begin start installing storm pipe 7-27-22 AN. KAT was continuing to install storm pipe 7-28-22 AN Kat was going to work but it has Ben raining all morning 7-29-22 AN KAT is trying to locate the fire line so they can install the storm pipe. 8-1-22 AN crew is continuing to install storm pipe 8-2-22 AN crew still working on the storm 2 pics attached 9-28-22 AN all of the storm is completed
Sidewalk Inspection Partial 09/28/2022
Misc
Informational
09/27/2022
9-27-22 AN crew has sidewalks framed up and ready to go 9-28-22 AN crew did some more sidewalks and have one small section to go
Site Visit Complete 10/04/2022
Misc
Informational
08/30/2022
2-10-22 AN concrete crew still working on footings. No other work being done
Misc
Informational
08/30/2022
3-22-22 AN no work being done today. Rained
Misc
Informational
08/30/2022
3-23-22 AN no work being done 3-24-22 no work 3-25-22 no work
Misc
Informational
08/30/2022
3-28-22 AN no work being done today
Misc
Informational
08/30/2022
3-29, 3-30, 3-31, 4-1, 4-4, 4-5. None of my contractors have been working , the plumber still needs to do the sewer tie-in and install the fire hydrant
Misc
Informational
08/30/2022
4-6, 4-7-22. AN no work being done.. just workers putting up the steal structure for the building
Misc
Informational
08/30/2022
No utility work being done. Crews working on metal framing for building. 4/13/22 ES No utility work being done. Crews working on building. 4/15/22 ES Plumbers working on hydrant and other crews working on building. 4/15/22 ES
Misc
Informational
08/30/2022
4-8 thu 4-12-22. And 4-16 thu 5-5 no work being done
Misc
Informational
08/30/2022
5-6-22 AN. Plumber we’re out surviving to get some height for the sewer tie-in
Misc
Informational
08/30/2022
Plumbers were on-site potholing utilities in preparation for sewer line connection. They also stated they would be doing the fire hydrant tie in soon also. 5/9/22 ES
Misc
Informational
08/30/2022
Building work taking place, no utility work being done. 5/9/22 ES
Misc
Informational
08/30/2022
6-17-22 AN still waiting on the plumber to do the FH 6-20-22 AN no work for development 6-21-22 AN no work for development 6-21 to 6-28-22 AN no work for development and still waiting fo the fire hydrant to be installed 6-28 to 6-30 AN no work for development. If fire hydrant is not installed soon the hole will need to be back filled 7-7-22 RH. No work for development today. Hole was backfilled around hydrant. 7-8-22 RH. No work for development today. 7-12-22 RH. No work for development today. 7-13-22 AN No work for development. Crew working on the building 7-18-22 AN crew working on the exterior of the building 7-19-22AN crew is still working on the exterior of the building 7-20 - 7-21 crew continuing to work on the building 7-25-22 AN not much going on some were work in the interior of the building 8-3-22AN working on building 8-4-22AN working on building 8-8-22 AN working on building 8-9-22 RH. Working on building no work for development. 8-11-22 AN no crew is on site today 8-15-22 AN. Working on building 8-16-22 AN raining no work 8-17-22 AN crew just working on the building 8-18-22 AN working on the building 8-19-22 AN working on the building No utility or grading work being done. Building work only. 8/30/22 ES.
