Permit Application Status

PRCOM20216411


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20216411
Building Permit - Commercial
Certificate of Occupancy
KRAFT THOMAS ANTHONY TRUST
NEW COMMERCIAL
NEW BUILDING FOR COLLISION REPAIR
12/16/2021
03/04/2022
08/24/2022
01/20/2023
Locations
Contacts
Deerfield Construction Co Inc, Address:8960 Glendale Milford Rd, Phone:(513) 368-0979  
Brett.Bitzer@Deerfield1.com, Address:Brett.Bitzer@Deerfield1.com, Phone:(513) 368-0979  
QUESTEC MECHANICAL INC, Address:1390 E BOONE INDUSTRIAL DR, SUITE 260, Phone:(573) 875-0260  
MD Electric Inc, Address:9340 W. 247th St.   
B & C MECHANICAL SERVICES LLC, Address:2008 E SPRUCE CIR STE B, Phone:(913) 681-0088  
Oxford Architecture, Address:2934 Sidco Dr, Suite 120, Phone:(615) 256-3455 Ext:15  
KRAFT THOMAS ANTHONY TRUST, Address:1508 SW HOOK RD  
Intertek-PSI, Address:2828 S. 44th Street, Phone:(913) 310-1600  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 06/27/2022 06/27/2022
Jim Eden
Construction documents - Fire protection systems
Informational
06/27/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Plans received June 22, 2022.
Installation acceptance testing
Informational
06/27/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule a hydrostatic and flow test.
Miscellaneous Correction
Resolved
06/27/2022

The hydrant to supply the FDC is located after the backflow, therefore a one way check valve is required at the base of the riser to prevent the system from churning when supplied throgh the FDC.
Sprinkler Plan Review Rejected 06/22/2022
Jim Eden
Construction documents - Fire protection systems
Informational
06/22/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Plans received June 22, 2022.
Installation acceptance testing
Corrective Action Required
06/22/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule a hydrostatic and flow test.
Miscellaneous Correction
Corrective Action Required
06/22/2022

The hydrant to supply the FDC is located after the backflow, therefore a one way check valve is required at the base of the riser to prevent the system from churning when supplied throgh the FDC.
Alarm Plan Review Released for Construction 05/04/2022
Jim Eden
Installation acceptance testing
Corrective Action Required
05/04/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Action required- Coordinate with the sprinkler company and call (816) 969-1300 to schedule a test.
Miscellaneous Correction
Corrective Action Required
05/04/2022

If the alarm company is responsible for the Knox Box, it needs to be moved to be mounted at 6'AFF between the exterior hor/stobe and the FDC. Verified at inspection.
Licensed Contractors Approved 03/04/2022 03/04/2022
Joe Frogge
LC - General Contractor
Resolved
03/04/2022

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact which is where inspection reports will be sent. 2/1/22 - not addressed 2/28/22 - not addressed
LC - MEP Subs
Resolved
03/04/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 2/1/22 - not addressed 2/28/22 - not addressed
Final Development Plan Review Approved 03/07/2022 03/04/2022
Scott Ready
Fire Plan Review Approved with Conditions 03/04/2022 03/03/2022
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
02/25/2022

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Hazardous material identification
Informational
02/25/2022

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 5003.5. (Verified At Inspection)
Knox box required
Informational
02/25/2022

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Actioin Required) Order a knox box from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
02/25/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
02/25/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Building Plan Review Approved 03/04/2022 02/28/2022
Joe Frogge
Special Inspections Review Approved 02/07/2022 02/02/2022
Joe Frogge
Building Plan Review Approved 02/07/2022 02/02/2022
Joe Frogge
IBC 1209.2 Finish materials
Resolved
02/01/2022

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant wall finish material at mop sink. If paint is used it must be epoxy based.
IBC 1704.2 Special Inspections
Resolved
02/02/2022

"2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 2/1/22 - acknowledged in letter
IMC 306.5 Equipment on roofs
Resolved
02/01/2022

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide permanent roof access ladder.
Engineered truss package
Resolved
02/01/2022

Copies of the pre-engineered metal building package were not provided at the time of permit application. Action required: Provide pre-engineered metal building package or request deferral.
IBC 1008.3 Emergency power for illumination - at exit discharge
Resolved
02/01/2022

2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at landing on exterior side of front double doors.
Licensed Contractors Rejected 02/07/2022 02/01/2022
Joe Frogge
LC - General Contractor
Corrective Action Required
01/31/2022

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact which is where inspection reports will be sent. 2/1/22 - not addressed
LC - MEP Subs
Corrective Action Required
01/31/2022

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 2/1/22 - not addressed
Fire Plan Review Approved with Conditions 02/07/2022 02/01/2022
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
01/31/2022

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Hazardous material identification
Informational
02/01/2022

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 5003.5. (Verified At Inspection)
Knox box required
Informational
02/01/2022

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Actioin Required) Order a knox box from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
02/01/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
01/31/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Illumination required
Resolved
02/01/2022

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. (Action Required) Provide exterior emergency lighting at the lobby entrance.
Building Plan Review Rejected 01/04/2022 12/21/2021
Joe Frogge
Final Development Plan
Resolved
01/31/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
IBC 1209.2 Finish materials
Corrective Action Required
12/21/2021

2018 IBC 1209.2 Finish Materials. Walls, Floors and partitions in toilet and bathrooms shall comply with Sections 209.2.1 through 1209.2.4. 2018 1209.2.1 Floors and wall bases. In other than dwelling units, toilet, bathing and shower room floor finish materials shall have a smooth, hard, nonabsorbent surface. The intersections of such floors with walls shall have a smooth, hard, nonabsorbent vertical base that extends upward onto the walls not less than 4 inches. 2018 1209.2.2 Walls and partitions. Walls and partitions within 2 feet of service sinks, urinals and water closets shall have a smooth, hard, nonabsorbent surface, to a height of not less than 4 feet above the floor, and except for structural elements, the materials used in such walls shall be of a type that is not adversely affected by moisture. (See code section for possible exceptions.) Action required: Specify compliant wall finish material at mop sink. If paint is used it must be epoxy based.
IBC 1704.2 Special Inspections
Corrective Action Required
12/21/2021

"2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections."
IMC 306.5 Equipment on roofs
Corrective Action Required
12/21/2021

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide permanent roof access ladder.
Engineered truss package
Corrective Action Required
12/21/2021

Copies of the pre-engineered metal building package were not provided at the time of permit application. Action required: Provide pre-engineered metal building package or request deferral.
IBC 1008.3 Emergency power for illumination - at exit discharge
Corrective Action Required
12/21/2021

2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at landing on exterior side of front double doors.
Licensed Contractors Rejected 01/04/2022 12/21/2021
Joe Frogge
LC - General Contractor
Corrective Action Required
12/21/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Corrective Action Required
12/21/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved with Conditions 01/04/2022 12/17/2021
Michael Weissenbach
Construction documents for fire alarm systems
Corrective Action Required
12/17/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Hazardous material identification
Corrective Action Required
12/17/2021

2018 IFC 407.3- Identification. Individual containers of hazardous materials, cartons or packages shall be marked or labeled in accordance with applicable federal regulations. Buildings, rooms and spaces containing hazardous materials shall be identified by hazard warning signs in accordance with Section 5003.5. (Verified At Inspection)
Knox box required
Corrective Action Required
12/17/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Actioin Required) Order a knox box from knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
12/17/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
12/17/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Illumination required
Corrective Action Required
12/17/2021

