Planning Application Status

PL2016121




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2016121
SUMMIT SQUARE APARTMENTS
Commercial Final Development Plan
Commercial Final Development Plan
Approved
06/16/2016
TOWNSEND SUMMIT LLC
Locations
Contacts
NORTHPOINT DEVELOPMENT, Address:8015 NW CANAL ST, Phone:(816) 888-7390  
THHINC MCCLURE ENGINEERING CO, Address:1901 PENNSYLVANIA DRIVE, Phone:(573) 814-1568  
NSPJ ARCHITECTS, Address:3515 W 75TH ST, SUITE 201, Phone:(913) 831-1415 Ext:278  
TOWNSEND SUMMIT LLC, Address:1311 MCCORMICK RD STE 470, Phone:(303) 947-2044  
Reviews
Review Type Outcome Est. Completion Date Completed
Traffic Review No Comments 10/04/2016 10/05/2016
Michael Park
Fire Review Approved with Conditions 10/04/2016 10/05/2016
Jim Eden
Code Statement
Corrective Action Required
09/27/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only. FDP Conditions are also to be reviewed during review for the building permit.
FDC
Partial Correction
10/05/2016

IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official. FYI- The FDC is shown on the opposite side of the building from the riser. This meets intent of the code, but may cause design concerns with the sprinkler contractor.Relocating the FDC to the other side of the building would still meet the requirements of the code.
Engineering Review Approved with Conditions 10/04/2016 10/04/2016
Gene Williams, P.E.
DE Engineers Estimate
Corrective Action Required
10/04/2016

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Public Works Review and Inspection Fee of $38,219.78 (which is based on 3% of the total infrastructure cost plus a water test inspection fee) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit from the Codes Administration Department.
DE Contact Field Eng. Inspector
Corrective Action Required
10/04/2016

Contact Public Works Inspections at (816) 969-1800 at least 48 hours prior to the onset of construction.
DE Contact ROW Inspector
Corrective Action Required
10/04/2016

Contact a Right-of-Way Inspector at (816) 969-1800 prior to any land disturbance within the right-of-way. These activities may require a permit.
DE Future Repair Work
Corrective Action Required
10/04/2016

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
PW Submit Land Disturbance (DELETE)
Corrective Action Required
10/04/2016

If ground breaking will take place prior to issuance of a building permit, please submit a Land Disturbance Permit application and the required attachments and fees to James Fletchall. Mr. Fletchall can be reached at 816-969-1835.
Planning Review No Comments 10/04/2016 09/28/2016
Christina Stanton
Planning Review Corrections 09/23/2016 09/23/2016
Christina Stanton
Corrective Action Required
09/23/2016

Revised architectural plans were not received with previous resubmittal. Comments #1 and #7, from the previous comment letter, have not been addressed since revised architectural plans were not submitted.
Corrective Action Required
09/23/2016

In the revised plans, include a breakdown of the number of parking required and provided (further break this down by # spaces surface, # spaces detached garage, # spaces attached garage, and # spaces carport).
Corrective Action Required
09/23/2016

The ADA sign detail was not revised (comment #6 on the previous comment letter). The description is correct, but the detail is still incorrect.
Corrective Action Required
09/23/2016

Provide a spec sheet for lighting type "SL11".
Engineering Review Corrections 09/23/2016 09/23/2016
Gene Williams, P.E.
Corrective Action Required
09/23/2016

Please refer to comment #7 of the applicant letter dated July 26, 2016. The note concerning the backflow method for the fire line did not appear to have been changed. Two (2) backflow vaults should be shown at both connections to the public main on Donovan Rd. The location of these backflow vaults should be outside any easement or right of way, on the private side.
Corrective Action Required
09/23/2016

Please refer to comment #8 of the applicant letter dated July 26, 2016. A backflow vault and backflow assembly should be shown at both locations where the private fire line is connected to the public water main on Donovan Rd.
Corrective Action Required
09/23/2016

Please refer to comment #10 of the applicant letter dated July 26, 2016. No response was given concerning the irrigation meter being shown at a significant distance from the domestic water meter. Is there any reason the two meters cannot be closer together?
Corrective Action Required
09/23/2016

Please see comment #12 of the applicant letter dated July 26, 2016. Manhole A3 should be shown as a five (5) foot diameter manhole, but it is still being shown as a standard four (4) foot diameter manhole.
Corrective Action Required
09/23/2016

