Permit Application Status

PRCOMCOM20240778


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOMCOM20240778
Building Permit - Commercial
Issued
JR COLLEGE DISTRICT OF METROPOLITAN KCMO
ADDITION COMMERCIAL
MCC AUTOMOTIVE INSTITUTE - BUILDING ADDITION AND RENOVATION OF EXISTING
02/22/2024
07/29/2024
09/04/2024
Locations
Contacts
MCCOWN GORDON CONSTRUCTION LLC, Address:850 MAIN ST, Phone:(816) 960-1111  
Dan Daly - McCown Gordon, Phone:(816) 423-7918  
PRO-MECHANICAL, Address:P O BOX 903, Phone:(816) 743-4800  
MARK ONE ELECTRIC CO INC, Address:1414 GENESSEE ST, Phone:(816) 842-7023  
LEXINGTON PLUMBING & HEATING, Address:1620 TROOST AVE, Phone:(816) 231-2254  
DLR GROUP, Address:7290 W 133RD ST, Phone:(913) 897-7811  
KRUGER TECHNOLOGIES INC, Address:8271 MELROSE DR, Phone:(913) 498-1114  
JR COLLEGE DISTRICT OF METROPOLITAN KCMO, Address:3200 BROADWAY  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 02/07/2025 02/07/2025
Craig Hill
Misc
Corrective Action Required
02/07/2025

Information only: Call (816) 969-1300 24 hours prior to requesting a hydrostatic test and a flow test.
REVISED SPRINKLER PLANS UPLOADED
Building Plan Review Approved with Conditions 04/08/2024 08/19/2024
Joe Frogge
Final Development Plan
Resolved
08/19/2024

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational. 4/8/24 - acknowledged in letter.
IBC 1704.2 Special Inspections
Resolved
04/08/2024

"2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections."
IBC 1004.1 Design occupant load
Resolved
04/08/2024

2018 IBC 1004.1 Design occupant load. In determining means of egress requirements, the number of occupants for whom means of egress facilities shall be provided shall be determined in accordance with this section. Action required: Provide total occupant loads for renovation and addition. Also, justify use of 1:300 calc in shop areas. Should it be Educational/Shops & other at 1:50, or maybe Industrial at 1:100? Clarify.
Elevator Equipment Permit
Corrective Action Required
04/01/2024

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational. 4/8/24 - acknowledged in letter.
Elevator Equipment Inspection
Corrective Action Required
04/01/2024

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational. 4/8/24 - acknowledged in letter.
Elevator Certificate of Inspection
Corrective Action Required
04/01/2024

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational. 4/8/24 - acknowledged in letter.
Planning - Screening of ground mounted equipment
Resolved
04/08/2024

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section.
ICC A117.1 404.2.3.2 Swinging Doors Maneuvering Clearance
Resolved
04/08/2024

ICC A117.1 Section 404.2.3.2 Swinging Doors and gates. Swinging doors and gates shall have maneuvering clearances complying with Table 404.2.3.2. Action required: Provide minmum 18" clearance at latch side of door B107.1 (out of Lobby B107 into stair).
NEC Article 110.26 (C)(2) Large equipment
Resolved
04/08/2024

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Provide panic hardware on doors A107 & B107.
IBC 706.1 Fire and Smoke Protection - General
Resolved
04/08/2024

2018 IBC 706.1 General. Fire walls shall be constructed in accordance with Sections 706.2 through 706.11. The extent and location of such fire walls shall provide a complete separation. Where a fire wall also separates occupancies that are required to be separated by a fire barrier wall, the most restrictive requirements of each separation shall apply. Action required: Provide complete construction details for UL 411.
IBC 603.1 Type of Construction - Allowable Materials
Resolved
04/08/2024

2018 IBC 603.1 Allowable Materials. Combustible materials shall be permitted in buildings of Type I or II construction in the following applications and in accordance with Sections 603.1.1 through 603.1.3: (see code for specific examples and exceptions) Action required: Provide verification that wood labelled as "treated" in parapet detail (and similar) is fire retardant treated.
IBC 1803.1 General - geotech
Resolved
04/08/2024

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf. (2,500 shown on sheet S0.1)
IPC 1101.3 Prohibited drainage
Resolved
04/08/2024

.2018 IPC 1101.3 Prohibited drainage. (as amended by LSCO 7-413) Sanitary sewer systems shall be designed, built and maintained in such a manner to prevent all storm or ground water from draining, discharging or entering into the sanitary sewer system. Connection of sump pumps, foundation drains, yard drains, gutter downspouts and any other storm water drainage receptacle(s) or system(s) are specifically prohibited from being connected to the sanitary sewer system. Action required: Re-route elevator sump discharge piping to storm drains or daylight.
IPC 708.1 Cleanouts required
Resolved
04/08/2024