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. (Action Required) Provide exterior emergency lighting at the lobby entrance.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $8,400.00 $8,400.00 Paid 03/04/2022
8331507-Sewer Connection Fee $240.00 $240.00 Paid 03/04/2022
7232302-Commercial License Tax Fee $23,970.00 $23,970.00 Paid 07/20/2022
91100C8-Sanitary Sewer Insp Fees $404.40 $404.40 Paid 03/04/2022
91100C9-Water Insp Fee $446.85 $446.85 Paid 03/04/2022
9110068-Storm Fee $5,300.85 $5,300.85 Paid 03/04/2022
9110081-Paved Surface Inspection Fee $3,042.60 $3,042.60 Paid 03/04/2022
9110071-Site Grading Fee $3,031.05 $3,031.05 Paid 03/04/2022
8350015-Water Meter Fee $1,640.58 $1,640.58 Paid 03/04/2022
8331401-Water Tap Fee $19,500.00 $19,500.00 Paid 03/04/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 03/04/2022
9110072-Water Test Fee $400.00 $400.00 Paid 03/04/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 12/14/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 01/20/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Partial 03/14/2022
Misc
Informational
03/14/2022
Silt fence installed. 3/14/22 ES
Site Visit Partial 03/28/2022
Misc
Informational
03/28/2022
No work being completed. 3/28/22 ES
Site Visit Partial 04/05/2022
Misc
Informational
03/28/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/05/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Site Visit Partial 4/5/2022 4/5/2022 04/05/2022
Misc
Informational
04/05/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/05/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/05/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Site Visit Partial 04/05/2022
Misc
Informational
04/05/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/05/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/05/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/05/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Storm - Material Verification Partial 04/06/2022
Misc
Informational
04/06/2022
Had 21 sticks of 8’ elliptical 14” concrete pipe delivered along with 2 end flanges. 4/6/22 ES
Sanitary - Material Verification Partial 04/06/2022
Misc
Corrective Action Required
04/06/2022
Had sewer materials delivered. Have wyes for tie in on main and clean outs. Clean out caps, and pipe(all SDR26). Metal Sewer clean out rings and lids. Also had hard back furnco adapters, let Glynn know these would need to be replaced and use Max Adapters. 4/5/22 ES
Water - Material Verification Partial 04/06/2022
Misc
Informational
04/06/2022
Had 6” C900 water pipe, two 6” epoxy gate valves, epoxy coated adapters, meter wells, meter lids/rings, backflow devices for domestic and irrigation lines, tracer wire, locate tape and curb stop valve risers delivered. 4/5/22 ES
Storm - Pipe Partial 04/07/2022
Misc
Informational
04/07/2022
4-7-22 AN spoke to contractor about concerns he had with the ditch south of the entrance and main drive (not getting12in rock on top of culvert) pic attached Ditch south of the drive - Try and get as much rock on top of culvert as possible and grade the dirt to eliminate the ditch where the culvert is but still allowing the water to flow to the south ditch and not toward the building. Culvert under drive - depending on the final grade of the drive they can either use flowable fill around the culvert and under the drive or if there is even less clearance between the pipe and drive they can encase the culvert in concrete.
Storm - Pipe Partial 04/11/2022
Misc
Informational
04/07/2022
4-7-22 AN spoke to contractor about concerns he had with the ditch south of the entrance and main drive (not getting12in rock on top of culvert) pic attached Ditch south of the drive - Try and get as much rock on top of culvert as possible and grade the dirt to eliminate the ditch where the culvert is but still allowing the water to flow to the east ditch and not toward the building. Culvert under drive - depending on the final grade of the drive they can either use flowable fill around the culvert and under the drive or if there is even less clearance between the pipe and drive they can encase the culvert in concrete.
Misc
Informational
04/11/2022
4-11-22AN contractor is going to use digable flowable fill around the culvert on 4-12
Storm - Pipe Partial 04/12/2022
Misc
Informational
04/11/2022
4-7-22 AN spoke to contractor about concerns he had with the ditch south of the entrance and main drive (not getting12in rock on top of culvert) pic attached Ditch south of the drive - Try and get as much rock on top of culvert as possible and grade the dirt to eliminate the ditch where the culvert is but still allowing the water to flow to the east ditch and not toward the building. Culvert under drive - depending on the final grade of the drive they can either use flowable fill around the culvert and under the drive or if there is even less clearance between the pipe and drive they can encase the culvert in concrete.
Misc
Informational
04/11/2022
4-11-22AN contractor is going to use digable flowable fill around the culvert on 4-12
Misc
Informational
04/12/2022
Contractor put 8 yds of flowable fill on top and sides of pipe across where entrance will be off of blue pkwy. 4/12/22 ES
Site Visit Partial 04/14/2022
Misc
Informational
04/05/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/05/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/05/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/05/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Site Visit Partial 04/18/2022
Misc
Informational
04/14/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/14/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/14/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/14/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/18/2022
No work being performed due to rain over weekend. 4/18/22 ES
Site Visit Partial 4/19/2022 04/20/2022
Misc
Informational
04/18/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/18/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/18/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/18/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/18/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/18/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/20/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Site Visit Partial 4/20/2022 04/25/2022
Misc
Informational
04/20/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/20/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/20/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/20/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/20/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/20/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/20/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
04/25/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Sanitary Sewer Construction Inspection Partial 04/25/2022
Misc
Informational
04/25/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Site Visit Partial 04/25/2022
Misc
Informational
04/25/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/25/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/25/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/25/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/25/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/25/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/25/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
04/25/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
04/25/2022
Started sanitary sewer line construction. 4/25/22 ES
Site Visit Partial 04/26/2022
Misc
Informational
04/25/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/25/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/25/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/25/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/25/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/25/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/25/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
04/25/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
04/25/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
04/26/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Sanitary Sewer Construction Inspection Partial 04/26/2022
Misc
Informational
04/25/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
04/26/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Site Visit Partial 04/28/2022
Misc
Informational
04/26/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/26/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/26/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/26/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/26/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/26/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/26/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
04/26/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
04/26/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
04/26/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
04/28/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Sanitary Sewer Construction Inspection Partial 04/28/2022
Misc
Informational
04/26/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
04/26/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
04/28/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Site Visit Partial 04/29/2022
Misc
Informational
04/28/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/28/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/28/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/28/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/28/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/28/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/28/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
04/28/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
04/28/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
04/28/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
04/28/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
04/29/2022
No utility work being done today. 4/29/22 ES
Storm Sewer Construction Inspection Partial 05/03/2022
Misc
Informational
05/03/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Storm Sewer Construction Inspection Partial 05/03/2022
Misc
Informational
05/03/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
05/03/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Site Visit Partial 05/03/2022
Misc
Informational
04/29/2022
No work being completed. 3/28/22 ES
Misc
Informational
04/29/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
04/29/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
04/29/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
04/29/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
04/29/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
04/29/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
04/29/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
04/29/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
04/29/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
04/29/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
04/29/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/03/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Storm Sewer Construction Inspection Partial 05/09/2022
Misc
Informational
05/03/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
05/03/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
05/09/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Site Visit Partial 05/09/2022
Misc
Informational
05/03/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/03/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/03/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/03/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/03/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/03/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/03/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/03/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/03/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/03/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/03/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/03/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/03/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/09/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Storm Sewer Construction Inspection Partial 05/09/2022
Misc
Informational
05/09/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
05/09/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
05/09/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
05/09/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES
Storm Sewer Construction Inspection Partial 05/12/2022
Misc
Informational
05/09/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
05/09/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
05/09/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
05/09/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES
Misc
Informational
05/12/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Storm Sewer Construction Inspection Partial 05/12/2022
Misc
Informational
05/12/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
05/12/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
05/12/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
05/12/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
05/12/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Site Visit Partial 05/12/2022
Misc
Informational
05/09/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/09/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/09/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/09/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/09/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/09/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/09/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/09/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/09/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/09/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/09/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/09/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/09/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/09/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/12/2022
Linaweaver working on storm lines. 5/9/22 ES
Site Visit Partial 05/12/2022
Misc
Informational
05/12/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/12/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/12/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/12/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/12/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/12/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/12/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/12/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/12/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/12/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/12/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/12/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/12/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/12/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/12/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES
Sanitary Sewer Construction Inspection Partial 05/23/2022
Misc
Informational
04/28/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
04/28/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
04/28/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
05/23/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES
Sanitary Sewer Construction Inspection Partial 05/23/2022
Misc
Informational
05/23/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
05/23/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
05/23/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
05/23/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES
Sanitary Sewer Construction Inspection Partial 05/23/2022
Misc
Informational
05/23/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
05/23/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
05/23/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
05/23/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Site Visit Partial 05/23/2022
Misc
Informational
05/12/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/12/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/12/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/12/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/12/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/12/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/12/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/12/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/12/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/12/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/12/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/12/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/12/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/12/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/12/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES
Site Visit Partial 05/23/2022
Misc
Informational
05/23/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/23/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/23/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/23/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/23/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/23/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/23/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/23/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/23/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/23/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/23/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/23/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/23/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/23/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/23/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES
Site Visit Partial 05/23/2022
Misc
Informational
05/23/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/23/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/23/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/23/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/23/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/23/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/23/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/23/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/23/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/23/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/23/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/23/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/23/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/23/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/23/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES
Site Visit Partial 05/24/2022
Misc
Informational
05/23/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/23/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/23/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/23/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/23/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/23/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/23/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/23/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/23/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/23/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/23/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/23/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/23/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/23/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/23/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES
Fire Line Construction Inspection Partial 05/27/2022
Misc
Informational
05/27/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES
Site Visit Partial 05/27/2022
Misc
Informational
05/24/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/24/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/24/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/24/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/24/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/24/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/24/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/24/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/24/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/24/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/24/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/24/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/24/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/24/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/24/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES
Site Visit Partial 05/31/2022
Misc
Informational
05/27/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/27/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/27/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/27/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/27/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/27/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/27/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/27/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/27/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/27/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/27/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/27/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/27/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/27/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/27/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES No construction work today with rain storms. 5/31/22 ES
Site Visit Partial 05/31/2022
Misc
Informational
05/31/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/31/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/31/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/31/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/31/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/31/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/31/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/31/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/31/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/31/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/31/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/31/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/31/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/31/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/31/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES
Site Visit Partial 06/02/2022
Misc
Informational
05/31/2022
No work being completed. 3/28/22 ES
Misc
Informational
05/31/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
05/31/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
05/31/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
05/31/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
05/31/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
05/31/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
05/31/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
05/31/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
05/31/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
05/31/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
05/31/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
05/31/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
05/31/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
05/31/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. 6/1/22 ES
Site Visit Partial 06/02/2022
Misc
Informational
06/02/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/02/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/02/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/02/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/02/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/02/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/02/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/02/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/02/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/02/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/02/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/02/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/02/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/02/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/02/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES
Water Service Inspection Partial 06/02/2022
Misc
Informational
06/02/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES
Water Service Inspection Partial 06/02/2022
Misc
Informational
06/02/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES Water performed 2 - 1” taps using 12” clamps with outlets. 6/1/22 ES
Water Service Inspection Partial 06/03/2022
Misc
Informational
06/02/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES Water performed 2 - 1” taps using 12” clamps with outlets. 6/1/22 ES Richard’s crew was working on running copper from main to meter setups, also running 10’ copper out of meter pits. 6/3/22 ES
Fire Line Construction Inspection Partial 06/03/2022
Misc
Informational
05/27/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES
Site Visit Partial 06/03/2022
Misc
Informational
06/02/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/02/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/02/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/02/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/02/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/02/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/02/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/02/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/02/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/02/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/02/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/02/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/02/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/02/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/02/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES
Site Visit Partial 06/03/2022
Misc
Informational
06/03/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/03/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/03/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/03/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/03/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/03/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/03/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/03/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/03/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/03/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/03/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/03/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/03/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/03/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/03/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES
Water Service Inspection Partial 06/03/2022
Misc
Informational
06/03/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES Water performed 2 - 1” taps using 12” clamps with outlets. 6/1/22 ES Richard’s crew was working on running copper from main, didn’t have survey stakes set for meter pits. 6/2/22 ES Richard’s crew was working on running copper from main to meter setups, also running 10’ copper out of meter pits. 6/3/22 ES
Water Service Inspection Partial 06/08/2022
Misc
Informational
06/03/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES Water performed 2 - 1” taps using 12” clamps with outlets. 6/1/22 ES Richard’s crew was working on running copper from main, didn’t have survey stakes set for meter pits. 6/2/22 ES Richard’s crew was working on running copper from main to meter setups, also running 10’ copper out of meter pits. 6/3/22 ES Richard’s crew filled over pipe and services with gravel. Then filled under roadway with flowable fill. 6/6/22 ES
Site Visit Partial 06/08/2022
Misc
Informational
06/03/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/03/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/03/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/03/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/03/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/03/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/03/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/03/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/03/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/03/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/03/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/03/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/03/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/03/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/03/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES
Fire Line Construction Inspection Partial 06/08/2022
Misc
Informational
06/03/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES
Site Visit Partial 06/08/2022
Misc
Informational
06/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES
Storm Sewer Construction Inspection Partial 06/08/2022
Misc
Informational
05/12/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
05/12/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
05/12/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
05/12/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
05/12/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
06/08/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES
Fire Line Construction Inspection Partial 06/08/2022
Misc
Informational
06/08/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES
Storm Sewer Construction Inspection Partial 06/08/2022
Misc
Informational
06/08/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
06/08/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
06/08/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
06/08/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
06/08/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
06/08/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES
Site Visit Partial 06/08/2022
Misc
Informational
06/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES
Fire Line Construction Inspection Partial 06/09/2022
Misc
Informational
06/08/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES
Site Visit Partial 06/09/2022
Misc
Informational
06/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES
Fire Line Construction Inspection Partial 06/13/2022
Misc
Informational
06/09/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES
Fire Line Construction Inspection Partial 06/13/2022
Misc
Informational
06/13/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES
Fire Line Construction Inspection Partial 06/14/2022
Misc
Informational
06/13/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES
Site Visit Partial 06/14/2022
Misc
Informational
06/09/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/09/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/09/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/09/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/09/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/09/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/09/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/09/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/09/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/09/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/09/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/09/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/09/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/09/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/09/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES
Site Visit Partial 06/14/2022
Misc
Informational
06/14/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/14/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/14/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/14/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/14/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/14/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/14/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/14/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/14/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/14/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/14/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/14/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/14/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/14/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES
Fire Line Construction Inspection Partial 06/14/2022
Misc
Informational
06/14/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES Richard’s crew installed 2 - 45 bends from pipe coming from water main to get up to backflow pit, installed 2 - 45 bends one out of pit and one to straighten line back up for hydrant and T run. Installed 6x6x6” tee and fire hydrant and assembly. Fire hydrant was installed as a straight set and not on a 45 bend as plans show. Verified this to be ok with Sue Pyles. 6/10/22 ES
Site Visit Partial 06/14/2022
Misc
Informational
06/14/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/14/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/14/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/14/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/14/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/14/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/14/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/14/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/14/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/14/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/14/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/14/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/14/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/14/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES
Fire Line Construction Inspection Partial 06/14/2022
Misc
Informational
06/14/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES Richard’s crew installed 2 - 45 bends from pipe coming from water main to get up to backflow pit, installed 2 - 45 bends one out of pit and one to straighten line back up for hydrant and T run. Installed 6x6x6” tee and fire hydrant and assembly. Fire hydrant was installed as a straight set and not on a 45 bend as plans show. Verified this to be ok with Sue Pyles. 6/10/22 ES Richard’s crew installed a 6” cap with 2” outlet and blowoff valve for building fire line. Also poly wrapped T and hydrant/assembly/valve. 6/14/22 ES
Fire Line Construction Inspection Partial 06/16/2022
Misc
Informational
06/14/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES Richard’s crew installed 2 - 45 bends from pipe coming from water main to get up to backflow pit, installed 2 - 45 bends one out of pit and one to straighten line back up for hydrant and T run. Installed 6x6x6” tee and fire hydrant and assembly. Fire hydrant was installed as a straight set and not on a 45 bend as plans show. Verified this to be ok with Sue Pyles. 6/10/22 ES Richard’s crew installed a 6” cap with 2” outlet and blowoff valve for building fire line. Also poly wrapped T and hydrant/assembly/valve. 6/14/22 ES Richard’s crew filled installed fire line w/ 90 bend and stand pipe for building fire line. 6/15/22 ES
Misc
Informational
06/16/2022
Richard’s crew will be working on pressure testing and chlorinating line today after WU finishes their construction tap. 6/16/22 ES
Fire Line Construction Inspection Partial 06/16/2022
Misc
Informational
06/16/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES Richard’s crew installed 2 - 45 bends from pipe coming from water main to get up to backflow pit, installed 2 - 45 bends one out of pit and one to straighten line back up for hydrant and T run. Installed 6x6x6” tee and fire hydrant and assembly. Fire hydrant was installed as a straight set and not on a 45 bend as plans show. Verified this to be ok with Sue Pyles. 6/10/22 ES Richard’s crew installed a 6” cap with 2” outlet and blowoff valve for building fire line. Also poly wrapped T and hydrant/assembly/valve. 6/14/22 ES Richard’s crew filled installed fire line w/ 90 bend and stand pipe for building fire line. 6/15/22 ES
Misc
Informational
06/16/2022
Richard’s crew will be working on pressure testing and chlorinating line today after WU finishes their construction tap. 6/16/22 ES Richard’s crew flushed fire line today. We then performed a hydrostatic test on the line at 200 psi for 2 hours. Passed. After hydrostatic test passed we chlorinated line. 6/16/22 ES
Fire Line Construction Inspection Passed 06/16/2022
Misc
Informational
06/16/2022
Richard’s crew performed fire line tie in. Using all epoxy coated fittings; 8”x6” tee, solid sleeves, 6” gate valve and anchor coupling. Once installed wrapped all components with poly wrap and taped up. Will perform tracer wire tie in when continuing construction of pipe from valve to back flow vault. 5/27/22 ES Richard’s crew was working on getting fire line ran from valve out to where the vault will be set. Vault won’t be delivered til 6/7 or so. 6/3/22 ES Richard’s crew worked on backfilling what pipe was in ground and getting flowable fill above pipe/gravel under roadway. 6/6/22 ES Glynn/Richard called about using 90° bends on fire line to make up ground from depth of water main under road to into backflow vault structure. Informed them that preference would be 45s, and we would evaluate the situation once vault structure was delivered and set in place. 6/7/22 ES Had backflow vault delivered. 6/8/22 ES Installed backflow vault using 2 - 45 bends to get from water main level up to vault level. 6/9/22 ES Richard’s crew installed 2 - 45 bends from pipe coming from water main to get up to backflow pit, installed 2 - 45 bends one out of pit and one to straighten line back up for hydrant and T run. Installed 6x6x6” tee and fire hydrant and assembly. Fire hydrant was installed as a straight set and not on a 45 bend as plans show. Verified this to be ok with Sue Pyles. 6/10/22 ES Richard’s crew installed a 6” cap with 2” outlet and blowoff valve for building fire line. Also poly wrapped T and hydrant/assembly/valve. 6/14/22 ES Richard’s crew filled installed fire line w/ 90 bend and stand pipe for building fire line. 6/15/22 ES
Misc
Informational
06/16/2022
Richard’s crew will be working on pressure testing and chlorinating line today after WU finishes their construction tap. 6/16/22 ES Richard’s crew flushed fire line today. We then performed a hydrostatic test on the line at 200 psi for 2 hours. Passed. After hydrostatic test passed we chlorinated line. 6/16/22 ES Fire line passed testing and is chlorinated. 6/16/22 ES
Site Visit Partial 06/16/2022
Misc
Informational
06/14/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/14/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/14/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/14/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/14/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/14/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/14/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/14/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/14/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/14/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/14/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/14/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/14/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/14/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES
Site Visit Partial 06/16/2022
Misc
Informational
06/16/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/16/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/16/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/16/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/16/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/16/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/16/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/16/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/16/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/16/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/16/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/16/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/16/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/16/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/16/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES
Site Visit Partial 06/16/2022
Misc
Informational
06/16/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/16/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/16/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/16/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/16/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/16/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/16/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/16/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/16/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/16/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/16/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/16/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/16/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/16/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/16/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES
Fire Line - Hydrostatic Test Passed 06/16/2022
Misc
Informational
06/16/2022
Fire line was pumped up to 200psi and held pressure for 2 hours. After line passed it was chlorinated in preparation for Bac-T testing. 6/16/22 ES
Water - Material Verification Passed 06/16/2022
Misc
Informational
04/06/2022
Had 6” C900 water pipe, two 6” epoxy gate valves, epoxy coated adapters, meter wells, meter lids/rings, backflow devices for domestic and irrigation lines, tracer wire, locate tape and curb stop valve risers delivered. 4/5/22 ES All water components used for completion of fire line, water taps, water service lines all approved products. C900 pipe, epoxy coated valves and fittings on fire line, and copper line for taps and poly tubing from copper on back of meters to building. 6/16/22 ES
Footing Inspection - Commercial Partial 6/17/2022 (8:00) 6/17/2022 06/17/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/17/2022
-COLUMN PADS AT LINE E: 1-6
Site Visit Partial 06/20/2022
Misc
Informational
06/16/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/16/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/16/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/16/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/16/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/16/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/16/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/16/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/16/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/16/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/16/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/16/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/16/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/16/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/16/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES
Detention Basin Partial 06/20/2022
Misc
Informational
06/17/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES
Detention Basin Partial 06/20/2022
Misc
Informational
06/20/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. 6/20/22 ES
Water Line - Coliform Test 1 Partial 06/20/2022
Misc
Informational
06/20/2022
Richard’s crew chlorinated fire line from construction tap to end of line. Will let sit chlorinated over weekend. 6/16/22 ES
Site Visit Partial 06/20/2022
Misc
Informational
06/20/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/20/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/20/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/20/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/20/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/20/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/20/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/20/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/20/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/20/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/20/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/20/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/20/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/20/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/20/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. 6/20/22 ES
Water Line - Coliform Test 1 Partial 06/20/2022
Misc
Informational
06/20/2022
Richard’s crew chlorinated fire line from construction tap to end of line. Will let sit chlorinated over weekend. 6/16/22 ES Dechlorinated line with dechlorination pellets and flushed after dechlorinating. 6/20/22 ES
Storm Sewer Construction Inspection Partial 06/20/2022
Misc
Informational
06/08/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
06/08/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
06/08/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
06/08/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
06/08/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
06/08/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES
Storm Sewer Construction Inspection Partial 06/20/2022
Misc
Informational
06/20/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
06/20/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
06/20/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
06/20/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
06/20/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
06/20/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. 6/20/22 ES
Detention Basin Partial 06/20/2022
Misc
Informational
06/20/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES
Site Visit Partial 06/20/2022
Misc
Informational
06/20/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/20/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/20/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/20/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/20/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/20/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/20/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/20/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/20/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/20/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/20/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/20/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/20/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/20/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/20/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES
Storm Sewer Construction Inspection Partial 06/20/2022
Misc
Informational
06/20/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
06/20/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
06/20/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
06/20/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
06/20/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
06/20/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES
Water Line - Coliform Test 1 Partial 06/21/2022
Misc
Informational
06/20/2022
Richard’s crew chlorinated fire line from construction tap to end of line. Will let sit chlorinated over weekend. 6/16/22 ES Dechlorinated line with dechlorination pellets and flushed after dechlorinating. 6/20/22 ES Took 2 samples from fire line. 1 from before backflow on public side and one from end of line. 6/21/22 ES
Site Visit Partial 06/21/2022
Misc
Informational
06/20/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/20/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/20/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/20/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/20/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/20/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/20/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/20/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/20/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/20/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/20/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/20/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/20/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/20/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/20/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES
Detention Basin Partial 06/21/2022
Misc
Informational
06/20/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES
Detention Basin Partial 06/22/2022
Misc
Informational