The Engineer's Estimate of Probable Construction Costs dated Sept. 14, 2016 appeared to be missing the following items: 1) backflow vaults and backflow assemblies, 2) final restoration, including sodding, seeding, fertilizer, mulch, and 3) erosion and sediment control measures and devices.
Traffic Review No Comments 09/23/2016 09/23/2016
Michael Park
Fire Review Approved with Conditions 09/23/2016 09/20/2016
Jim Eden
Code Statement
Corrective Action Required
09/20/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only. FDP Conditions are also to be reviewed during review for the building permit.
FDC
Corrective Action Required
09/20/2016

IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official. Action required. The FDC was not shown on Building #4. If positioned near the location of the fire main, it will meet requirements.
Fire Review Corrections 07/25/2016 07/26/2016
Jim Eden
Code Statement
Corrective Action Required
07/26/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code. For information only.
FDC
Corrective Action Required
07/26/2016

IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official. Action required: Not shown on resubmittal. Show the location of the fire department connection (FDC) for each building in relation to a fire hydrant. Provide accessible hydrants as needed to met this requirement. Is the pool house going to be sprinklered?
Hydrants
Corrective Action Required
07/26/2016

IFC 507.5.1- Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official. Action required:
Fire Lanes
Corrective Action Required
07/26/2016

IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm). AERIAL FIRE APPARATUS ACCESS ROADS D105.1 Where required. Where the vertical distance between the grade plane and the highest roof surface exceeds 30 feet (9144 mm), approved aerial fire apparatus access roads shall be provided. For purposes of this section, the highest roof surface shall be determined by measurement to the eave of a pitched roof, the intersection of the roof to the exterior wall, or the top of parapet walls, whichever is greater. D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed width of 26 feet (7925 mm), exclusive of shoulders, in the immediate vicinity of the building or portion thereof. D105.3 Proximity to building. At least one of the required access routes meeting this condition shall be located within a minimum of 15 feet (4572 mm) and a maximum of 30 feet (9144 mm) from the building, and shall be positioned parallel to one entire side of the building. The side of the building on which the aerial fire apparatus access road is positioned shall be approved by the fire code official. Action required: The width of the fire lane next to the buildings shall meet this requirement. The width requirement includes the drivable surface only.Correct dimensions.
Imposed Loads
Corrective Action Required
07/26/2016

IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities. Action required: Drawings C104, C105, and C106 do not show the fire acess lanes as being heavy duty asphalt. Make corrections or confirm that what is provided will support 75,000-pounds.
Fire Lanes - Marking
Corrective Action Required
07/26/2016

IFC 503.3- Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility. Action required: Show where fire lanes will be posted.
Fire Lanes
Corrective Action Required
07/26/2016

IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm) Action required: Provide a detail for the island in the fire access lane between Building #5 and #7.
Engineering Review Corrections 07/25/2016 07/25/2016
Gene Williams, P.E.
Corrective Action Required
07/25/2016

It appears the stormwater report dated July 13, 2016 contained a typographical error on the second page of the body of the report. Is this a stilling basin rather than a distilling basin?
Corrective Action Required
07/25/2016

It appears the stormwater report dated July 13, 2016 was missing the hydraulic grade line calculations. Pipe capacity and flow information was provided, but it did not appear that the hydraulic grade line calculations were provided.
Corrective Action Required
07/25/2016

Sheet C102: Please label the sanitary sewer (in bold) as private.
Corrective Action Required
07/25/2016

Sheet C103: Please labe the sanitary sewer (in bold) as private.
Corrective Action Required
07/25/2016

All Water Line Sheets (C110 to C112): There is a concern that the linework on the fire line and domestic lines may lead to a inadvertant interconnect between the fire line (unmetered) and the domestic water supply. Please use a standard drafting symbology to denote line intersections are not physically connected.
Corrective Action Required
07/25/2016

All Water Line Sheets (C110 to C112): Please label all interior fire lines and domestic lines as private.
Corrective Action Required
07/25/2016

All Water Line Sheets (C110 to C112): Please revise the note to state "...Backflow prevention to be provided via a backflow vault and backflow assembly as shown on the plans", or equivalent language. The buildings are too far away from the future public line to place backflow equipment within the building (i.e., the distance is greater than 50 feet, which will lead to bacteria build-up).
Corrective Action Required
07/25/2016

Sheet C111: A backflow vault and backflow assembly must be shown at all points where it connects to the public water line on Donovan. The vault should be located outside of any easement or right of way, and on the "private" side. A gate valve must be shown prior to the backflow vault. This valve is required even though a gate valve is shown on the opposite side of the street, in order to isolate the line in the event of a break.
Corrective Action Required
07/25/2016