Erosion Control Inspection Residential Passed 10/04/2022
Misc
Informational
09/09/2022
6-20-22 AN silt fence is looking good 7-7-22 RH. Silt fence is in working order. 7-12-22 RH. Silt fence is in and working order. 7-20-22 AN silt fence is in good working order 7-26-22 AN silt fence is still in good working order 8-4-22 AN silt fence looks good 8-11-22 AN no erosion issues 8-15-22 AN no erosion issues 8-22-22 AN no erosion control issues 9-9-22 AN no erosion control issues 9-4-22 AN. No erosion control issues
Sprinkler - Hydrostatic Test Failed 10/18/2022 10/18/2022
ESC - (Vegetation/Ground Cover) Partial 10/19/2022
Misc
Informational
10/19/2022
10-19-22 AN trees, bushes and being planted and sod in getting delivered to put down
Sprinkler - Hydrostatic Test Passed 10/19/2022 10/19/2022
ESC - (Vegetation/Ground Cover) Partial 10/21/2022
Misc
Informational
10/19/2022
10-19-22 AN trees, bushes and being planted and sod in getting delivered to put down 10-20-22 AN laying sod
ESC - (Vegetation/Ground Cover) Partial 10/21/2022
Misc
Informational
10/21/2022
10-19-22 AN trees, bushes and being planted and sod in getting delivered to put down 10-20-22 AN laying sod 10-21-22 AN laying sod
Grading/Excavation/Fill Inspection Passed 10/21/2022
Misc
Informational
08/24/2022
7-14-22 AN KAT excavation is removing excess dirt from the site and taking it to another lot down the street that does have a LD permit 8-12-22 AN survey stacks are in place for the grading of the parking lot 8-23-22 AN Kat is grading for the parking lot area 8-24-22 AN Kat is going to finish the grading today and do a proof roll in the afternoon 10-21-22 AN. All the grading has been completed
Sidewalk Inspection Passed 10/26/2022
Misc
Informational
09/28/2022
9-27-22 AN crew has sidewalks framed up and ready to go 9-28-22 AN crew did some more sidewalks and have one small section to go 10-26-22 AN all the sidewalks and approaches are completed
ESC - (Vegetation/Ground Cover) Passed 10/26/2022
Misc
Informational
10/21/2022
10-19-22 AN trees, bushes and being planted and sod in getting delivered to put down 10-20-22 AN laying sod 10-21-22 AN laying sod 10-26-22 AN. Sod, trees , bushes are in and completed
Water Line - Fire Hydrant Failed 10/26/2022
Miscellaneous Correction
Corrective Action Required
10/26/2022
10-26-22 AN need to locate valve for hydrant on east side of building
Water Line - Fire Hydrant Passed 10/26/2022
Miscellaneous Correction
Corrective Action Required
10/26/2022
10-26-22 AN need to locate valve for hydrant on east side of building 10-26-22 AN valve was located
Sidewalk Inspection Failed 10/26/2022
Misc
Corrective Action Required
10/26/2022
10-26-22 AN busted sidewalk panel needs to be fixed. Contractor knows about the panel and said he will get it fixed
Alarm Test Passed 11/2/2022 11/02/2022
Corrective Action Required
11/02/2022
Alarm did not did not terminate on silence. Will retest on final inspection. Duct detection still needs to be tested on final.
Sprinkler - Flow Test Passed 11/2/2022 11/02/2022
Occupancy Inspection - Engineering Temporary C of O 11/04/2022
Miscellaneous Correction
Corrective Action Required
11/04/2022
11-4-22 AN Needed for final occupancy. 1. Fix broken sidewalk panel. 2. Pay overtime fees.
Occupancy Inspection - Codes Commercial Failed 11/4/2022 11/4/2022 11/04/2022
Miscellaneous Correction
Corrective Action Required
11/04/2022
**2603 -Approval from water and planning departments required -Paint all exterior gas lines -Provide tamper resistant schrader valvles at exterior units -Secure AC whips per code -Relocate grab bars in restrooms to comply with 2017 ICC A117.1
Occupancy Inspection - Planning Passed 11/04/2022
Occupancy Inspection - Fire Passed 11/4/2022 11/4/2022 11/07/2022
11/07/2022
All life safety was appropriate. Okay to occupy with approval from codes.
Corrective Action Required
11/07/2022
All life safety was appropriate. Okay to occupy with approval from codes.