06/21/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES
Water Line - Coliform Test 2 Partial 06/22/2022
Misc
Informational
06/22/2022
Pulled 2nd set of samples at 9:45-10am. 6/22/22 ES
Footing Inspection - Commercial Partial 6/22/2022 6/22/2022 06/22/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/17/2022
-COLUMN PADS AT LINE E: 1-6, LINE 1: A-E, LINE A: 1-6, LINE 6: A-E
Detention Basin Partial 06/23/2022
Misc
Informational
06/22/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES
Water Line - Coliform Test 1 Passed 06/23/2022
Misc
Informational
06/21/2022
Richard’s crew chlorinated fire line from construction tap to end of line. Will let sit chlorinated over weekend. 6/16/22 ES Dechlorinated line with dechlorination pellets and flushed after dechlorinating. 6/20/22 ES Took 2 samples from fire line. 1 from before backflow on public side and one from end of line. 6/21/22 ES Water samples #1 passed. 6/22/22 ES
Detention Basin Partial 06/23/2022
Misc
Informational
06/23/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES
Footing Inspection - Commercial Partial 6/24/2022 6/24/2022 06/24/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/22/2022
-COLUMN PADS AT LINE E: 1-6, LINE 1: A-E, LINE A: 1-6, LINE 6: A-E -PILASTERS AT LINE E: 1-6, LINE 6: E-A.2
Water Line - Coliform Test 2 Partial 06/24/2022
Misc
Informational
06/22/2022
Pulled 2nd set of samples at 9:45-10am. 6/22/22 ES 2nd Set of samples had a failure. Will need to retest. 6/24/22 ES
Water Line - Coliform Test 2 Partial 06/27/2022
Misc
Informational
06/27/2022
2nd set of samples taken and delivered to Keystone labs. 6/23/22 ES
Detention Basin Partial 06/27/2022
Misc
Informational
06/23/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started excavating for the middle basin. 6/27/22 ES
Water Line - Coliform Test 2 Partial 06/28/2022
Misc
Informational
06/27/2022
2nd set of samples taken and delivered to Keystone labs. 6/23/22 ES 2nd set had a fail on sample #2. 6/24/22 ES
Water Line - Coliform Test 1 Partial 06/28/2022
Misc
Informational
06/28/2022
Took first set of samples. 6/28/22 ES
Footing Inspection - Commercial Partial 6/28/2022 (10:00) 6/28/2022 06/28/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/24/2022
-COLUMN PADS AT LINE E: 1-6, LINE 1: A-E, LINE A: 1-6, LINE 6: A-E -PILASTERS AT LINE E: 1-6, LINE 6: E-A.2, LINE A: 2-6 -FOOTINGS AT LINE E: 1-6, LINE 6: A-E
Detention Basin Partial 06/28/2022
Misc
Informational
06/27/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started working on the middle basin. Observed the removal of fill to proper depth. Fabric was placed and Clean aggregate was placed on top of that. 6/28/22 ES
Water Line - Coliform Test 1 Partial 06/28/2022
Misc
Informational
06/28/2022
Took first set of samples. 6/28/22 ES Delivered to Keystone labs 12pm. 6-28-22 ES
Site Visit Partial 06/28/2022
Misc
Informational
06/21/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/21/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/21/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/21/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/21/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/21/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/21/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/21/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/21/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/21/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/21/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/21/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/21/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/21/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/21/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES
Detention Basin Partial 06/30/2022
Misc
Informational
06/28/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started working on the middle basin. Observed the removal of fill to proper depth. Fabric was placed and Clean aggregate was placed on top of that. 6/28/22 ES Richard’s crew completed middle basin and lower drain line. Backfilled with clean rock above basin then wrapped with fabric. Then put AB3 on top of clean rock/matting in 1’ lifts and began compacting. 6/29/22 ES
Water Line - Coliform Test 2 Partial 06/30/2022
Misc
Informational
06/28/2022
2nd set of samples taken and delivered to Keystone labs. 6/23/22 ES 2nd set had a fail on sample #2. 6/24/22 ES 2nd set of samples pulled in am of 6/29 and delivered to Keystone labs. 6/29/22 ES
Footing Inspection - Commercial Partial 6/30/2022 06/30/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/28/2022
-COLUMN PADS AT LINE E: 1-6, LINE 1: A-E, LINE A: 1-6, LINE 6: A-E -PILASTERS AT LINE E: 1-6, LINE 6: E-A.2, LINE A: 2-6 -BOTTOM FOOTINGS AT LINE E: 1-6, LINE 6: A-E, LINE A: 6-1, LINE 1: A-C
Footing Inspection - Commercial Partial 7/1/2022 7/1/2022 07/01/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/30/2022
-COLUMN PADS AT LINE E: 1-6, LINE 1: A-E, LINE A: 1-6, LINE 6: A-E -PILASTERS AT LINE E: 1-6, LINE 6: E-A.2, LINE A: 2-6 -FOOTINGS AT LINE E: 1-6, LINE 6: A-E, LINE A: 6-1, LINE 1: A-C
Detention Basin Partial 07/05/2022
Misc
Informational
06/30/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started working on the middle basin. Observed the removal of fill to proper depth. Fabric was placed and Clean aggregate was placed on top of that. 6/28/22 ES Richard’s crew completed middle basin and lower drain line. Backfilled with clean rock above basin then wrapped with fabric. Then put AB3 on top of clean rock/matting in 1’ lifts and began compacting. 6/29/22 ES Richard’s crew working on backfilling final ADS systems. Using clean rock on top and wrapped, and then AB3/Type 5 rock in lifts and compacting with sheepsfoot. 7/5/22 ES
Erosion Control Inspection Residential Partial 07/05/2022
Misc
Informational
07/05/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES
Footing Inspection - Commercial Partial 7/6/2022 7/6/2022 07/06/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/01/2022
-COLUMN PADS AT LINE E: 1-6, LINE 1: A-E, LINE A: 1-6, LINE 6: A-E, LINE 6.1-A.1, A.2, LINE 6.2-C.1, D.1 -PILASTERS AT LINE E: 1-6, LINE 6: E-A.2, LINE A: 2-6 -FOOTINGS AT LINE E: COMPLETE, LINE 6: A-E, LINE A: 6-1, LINE 1: COMPLETE -
Storm Sewer Construction Inspection Partial 07/06/2022
Misc
Informational
06/20/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
06/20/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
06/20/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
06/20/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
06/20/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
06/20/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Site Visit Partial 07/07/2022
Misc
Informational
06/28/2022
No work being completed. 3/28/22 ES
Misc
Informational
06/28/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
06/28/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
06/28/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
06/28/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
06/28/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
06/28/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
06/28/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
06/28/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
06/28/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
06/28/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
06/28/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
06/28/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
06/28/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
06/28/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES
Water Service Inspection Partial 07/07/2022
Misc
Informational
06/08/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES Water performed 2 - 1” taps using 12” clamps with outlets. 6/1/22 ES Richard’s crew was working on running copper from main, didn’t have survey stakes set for meter pits. 6/2/22 ES Richard’s crew was working on running copper from main to meter setups, also running 10’ copper out of meter pits. 6/3/22 ES Richard’s crew filled over pipe and services with gravel. Then filled under roadway with flowable fill. 6/6/22 ES Glynn’s concrete crew poured the street patch and curb back where the fire line and water service tie ins were done. 7/5/22 ES
Site Visit Partial 07/08/2022
Misc
Informational
07/07/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/07/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/07/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/07/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/07/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/07/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/07/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/07/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/07/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/07/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/07/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/07/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/07/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/07/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/07/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES
Underslab Plumbing Inspection - Commercial Partial 7/8/2022 7/8/2022 07/08/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/08/2022
DWV AT 114,103,107,109, 100, 112,113
Miscellaneous Correction
Corrective Action Required
07/08/2022
-PROVIDE CLEAN OUT AT EAST EXTERIOR CHANGE OF DIRECTION
Site Visit Partial 07/11/2022
Misc
Informational
07/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES
Erosion Control Inspection Residential Partial 07/11/2022
Misc
Informational
07/11/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES
Site Visit Partial 07/12/2022
Misc
Informational
07/11/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/11/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/11/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/11/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/11/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/11/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/11/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/11/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/11/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/11/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/11/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/11/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/11/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/11/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/11/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Site Visit Partial 07/14/2022
Misc
Informational
07/12/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/12/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/12/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/12/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/12/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/12/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/12/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/12/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/12/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/12/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/12/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/12/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/12/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/12/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/12/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/14/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES
Site Visit Partial 07/15/2022
Misc
Informational
07/14/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/14/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/14/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/14/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/14/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/14/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/14/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/14/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/14/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/14/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/14/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/14/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/14/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/14/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/14/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES
Site Visit Partial 07/18/2022
Misc
Informational
07/15/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/15/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/15/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/15/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/15/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/15/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/15/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/15/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/15/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/15/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/15/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/15/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/15/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/15/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/15/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/15/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. 7/19/22 ES
Erosion Control Inspection Residential Partial 07/18/2022
Misc
Informational
07/11/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES
Site Visit Partial 07/18/2022
Misc
Informational
07/18/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/18/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/18/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/18/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/18/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/18/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/18/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/18/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/18/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/18/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/18/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/18/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/18/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/18/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/18/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/18/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES
Footing Inspection - Commercial Partial 7/19/2022 (9:00) 7/19/2022 07/19/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/06/2022
-MAIN BUILDING FOOTING AND PIER PADS COMPLETE -
Site Visit Partial 07/19/2022
Misc
Informational
07/18/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/18/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/18/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/18/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/18/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/18/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/18/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/18/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/18/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/18/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/18/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/18/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/18/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/18/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/18/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/18/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES
Sanitary Sewer Construction Inspection Partial 07/20/2022
Misc
Informational
05/23/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
05/23/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
05/23/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
05/23/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Misc
Informational
07/20/2022
Glynn’s concrete crew poured the approach back for business across the street. 7/20/22 ES
Footing Inspection - Commercial Partial 7/22/2022 (10:00) 7/22/2022 07/22/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/19/2022
-MAIN BUILDING FOOTING AND PIER PADS COMPLETE -PAINT BOOTH SLAB
Site Visit Partial 07/22/2022
Misc
Informational
07/19/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/19/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/19/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/19/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/19/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/19/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/19/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/19/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/19/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/19/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/19/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/19/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/19/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/19/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/19/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/19/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES Building and pad work being done no utility work. 7/22/22 ES
Site Visit Partial 07/26/2022
Misc
Informational
07/22/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/22/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/22/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/22/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/22/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/22/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/22/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/22/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/22/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/22/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/22/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/22/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/22/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/22/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/22/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/22/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Footing Inspection - Commercial Partial 7/27/2022 (1:00) 7/27/2022 07/27/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/22/2022
-MAIN BUILDING FOOTING AND PIER PADS COMPLETE -PAINT BOOTH SLAB -STEM WALL AT PAINT BOOTH
Erosion Control Inspection Residential Partial 08/02/2022
Misc
Informational
07/18/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES
Site Visit Partial 08/02/2022
Misc
Informational
07/26/2022
No work being completed. 3/28/22 ES
Misc
Informational
07/26/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
07/26/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
07/26/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
07/26/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
07/26/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
07/26/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
07/26/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
07/26/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
07/26/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
07/26/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
07/26/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
07/26/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
07/26/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
07/26/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
07/26/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
08/02/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES
Footing Inspection - Commercial Partial 8/2/2022 (3:00) 8/2/2022 08/02/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/27/2022
-MAIN BUILDING FOOTING AND PIER PADS COMPLETE -PAINT BOOTH SLAB -STEM WALL AT PAINT BOOTH
Site Visit Partial 08/03/2022
Misc
Informational
08/02/2022
No work being completed. 3/28/22 ES
Misc
Informational
08/02/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
08/02/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
08/02/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
08/02/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
08/02/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
08/02/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
08/02/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
08/02/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
08/02/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
08/02/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
08/02/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
08/02/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
08/02/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
08/02/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
08/02/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
08/02/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES
Underslab Plumbing Inspection - Commercial Partial 8/4/2022 8/4/2022 08/04/2022
THE FOLLOWING AREAS ARE APPROVED
Informational
08/04/2022
DWV AT 114,103,107,109, 100, 112,113
Site Visit Partial 08/04/2022
Misc
Informational
08/03/2022
No work being completed. 3/28/22 ES
Misc
Informational
08/03/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
08/03/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
08/03/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
08/03/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
08/03/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
08/03/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
08/03/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
08/03/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
08/03/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
08/03/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
08/03/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
08/03/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
08/03/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
08/03/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
08/03/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
08/03/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES
Storm Sewer Construction Inspection Partial 08/08/2022
Misc
Informational
07/06/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
07/06/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
07/06/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
07/06/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
07/06/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
07/06/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/08/2022
Erosion Control Inspection Residential Partial 08/08/2022
Misc
Informational
08/02/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES
Sanitary Sewer Construction Inspection Partial 08/08/2022
Misc
Informational
07/20/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
07/20/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
07/20/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
07/20/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Misc
Informational
07/20/2022
Glynn’s concrete crew poured the approach back for business across the street. 7/20/22 ES Spoke with Richard about getting area around drive across street backfilled. He said once his skid steer was delivered later today they would work on it. 8/8/22 ES
Detention Basin Partial 08/10/2022
Misc
Informational
07/05/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started working on the middle basin. Observed the removal of fill to proper depth. Fabric was placed and Clean aggregate was placed on top of that. 6/28/22 ES Richard’s crew completed middle basin and lower drain line. Backfilled with clean rock above basin then wrapped with fabric. Then put AB3 on top of clean rock/matting in 1’ lifts and began compacting. 6/29/22 ES Richard’s crew working on backfilling final ADS systems. Using clean rock on top and wrapped, and then AB3/Type 5 rock in lifts and compacting with sheepsfoot. 7/5/22 ES
Misc
Informational
08/10/2022
Linaweaver working on finishing connections of detention basin. Installed storm box 3 base, and 2 nyloplast connections to first basin. 8/9/22 ES
Detention Basin Partial 08/10/2022
Misc
Informational