2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. Action required: Provide cleanouts near where waste pipes exit building.
Misc
Resolved
04/08/2024

Unable to find plumbing materials. Action required: Provide pipe material schedule that includes, but is not limited to, water, waste, vent, gas, compressed air, etc.
IMC 606.2.1 Duct detector
Resolved
04/08/2024

2018 IMC 606.2.1 Return air systems. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm, in the return air duct or plenum upstream of any filters, exhaust air connections, outdoor air connections, or decontamination equipment and appliances. Exception: Smoke detectors are not required in the return air system where all portions of the building served by the air distribution system are protected by area smoke detectors connected to a fire alarm system in accordance with the International Fire Code. The area smoke detection system shall comply with Section 606.4. Action required: Provide duct mounted smoke detector in a/c unit IU-A201A
Code analysis required
Resolved
04/08/2024

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Modify code information on sheet CP0.1 to reflect correct occupancy classification which is S1.
Alarm Plan Review Released for Construction 08/07/2024 08/05/2024
Jim Eden
Miscellaneous Correction
Resolved
08/05/2024

Corrective Action: Exterior horn strobes are only required in courtyard spaces. Remove all exterior horn strobes except the one above the FDC. Corrected on resubmittal.
Misc
Resolved
08/05/2024

Any high-volume large-diameter fans shall shutdown upon any activation of the fire alarm. Corrected on resubmittal.
Installation acceptance testing
Corrective Action Required
08/05/2024

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule testing.
Sprinkler Plan Review Released for Construction 07/31/2024 07/30/2024
Craig Hill
Miscellaneous Correction
Corrective Action Required
07/24/2024

Action required: FDC Fire department connection shows 5" connection. FDC needs to be a 4” storz with a 30 degree elbow.
Alarm Plan Review Rejected 07/29/2024 07/29/2024
Craig Hill
Miscellaneous Correction
Corrective Action Required
07/29/2024

Corrective Action: Exterior horn strobes are only required in courtyard spaces. Remove all exterior horn strobes except the one above the FDC.
Misc
Corrective Action Required
07/29/2024

Any high-volume large-diameter fans shall shutdown upon any activation of the fire alarm.
Final Development Plan Review Approved 07/19/2024 07/22/2024
Scott Ready
Sprinkler Plan Review Rejected 07/19/2024 07/16/2024
Craig Hill
Miscellaneous Correction
Corrective Action Required
07/16/2024

Action required: FDC Fire department connection shows 5" connection. FDC needs to be a 4” storz with a 30 degree elbow.
Licensed Contractors Approved 04/08/2024 04/12/2024
Joe Frogge
LC - General Contractor
Resolved
04/08/2024

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Resolved
04/12/2024

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Fire Plan Review Approved with Conditions 04/08/2024 04/08/2024
Jim Eden
Construction documents for fire alarm systems
Informational
04/08/2024

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Provide shop drawings for review and approval. Acknowledged
Address numbers required
Corrective Action Required
04/08/2024

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). Verified at inspection.Ensure the building address/Identifier is visible on the new facade.
Construction documents - Fire protection systems
Informational
04/08/2024

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide shop drawings for review and approval. Will this be a seperate system from the existing automotive building. Acknowledged
Portable fire extinguishers - general
Corrective Action Required
04/01/2024

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. The design professional shall ensure the correct size and distribution of fire extinguishers..
Miscellaneous Correction
Resolved
04/08/2024

Complete site items listed on the Final Development Plan.
Miscellaneous Correction
Resolved
04/08/2024

The classification is a B/S1 Automotive Repair.
Duct smoke detection
Resolved
04/08/2024

2018 IFC 907.2.12.1.2 Duct smoke detection. Duct smoke detectors complying with Section 907.3.1 shall be located as follows:a/c unit IU-A201A.
Emergency power for illumination
Resolved
04/08/2024

2018 IFC 1008.3.1 & 3.2 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises' electrical supply. In the event of power supply failure, an emergency electrical system shall automatically illuminate all of the following: 1. Aisles and unenclosed egress stairways in rooms and spaces that require two or mor means of egress. 2. Corridors, interior exit stairways and ramps and exit passageways in buildings required to have two or more exits. 3. Exterior egress components at other than their levels of exit discharge until exit discharge is accomplished for buildings required to have two or more exits. Provide exterior emergency lighting over door A108E.
Special Inspections Review Approved 04/08/2024
Joe Frogge
Fire Plan Review Rejected 03/07/2024 03/08/2024
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
03/07/2024

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Provide shop drawings for review and approval.
Address numbers required
Corrective Action Required
03/07/2024

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). Verified at inspection.
Construction documents - Fire protection systems
Corrective Action Required
03/07/2024