In-wall Inspection Passed 11/07/2022
Misc
Informational
07/11/2022
IN-WALL-OK TO COVER BELOW: -OFFICE AND RESTROOM -DEMISING WALL-OK TO COVER, EXCEPT AT OPENING AT SOUTH END OF WALL
Underslab Plumbing Inspection - Commercial Passed 11/07/2022
Misc
Informational
03/07/2022
-Underslab SS OK below: -4" building drain -2 west restrooms and sprinkler rm
Footing Inspection - Commercial Passed 11/07/2022
Misc
Resolved
11/07/2022
Exterior footing per page S100-ok to pour -East side of footing (S101) changed from the approved plan. Submit change to the footing to the city. OK to pour
Underground Electrical Inspection - Commercial Passed 11/07/2022
Misc
Resolved
11/07/2022
-UNDERGROUND ELECTRICAL FROM TRANSFORMER TO BUILDING-OK
Occupancy Inspection - Codes Commercial Ready for Temp CO 11/7/2022 11/7/2022 11/07/2022
Miscellaneous Correction
Corrective Action Required
11/04/2022
**2603 tenant -Approval from water and field engineer
Occupancy Inspection - Water Utilities Passed 11/7/2022 11/09/2022
Misc
Corrective Action Required
11/09/2022
Eric Wiggins advised Chris that we need the backflow reports for fireline and fireline bypass. Chris said he would get those submitted.
Sidewalk Inspection Passed 11/16/2022
Misc
Corrective Action Required
10/26/2022
10-26-22 AN busted sidewalk panel needs to be fixed. Contractor knows about the panel and said he will get it fixed 11-16-22 AN sidewalk has been replaced
Occupancy Inspection - Engineering Passed 11/16/2022
Miscellaneous Correction
Corrective Action Required
11/04/2022
11-4-22 AN Needed for final occupancy. 1. Fix broken sidewalk panel. 2. Pay overtime fees. Sidewalk is fixed and overtime fees are paid
Occupancy Inspection - Codes Commercial Full C of O 11/18/2022 11/18/2022
Miscellaneous Correction
Resolved
11/18/2022
**2603 tenant -Approval from water and field engineer
Documents & Images
Date Uploaded File Type Document Name
09/27/2021 Application Form Lot 10 Comm Permit Application (filled)
09/27/2021 Application Form Lot 10 License Tax - Copy (filled)
09/29/2021 Plans 20210924-LakewoodBusiness-Lot10-IssueForPermit
09/29/2021 Letter License Tax Bill
09/29/2021 Letter Fire Building Plan Review
10/07/2021 Letter DS P/R Corrections Document
10/19/2021 Letter Lee's Summit Engagement Letter I-470 Business and Technology Center
10/26/2021 Receipt Receipt for transaction: 2021-008262
12/13/2021 Letter Stop Work Order
12/14/2021 Engineer Report/Study 20211203-Geo Tech Report - Lot 10
12/14/2021 Application Form 20211111 Comm Permit Application (filled)
12/14/2021 Engineer Report/Study Special Inspection Engagement Letter-Lakewood Lot 10 - New Unit Rate - Ward Development
12/14/2021 Letter Fire Building Plan Review
12/15/2021 Plans Lakewood Lot 10 Permit Plans0
12/16/2021 Letter DS P/R Corrections Document
12/23/2021 Application Form 20211222-Lot10-Comm Permit Application (filled)
12/23/2021 Engineer Report/Study 20211203-Lot10-Geo Tech Report - Lot 10
12/23/2021 Plans 20211222-Lot10-BldgPermit-Resubmittal_02
12/23/2021 Letter 20211222-Lot10-Building Permit - Comment Response Rev 02
12/27/2021 Letter Fire Building Plan Review
12/27/2021 Plans 20211227-Lot10-BldgPermit-Resubmittal_02
12/28/2021 Engineer Report/Study 20211228-Lot10-Engagement Letter-I-470 Business and Technology Center
12/29/2021 Receipt Receipt for transaction: 2021-009530