08/10/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started working on the middle basin. Observed the removal of fill to proper depth. Fabric was placed and Clean aggregate was placed on top of that. 6/28/22 ES Richard’s crew completed middle basin and lower drain line. Backfilled with clean rock above basin then wrapped with fabric. Then put AB3 on top of clean rock/matting in 1’ lifts and began compacting. 6/29/22 ES Richard’s crew working on backfilling final ADS systems. Using clean rock on top and wrapped, and then AB3/Type 5 rock in lifts and compacting with sheepsfoot. 7/5/22 ES
Misc
Informational
08/10/2022
Linaweaver working on finishing connections of detention basin. Installed storm box 3 base, and 2 nyloplast connections to first basin. 8/9/22 ES Linaweaver finished filling top of detention basin with clean rock and covered with fabric. Continued fill with AB3/Type 5 rock in lifts compacting in lifts. 8/10/22 ES
Storm Sewer Construction Inspection Partial 08/10/2022
Misc
Informational
08/08/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
08/08/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
08/08/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
08/08/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
08/08/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
08/08/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/08/2022
Richard’s crew back on site working on final portion of underground detention basin. Will be sitting box 3 and nyloplasts today and working towards box 4. 8/8/22 ES Linaweaver crew completed detention basin outside of a single connection from first basin to storm box 3. both nyloplasts installed and ready to begin working towards box 4.
Storm Sewer Construction Inspection Partial 08/10/2022
Misc
Informational
08/10/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
08/10/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
08/10/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
08/10/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
08/10/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
08/10/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/10/2022
Richard’s crew back on site working on final portion of underground detention basin. Will be sitting box 3 and nyloplasts today and working towards box 4. 8/8/22 ES Linaweaver crew completed detention basin outside of a single connection from first basin to storm box 3. both nyloplasts installed and ready to begin working towards box 4. Linaweaver began construction of line coming from nyloplast at entry to underground detention basin going towards storm box 4. 8/10/22 ES
Storm Sewer Construction Inspection Partial 08/11/2022
Misc
Informational
08/10/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
08/10/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
08/10/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
08/10/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
08/10/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
08/10/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/10/2022
Richard’s crew back on site working on final portion of underground detention basin. Will be sitting box 3 and nyloplasts today and working towards box 4. 8/8/22 ES Linaweaver crew completed detention basin outside of a single connection from first basin to storm box 3. both nyloplasts installed and ready to begin working towards box 4. Linaweaver began construction of line coming from nyloplast at entry to underground detention basin going towards storm box 4. 8/10/22 ES Linaweaver completed construction of storm lines on east side of building including setting boxes 4 and 5. 8/10/22 ES
Storm Sewer Construction Inspection Partial 08/11/2022
Misc
Informational
08/11/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
08/11/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
08/11/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
08/11/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
08/11/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
08/11/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/11/2022
Richard’s crew back on site working on final portion of underground detention basin. Will be sitting box 3 and nyloplasts today and working towards box 4. 8/8/22 ES Linaweaver crew completed detention basin outside of a single connection from first basin to storm box 3. both nyloplasts installed and ready to begin working towards box 4. Linaweaver began construction of line coming from nyloplast at entry to underground detention basin going towards storm box 4. 8/10/22 ES Linaweaver completed construction of storm lines on east side of building including setting boxes 4 and 5. 8/10/22 ES Linaweaver poured collars and inverts, around and in storm boxes 3, 4, and 5. 8/11/22 ES
Grading/Excavation/Fill Inspection Partial 08/11/2022
Misc
Informational
08/11/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES
Grading/Excavation/Fill Inspection Partial 08/11/2022
Misc
Informational
08/11/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES
Pavement-Stabilized Subgrade Partial 08/11/2022
Misc
Informational
08/11/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES
Site Visit Partial 08/16/2022
Misc
Informational
08/04/2022
No work being completed. 3/28/22 ES
Misc
Informational
08/04/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
08/04/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
08/04/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
08/04/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
08/04/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
08/04/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
08/04/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
08/04/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
08/04/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
08/04/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
08/04/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
08/04/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
08/04/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
08/04/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
08/04/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
08/04/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES
Erosion Control Inspection Residential Partial 08/16/2022
Misc
Informational
08/08/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES
Site Visit Partial 08/17/2022
Misc
Informational
08/16/2022
No work being completed. 3/28/22 ES
Misc
Informational
08/16/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
08/16/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
08/16/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
08/16/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
08/16/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
08/16/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
08/16/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
08/16/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
08/16/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
08/16/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
08/16/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
08/16/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
08/16/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
08/16/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
08/16/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
08/16/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES
Pavement-Stabilized Subgrade Partial 08/17/2022
Misc
Informational
08/11/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES
Grading/Excavation/Fill Inspection Partial 08/19/2022
Misc
Informational
08/11/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES
Grading/Excavation/Fill Inspection Partial 08/19/2022
Misc
Informational
08/19/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES
Pavement-Stabilized Subgrade Partial 08/19/2022
Misc
Informational
08/17/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES
Pavement-Stabilized Subgrade Partial 08/19/2022
Misc
Informational
08/19/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES
Erosion Control Inspection Residential Partial 08/23/2022
Misc
Informational
08/16/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES
Grading/Excavation/Fill Inspection Partial 08/23/2022
Misc
Informational
08/19/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES
Roof Drain Partial 08/23/2022
Misc
Informational
08/23/2022
Linaweaver installed all roof drains on west side of building. 8/22/22 ES
Storm Sewer Construction Inspection Partial 08/23/2022
Misc
Informational
08/11/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
08/11/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
08/11/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
08/11/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
08/11/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
08/11/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/11/2022
Richard’s crew back on site working on final portion of underground detention basin. Will be sitting box 3 and nyloplasts today and working towards box 4. 8/8/22 ES Linaweaver crew completed detention basin outside of a single connection from first basin to storm box 3. both nyloplasts installed and ready to begin working towards box 4. Linaweaver began construction of line coming from nyloplast at entry to underground detention basin going towards storm box 4. 8/10/22 ES Linaweaver completed construction of storm lines on east side of building including setting boxes 4 and 5. 8/10/22 ES Linaweaver poured collars and inverts, around and in storm boxes 3, 4, and 5. 8/11/22 ES Linaweaver getting measurements on storm inlets to make final adjustments. 8/22/22 ES
Grading/Excavation/Fill Inspection Partial 08/23/2022
Misc
Informational
08/23/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES
Sanitary Sewer Construction Inspection Partial 08/23/2022
Misc
Informational
08/08/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
08/08/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
08/08/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
08/08/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Misc
Informational
08/08/2022
Glynn’s concrete crew poured the approach back for business across the street. 7/20/22 ES Spoke with Richard about getting area around drive across street backfilled. He said once his skid steer was delivered later today they would work on it. 8/8/22 ES Linaweaver working on cutting clean outs down to grade in parking lot areas. 8/23/22 ES
Sanitary Sewer Construction Inspection Partial 08/23/2022
Misc
Informational
08/23/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
08/23/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
08/23/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
08/23/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Misc
Informational
08/23/2022
Glynn’s concrete crew poured the approach back for business across the street. 7/20/22 ES Spoke with Richard about getting area around drive across street backfilled. He said once his skid steer was delivered later today they would work on it. 8/8/22 ES Linaweaver working on cutting clean outs down to grade in parking lot areas. 8/23/22 ES
Grading/Excavation/Fill Inspection Partial 08/23/2022
Misc
Informational
08/23/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES
Underground Electrical Inspection - Commercial Partial 8/24/2022 8/24/2022 08/24/2022
Miscellaneous Correction
Corrective Action Required
08/24/2022
Secondary conduit from transformer to building
Underground Plumbing Inspection - Commercial Passed 8/25/2022 8/25/2022 08/25/2022
Pavement-Stabilized Subgrade Partial 08/25/2022
Misc
Informational
08/19/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES Electricians cut through subgrade and base rock for main power and light pole power. Spoke with Mr. Bridwell and informed him we would need to have those trenches brought back to grade with all type 5 rock compacted in lifts or flowable fill as to not leave a washboard parking lot from trenching. 8/25/22 ES
Underground Electrical Inspection - Commercial Partial 8/26/2022 8/26/2022 08/26/2022
Miscellaneous Correction
Corrective Action Required
08/24/2022
Secondary conduit from transformer to building and conduit for data
Erosion Control Inspection Residential Partial 08/29/2022
Misc
Informational
08/23/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES
Pavement-Stabilized Subgrade Partial 08/29/2022
Misc
Informational
08/25/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES Electricians cut through subgrade and base rock for main power and light pole power. Spoke with Mr. Bridwell and informed him we would need to have those trenches brought back to grade with all type 5 rock compacted in lifts or flowable fill as to not leave a washboard parking lot from trenching. 8/25/22 ES Electrical trenches were backfilled with AB3 and compacted. 8/26/22 ES
Commercial Curb Inspection Partial 08/29/2022
Misc
Informational
08/29/2022
Phoenix concrete began installing their stakes and guide string for curbs. 8/26/22 ES
Pavement-Stabilized Subgrade Partial 08/29/2022
Misc
Informational
08/29/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES Electricians cut through subgrade and base rock for main power and light pole power. Spoke with Mr. Bridwell and informed him we would need to have those trenches brought back to grade with all type 5 rock compacted in lifts or flowable fill as to not leave a washboard parking lot from trenching. 8/25/22 ES Electrical trenches were backfilled with AB3 and compacted. 8/26/22 ES Phoenix had to raise some areas of subgrade around building to get it to correct depth. 8/27/22 ES
Commercial Curb Inspection Partial 08/29/2022
Misc
Informational
08/29/2022
Phoenix concrete began installing their stakes and guide string for curbs. 8/26/22 ES Phoenix concrete began pouring curbs using KCMMB concrete. Left front of building and hand pour areas to complete as well as NW corner in front of building due to water/puddling issues. 8/29/22 ES
Roof Drain Passed 08/29/2022
Misc
Informational
08/23/2022
Linaweaver installed all roof drains on west side of building. 8/22/22 ES
Detention Basin Passed 08/29/2022
Misc
Informational
08/10/2022
Richard’s crew had dug out the pit for the northern most ADS underground detention basin. 6/17/22 ES Richard’s crew working on ADS system. Richard’s crew got mats down and started on rock layer below chambers. 6/20/22 ES Looked at detention basin design concerns with Glynn and Richard. 6/21/22a.m. ES Richard’s crew met with ADS this morning to verify basin elevations. Had 2 northern chambers installed minus end caps with pipe inlet/outlets. 6/22/22 ES Richard’s crew continued working on ADS system. 6/22/22 ES Richard’s crew working on first tie in coming from chambers in north pit. 6/23/22 ES Richard’s crew finished northern most basins. Poured collars at structure 2 and backfilled. Covered chambers with 1’ of clean aggregate and then wrapped with matting. Backfilled with clean dirt in 1’ lifts using a sheeps foot to compact soil. 6/27/22 ES Richard’s crew started working on the middle basin. Observed the removal of fill to proper depth. Fabric was placed and Clean aggregate was placed on top of that. 6/28/22 ES Richard’s crew completed middle basin and lower drain line. Backfilled with clean rock above basin then wrapped with fabric. Then put AB3 on top of clean rock/matting in 1’ lifts and began compacting. 6/29/22 ES Richard’s crew working on backfilling final ADS systems. Using clean rock on top and wrapped, and then AB3/Type 5 rock in lifts and compacting with sheepsfoot. 7/5/22 ES
Misc
Informational
08/10/2022
Linaweaver working on finishing connections of detention basin. Installed storm box 3 base, and 2 nyloplast connections to first basin. 8/9/22 ES Linaweaver finished filling top of detention basin with clean rock and covered with fabric. Continued fill with AB3/Type 5 rock in lifts compacting in lifts. 8/10/22 ES Detention basin installed. Nyloplasts installed with risers to get to parking lot grade. 8/22/22 ES
Erosion Control Inspection Residential Partial 09/07/2022
Misc
Informational
08/29/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES
Site Visit Partial 09/07/2022
Misc
Informational
08/17/2022
No work being completed. 3/28/22 ES
Misc
Informational
08/17/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
08/17/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
08/17/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
08/17/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
08/17/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
08/17/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
08/17/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
08/17/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
08/17/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
08/17/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
08/17/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
08/17/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
08/17/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
08/17/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
08/17/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
08/17/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES
Site Visit Partial 09/08/2022
Misc
Informational
09/07/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/07/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/07/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/07/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/07/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/07/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/07/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/07/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/07/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/07/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/07/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/07/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/07/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/07/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/07/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/07/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/07/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES
Site Visit Partial 09/08/2022
Misc
Informational
09/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/08/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/08/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES
Footing Inspection - Commercial Partial 8/9/2022 (3:00) 9/9/2022 09/09/2022
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/02/2022
-MAIN BUILDING FOOTING AND PIER PADS COMPLETE -PAINT BOOTH SLAB -STEM WALL AT PAINT BOOTH - 9/9/22 FOOTING TRASH ENCLOSURE PER PLAN -
In-wall Inspection Partial 9/9/2022 9/9/2022 09/09/2022
Misc
Informational
09/09/2022
- 9/9/22 OFFICE AREA METAL STUD, ELECTRICAL, PLUMBING OK TO COVER -
Site Visit Partial 09/09/2022
Misc
Informational
09/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/08/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/08/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES
Rated Assembly Inspection Partial 9/13/2022 9/13/2022 09/13/2022
Misc
Informational
09/13/2022
-Verified rated plywood at exterior walls
Piers/Caissons Inspection - Commercial Failed 09/14/2022
Misc
Corrective Action Required
09/14/2022
-Remove all loose soil from piers -Support and secure rebar to maintain min 3" clearance to soil
Site Visit Partial 09/15/2022
Misc
Informational
09/09/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/09/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/09/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/09/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/09/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/09/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/09/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/09/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/09/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/09/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/09/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/09/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/09/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/09/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/09/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/09/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/09/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES
Site Visit Partial 09/15/2022
Misc
Informational
09/15/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/15/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/15/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/15/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/15/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/15/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/15/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/15/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/15/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/15/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/15/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/15/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/15/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/15/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/15/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/15/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/15/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES
Site Visit Partial 09/15/2022
Misc
Informational
09/15/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/15/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/15/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/15/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/15/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/15/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/15/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/15/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/15/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/15/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/15/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/15/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/15/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/15/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/15/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/15/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/15/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES
Rated Assembly Inspection Failed 9/15/2022 9/15/2022 09/15/2022
Misc
Informational
09/13/2022
-Verified rated plywood at exterior walls
Misc
Corrective Action Required
09/15/2022
-Extend wall to deck above on all sides and complete screw pattern and drywall
Piers/Caissons Inspection - Commercial Passed 09/15/2022
Misc
Corrective Action Required
09/14/2022
(5) Light pole bases with ground rod
Site Visit Partial 09/16/2022
Misc
Informational
09/15/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/15/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/15/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/15/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/15/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/15/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/15/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/15/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/15/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/15/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/15/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/15/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/15/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/15/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/15/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/15/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/15/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES
Rated Assembly Inspection Failed 9/19/2022 9/19/2022 09/19/2022
Misc
Informational
09/15/2022
-Verified rated plywood at exterior walls
Misc
Corrective Action Required
09/15/2022
-Extend wall to deck above on all sides and complete screw pattern and drywall
Rated Assembly Inspection Passed 9/22/2022 9/22/2022 09/22/2022
Misc
Resolved
09/22/2022
-Verified rated plywood at exterior walls
Misc
Resolved
09/22/2022
-Extend wall to deck above on all sides and complete screw pattern and drywall