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Provide shop drawings for review and approval. Will this be a seperate system from the existing automotive building.
Portable fire extinguishers - general
Corrective Action Required
03/07/2024

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10.
Miscellaneous Correction
Corrective Action Required
03/07/2024

Complete site items listed on the Final Development Plan.
Miscellaneous Correction
Corrective Action Required
03/07/2024

The classification is a B/S1 Automotive Repair.
Duct smoke detection
Corrective Action Required
03/08/2024

2018 IFC 907.2.12.1.2 Duct smoke detection. Duct smoke detectors complying with Section 907.3.1 shall be located as follows:a/c unit IU-A201A.
Emergency power for illumination
Corrective Action Required
03/08/2024

2018 IFC 1008.3.1 & 3.2 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises' electrical supply. In the event of power supply failure, an emergency electrical system shall automatically illuminate all of the following: 1. Aisles and unenclosed egress stairways in rooms and spaces that require two or mor means of egress. 2. Corridors, interior exit stairways and ramps and exit passageways in buildings required to have two or more exits. 3. Exterior egress components at other than their levels of exit discharge until exit discharge is accomplished for buildings required to have two or more exits. Provide exterior emergency lighting over door A108E.
Building Plan Review Rejected 03/07/2024 03/06/2024
Joe Frogge
Final Development Plan
Corrective Action Required
03/06/2024

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Corrective Action Required
03/06/2024

"2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections."
IBC 1004.1 Design occupant load
Corrective Action Required
03/06/2024

2018 IBC 1004.1 Design occupant load. In determining means of egress requirements, the number of occupants for whom means of egress facilities shall be provided shall be determined in accordance with this section. Action required: Provide total occupant loads for renovation and addition. Also, justify use of 1:300 calc in shop areas. Should it be Educational/Shops & other at 1:50, or maybe Industrial at 1:100? Clarify.
Elevator Equipment Permit
Corrective Action Required
03/06/2024

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational.
Elevator Equipment Inspection
Corrective Action Required
03/06/2024

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational.
Elevator Certificate of Inspection
Corrective Action Required
03/06/2024

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational.
Planning - Screening of ground mounted equipment
Corrective Action Required
03/06/2024

Unified Development Ordinance Article 8, Section 8.180.F Ground mounted equipment – Ground mounted equipment shall be totally screened from view by landscaping or masonry wall up to a height of the units to be screened. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section.
ICC A117.1 404.2.3.2 Swinging Doors Maneuvering Clearance
Corrective Action Required
03/06/2024

ICC A117.1 Section 404.2.3.2 Swinging Doors and gates. Swinging doors and gates shall have maneuvering clearances complying with Table 404.2.3.2. Action required: Provide minmum 18" clearance at latch side of door B107.1 (out of Lobby B107 into stair).
NEC Article 110.26 (C)(2) Large equipment
Corrective Action Required
03/06/2024

2017 NEC Article 110.26 (C)(3) Personnel Doors. Where equipment rated 800 A or more that contains overcurrent devices, switching devices, or control devices is installed and there is a personnel door(s) intended for entrance to and egress from the working space less than 25 feet from the nearest edge of the working space, the door(s) shall open in the direction of egress and be equipped with panic hardware. Action required: Provide panic hardware on doors A107 & B107.
IBC 706.1 Fire and Smoke Protection - General
Corrective Action Required
03/06/2024

2018 IBC 706.1 General. Fire walls shall be constructed in accordance with Sections 706.2 through 706.11. The extent and location of such fire walls shall provide a complete separation. Where a fire wall also separates occupancies that are required to be separated by a fire barrier wall, the most restrictive requirements of each separation shall apply. Action required: Provide complete construction details for UL 411.
IBC 603.1 Type of Construction - Allowable Materials
Corrective Action Required
03/06/2024

2018 IBC 603.1 Allowable Materials. Combustible materials shall be permitted in buildings of Type I or II construction in the following applications and in accordance with Sections 603.1.1 through 603.1.3: (see code for specific examples and exceptions) Action required: Provide verification that wood labelled as "treated" in parapet detail (and similar) is fire retardant treated.
IBC 1803.1 General - geotech
Corrective Action Required
03/06/2024

2018 IBC 1803.1 General. Geotechnical investigations shall be conducted in accordance with Section 1803.2 and reported in accordance with Section 1803.6. Where required by the building official or where geotechnical investigations involve in-situ testing, laboratory testing or engineering calculations, such investigations shall be conducted by a registered design professional. Action required: Provide soils report to justify design assumption of soil bearing capacity greater than 2,000psf. (2,500 shown on sheet S0.1)
IPC 1101.3 Prohibited drainage
Corrective Action Required
03/06/2024