12/29/2021 Letter DS Building Permit
01/19/2022 Letter Stop Work Order
01/19/2022 Letter INSPECTION SUMMARY
01/19/2022 Letter INSPECTION SUMMARY
01/26/2022 Letter DS Building Permit
01/26/2022 Receipt Receipt for transaction: 2022-000441
01/18/2022 Approved Plans Approved Civil 2601 NE McBaine Dr
01/31/2022 Approved Plans approved - Lakewood Lot 10 Permit Plans1
02/01/2022 Letter INSPECTION SUMMARY
02/07/2022 Letter INSPECTION SUMMARY
02/08/2022 Letter INSPECTION SUMMARY
02/09/2022 Letter INSPECTION SUMMARY
02/09/2022 Letter INSPECTION SUMMARY
02/10/2022 Letter INSPECTION SUMMARY
02/10/2022 Letter INSPECTION SUMMARY
02/10/2022 Plans 22-0128 Lot 10 Lakewood Business - PEMB Updates
02/10/2022 Approved Plans approved - Struct revised - 22-0128 Lot 10 Lakewood Business - PEMB Updates
02/11/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/22/2022 Letter INSPECTION SUMMARY
02/23/2022 Letter INSPECTION SUMMARY
02/28/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/02/2022 Photograph 27F9D37B-8537-482D-A6A2-8DFF1F1128E8
03/02/2022 Photograph 201668C1-28A6-4032-90A1-A812038A3DE3
03/02/2022 Letter INSPECTION SUMMARY
03/03/2022 Letter INSPECTION SUMMARY
03/07/2022 Letter INSPECTION SUMMARY
03/09/2022 Letter INSPECTION SUMMARY
03/09/2022 Letter INSPECTION SUMMARY
03/09/2022 Letter INSPECTION SUMMARY
03/09/2022 Letter INSPECTION SUMMARY
03/10/2022 Receipt Receipt for transaction:2022-001287
03/11/2022 Receipt Receipt for transaction: 2022-001317
03/14/2022 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/16/2022 Letter INSPECTION SUMMARY
03/16/2022 Letter INSPECTION SUMMARY
03/16/2022 Letter INSPECTION SUMMARY
03/16/2022 Letter INSPECTION SUMMARY
03/16/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 WO#1FC1441 - City of Lees Summit
03/22/2022 WO#1FC1441 - City of Lees Summit water 1
03/22/2022 WO#1FC1567 - City of Lees Summit water 2
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/06/2022 Application Form Document_2022-03-14_154253
04/07/2022 Letter INSPECTION SUMMARY
04/13/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/15/2022 Letter INSPECTION SUMMARY
04/15/2022 Letter INSPECTION SUMMARY
05/06/2022 Letter INSPECTION SUMMARY
05/09/2022 Letter INSPECTION SUMMARY
05/09/2022 Letter INSPECTION SUMMARY
05/09/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/11/2022 Letter INSPECTION SUMMARY
05/11/2022 Letter INSPECTION SUMMARY
05/11/2022 Letter INSPECTION SUMMARY
05/12/2022 Letter INSPECTION SUMMARY
05/12/2022 Letter INSPECTION SUMMARY
05/12/2022 A47FDE3A-182F-4205-A3B2-DB23D5E82702
05/12/2022 31029FF8-5570-40A5-BB5D-1FCA1F6C70B9
05/12/2022 E51A78B8-839D-4B72-A5AA-7240D11517E5
05/12/2022 89328AA6-2511-4989-9BC2-E67641636D3A
05/12/2022 060104C4-4121-479A-A1C0-69AA7404D08B
05/12/2022 4BA0602F-ED78-493B-8AF9-2D7345D3BD56
05/12/2022 E92A7A76-BE29-4791-97A6-DCDC00FE7D38
05/18/2022 Letter INSPECTION SUMMARY
05/26/2022 Letter Fire (Sprinkler) Plan Review
05/27/2022 Letter Fire (Sprinkler) Plan Review
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/17/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
07/01/2022 Letter INSPECTION SUMMARY
07/03/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/08/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter INSPECTION SUMMARY
07/14/2022 Letter INSPECTION SUMMARY