Erosion Control Inspection Residential Partial 09/26/2022
Misc
Informational
09/07/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES
Site Visit Partial 09/26/2022
Misc
Informational
09/16/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/16/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/16/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/16/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/16/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/16/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/16/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/16/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/16/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/16/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/16/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/16/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/16/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/16/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/16/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/16/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/16/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES
Site Visit Partial 09/27/2022
Misc
Informational
09/26/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/26/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/26/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/26/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/26/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/26/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/26/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/26/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/26/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/26/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/26/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/26/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/26/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/26/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/26/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/26/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/26/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES
Pavement-Curb Construction Partial 09/28/2022
Misc
Informational
09/08/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES
Commercial Curb Inspection Partial 09/28/2022
Misc
Informational
08/29/2022
Phoenix concrete began installing their stakes and guide string for curbs. 8/26/22 ES Phoenix concrete began pouring curbs using KCMMB concrete. Left front of building and hand pour areas to complete as well as NW corner in front of building due to water/puddling issues. 8/29/22 ES There are some concerns about the elevations of curb/paving in front of building. Specifically the amount of slope that will be required if ADA parking stalls are installed where shown on plans as there is too much fall from the doorway/building out to the parking areas. Glynn was going to pass along information up his chain of command and I will speak with Sue about it from our side. 8/29/22 ES All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES
Driveway Inspection Partial 09/28/2022
Misc
Informational
09/28/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES
Sidewalk Inspection Partial 09/28/2022
Misc
Informational
09/28/2022
All American construction onsite had setup sidewalk in front of building. with chalk line set for the ramps to come down for ADA access. 9/28/22 ES
Pavement-Curb Construction Partial 09/29/2022
Misc
Informational
09/28/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American construction onsite working on curbing and digging out approach area for driveway. 9/29/22am ES
Sprinkler - Hydrostatic Test Passed 9/30/2022 09/30/2022
Commercial Curb Inspection Partial 09/30/2022
Misc
Informational
09/28/2022
Phoenix concrete began installing their stakes and guide string for curbs. 8/26/22 ES Phoenix concrete began pouring curbs using KCMMB concrete. Left front of building and hand pour areas to complete as well as NW corner in front of building due to water/puddling issues. 8/29/22 ES There are some concerns about the elevations of curb/paving in front of building. Specifically the amount of slope that will be required if ADA parking stalls are installed where shown on plans as there is too much fall from the doorway/building out to the parking areas. Glynn was going to pass along information up his chain of command and I will speak with Sue about it from our side. 8/29/22 ES All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on final setup on curbs coming to Blue Pkwy. 9/30/22am ES
Driveway Inspection Partial 09/30/2022
Misc
Informational
09/28/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES
Sidewalk Inspection Partial 09/30/2022
Misc
Informational
09/28/2022
All American construction onsite had setup sidewalk in front of building. with chalk line set for the ramps to come down for ADA access. 9/28/22 ES All American poured concrete in front of building with flat ramp entrance coming in from ADA spots to west of entryway. 9/30/22 ES
Erosion Control Inspection Residential Partial 10/03/2022
Misc
Informational
09/26/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES
Driveway Inspection Partial 10/03/2022
Misc
Informational
09/30/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES All American working on driveway approach. Also started pouring parking lot area between parking lot and back lot. 10/3/22am ES
Driveway Inspection Partial 10/03/2022
Misc
Informational
10/03/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES All American working on driveway approach. Also started pouring parking lot area between parking lot and back lot. 10/3/22am ES Lyle’s crew working on driveway approach/apron coming off of Blue Pkwy. Pouring just front portion and will complete 10/5. Attempted multiple times to reach out to Nathan Juliana with MODOT for any requirements they might want to see with no response. 10/3/22 ES
Driveway Inspection Partial 10/04/2022
Misc
Informational
10/03/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES All American working on driveway approach. Also started pouring parking lot area between parking lot and back lot. 10/3/22am ES Lyle’s crew working on driveway approach/apron coming off of Blue Pkwy. Pouring just front portion and will complete 10/5. Attempted multiple times to reach out to Nathan Juliana with MODOT for any requirements they might want to see with no response. 10/3/22 ES Spoke with Nathan Juliana this morning, he was going to look at the approach where it came out to Blue Pkwy. 10/4/22 ES
Commercial Curb Inspection Partial 10/04/2022
Misc
Informational
09/30/2022
Phoenix concrete began installing their stakes and guide string for curbs. 8/26/22 ES Phoenix concrete began pouring curbs using KCMMB concrete. Left front of building and hand pour areas to complete as well as NW corner in front of building due to water/puddling issues. 8/29/22 ES There are some concerns about the elevations of curb/paving in front of building. Specifically the amount of slope that will be required if ADA parking stalls are installed where shown on plans as there is too much fall from the doorway/building out to the parking areas. Glynn was going to pass along information up his chain of command and I will speak with Sue about it from our side. 8/29/22 ES All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on final setup on curbs coming to Blue Pkwy. 9/30/22am ES Lyle's crew had formed up curbing and flume on SW corner of building. 10/4/22 ES
Driveway Inspection Partial 10/04/2022
Misc
Informational
10/04/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES All American working on driveway approach. Also started pouring parking lot area between parking lot and back lot. 10/3/22am ES Lyle’s crew working on driveway approach/apron coming off of Blue Pkwy. Pouring just front portion and will complete 10/5. Attempted multiple times to reach out to Nathan Juliana with MODOT for any requirements they might want to see with no response. 10/3/22 ES Spoke with Nathan Juliana this morning, he was going to look at the approach where it came out to Blue Pkwy. 10/4/22 ES Met with Lyle onsite, they will be pouring concrete drive approach and flume coming off of SW side of lot tomorrow morning. 10/4/22 ES
Driveway Inspection Partial 10/05/2022
Misc
Informational
10/04/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES All American working on driveway approach. Also started pouring parking lot area between parking lot and back lot. 10/3/22am ES Lyle’s crew working on driveway approach/apron coming off of Blue Pkwy. Pouring just front portion and will complete 10/5. Attempted multiple times to reach out to Nathan Juliana with MODOT for any requirements they might want to see with no response. 10/3/22 ES Spoke with Nathan Juliana this morning, he was going to look at the approach where it came out to Blue Pkwy. 10/4/22 ES Met with Lyle onsite, they will be pouring concrete drive approach and flume coming off of SW side of lot tomorrow morning. 10/4/22 ES Lyle's crew pouring remainder of concrete driveway approach. 10/5/22 ES
Site Visit Partial 10/07/2022
Misc
Informational
09/27/2022
No work being completed. 3/28/22 ES
Misc
Informational
09/27/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
09/27/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
09/27/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
09/27/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
09/27/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
09/27/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
09/27/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
09/27/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
09/27/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
09/27/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
09/27/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
09/27/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
09/27/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
09/27/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
09/27/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
09/27/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES
Erosion Control Inspection Residential Partial 10/11/2022
Misc
Informational
10/03/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES
Site Visit Partial 10/11/2022
Misc
Informational
10/07/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/07/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/07/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/07/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/07/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/07/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/07/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/07/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/07/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/07/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/07/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/07/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/07/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/07/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/07/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/07/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/07/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES
Pavement-Stabilized Subgrade Partial 10/11/2022
Misc
Informational
08/29/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES Electricians cut through subgrade and base rock for main power and light pole power. Spoke with Mr. Bridwell and informed him we would need to have those trenches brought back to grade with all type 5 rock compacted in lifts or flowable fill as to not leave a washboard parking lot from trenching. 8/25/22 ES Electrical trenches were backfilled with AB3 and compacted. 8/26/22 ES Phoenix had to raise some areas of subgrade around building to get it to correct depth. 8/27/22 ES Linaweaver working on raising grade for pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES
Grading/Excavation/Fill Inspection Partial 10/11/2022
Misc
Informational
08/23/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES Linaweaver working on raising grade of pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES
Grading/Excavation/Fill Inspection Partial 10/12/2022
Misc
Informational
10/11/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES Linaweaver working on raising grade of pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES
Pavement-Stabilized Subgrade Partial 10/12/2022
Misc
Informational
10/11/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES Electricians cut through subgrade and base rock for main power and light pole power. Spoke with Mr. Bridwell and informed him we would need to have those trenches brought back to grade with all type 5 rock compacted in lifts or flowable fill as to not leave a washboard parking lot from trenching. 8/25/22 ES Electrical trenches were backfilled with AB3 and compacted. 8/26/22 ES Phoenix had to raise some areas of subgrade around building to get it to correct depth. 8/27/22 ES Linaweaver working on raising grade for pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES
Pavement-Proof Roll Partial 10/12/2022 (10:00) 10/12/2022 10/14/2022
Misc
Informational
10/14/2022
Proof roll was performed with PSI onsite for 3rd party testing. 10/14/22 ES
Site Visit Partial 10/14/2022
Misc
Informational
10/11/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/11/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/11/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/11/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/11/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/11/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/11/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/11/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/11/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/11/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/11/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/11/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/11/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/11/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/11/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/11/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/11/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES
Grading/Excavation/Fill Inspection Partial 10/14/2022
Misc
Informational
10/12/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES Linaweaver working on raising grade of pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES Linaweaver onsite grading areas and hauling off excess materials. 10/14/22 ES
Pavement-Surface Partial 10/17/2022
Misc
Informational
10/17/2022
Updike paving was onsite this morning and began laying base asphalt today. 10/17/22am ES
Sanitary Sewer Construction Inspection Partial 10/18/2022
Misc
Informational
08/23/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
08/23/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
08/23/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
08/23/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Misc
Informational
08/23/2022
Glynn’s concrete crew poured the approach back for business across the street. 7/20/22 ES Spoke with Richard about getting area around drive across street backfilled. He said once his skid steer was delivered later today they would work on it. 8/8/22 ES Linaweaver working on cutting clean outs down to grade in parking lot areas. 8/23/22 ES Asphalt crew hit and broke one of the cleanout pipes near SE corner of building. Linaweaver crew on site replacing that cleanout pipe and cleaning debris from inside line. 10/18/22 ES
Pavement-Surface Partial 10/18/2022
Misc
Informational
10/17/2022
Updike paving was onsite this morning and began laying base asphalt today. 10/17/22am ES Updike asphalt completed base asphalt on 10/17. Will return on 10/20 to complete surface once temps increase. 10/18/22 ES
Erosion Control Inspection Residential Partial 10/19/2022
Misc
Informational
10/11/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES
Site Visit Partial 10/20/2022
Misc
Informational
10/14/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/14/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/14/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/14/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/14/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/14/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/14/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/14/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/14/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/14/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/14/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/14/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/14/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/14/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/14/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/14/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/14/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES
Pavement-Surface Passed 10/20/2022
Misc
Informational
10/18/2022
Updike paving was onsite this morning and began laying base asphalt today. 10/17/22am ES Updike asphalt completed base asphalt on 10/17. Will return on 10/20 to complete surface once temps increase. 10/18/22 ES
Misc
Informational
10/20/2022
On Thursday, 10-20-2022. Updike Asphalt layed surface type 2 recycle finish lift for parking lot. Tom Taylor completed the inspection. Base coarse lift was tacked before surface lift was placed.
Site Visit Partial 10/21/2022
Misc
Informational
10/20/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/20/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/20/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/20/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/20/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/20/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/20/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/20/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/20/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/20/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/20/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/20/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/20/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/20/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/20/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/20/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/20/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES Morgan Contracting was onsite today striping and marking ADA stalls. 10/21/22 ES
Above Ceiling Inspection Passed 10/27/2022 10/27/2022 10/27/2022
Electrical Service Inspection Passed 10/27/2022 10/27/2022 10/27/2022
Erosion Control Inspection Residential Partial 10/28/2022
Misc
Informational
10/19/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures are functioning. 10/25/22 ES
Site Visit Partial 10/28/2022
Misc
Informational
10/21/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/21/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/21/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/21/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/21/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/21/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/21/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/21/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/21/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/21/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/21/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/21/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/21/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/21/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/21/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/21/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/21/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES Morgan Contracting was onsite today striping and marking ADA stalls. 10/21/22 ES No site utility work being performed this week. Did speak with Glynn about vegetation issues and landscaping. 10/27/22
Gas Service Inspection - Commercial Passed 10/31/2022 10/31/2022 10/31/2022
Site Visit Partial 10/31/2022
Misc
Informational
10/28/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/28/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/28/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/28/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/28/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/28/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/28/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/28/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/28/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/28/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/28/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/28/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/28/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/28/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/28/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/28/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/28/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES Morgan Contracting was onsite today striping and marking ADA stalls. 10/21/22 ES No site utility work being performed this week. Did speak with Glynn about vegetation issues and landscaping. 10/27/22 No site utility work being performed. Building and rock work. 10/31/22 ES
Erosion Control Inspection Residential Partial 10/31/2022
Misc
Informational
10/28/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures are functioning. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES
Site Visit Partial 11/08/2022
Misc
Informational
10/31/2022
No work being completed. 3/28/22 ES
Misc
Informational
10/31/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
10/31/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
10/31/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
10/31/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
10/31/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
10/31/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
10/31/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
10/31/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
10/31/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
10/31/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
10/31/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
10/31/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
10/31/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
10/31/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
10/31/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
10/31/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES Morgan Contracting was onsite today striping and marking ADA stalls. 10/21/22 ES No site utility work being performed this week. Did speak with Glynn about vegetation issues and landscaping. 10/27/22 No site utility work being performed. Building and rock work. 10/31/22 ES No site utility work being performed. 11/7/22 ES
Erosion Control Inspection Residential Partial 11/08/2022
Misc
Informational
10/31/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures are functioning. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. 11/7/22 ES
Site Visit Partial 11/17/2022
Misc
Informational
11/08/2022
No work being completed. 3/28/22 ES
Misc
Informational
11/08/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
11/08/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
11/08/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
11/08/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
11/08/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
11/08/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
11/08/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
11/08/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
11/08/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
11/08/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
11/08/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
11/08/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
11/08/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
11/08/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