Sheet C111: The water meter does not appear to be located within an easement. If not, then it should either be moved, or an easement created on the plat. The easement should be contiguous with the street frontage easement to be dedicated on the plat.
Corrective Action Required
07/25/2016

Sheet C111: Is there a reason the irrigation system meter cannot be placed adjacent to the 3" meter?
Corrective Action Required
07/25/2016

Sheet C112: Please see previous comments above since many apply to this sheet.
Corrective Action Required
07/25/2016

Sheet C302: Although sanitary sewer comments for the public sanitary sewer plans have not yet been finalized, manhole A3 should be called-out as 5 foot diameter due to the excessive depth.
Corrective Action Required
07/25/2016

An Engineer's Estimate of Probable Construction Costs appeared to be missing from the resubmittal.
Planning Review Corrections 07/25/2016 07/25/2016
Christina Stanton
Corrective Action Required
07/25/2016

Parking. The approved preliminary development plan included various development standards such as parking, it indicated 1.75 spaces would be provided per unit in the multi-family portion of the development. Provide parking counts to show the required number and how many are provided.
Corrective Action Required
07/25/2016

Parking Dimensions. The required standard parking space dimensions are 9 feet wide by 19 feet long. The depth is allowed to be reduced by up to 2 feet if the parking abuts a 6 foot sidewalk or curbed landscaped area. Sheet C105 indicates parking located to the east of Building #4 has a depth of 16 feet, the minimum allowed depth is 17 feet.
Corrective Action Required
07/25/2016

Incorrect Dimensional Labels. On Sheet C105 there are 3 dimensions that are incorrectly labeled: 1) On the south side of the southern entrance it is labeled 540 feet; 2) The depth of the south-facing parking serving Building #4 (immediately north of steps to the Club House) is labeled 556.6 feet; 3) The depth of the first row of east-facing parking, serving Building #3, as you come in the northern entrance is labeled 0.6 feet. Please correct these labels.
Corrective Action Required
07/25/2016

Lighting Schedule. According to my counts the fixture quantity is off by one for SL2, SL6, and SL8. Please double check quantities.
Corrective Action Required
07/25/2016

Should SL2 be on all buildings? It does not appear to be located on Buildings #1, #2, and #6. There are the two on either side of the southernmost entry drive and the northernmost building.
Corrective Action Required
07/25/2016

ADA Sign Detail. Detail #8, on Sheet C501, does not match the description provided. The description is correct, the detail is not correct.
Corrective Action Required
07/25/2016

Revise the elevations to include a schedule of materials and colors for the buildings.
Corrective Action Required
07/25/2016

The Landscape Plans show carports, but none of the other sheets indicate carports. Please reconcile.
Corrective Action Required
07/25/2016

Revise General Note #2.B, on the Landscape Plans, to state that all trees shall be a minimum of 4 feet from paving edge to meet Section 14.110.C of the UDO.
Corrective Action Required
07/25/2016

Provide parking lot screening up to a height of 2.5 feet for the parking lot adjacent to NW Chipman Road in order to comply with Section 14.120 of the UDO.
Corrective Action Required
07/25/2016

Per the ordinance (#7885) that approved the preliminary development plan, condition #7: "In lieu of a 5' sidewalk a 10-foot shared-use path shall be required along the north side of NW Chipman Road between NW Dononvan Road and the UPRR prior to the issuance of any occupancy permit within Phase 1." This was a condition of the approved preliminary development plan and cannot be waived without going back through the preliminary development plan process.
Traffic Review No Comments 07/25/2016 07/22/2016
Michael Park
Engineering Review Corrections 06/30/2016 06/30/2016
Gene Williams, P.E.
Corrective Action Required
06/30/2016

Please provide an overview sheet of the entire project, in addition to the smaller overview sheets provided.
Corrective Action Required
06/30/2016

Please be aware that the off-site sanitary sewer line should be installed and substantially complete prior to approval of the Final Development Plan. This will require a permit from the railroad, off-site easements, and hence will likely be a critical item in the timing for the project. Separate comments for the sanitary sewer will be provided no later than July 8th.
Corrective Action Required
06/30/2016

It did not appear that a final stormwater detention study was provided. Have plans for stormwater detention/water quality detention changed?
Corrective Action Required
06/30/2016

It appears two (2) of the three (3) site overview sheets were missing a private fire line plan, including locations of backflow vaults, fire hydrants, and fire department connections.
Corrective Action Required
06/30/2016