07/14/2022 Letter INSPECTION SUMMARY
07/14/2022 Letter INSPECTION SUMMARY
07/15/2022 Letter INSPECTION SUMMARY
07/18/2022 Letter INSPECTION SUMMARY
07/18/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/28/2022 Letter INSPECTION SUMMARY
07/28/2022 Letter INSPECTION SUMMARY
07/29/2022 Letter INSPECTION SUMMARY
08/01/2022 Letter INSPECTION SUMMARY
08/02/2022 Letter INSPECTION SUMMARY
08/02/2022 Storm 1
08/02/2022 Storm 2_Storm 2
08/02/2022 Storm 3
08/04/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
08/05/2022 Plans revised electric service plans 21-049_REV2
08/05/2022 Approved Plans approved - revised electric service plans 21-049_REV2
08/08/2022 Letter INSPECTION SUMMARY
08/09/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/12/2022 Letter INSPECTION SUMMARY
08/12/2022 Letter INSPECTION SUMMARY
08/15/2022 Letter INSPECTION SUMMARY
08/15/2022 Letter INSPECTION SUMMARY
08/17/2022 Letter INSPECTION SUMMARY
08/17/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/22/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/30/2022 Letter INSPECTION SUMMARY
08/30/2022 Letter INSPECTION SUMMARY
08/31/2022 Photograph Ticket for Proof Roll
08/31/2022 Photograph Parking Area that needs to Dry 1
08/31/2022 Photograph Parking Area that needs to Dry 2
09/02/2022 Drawing Lot 10 - Electrical - Rev4
09/02/2022 Accepted Record Drawings approved - Lot 10 - Electrical - Rev4
09/06/2022 Letter INSPECTION SUMMARY
09/06/2022 Letter INSPECTION SUMMARY
09/06/2022 Letter INSPECTION SUMMARY
09/08/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/12/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/16/2022 Drawing 2603-2605 gas line revisions
09/22/2022 Approved Plans ajpproved - 2603-2605 gas line revisions
09/22/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
10/04/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter Fire Loss Reduction Form
10/19/2022 Letter INSPECTION SUMMARY
10/21/2022 Letter INSPECTION SUMMARY
10/21/2022 Letter INSPECTION SUMMARY
10/21/2022 Letter INSPECTION SUMMARY
10/25/2022 firelite mmf300
10/25/2022 Fire-Lite_ES-50X_Datasheet
10/25/2022 Indoor_Ceiling_Strobes_HornStrobes_AVDS101
10/25/2022 Indoor_Wall_Horns_Strobes_HornStrobes_DataSheet
10/25/2022 LOT 10 BATTS 10_21_22
10/25/2022 mdf 300 data sheet
10/25/2022 SD365_data sheet
10/25/2022 FA101
10/26/2022 Letter INSPECTION SUMMARY
10/26/2022 Letter INSPECTION SUMMARY
10/26/2022 Letter INSPECTION SUMMARY
10/26/2022 Letter INSPECTION SUMMARY
10/26/2022 Letter INSPECTION SUMMARY
10/31/2022 Letter Fire (Alarm) Plan Review Notice
11/02/2022 Letter Fire Loss Reduction Form
11/04/2022 Letter INSPECTION SUMMARY
11/04/2022 Letter INSPECTION SUMMARY
11/04/2022 Receipt Receipt for transaction:2022-008726
11/07/2022 Letter Fire Loss Reduction Form
11/07/2022 Certificate/License Codes Temporary Certificate of Occupancy
11/07/2022 Receipt Receipt for transaction:2022-008755
11/16/2022 Letter INSPECTION SUMMARY
11/16/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter Codes Final Certificate of Occupancy
11/18/2022 Letter Field Certificate of Occupancy
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
12/20/2023 Codes Temporary Certificate of Occupancy30
12/20/2023 Codes Temporary Certificate of Occupancy30
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home