11/08/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
11/08/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES Morgan Contracting was onsite today striping and marking ADA stalls. 10/21/22 ES No site utility work being performed this week. Did speak with Glynn about vegetation issues and landscaping. 10/27/22 No site utility work being performed. Building and rock work. 10/31/22 ES No site utility work being performed. 11/7/22 ES Crew poured concrete in front of dumpster pad area on 11/15, removing the heavy duty asphalt that was in place. 11/16/22 ES Spoke with Glynn about handicap parking signs. They will be installing these signs behind the sidewalk in green space between sidewalk and building. They know the bottom of the signs must be at least 5' from ground level. 11/17/22 ES
Commercial Curb Inspection Passed 11/18/2022
Misc
Informational
10/04/2022
Phoenix concrete began installing their stakes and guide string for curbs. 8/26/22 ES Phoenix concrete began pouring curbs using KCMMB concrete. Left front of building and hand pour areas to complete as well as NW corner in front of building due to water/puddling issues. 8/29/22 ES There are some concerns about the elevations of curb/paving in front of building. Specifically the amount of slope that will be required if ADA parking stalls are installed where shown on plans as there is too much fall from the doorway/building out to the parking areas. Glynn was going to pass along information up his chain of command and I will speak with Sue about it from our side. 8/29/22 ES All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on final setup on curbs coming to Blue Pkwy. 9/30/22am ES Lyle's crew had formed up curbing and flume on SW corner of building. 10/4/22 ES All curbing had been installed. 11/18/22 ES
Driveway Inspection Passed 11/18/2022
Misc
Informational
10/05/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American working on getting grade and aggregate in for drive approach coming off of Blue Pkwy. 9/30/22am ES All American working on driveway approach. Also started pouring parking lot area between parking lot and back lot. 10/3/22am ES Lyle’s crew working on driveway approach/apron coming off of Blue Pkwy. Pouring just front portion and will complete 10/5. Attempted multiple times to reach out to Nathan Juliana with MODOT for any requirements they might want to see with no response. 10/3/22 ES Spoke with Nathan Juliana this morning, he was going to look at the approach where it came out to Blue Pkwy. 10/4/22 ES Met with Lyle onsite, they will be pouring concrete drive approach and flume coming off of SW side of lot tomorrow morning. 10/4/22 ES Lyle's crew pouring remainder of concrete driveway approach. 10/5/22 ES Driveway approach completed, meets LS spec. 11/18/22 ES
Pavement-Proof Roll Passed 11/18/2022
Misc
Informational
10/14/2022
Proof roll was performed with PSI onsite for 3rd party testing. 10/14/22 ES All paved surfaces in place. 11/18/22 ES
Pavement-Curb Construction Passed 11/18/2022
Misc
Informational
09/29/2022
All American construction onsite working on final curb sections at driveway approach off Blue Pkwy. Met with their foreman and Glynn to discuss the curb heights and the approach layout. 9/28/22 ES All American construction onsite working on curbing and digging out approach area for driveway. 9/29/22am ES All curbing along building, driveway and parking areas completed. 11/18/22 ES
Grading/Excavation/Fill Inspection Partial 11/18/2022
Misc
Informational
10/14/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES Linaweaver working on raising grade of pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES Linaweaver onsite grading areas and hauling off excess materials. 10/14/22 ES Site grading was completed and sprinkler system installed. Should be laying sod on 11/21/22. 11/18/22 ES
Pavement-Stabilized Subgrade Passed 11/18/2022
Misc
Informational
10/12/2022
Linaweaver onsite cutting grade on East and South sides of building preparing for cement treated subgrade on parking lots. 8/11/22 ES Linaweaver tilled in cement treatment for sub base. After treatment was applied and base compacted with sheeps foot then it was trimmed by dozer to grade. 8/17/22 ES Linaweaver spreading and compacting type 5 base for parking lot/curbs. 8/18/22 ES Linaweaver continuing to work on putting type 5 base down for parking lot/curbs. 8/19/22 ES Electricians cut through subgrade and base rock for main power and light pole power. Spoke with Mr. Bridwell and informed him we would need to have those trenches brought back to grade with all type 5 rock compacted in lifts or flowable fill as to not leave a washboard parking lot from trenching. 8/25/22 ES Electrical trenches were backfilled with AB3 and compacted. 8/26/22 ES Phoenix had to raise some areas of subgrade around building to get it to correct depth. 8/27/22 ES Linaweaver working on raising grade for pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES All paved areas are completed. 11/18/22 ES
Sanitary - Material Verification Passed 11/18/2022
Misc
Corrective Action Required
04/06/2022
Had sewer materials delivered. Have wyes for tie in on main and clean outs. Clean out caps, and pipe(all SDR26). Metal Sewer clean out rings and lids. Also had hard back furnco adapters, let Glynn know these would need to be replaced and use Max Adapters. 4/5/22 ES
Sanitary Sewer Construction Inspection Passed 11/18/2022
Misc
Informational
10/18/2022
Began sewer installation today on south side of roadway. Still waiting for traffic permit to make street crossing. 4/25/22 ES
Misc
Informational
10/18/2022
Continued sanitary line connection, got first 2 cleanouts installed. 4/26/22 ES
Misc
Informational
10/18/2022
Linaweaver completed the sanitary line up to where it will come out of the building pad. Now just need to get street crossing completed. Still waiting on traffic plan approval for closing 7th st to do this and water tie in. 4/27/22 ES
Misc
Informational
10/18/2022
Richard’s crew street cut 7th St and performed the sanitary wye installation and ran a stick of pipe off of the wye. 5/18/22 ES Richard’s crew completed sanitary line across 7th St and tied into where they began their line. Installed 2 - 45s and clean outs and remainder of pipe. 5/19/22 ES Richard’s crew poured flow fill into the area underneath 7th St. left about 8-10” of space to pour top cap in KCMMB concrete on Monday. Covered patch with street plates and placed cold patch around plates for transition. 5/20/22 ES
Misc
Informational
10/18/2022
Glynn’s concrete crew poured the approach back for business across the street. 7/20/22 ES Spoke with Richard about getting area around drive across street backfilled. He said once his skid steer was delivered later today they would work on it. 8/8/22 ES Linaweaver working on cutting clean outs down to grade in parking lot areas. 8/23/22 ES Asphalt crew hit and broke one of the cleanout pipes near SE corner of building. Linaweaver crew on site replacing that cleanout pipe and cleaning debris from inside line. 10/18/22 ES All sewer construction completed. 11/18/22 ES
Sidewalk Inspection Passed 11/18/2022
Misc
Informational
09/30/2022
All American construction onsite had setup sidewalk in front of building. with chalk line set for the ramps to come down for ADA access. 9/28/22 ES All American poured concrete in front of building with flat ramp entrance coming in from ADA spots to west of entryway. 9/30/22 ES Sidewalk in front of building completed. 11/18/22 ES
Storm - Material Verification Passed 11/18/2022
Misc
Informational
04/06/2022
Had 21 sticks of 8’ elliptical 14” concrete pipe delivered along with 2 end flanges. 4/6/22 ES Had 15" and 18" HDPE pipe, ADS detention basin system components installed along with concrete structures. 11/18/22 ES
Storm - Pipe Passed 11/18/2022
Misc
Informational
04/12/2022
4-7-22 AN spoke to contractor about concerns he had with the ditch south of the entrance and main drive (not getting12in rock on top of culvert) pic attached Ditch south of the drive - Try and get as much rock on top of culvert as possible and grade the dirt to eliminate the ditch where the culvert is but still allowing the water to flow to the east ditch and not toward the building. Culvert under drive - depending on the final grade of the drive they can either use flowable fill around the culvert and under the drive or if there is even less clearance between the pipe and drive they can encase the culvert in concrete.
Misc
Informational
04/12/2022
4-11-22AN contractor is going to use digable flowable fill around the culvert on 4-12
Misc
Informational
04/12/2022
Contractor put 8 yds of flowable fill on top and sides of pipe across where entrance will be off of blue pkwy. 4/12/22 ES Storm pipe along Blue Pkwy was installed and holding. 11/18/22
Storm Sewer Construction Inspection Passed 11/18/2022
Misc
Informational
08/23/2022
Linaweaver exposed around existing storm manhole structure to prepare for construction. 5/2/22 ES
Misc
Informational
08/23/2022
Linaweaver started construction from existing storm structure. Encountered and 8” water line as they came out of structure. Will maintain 18” of clearance above that line with storm pipe. Put in a temporary connection to existing corrugated metal pipe in anticipation of rain. Will be pouring new floor and collar tomorrow morning. 5/3/22 ES
Misc
Informational
08/23/2022
Linaweaver had one stick of pipe in and poured collars around pipe going into storm structure. 5/4/22 ES
Misc
Informational
08/23/2022
Linaweaver continued construction on storm line. Was working towards making tie in into existing field inlet box. 5/9/22 ES Linaweaver had set box 1A and we’re going to work towards box 2 and 1B. Then pour collars tomorrow. 5/11/22 ES
Misc
Informational
08/23/2022
5-12-22 AN crew has two storm boxes installed and continuing to lay more pipe. 2 pics attached
Misc
Informational
08/23/2022
Richard’s crew worked on getting storm junction box 2 installed and ran from box 1A in preparation for underground detention basin install. 6/7/22 ES Richard’s crew working on inverts in boxes 1, 1A, 1B, also poured collars on South side of box 1A and North side of box 2. 6/8/22 ES Richard’s crew dug out pit to start ADS system install. 6/17/22 ES Richard’s crew working on detention basin. They got mats down and initial rock layer for farthest north chambers. 6/20/22 ES Richard’s crew waiting on nyloplast junction boxes and end cap to finish UGD basin install. Working on setting storm structure 3 and structure 5. 7/6/22 ES
Misc
Informational
08/23/2022
Richard’s crew back on site working on final portion of underground detention basin. Will be sitting box 3 and nyloplasts today and working towards box 4. 8/8/22 ES Linaweaver crew completed detention basin outside of a single connection from first basin to storm box 3. both nyloplasts installed and ready to begin working towards box 4. Linaweaver began construction of line coming from nyloplast at entry to underground detention basin going towards storm box 4. 8/10/22 ES Linaweaver completed construction of storm lines on east side of building including setting boxes 4 and 5. 8/10/22 ES Linaweaver poured collars and inverts, around and in storm boxes 3, 4, and 5. 8/11/22 ES Linaweaver getting measurements on storm inlets to make final adjustments. 8/22/22 ES Storm construction was completed and all inlet boxes adjusted. 11/18/22 ES
Water - Material Verification Passed 11/18/2022
Misc
Informational
11/18/2022
They had an 8x8x6" fusion epoxy coated tee, 6" gate valve, and epoxy coated fittings for their water tie in and connection to backflow vault. Had 6" C900 PVC pipe for fire line and a ductile stand pipe for riser coming into building. Also had a Kennedy hydrant with epoxy coated shoe delivered for the end of their fire line. Used poly for their domestic and irrigation lines after copper from main and 10' out back side of meter pit. 11/18/22 ES
Water Line - Coliform Test 1 Passed 11/18/2022
Misc
Informational
06/28/2022
Took first set of samples. 6/28/22 ES Delivered to Keystone labs 12pm. 6-28-22 ES There were failures on this line beyond the backflow due to contractor pulling from fire hydrant. Spoke with WU and the line is considered passed as we had 4 samples with passes at the public side of backflow vault. 11/18/22 ES
Water Line - Coliform Test 2 Passed 11/18/2022
Misc
Informational
06/30/2022
2nd set of samples taken and delivered to Keystone labs. 6/23/22 ES 2nd set had a fail on sample #2. 6/24/22 ES 2nd set of samples pulled in am of 6/29 and delivered to Keystone labs. 6/29/22 ES There were failures on this line beyond the backflow due to contractor pulling from fire hydrant. Spoke with WU and the line is considered passed as we had 4 samples with passes at the public side of backflow vault. 11/18/22 ES
Erosion Control Inspection Residential Passed 11/30/2022
Misc
Informational
11/08/2022
Erosion control measures still installed, intact and functioning. 7/5/22 ES Erosion control measures intact and functioning. 7/11/22 ES Erosion control measures intact and functioning 7/18/22 ES Erosion control measures intact and functioning. 8/2/22 ES Erosion control measures intact and functioning. 8/8/22 ES Erosion control measures intact and functioning. 8/15/22 ES Erosion control installed, intact, and functioning. 8/22/22 ES Erosion control installed, intact and functioning. 8/29/22 ES Erosion control installed, intact and functioning. 9/6/22 ES Erosion control installed, intact and functioning. 9/26/22 ES Erosion control measures installed, intact, and functioning. 10/3/22 ES Erosion control measures installed, intact, and functioning. 10/10/22 ES Erosion control measures installed, intact and functioning. 10/18/22 ES Rain event 10/24. Erosion control measures are functioning. 10/25/22 ES Erosion control measures installed, intact, and functioning. 10/31/22 ES Erosion control measures installed, intact, and functioning. 11/7/22 ES 11-30-22 No erosion control issues
Grading/Excavation/Fill Inspection Partial 11/30/2022
Misc
Informational
11/18/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES Linaweaver working on raising grade of pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES Linaweaver onsite grading areas and hauling off excess materials. 10/14/22 ES Site grading was completed and sprinkler system installed. Should be laying sod on 11/21/22. 11/18/22 ES 11-30-22 AN grading is completed and laying sod
Grading/Excavation/Fill Inspection Passed 11/30/2022
Misc
Informational
11/30/2022
Linaweaver onsite cutting grade and hauling excess material from job site. 8/10/22 ES Linaweaver onsite cutting grade and hauling excess material from job site. 8/11/22 ES Linaweaver spreading MoDot type 5 rock across parking lot for base. 8/18/22 ES Linaweaver onsite working on parking lot base again and hauling out excess dirt. 8/19/22 ES Linaweaver removing excess dirt/fill materials. 8/22/22 ES Linaweaver recutting swell on west side of building. 8/22/22 ES Linaweaver working on grading and backfilling areas outside of parking lot. 8/23/22 ES Linaweaver working on raising grade of pavement areas. Using AB3 and compacting with a roller. 10/11/22 ES Linaweaver completed rock grading. Glynn called to schedule proof roll at 10am tomorrow. 10/12/22 ES Linaweaver onsite grading areas and hauling off excess materials. 10/14/22 ES Site grading was completed and sprinkler system installed. Should be laying sod on 11/21/22. 11/18/22 ES 11-30-22 AN grading is completed and laying sod
Site Visit Complete 11/30/2022
Misc
Informational
11/17/2022
No work being completed. 3/28/22 ES
Misc
Informational
11/17/2022
Site and foundation grading continues. Spoke with Glynn about entrance off of Blue Pkwy. They will be installing their permanent culvert instead of temporary pipes under construction entrance. 4/4/22 ES
Misc
Informational
11/17/2022
Site grading continues. Survey stakes appeared to be wrong and grading was taking place across property line. Glynn working with surveyor for correction. Had sewer and water materials delivered. 4/5/22 ES
Misc
Informational
11/17/2022
Site grading and swell construction continued. Plans show swell on adjacent property. 4/5/22 ES
Misc
Informational
11/17/2022
No work being done. 4/13/22 ES Building site grading being done. Waiting for testing proctor for building sub base stabilization. Also had plans resubmitted for change in storm swell and inlet location. 4/14/22 ES
Misc
Informational
11/17/2022
No work being performed due to rain over weekend. 4/18/22 ES
Misc
Informational
11/17/2022
Began sub base stabilization on building pad site. 4/19/22 ES
Misc
Informational
11/17/2022
They did a building pad proof roll. No other construction happening. 4/22/22 ES
Misc
Informational
11/17/2022
Started sanitary sewer line construction. 4/25/22 ES
Misc
Informational
11/17/2022
Met with Glynn, they are continuing sanitary sewer construction. 4/26/22 ES
Misc
Informational
11/17/2022
Linaweaver was on-site doing some minor site grading prior to rain. No other utility work being performed. 4/28/22 ES
Misc
Informational
11/17/2022
No utility work being done today. 4/29/22 ES
Misc
Informational
11/17/2022
Linaweaver started construction on offsite storm line on NE corner. 5/3/22 ES
Misc
Informational
11/17/2022
5/5/-5/6 no utility work being done due to rain. 5/6/22 ES
Misc
Informational
11/17/2022
Linaweaver working on storm lines. 5/9/22 ES Linaweaver worked on storm lines. 5/11/22 ES Linaweaver crew working on sewer street crossing. 5/18/22 ES Linaweaver crew working on sewer street crossing. 5/19/22 ES Linaweaver crew working on backfilling and flow filled across street. 5/20/22 ES Linaweaver crew was pouring KCMMB 4K concrete 8-10” thick across 7th street spanning 12” outside their full depth dig area. 5/23/22 ES Linaweaver crew saw cut street and dug to expose water main to get prepped for fire line and service connections. 5/25/22 ES Linaweaver crew performed fire line tie in late night 5/27/22 ES No construction work today with rain storms. 5/31/22 ES Linaweaver crew was onsite to get hole ready for water taps. Water performed 2 - 1” water taps. 6/1/22 ES Linaweaver crew was onsite working on service/irrigation lines. 6/2/22 ES Linaweaver crew working on fire line, meter pits and running tracer wire. 6/3/22 ES Linaweaver crew working on fire line and final setting on meters. 6/6/22 ES Linaweaver crew working on setting storm structure in preparation for starting underground detention basin. 6/7/22 ES Linaweaver crew working on inverts and collars on storm boxes and waiting on vault for fire line to be delivered. 6/8/22 ES Linaweaver had backflow vault for fire line delivered. 6/8/22 ES Linaweaver was working on setting backflow pit for fire lines. 6/9/22 ES Linaweaver continued working on fire line. 6/10/22 ES Linaweaver working on backfilling fire line and installed a 6” cap with a 2” blowoff assembly for building fire line after tee. 6/13/22 ES Linaweaver working on fire line. 6/14/22 ES Linaweaver working on fire line and concrete crew working on footings and pillars. 6/15/22 ES Linaweaver hydrostatic tested fire line and chlorinated. Concrete crew working on footing and pillars. 6/16/22 ES Linaweaver backfilled fire stand pipe, starting digging pit for underground detention system. 6/17/22 ES Linaweaver flushed fire line and dechlorinated water in process. Will take samples tomorrow. Also working on ADS detention system. Got mats and first part of rock layer laid. 6/20/22 ES Collected water samples from fire line, and looked at detention basin design issues. 6/21/22a.m. ES Spoke to Glen about driveway approach across from Job site where sanitary sewer tied in. It was settled with area marked out what will be replaced by contractor. Letter to Glen will be needed from city to progress. Pending pour will be next week Tuesday. 6-28-22 ES Evergy was onsite today setting 1 power pole. Linaweaver and concrete crew not on site due to rain. 7/7/22 ES No utility work being completed today. 7/8/22 ES No utility work being done(AM). Concrete crew working on rock base for pad site. 7/11/22 ES No utility work being done. Concrete crew putting down moisture barrier and rebar on pad site. Spoke with Glynn about getting the approach poured for the irrigation business on 7th Terr. Told him we needed that completed by end of week. Said he would likely get it done Friday. 7/12/22 ES
Misc
Informational
11/17/2022
Concrete crew finished pouring slab and working on finishing. No utility work being done. 7/14/22 ES Concrete crew pulling forms from slab. Spoke with Glynn again about pouring adjacent approach, they called it off today due to rain. Will be pouring 1pm on Monday 7/19. 7/15/22 ES Concrete crew working on slab, also spoke with Glynn. They still plan on pouring the approach around 1pm. Concrete crew had issues and did not get approach poured today. Glynn states they will be back out to pour it tomorrow. 7/18/22 ES Concrete crew had approach torn out and framed back up with aggregate in and compacted. Ready to pour. 7/19/22 ES Concrete approach poured 7/20/22. Spoke with Glynn about getting relieve joints cut in. 7/22/22 ES No utility work being done. Concrete crew onsite working around pad, and did cut joints into approach for irrigation company. 7/26/22 ES
Misc
Informational
11/17/2022
No utility work being done, building work only. Spoke with Glynn about getting area around lawn care business approach backfilled and done. 8/2/22 ES No utility work being done. Building pad/site being worked on. 8/3/22 ES No utility work being done. Building pad/site being worked on. 8/4/22 ES No utility work being done. Building work continues. 8/15/22 ES No work being done due to rain. 8/16/22 ES No utility work being done, building work only. 9/6/22 ES No utility work being done. 9/7/22 ES No utility work being done. 9/8/22 ES Building work only. 9/9/22ES No utility work needing inspected. 9/12/22 ES No utility work only building. 9/13/22 ES Only building work. Glynn doesn’t believe they will be doing the asphalt parking lot next week as planned. 9/14/22 ES Spoke with Glynn, no work for me to inspect. Expects Linaweaver to be onsite early next week for aggregate base buildup and grading for parking lot. 9/16/22 ES No work for me to inspect. Linaweaver should be out this week to complete aggregate base for parking lot. 9/26/22 ES No utility work being performed. 9/27/22 ES Only building work being completed today. 10/7/22 ES No utility work being done requiring inspection. 10/10/22 ES Met with Glynn, they will be looking to lay asphalt on Monday. 10/14/22 ES No site utility work being done today. 10/19/22 ES Morgan Contracting was onsite today striping and marking ADA stalls. 10/21/22 ES No site utility work being performed this week. Did speak with Glynn about vegetation issues and landscaping. 10/27/22 No site utility work being performed. Building and rock work. 10/31/22 ES No site utility work being performed. 11/7/22 ES Crew poured concrete in front of dumpster pad area on 11/15, removing the heavy duty asphalt that was in place. 11/16/22 ES Spoke with Glynn about handicap parking signs. They will be installing these signs behind the sidewalk in green space between sidewalk and building. They know the bottom of the signs must be at least 5' from ground level. 11/17/22 ES.
Water Service Inspection Passed 11/30/2022
Misc
Informational
07/07/2022
Richard’s crew was onsite getting hole ready for water taps. 6/1/22 ES Water performed 2 - 1” taps using 12” clamps with outlets. 6/1/22 ES Richard’s crew was working on running copper from main, didn’t have survey stakes set for meter pits. 6/2/22 ES Richard’s crew was working on running copper from main to meter setups, also running 10’ copper out of meter pits. 6/3/22 ES Richard’s crew filled over pipe and services with gravel. Then filled under roadway with flowable fill. 6/6/22 ES Glynn’s concrete crew poured the street patch and curb back where the fire line and water service tie ins were done. 7/5/22 ES.
ESC - (Vegetation/Ground Cover) Partial 11/30/2022
Misc
Informational
11/30/2022
11-30-22 AN crew is laying sod
ESC - (Vegetation/Ground Cover) Passed 12/02/2022
Misc
Informational
11/30/2022
11-30-22 AN crew is laying sod 12-2-22 AN sod is down and matting
Occupancy Inspection - Engineering Temporary C of O 12/02/2022
Misc
Informational
12/02/2022