It appears all of the overview sheets were missing a domestic water service plan, showing the location(s) of the domestic water meter.
Corrective Action Required
06/30/2016

There appear to be two Site Overview B and Site Overview C sheets (i.e., Sheets C102 and C103 are labeled as Site Overview B and C, while C105 and C106 have the same label).
Corrective Action Required
06/30/2016

A utility plan was not provided. Although aspects of the City utilities are shown elsewhere in the plan set, a dedicated utility plan should be provided. it should address the private fire line, the private domestic service and meter location(s), and private sanitary sewer services. Storm sewer plan and profiles should be included on their own dedicated sheets (as was provided).
Corrective Action Required
06/30/2016

It was our understanding that a detention basin/water quality basin was going to be installed on the east side of the property. It does not appear that any plans were shown for this basin. Have plans changed for this work?
Corrective Action Required
06/30/2016

The private fire line plan should also include the locations of all fire hydrants.
Corrective Action Required
06/30/2016

Storm Profiles should include the hydraulic grade line and design storm, along with calculations on a separate sheet.
Corrective Action Required
06/30/2016

There appear to be numerous QA/QC issues with the private stormwater plans. For instance, Sheet C201 shows a manhole installed below grade. Sheet C201 also shows a stormwater manhole installed 8 feet above grade. Sheet C202 shows the same. Sheet C203 shows unidentified structures on the profile. Plan views on all sheets in the stormwater section are not labeled. In other words, the stormwater section of the Final Development Plan is not reviewable at this time.
Corrective Action Required
06/30/2016

Please label all interior storm lines as private, with the exception of the storm lines within easements. Please label the fire line as private. Please label the domestic lines as private. Please label the sanitary sewer laterals as private.
Corrective Action Required
06/30/2016

Sheet C101 shows an unidentifed structure within an easement. The location of this structure is on the southwest corner of the sheet. The bigger question, however, is what is the purpose of this easement? It does not appear that any City-owned utilities are planned within this easement.
Corrective Action Required
06/30/2016

The alignment of the public sanitary sewer and public water line will be addressed under a separate comment letter. These will be provided no later than July 8th. As such, please be aware that it may affect the Final Development Plan.
Corrective Action Required
06/30/2016

Sheet 501: The detail for asphalt pavement does not meet the standards set forth in the Unified Development Ordinance Article 12, "Parking". Either flyash stabilized subgrade, or geogrid is required in addition to the compacted subgrade.
Corrective Action Required
06/30/2016

Sheet C501: The detail for curb and gutter does not meet the standard detail contained within the Design and Construction Manual. Aggregate base, subgrade stabilization/geogrid, and compaction is required a minimum of one (1) foot beyond the back of curb rather than 6" beyond the back of curb.
Corrective Action Required
06/30/2016

An erosion and sediment control plan appeared missing from the Final Development Plan.
Corrective Action Required
06/30/2016

The detail for sediment fence is no longer allowed in Lee's Summit. Sediment fence must be machine laid, and the base cannot be backfilled as shown.
Corrective Action Required
06/30/2016

General Comment: The public stormwater portion shown on the Final Development Plan should be included in the public street and stormwater plans submitted on June 21st, and to be reviewed separately. Comments on these plans will be provided no later than July 13th.
Corrective Action Required
06/30/2016

The storm sewer shown on the north end of the project (i.e., see sheet C101) would appear to be better suited as a private stormwater line. As such, no utility easement would be desired, and it should be labeled as private. Details should be provided on this line concerning end of pipe, energy dissipation, etc. Since it is a private line rather than a public line, these details should be included in the Final Development Plan.
Corrective Action Required
06/30/2016

An itemized and sealed Engineer's Estimate of Probable Construction Costs should accompany your final submittal drawings.
Traffic Review No Comments 06/30/2016 06/29/2016
Michael Park
Fire Review Corrections 06/30/2016 06/29/2016
Jim Eden
Hydrants
Corrective Action Required
06/29/2016

IFC 507.5.1- Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official. Action required: Provide a complete water utility plan. Include the locations of fire mains to the building sprinkler systems and backflow valves and vaults.
FDC
Corrective Action Required
06/29/2016

IFC 903.3.7- Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official. Action required: Show the location of the fire department connection (FDC) for each building in relation to a fire hydrant.
Water Supply
Corrective Action Required
06/29/2016