12-2-22 AN development is good for TCO Needed for final 1. Fix ruts side of building 2. check for seed to germinate in the spring where the grass mating is
Footing Inspection - Commercial Passed 9/14/2022 (8:00) 12/02/2022
THE FOLLOWING AREAS ARE APPROVED
Resolved
12/02/2022
-MAIN BUILDING FOOTING AND PIER PADS COMPLETE -PAINT BOOTH SLAB -STEM WALL AT PAINT BOOTH - 9/9/22 FOOTING TRASH ENCLOSURE PER PLAN -
In-wall Inspection Passed 12/02/2022
Misc
Resolved
12/02/2022
- 9/9/22 OFFICE AREA METAL STUD, ELECTRICAL, PLUMBING OK TO COVER -
Rated Assembly Inspection Passed 12/02/2022
Misc
Resolved
12/02/2022
-Verified rated plywood at exterior walls
Misc
Resolved
12/02/2022
-Extend wall to deck above on all sides and complete screw pattern and drywall
Underground Electrical Inspection - Commercial Passed 12/02/2022
Miscellaneous Correction
Resolved
12/02/2022
Secondary conduit from transformer to building and conduit for data
Underslab Plumbing Inspection - Commercial Passed 12/02/2022
THE FOLLOWING AREAS ARE APPROVED
Resolved
12/02/2022
DWV AT 114,103,107,109, 100, 112,113
Miscellaneous Correction
Resolved
12/02/2022
-PROVIDE CLEAN OUT AT EAST EXTERIOR CHANGE OF DIRECTION
Alarm Test Passed 12/6/2022 12/06/2022
Sprinkler - Flow Test Passed 12/6/2022 12/06/2022
Corrective Action Required
12/06/2022
Label Sprinkler Room Door Tag Sprinkler system.
Occupancy Inspection - Codes Commercial Failed 12/8/2022 12/8/2022 12/08/2022
Miscellaneous Correction
Corrective Action Required
12/08/2022
-Complete corrections for all other departments -Provide address -Open hand holes at light poles for inspection -Label RTUs -Provide cover plates and box extensions at reception desk -Label panels -Label disconnect at compressor
Occupancy Inspection - Fire Passed 12/14/2022 12/14/2022 12/14/2022
Corrective Action Required
12/14/2022
All life safety was appropriate. Okay to occupy with the approval form codes.
Occupancy Inspection - Codes Commercial Ready for Temp CO 12/14/2022 12/14/2022 12/14/2022
Miscellaneous Correction
Corrective Action Required
12/08/2022
-Complete corrections for all other departments -Complete awnings
Occupancy Inspection - Codes Commercial Temporary C of O 12/14/2022
Miscellaneous Correction
Corrective Action Required
12/14/2022
-Complete corrections for all other departments -Complete awnings
Occupancy Inspection - Engineering Temporary C of O 12/15/2022
Misc
Informational
12/02/2022
12-2-22 AN development is good for TCO Needed for final 1. Fix ruts side of building---- ruts fixed 2. check for seed to germinate in the spring where the grass mating is
Miscellaneous Correction
Corrective Action Required
12/15/2022
12-15-22 AN 1. NEED AS BUILTS OF THE OUTLET STRUCTURES FOR THE BASIN 2. check for seed to germinate in the spring where the grass mating is
Occupancy Inspection - Codes Commercial Ready for Temp CO 1/13/2023 01/13/2023
Miscellaneous Correction
Corrective Action Required
12/14/2022
-Complete corrections for all other departments -Codes complete
Occupancy Inspection - Codes Commercial Full C of O 01/20/2023
Documents & Images
Date Uploaded File Type Document Name
12/16/2021 Approved Plans Commercial Permit Application 12-16-21 signed
12/16/2021 Specifications 00_Caliber Collision_Lees Summit, MO_Specifications
12/16/2021 Engineer Report/Study Geotechnical Report
12/16/2021 Plans Lees Summit, MO Permit Set
12/17/2021 Letter Fire Building Plan Review
12/21/2021 Letter DS P/R Corrections Document
01/31/2022 Letter Review Comment Responses
01/31/2022 Plans metal building 71872 RevA Permit
01/31/2022 Plans Lees Summit, MO Revision 1
01/31/2022 Letter 2022-01-30 Revision 1 Verbiage
02/01/2022 Letter Fire Building Plan Review
02/01/2022 Plans - Lees Summit, MO Revision 1
02/01/2022 Plans - 71872 RevA Permit
02/02/2022 Engineer Report/Study Caliber Collision - Lee's Summit
02/25/2022 Plans 71872 RevA Permit
02/25/2022 Plans 71872 ABolt Rev0
02/25/2022 Engineer Report/Study 71872 LOC
02/25/2022 Letter 2022-02-07 Revision 1 Verbiage
02/25/2022 Plans 2022-02-07 Lees Summit, MO Revision 1
04/05/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/07/2022 Letter INSPECTION SUMMARY
04/07/2022 Letter INSPECTION SUMMARY
04/07/2022 Culvert at main entrance
04/11/2022 Letter INSPECTION SUMMARY
04/18/2022 Letter INSPECTION SUMMARY
04/20/2022 Letter INSPECTION SUMMARY
04/05/2022 Letter INSPECTION SUMMARY
05/04/2022 Letter Fire (Alarm) Plan Review Notice
05/04/2022 Caliber Collision-0000-Lees Summit-MO-FA-J02-04132022-FA-1 (30X42)-stamped
05/04/2022 Caliber Collision-0000-Lees Summit-MO-FA-J02-04132022-SUBBOOK
03/28/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter License Tax Bill
03/14/2022 Letter INSPECTION SUMMARY
03/07/2022 Approved Plans approved - 71872 RevA Permit0
03/07/2022 Approved Plans approved - 71872 ABolt Rev0
03/07/2022 Approved Plans approved - 2022-02-07 Lees Summit, MO Revision 1
02/23/2022 Approved Plans Approved FDP_Caliber Collision_021722_SITE DEVELOPMENT PLANS_REV1_REV4_2022-0208
03/04/2022 Letter DS Building Permit
04/28/2022 Letter INSPECTION SUMMARY
04/28/2022 Letter INSPECTION SUMMARY
04/26/2022 Letter INSPECTION SUMMARY
04/26/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
04/19/2022 Approved Plans Caliber_Approved FDP REV 041922_SITE DEVELOPMENT PLAN_2022-0414
05/27/2022 Letter INSPECTION SUMMARY
05/27/2022 Letter INSPECTION SUMMARY
05/31/2022 Letter INSPECTION SUMMARY
05/31/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/12/2022 Letter INSPECTION SUMMARY
05/03/2022 Letter INSPECTION SUMMARY
05/03/2022 Letter INSPECTION SUMMARY
06/03/2022 Letter INSPECTION SUMMARY
06/03/2022 Letter INSPECTION SUMMARY
06/03/2022 Letter INSPECTION SUMMARY
06/03/2022 Letter INSPECTION SUMMARY
06/03/2022 Letter INSPECTION SUMMARY
05/03/2022 Letter INSPECTION SUMMARY
04/29/2022 Letter INSPECTION SUMMARY
05/09/2022 Letter INSPECTION SUMMARY
05/09/2022 Letter INSPECTION SUMMARY
05/09/2022 Letter INSPECTION SUMMARY
05/12/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/11/2022 Letter License Tax Bill
05/12/2022 Letter INSPECTION SUMMARY
05/12/2022 Middle MH
05/12/2022 Field Inlet structure
05/12/2022 Letter INSPECTION SUMMARY
05/12/2022 Existing offsite NE manhole - new pipe collar
05/12/2022 Letter INSPECTION SUMMARY
06/02/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/23/2022 Letter INSPECTION SUMMARY
05/24/2022 Letter INSPECTION SUMMARY
06/02/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/02/2022 Letter INSPECTION SUMMARY
06/02/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/09/2022 Letter INSPECTION SUMMARY
06/09/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/22/2022 (stamped) Caliber Collision - Calculations
06/22/2022 (stamped) Caliber Collision-FP1
06/22/2022 Letter Fire (Sprinkler) Plan Review
06/23/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/17/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
07/05/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
06/22/2022 Letter INSPECTION SUMMARY
07/08/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
06/22/2022 Letter INSPECTION SUMMARY
07/12/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter INSPECTION SUMMARY
06/27/2022 (stamped) Caliber Collision Rev1 FP1
07/18/2022 Letter INSPECTION SUMMARY
07/18/2022 Letter INSPECTION SUMMARY
06/24/2022 Letter INSPECTION SUMMARY
07/19/2022 Letter INSPECTION SUMMARY
06/24/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
07/20/2022 Letter INSPECTION SUMMARY
06/27/2022 Letter Fire (Sprinkler) Plan Review
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
07/26/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
06/21/2022 Letter INSPECTION SUMMARY
08/03/2022 Letter INSPECTION SUMMARY
08/03/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
06/22/2022 Letter INSPECTION SUMMARY
08/08/2022 Letter INSPECTION SUMMARY
08/08/2022 Letter INSPECTION SUMMARY
08/08/2022 Letter INSPECTION SUMMARY
08/10/2022 Letter INSPECTION SUMMARY
08/10/2022 Letter INSPECTION SUMMARY
08/10/2022 Letter INSPECTION SUMMARY
08/10/2022 Letter INSPECTION SUMMARY
08/10/2022 Letter INSPECTION SUMMARY
06/22/2022 Letter INSPECTION SUMMARY
07/11/2022 Letter INSPECTION SUMMARY
07/14/2022 Letter INSPECTION SUMMARY
07/15/2022 Letter INSPECTION SUMMARY
07/18/2022 Letter INSPECTION SUMMARY
06/27/2022 Letter INSPECTION SUMMARY
06/27/2022 Letter INSPECTION SUMMARY
06/27/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/28/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
07/01/2022 Letter INSPECTION SUMMARY
07/20/2022 Receipt Receipt for transaction: 2022-005918
07/05/2022 Letter INSPECTION SUMMARY
07/06/2022 Letter INSPECTION SUMMARY
07/06/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
07/07/2022 Letter INSPECTION SUMMARY
07/08/2022 Letter INSPECTION SUMMARY
08/26/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
09/07/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/16/2022 Letter INSPECTION SUMMARY
08/16/2022 Letter INSPECTION SUMMARY
08/17/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
07/22/2022 Letter INSPECTION SUMMARY
07/27/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
08/02/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
08/02/2022 Letter INSPECTION SUMMARY
09/19/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
09/26/2022 Letter INSPECTION SUMMARY
09/26/2022 Letter INSPECTION SUMMARY
09/27/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
08/11/2022 Letter INSPECTION SUMMARY
09/08/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/08/2022 Letter INSPECTION SUMMARY
09/30/2022 Letter INSPECTION SUMMARY
09/30/2022 Letter INSPECTION SUMMARY
09/30/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
10/03/2022 Letter INSPECTION SUMMARY
09/08/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
09/09/2022 Letter INSPECTION SUMMARY
10/05/2022 Letter INSPECTION SUMMARY
10/07/2022 Letter INSPECTION SUMMARY
08/17/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
10/12/2022 Letter INSPECTION SUMMARY
10/12/2022 Letter INSPECTION SUMMARY
10/12/2022 Letter INSPECTION SUMMARY
10/14/2022 Letter INSPECTION SUMMARY
10/14/2022 Letter INSPECTION SUMMARY
10/14/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
08/19/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
10/21/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
10/28/2022 Letter INSPECTION SUMMARY
10/28/2022 Letter INSPECTION SUMMARY
10/31/2022 Letter INSPECTION SUMMARY
10/31/2022 Letter INSPECTION SUMMARY
10/31/2022 Letter INSPECTION SUMMARY
08/23/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
11/17/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
08/25/2022 Letter INSPECTION SUMMARY
09/08/2022 Letter INSPECTION SUMMARY
09/29/2022 Letter INSPECTION SUMMARY
10/04/2022 Letter INSPECTION SUMMARY
10/04/2022 Letter INSPECTION SUMMARY
10/04/2022 Letter INSPECTION SUMMARY
10/11/2022 Letter INSPECTION SUMMARY
09/13/2022 Letter INSPECTION SUMMARY
10/17/2022 Letter INSPECTION SUMMARY
09/14/2022 Letter INSPECTION SUMMARY
09/15/2022 Letter INSPECTION SUMMARY
09/16/2022 Letter INSPECTION SUMMARY
09/22/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
10/18/2022 Letter INSPECTION SUMMARY
10/19/2022 Letter INSPECTION SUMMARY
10/20/2022 Letter INSPECTION SUMMARY
10/20/2022 Letter INSPECTION SUMMARY
10/27/2022 Letter INSPECTION SUMMARY
10/27/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/08/2022 Letter INSPECTION SUMMARY
11/08/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 CC water line kicker ticket
11/18/2022 CC - Fire line bldg tee 2
11/18/2022 CC Water line tie in 2
11/18/2022 CC - Storm box 4 b
11/18/2022 CC Water line tie in BFV 3
11/18/2022 CC Storm box 1 a
11/18/2022 CC Water line tie in BFV 7
11/18/2022 CC - Storm box 4 a
11/18/2022 CC Water line tie in BFV 4
11/18/2022 CC - Storm box 5 a
11/18/2022 CC Storm line 1 c
11/18/2022 CC Storm line 1 b
11/18/2022 CC Water Taps
11/18/2022 CC Storm box 1A 2
11/18/2022 CC Storm box 1 c
11/18/2022 CC Storm box 2 b
11/18/2022 CC entry storm pipe 1
11/18/2022 CC Storm box 1 b
11/18/2022 CC Water line tie in BFV 2
11/18/2022 CC entry storm pipe 3
11/18/2022 CC entry storm pipe 2
11/18/2022 CC entry storm pipe 5
11/18/2022 CC entry storm pipe 4
11/18/2022 CC - Fire line 2
11/18/2022 ADS nyloplast 2
11/18/2022 CC - Fire line
11/18/2022 ADS Fabric
11/18/2022 Existing drive 1
11/18/2022 ADS Fabric 2
11/18/2022 CC - existing Storm structure 2
11/18/2022 CC - SS Connection 3
11/18/2022 ADS UGDB 13
11/18/2022 Letter INSPECTION SUMMARY
11/18/2022 CC - KCMMB ticket 7th st
11/18/2022 CC - Flow fill over water tie ins
11/18/2022 CC - Storm box 4 c
11/18/2022 CC - Fire line bldg tee
11/18/2022 CC - Storm box 5 b
11/18/2022 CC - Storm box 5 c
11/18/2022 CC Storm box 1A 1
11/18/2022 ADS UGDB 1a
11/18/2022 Caliber Collision 6-22 Sample 3
11/18/2022 Caliber Collision 6-28 Sample 2
11/18/2022 ADS UGDB 1
11/18/2022 Caliber Collision 6-21 Sample 2
11/18/2022 Caliber Collision 6-29 Sample 3
11/18/2022 CC Storm box 1B 1
11/18/2022 CC Storm box 1B 2
11/18/2022 CC Storm box 3
11/18/2022 CC Storm box 3a
11/18/2022 CC - Fire line 3
11/18/2022 CC Storm box 2 c
11/18/2022 Caliber Collision 6-21 Sample 1
11/18/2022 Caliber Collision 6-29 Sample 2
11/18/2022 Caliber Collision 6-22 Sample 2
11/18/2022 Caliber Collision 6-28 Sample 1
11/18/2022 CC - SS Connection 4
11/18/2022 ADS UGDB 12
11/18/2022 ADS nyloplast 4
11/18/2022 ADS UGDB 2
11/18/2022 ADS UGDB 11
11/18/2022 ADS nyloplast 3
11/18/2022 CC Fireline T - Dry block 3
11/18/2022 CC Fireline T - Dry block 4
11/18/2022 CC Storm box 2
11/18/2022 CC - Fire hydrant 2
11/18/2022 CC - Irrigation Backflow pit
11/18/2022 CC entry storm pipe 6
11/18/2022 CC Fireline T - Dry block 5
11/18/2022 CC Water line tie in 1
11/18/2022 ADS UGDB 10
11/18/2022 ADS Nyloplast 1
11/18/2022 CC - Fire hydrant 1
11/18/2022 CC Storm line 1 d
11/18/2022 ADS UGDB 6
11/18/2022 CC Fireline T - Dry block 1
11/18/2022 CC Water line tie in 3
11/18/2022 CC Fireline T - Dry block 2
11/18/2022 ADS UGDB 4
11/18/2022 ADS UGDB 3
11/18/2022 ADS UGDB 5
11/18/2022 CC - SS Connection 2
11/18/2022 ADS UGDB 8
11/18/2022 ADS UGDB 14
11/18/2022 CC - Fire line bldg 90
11/18/2022 CC - existing Storm structure
11/18/2022 ADS UGDB 7
11/18/2022 CC - existing Storm structure 3
11/18/2022 CC - SS Connection 1
11/18/2022 CC - Fire hydrant 3
11/18/2022 CC - SS Connection 5
11/18/2022 ADS UGDB 9
11/18/2022 CC Water line tie in BFV - Meter pits 2
11/18/2022 CC - SS Connection 6
11/18/2022 CC - SS Connection 7
11/18/2022 CC - SS Connection 8
11/18/2022 CC Water line tie in BFV - Meter pits 1
11/18/2022 CC Water line tie in BFV 1
11/18/2022 CC - SS Connection 9
11/18/2022 CC - SS Connection 10
11/18/2022 CC Water line tie in BFV 6
11/18/2022 ADS UGDB 15
11/18/2022 CC Water line tie in BFV 5
11/18/2022 CC Storm line 1 a
11/18/2022 CC - SS Fittings
11/18/2022 Existing drive 2
11/18/2022 Existing drive 3
11/18/2022 Existing drive 4
11/18/2022 Existing drive 5
11/18/2022 Existing drive 6
11/18/2022 Existing drive 7
11/18/2022 Existing drive 8
11/18/2022 Existing drive 9
11/18/2022 Existing drive 10
11/18/2022 Existing drive 11
11/18/2022 Existing drive 13
11/18/2022 Existing drive 14
11/18/2022 Storm repair from SS install
11/18/2022 Existing drive 12
11/18/2022 ADS nyloplast 5
11/18/2022 ADS Fabric 3
11/18/2022 ADS Fabric0
11/18/2022 ADS nyloplast 6
11/18/2022 ADS UGDB 16
11/18/2022 ADS UGDB 17
11/18/2022 ADS Nyloplast 7
11/18/2022 ADS UGDB 18
11/18/2022 ADS UGDB 19
11/18/2022 ADS nyloplast 8
11/18/2022 ADS UGDB 1a0
11/18/2022 ADS UGDB 20
11/18/2022 ADS UGDB 21
11/18/2022 ADS UGDB 22
11/18/2022 ADS UGDB 23
11/18/2022 ADS UGDB 24
11/18/2022 ADS UGDB 25
11/18/2022 ADS UGDB 26
11/18/2022 ADS UGDB 27
11/18/2022 ADS UGDB 28
11/18/2022 ADS UGDB 29
11/18/2022 ADS UGDB 30
11/18/2022 CC - existing Storm structure 4
11/18/2022 CC - existing Storm structure 5
11/18/2022 CC - existing Storm structure0
11/18/2022 CC - Fire hydrant 4
11/18/2022 CC - Fire hydrant 5
11/18/2022 CC - Fire line 4
11/18/2022 CC - Fire line bldg 91
11/18/2022 CC - KCMMB ticket 7th st0
11/18/2022 CC - Irrigation Backflow pit0
11/18/2022 CC - Flow fill over water tie ins0
11/18/2022 CC - SS Connection 11
11/18/2022 CC - Fire line bldg tee0
11/18/2022 CC - Fire hydrant 6
11/18/2022 CC - Fire line bldg tee 3
11/18/2022 CC - Fire line 5
11/18/2022 CC - Fire line0
11/18/2022 CC - SS Connection 12
11/18/2022 CC - SS Connection 13
11/18/2022 CC - Storm box 4 b0
11/18/2022 CC Fireline T - Dry block 6
11/18/2022 CC - Storm box 4 c0
11/18/2022 CC Fireline T - Dry block 7
11/18/2022 CC - SS Connection 14
11/18/2022 CC entry storm pipe 7
11/18/2022 CC Storm box 1B 3
11/18/2022 CC entry storm pipe 8
11/18/2022 CC - Storm box 5 b0
11/18/2022 CC entry storm pipe 9
11/18/2022 CC - SS Connection 15
11/18/2022 CC Fireline T - Dry block 8
11/18/2022 CC Fireline T - Dry block 9
11/18/2022 CC entry storm pipe 10
11/18/2022 CC - SS Connection 16
11/18/2022 CC - SS Connection 17
11/18/2022 CC entry storm pipe 11
11/18/2022 CC - SS Connection 18
11/18/2022 CC - SS Connection 19
11/18/2022 CC - Storm box 5 a0
11/18/2022 CC - Storm box 4 a0
11/18/2022 CC - SS Connection 20
11/18/2022 CC Storm box 2 b0
11/18/2022 CC Storm box 2 c0
11/18/2022 CC Storm box 1A 3
11/18/2022 CC Storm box 1 c0
11/18/2022 CC Storm box 4
11/18/2022 CC Storm box 3a0
11/18/2022 CC Storm line 1 b0
11/18/2022 CC Storm box 1A 4
11/18/2022 CC entry storm pipe 12
11/18/2022 CC Fireline T - Dry block 10
11/18/2022 CC Storm box 1B 4
11/18/2022 CC Storm box 1 b0
11/18/2022 CC Storm box 1 a0
11/18/2022 CC - Storm box 5 c0
11/18/2022 CC Storm line 1 c0
11/18/2022 CC water line kicker ticket0
11/18/2022 CC Water line tie in 4
11/18/2022 CC Water line tie in 5
11/18/2022 CC Water line tie in 6
11/18/2022 CC Water line tie in BFV - Meter pits 3
11/18/2022 CC Water line tie in BFV - Meter pits 4
11/18/2022 CC - SS Fittings0
11/18/2022 CC Storm box 5
11/18/2022 CC Storm line 1 a0
11/18/2022 CC Storm line 1 d0
11/21/2022 ADS UGDB 1a1
11/21/2022 Caliber Collision 6-22 Sample 4
11/21/2022 Caliber Collision 6-28 Sample 3
11/21/2022 ADS UGDB 31
11/21/2022 Caliber Collision 6-21 Sample 3
11/21/2022 Caliber Collision 6-29 Sample 4
11/21/2022 CC - KCMMB ticket 7th st1
11/21/2022 CC - Flow fill over water tie ins1
11/21/2022 CC - Storm box 4 c1
11/21/2022 CC - Fire line bldg tee1
11/21/2022 CC - Storm box 5 b1
11/21/2022 CC - Storm box 5 c1
11/21/2022 CC Storm box 1A 5
11/21/2022 CC Storm box 1B 5
11/21/2022 CC Storm box 1B 6
11/21/2022 CC Storm box 6
11/21/2022 CC Storm box 3a1
11/21/2022 CC - Fire line 6
11/21/2022 CC Storm box 2 c1
11/21/2022 CC water line kicker ticket1
11/21/2022 CC - Fire line bldg tee 4
11/21/2022 CC Water line tie in 7
11/21/2022 CC - Storm box 4 b1
11/21/2022 CC Water line tie in BFV 8
11/21/2022 CC Storm box 1 a1
11/21/2022 CC Water line tie in BFV 9
11/21/2022 CC - Storm box 4 a1
11/21/2022 CC Water line tie in BFV 10
11/21/2022 CC - Storm box 5 a1
11/21/2022 CC Storm line 1 c1
11/21/2022 CC Storm line 1 b1
11/21/2022 CC Water Taps0
11/21/2022 CC Storm box 1A 6
11/21/2022 CC Storm box 1 c1
11/21/2022 CC Storm box 2 b1
11/21/2022 CC entry storm pipe 13
11/21/2022 CC Storm box 1 b1
11/21/2022 CC Water line tie in BFV 11
11/21/2022 CC entry storm pipe 14
11/21/2022 CC entry storm pipe 15
11/21/2022 CC entry storm pipe 16
11/21/2022 CC entry storm pipe 17
11/21/2022 CC - Fire line 7
11/21/2022 ADS nyloplast 9
11/21/2022 CC - Fire line1
11/21/2022 ADS Fabric1
11/21/2022 Existing drive 15
11/21/2022 ADS Fabric 4
11/21/2022 CC - existing Storm structure 6
11/21/2022 CC - SS Connection 21
11/21/2022 ADS UGDB 32
11/21/2022 CC - SS Connection 22
11/21/2022 ADS UGDB 33
11/21/2022 ADS nyloplast 10
11/21/2022 ADS UGDB 34
11/21/2022 ADS UGDB 35
11/21/2022 ADS nyloplast 11
11/21/2022 CC Fireline T - Dry block 11
11/21/2022 CC Fireline T - Dry block 12
11/21/2022 CC Storm box 7
11/21/2022 CC - Fire hydrant 7
11/21/2022 CC - Irrigation Backflow pit1
11/21/2022 CC entry storm pipe 18
11/21/2022 CC Fireline T - Dry block 13
11/21/2022 CC Water line tie in 8
11/21/2022 ADS UGDB 36
11/21/2022 ADS Nyloplast 12
11/21/2022 CC - Fire hydrant 8
11/21/2022 CC Storm line 1 d1
11/21/2022 ADS UGDB 37
11/21/2022 CC Fireline T - Dry block 14
11/21/2022 CC Water line tie in 9
11/21/2022 CC Fireline T - Dry block 15
11/21/2022 ADS UGDB 38
11/21/2022 ADS UGDB 39
11/21/2022 ADS UGDB 40
11/21/2022 CC - SS Connection 23
11/21/2022 ADS UGDB 41
11/21/2022 ADS UGDB 42
11/21/2022 CC - Fire line bldg 92
11/21/2022 CC - existing Storm structure1
11/21/2022 ADS UGDB 43
11/21/2022 CC - existing Storm structure 7
11/21/2022 CC - SS Connection 24
11/21/2022 CC - Fire hydrant 9
11/21/2022 CC - SS Connection 25
11/21/2022 ADS UGDB 44
11/21/2022 CC Water line tie in BFV - Meter pits 5
11/21/2022 CC - SS Connection 26
11/21/2022 CC - SS Connection 27
11/21/2022 CC - SS Connection 28
11/21/2022 CC Water line tie in BFV - Meter pits 6
11/21/2022 CC Water line tie in BFV 12
11/21/2022 CC - SS Connection 29
11/21/2022 CC - SS Connection 30
11/21/2022 CC Water line tie in BFV 13
11/21/2022 ADS UGDB 45
11/21/2022 CC Water line tie in BFV 14
11/21/2022 CC Storm line 1 a1
11/21/2022 CC - SS Fittings1
11/21/2022 Existing drive 16
11/21/2022 Existing drive 17
11/21/2022 Existing drive 18
11/21/2022 Existing drive 19
11/21/2022 Existing drive 20
11/21/2022 Existing drive 21
11/21/2022 Existing drive 22
11/21/2022 Existing drive 23
11/21/2022 Existing drive 24
11/21/2022 Existing drive 25
11/21/2022 Existing drive 26
11/21/2022 Existing drive 27
11/21/2022 Storm repair from SS install0
11/21/2022 Existing drive 28
11/21/2022 CC - SS Connection 31
11/21/2022 CC - SS Connection 32
11/21/2022 CC - Storm box 4 b2
11/21/2022 CC Fireline T - Dry block 16
11/21/2022 CC - Storm box 4 c2
11/21/2022 CC Fireline T - Dry block 17
11/21/2022 CC - SS Connection 33
11/21/2022 CC entry storm pipe 19
11/21/2022 CC Storm box 1B 7
11/21/2022 CC entry storm pipe 20
11/21/2022 CC - Storm box 5 b2
11/21/2022 CC entry storm pipe 21
11/21/2022 CC - SS Connection 34
11/21/2022 CC Fireline T - Dry block 18
11/21/2022 CC Fireline T - Dry block 19
11/21/2022 CC entry storm pipe 22
11/21/2022 CC - SS Connection 35
11/21/2022 CC - SS Connection 36
11/21/2022 CC entry storm pipe 23
11/21/2022 CC - SS Connection 37
11/21/2022 CC - SS Connection 38
11/21/2022 CC - Storm box 5 a2
11/21/2022 CC - Storm box 4 a2
11/21/2022 CC - SS Connection 39
11/21/2022 CC Storm box 2 b2
11/21/2022 CC Storm box 2 c2
11/21/2022 CC Storm box 1A 7
11/21/2022 CC Storm box 1 c2
11/21/2022 CC Storm box 8
11/21/2022 CC Storm box 3a2
11/21/2022 CC Storm line 1 b2
11/21/2022 CC Storm box 1A 8
11/21/2022 CC entry storm pipe 24
11/21/2022 CC Fireline T - Dry block 20
11/21/2022 CC Storm box 1B 8
11/21/2022 CC Storm box 1 b2
11/21/2022 CC Storm box 1 a2
11/21/2022 CC - Storm box 5 c2
11/21/2022 CC Storm line 1 c2
11/21/2022 CC water line kicker ticket2
11/21/2022 CC Water line tie in 10
11/21/2022 CC Water line tie in 11
11/21/2022 CC Water line tie in 12
11/21/2022 CC Water line tie in BFV - Meter pits 7
11/21/2022 CC Water line tie in BFV - Meter pits 8
11/21/2022 CC - SS Fittings2
11/21/2022 CC Storm box 9
11/21/2022 CC Storm line 1 a2
11/21/2022 CC Storm line 1 d2
11/30/2022 Letter INSPECTION SUMMARY
11/30/2022 Letter INSPECTION SUMMARY
11/30/2022 Letter INSPECTION SUMMARY
11/30/2022 Letter INSPECTION SUMMARY
11/30/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/06/2022 Letter Fire Loss Reduction Form
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Letter INSPECTION SUMMARY
12/08/2022 Letter Fire Loss Reduction Form
12/14/2022 Letter Fire Loss Reduction Form
12/14/2022 Certificate/License Codes Temporary Certificate of Occupancy
12/14/2022 Receipt Receipt for transaction:2022-009508
12/14/2022 Certificate/License Codes Temporary Certificate of Occupancy
12/14/2022 Certificate/License Codes Temporary Certificate of Occupancy
12/15/2022 Letter INSPECTION SUMMARY
12/20/2023 Codes Temporary Certificate of Occupancy47
12/20/2023 Codes Temporary Certificate of Occupancy76
01/20/2023 Letter Field Certificate of Occupancy
01/20/2023 Letter Codes Final Certificate of Occupancy
01/20/2023 Receipt Receipt for transaction:2023-000383
01/20/2023 Certificate/License Codes Temporary Certificate of Occupancy
01/20/2023 Letter Caliber Collision Det Basin AsBuilts Accepted
01/17/2023 Letter Approved TCO Extension Request
01/12/2023 Letter Caliber Collision TCO Extension Request Form_PDF Doc
01/12/2023 Letter Caliber Collision TCO Extension Request Form_Word Doc
12/28/2022 Letter Revegetation Bond - Caliber Collision
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home