IFC 507.1 - An approved water supply capable of supplying the required fire flow for fire protection shall be provided to premises upon which facilities, buildings or portions of buildings are hereafter constructed or moved into or within the jurisdiction. Action required: Provide a water study.
Fire Lanes
Corrective Action Required
06/29/2016

IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm). AERIAL FIRE APPARATUS ACCESS ROADS D105.1 Where required. Where the vertical distance between the grade plane and the highest roof surface exceeds 30 feet (9144 mm), approved aerial fire apparatus access roads shall be provided. For purposes of this section, the highest roof surface shall be determined by measurement to the eave of a pitched roof, the intersection of the roof to the exterior wall, or the top of parapet walls, whichever is greater. D105.2 Width. Aerial fire apparatus access roads shall have a minimum unobstructed width of 26 feet (7925 mm), exclusive of shoulders, in the immediate vicinity of the building or portion thereof. D105.3 Proximity to building. At least one of the required access routes meeting this condition shall be located within a minimum of 15 feet (4572 mm) and a maximum of 30 feet (9144 mm) from the building, and shall be positioned parallel to one entire side of the building. The side of the building on which the aerial fire apparatus access road is positioned shall be approved by the fire code official. Action required: The width of the fire lane next to the buildings shall meet this requirement. The width requirement includes the drivable surface only.
Imposed Loads
Corrective Action Required
06/29/2016

IFC 503.2.3 -Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fire Lanes
Corrective Action Required
06/29/2016

IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm) Action required: Provide a detail for the island in the fire access lane.
Code Statement
Corrective Action Required
06/29/2016

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2012 International Fire Code .
Fire Lanes - Marking
Corrective Action Required
06/29/2016

IFC 503.3- Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility. Action required: Show where fire lanes will be posted.
Planning Review Corrections 06/30/2016 06/23/2016
Christina Stanton
Corrective Action Required
06/23/2016

Provide a schedule of materials and colors for the buildings.
Corrective Action Required
06/23/2016

Indicate the location of all mechanical equipment and how it shall be screened.
Corrective Action Required
06/23/2016

Provide the distance from all buildings to the nearest property line.
Corrective Action Required
06/23/2016

Parking. Provide a parking count and calculations. I counted 474 spaces (28 ADA accessible), but my count does not include garages that are part of the buildings. If each building has 15 garages, which is how it appears on the elevations, then there is a total of 579 usable parking spaces (some spaces shown do not meet minimum stall sizes, see next comment). Based on 312 dwelling units, 546 parking spaces would be required (11 are required to be ADA accessible).
Corrective Action Required
06/23/2016

Parking Dimensions. Per Section 12.120.C: 1. Standard parking space dimensions shall not be less than nine (9) feet wide by nineteen (19) feet long. 2. Where the head of the parking space abuts a six (6) foot wide sidewalk or curbed landscaped area, the length of the parking space may be reduced by two (2) feet to allow for vehicle overhang. Such overhang shall be measured from the face of the curb. On Sheet C104 --There is a dimension incorrectly labeled as 1' on the northernmost row of uncovered parking stalls. --The width of 2 stalls is questionable. One such stall is the stall located nearest to the trash enclosure; the other stall is located on the northernmost row of spaces serving Building #5. On Sheet C105 --There is a dimension incorrectly labeled as 1' on thefurthest drive aisle with parking serving Building #3. --The parking located immediately to the east of Building #4 indicates a stall depth of only 16 feet, this does not meet the minimum dimensions discussed above. --Unrelated to parking, there are two other dimensions incorrectly labeled on this sheet. One near the southernmost row of parking serving Building #4 (close to the stairs leading to the club house). The other is dimension labeling one half the southern entry drive.
Corrective Action Required
06/23/2016

Per Section 12.080.I of the UDO: "Every accessible parking space required by this Article shall be indentified by a sign mounted on a pole or other structure, located between thirty-six (36) inches and sixty (60) inches above the ground, measured from the bottom of the sign, at the head of the parking space..." Indicate the placement of these signs, on the stie plan, as required.
Corrective Action Required
06/23/2016

Lighting. Revise the "Site Light Fixture Schedule" to accurately reflect the quantity of each type of lighting being utilized.
Corrective Action Required
06/23/2016

Provide a detail of the proposed parking lot lighting pole depicting the height of any base and the overall height.
Corrective Action Required
06/23/2016

Should SL2 be on all buildings? There are 3 buildings that do not indicate this light is being used.
Corrective Action Required
06/23/2016

Uniformity Ratios. Revise the Photometric Site Plan so that the maximum to minimum and the average to minimum ratios meet the requirements of Section 7.250.F of the UDO.
Corrective Action Required
06/30/2016

Sidewalks. Sidewalks are required on both sides of NW Donovan Road (per Section 16.280 of the UDO). In addition, the ordinance that approved the preliminary development plan (Ord. #7885) listed condition #7: "In lieu of a 5' sidewalk a 10-foot shared-use path shall be required along the north side of NW Chipman Road between NW Donovan Road and the UPRR prior to the issuance of any occupancy permit within Phase 1."
Corrective Action Required
06/30/2016

Landscape Plan. Plans need to show the location of the required shrubs. Are there any existing trees planned to be retained? If so, identify and provide caliber. In addition, per Section 14.110.C of the UDO: "Tree planting areas shall be no less than ten (10) feet in width. No tree shall be located less than four (4) feet from the back of curb..."
Corrective Action Required
07/01/2016

Add the following building addresses: Building #1 783 NW Donovan Road Building #2 795 NW Donovan Road Club House 789 NW Donovan Road Building #3 801 NW Donovan Road Building #4 807 NW Donovan Road Building #5 819 NW Donovan Road Building #6 813 NW Donovan Road Building #7 825 NW Donovan Road
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $1,000.00 $1,000.00 Paid 06/16/2016
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
07/01/2016 Letter Applicant Letter - FDP (DFDP)
07/18/2016 Letter Resubmittal Routing Sheet - FDP
07/26/2016 Letter Applicant Letter - FDP (DFDP)
09/16/2016 Letter Resubmittal Routing Sheet - FDP
09/23/2016 Letter Applicant Letter - FDP (DFDP)
09/27/2016 Letter Resubmittal Routing Sheet - FDP
10/13/2016 Letter Applicant Letter - FDP (DFDP)
10/14/2016 A2.06 - Building Elevations
10/14/2016 A2.07 - Building Elevations
10/14/2016 A2.17 - Building Elevations
10/14/2016 A2.18 - Building Elevations
10/14/2016 A2.18A - Building Elevations
10/14/2016 A2.27 - Building Elevations
10/14/2016 A2.28 - Building Elevations
10/14/2016 A0.00 VOL 1 COVER
10/14/2016 C111 - Water System Plan Central
10/14/2016 C501 - Details
10/14/2016 F101 - Hydrant Layout
10/14/2016 C001 - Civil Cover Sheet
10/14/2016 C206 - Storm Plan/Profile
10/14/2016 C301 - Sanitary Plan/Profile
10/14/2016 C302 - Sanitary Plan/Profile
10/14/2016 C502 - Details
10/14/2016 C503 - Details
10/14/2016 C504 - Details
10/14/2016 C505 - Details
10/14/2016 C506 - Details
10/14/2016 C507 - Details
10/14/2016 C508 - Details
10/14/2016 C509 - Details
10/14/2016 C510 - Details
10/14/2016 C511 - Details
10/14/2016 E0-01 Photometric Site Plan
10/14/2016 Landscape-FDP ReSub
10/14/2016 ME1-01 Site Electrical/Details
10/30/2017 Activity Document Fee WorksheetUpdatedDevCentr
03/13/2018 Plans Unit Addresses
03/29/2018 Engineer Report/Study Stormwater Report
10/14/2016 C205 - Storm Plan/Profile
10/14/2016 C204 - Storm Plan/Profile
10/14/2016 C203 - Storm Plan/Profile
10/14/2016 C202 - Storm Plan/Profile
10/14/2016 C201 - Storm Plan/Profile
10/14/2016 C114 - Erosion Control Mass Grading
10/14/2016 C113 - Erosion Control Mass Grading
10/14/2016 C112 - Water System Plan South
10/14/2016 C110 - Water System Plan North
10/14/2016 C109 - Site Grading South
10/14/2016 C108 - Site Grading Central
10/14/2016 C107 - Site Grading North
10/14/2016 C106 - Site Layout South
10/14/2016 C105 - Site Layout Central
10/14/2016 C104 - Site Layout North
10/14/2016 C103 - Site Overview South
10/14/2016 C102 - Site Overview Central
10/14/2016 C101 - Site Overview North
10/14/2016 C100 - Site Overview/Layout
10/14/2016 C003 - Drainage Area
10/14/2016 C002 - Notes/Legend
10/06/2016 Letter Applicant Letter - FDP (DFDP)
06/16/2016 Letter Routing Sheet - FDP
06/16/2016 Receipt Receipt for transaction: 2016-003783
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home