.2018 IPC 1101.3 Prohibited drainage. (as amended by LSCO 7-413) Sanitary sewer systems shall be designed, built and maintained in such a manner to prevent all storm or ground water from draining, discharging or entering into the sanitary sewer system. Connection of sump pumps, foundation drains, yard drains, gutter downspouts and any other storm water drainage receptacle(s) or system(s) are specifically prohibited from being connected to the sanitary sewer system. Action required: Re-route elevator sump discharge piping to storm drains or daylight.
IPC 708.1 Cleanouts required
Corrective Action Required
03/06/2024

2018 IPC 708.1.3 Building drain and building sewer junction. The junction of the building drain and the building sewer shall be served by a cleanout that is located at the junction or within 10 feet of the developed length of piping upstream of the junction. For the requirements of this section, the removal of a water closet shall not be required to provide cleanout access. Action required: Provide cleanouts near where waste pipes exit building.
Misc
Corrective Action Required
03/06/2024

Unable to find plumbing materials. Action required: Provide pipe material schedule that includes, but is not limited to, water, waste, vent, gas, compressed air, etc.
IMC 606.2.1 Duct detector
Corrective Action Required
03/06/2024

2018 IMC 606.2.1 Return air systems. Smoke detectors shall be installed in return air systems with a design capacity greater than 2,000 cfm, in the return air duct or plenum upstream of any filters, exhaust air connections, outdoor air connections, or decontamination equipment and appliances. Exception: Smoke detectors are not required in the return air system where all portions of the building served by the air distribution system are protected by area smoke detectors connected to a fire alarm system in accordance with the International Fire Code. The area smoke detection system shall comply with Section 606.4. Action required: Provide duct mounted smoke detector in a/c unit IU-A201A
Code analysis required
Corrective Action Required
03/08/2024

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Modify code information on sheet CP0.1 to reflect correct occupancy classification which is S1.
Licensed Contractors Rejected 03/07/2024 03/06/2024
Joe Frogge
LC - General Contractor
Corrective Action Required
03/06/2024

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Provide an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Corrective Action Required
03/06/2024

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for Addition to Commercial $82,950.00 $82,950.00 Paid 04/16/2024
91100C9-Water Insp Fee $3,699.15 $3,699.15 Paid 07/29/2024
91100C8-Sanitary Sewer Insp Fees $502.80 $502.80 Paid 07/29/2024
9110068-Storm Sewer Inspection Fee $5,109.75 $5,109.75 Paid 07/29/2024
9110081-Paved Surface Inspection Fee $10,448.04 $10,448.04 Paid 07/29/2024
9110071-Site Grading Fee $3,998.63 $3,998.63 Paid 07/29/2024
9110072-Water Test Fee $400.00 $400.00 Paid 07/29/2024
Outstanding Fees Amount Paid Owing Date Paid
9110069-After Hours Inspections (Public Works)(Per Hour) $350.00 $0.00 $350.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$425.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sprinkler - Flow Test Pending
Grading/Excavation/Fill Inspection Pending
Sanitary - Material Verification Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Pavement-Surface Pending
Install Street and Stop Signs Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Occupancy Inspection - Codes Commercial Pending
THE FOLLOWING AREAS ARE APPROVED
Informational
08/12/2024
-PHASE ONE: COLLISION REPAIR CENTER
Misc
Corrective Action Required
08/12/2024
-PAINT BOOTH AREA THAT IS FENCED OFF : GRID LINES G- D.2, THIS WILL BE INSPECTED AT A LATER DATE. NO STAFF OF STUDENTS ALLOWED IN THIS AREA UNTIL APPROVAL IS GIVEN BY CODES AND FIRE.
Occupancy Inspection - Engineering Pending
Occupancy Inspection - Fire Pending
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Storm Sewer Construction Inspection Pending
Water Service Inspection Pending
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Storm Sewer Construction Inspection Pending
Water Line - Construction Inspection Pending
Misc
Informational
10/16/2024
10-15-24 DP. Floyds crew got the line to the fire hydrant up to 200 psi. It stayed at 200 psi for 2 hours. 10-16-24 DP. Floyds crew got the fire line chlorinated at 10AM today.
Underground Electrical Inspection - Commercial Pending
Misc
Corrective Action Required
10/17/2024
INSPECTED TRENCH AND CONDUIT - A4.5: 1.3-1.6
Misc
Corrective Action Required
10/17/2024
Approved to cover - UE from transformer to CT cabinet and 29 out it cabinet ( South West corner) - UE continue from out of CT cabinet to 1.7 then turn to A1 10/10/24 - 1.7: A2-A4 - A5: 1.4-1.6 AND ACROSS TO A2 10/15
Misc
Corrective Action Required
10/17/2024
INSPECTED ELEVATOR CONDUIT OUT TO VARIOUS LOCATIONS - SUMP - FIRE -ELECTRICAL
Underslab Electrical Inspection - Commercial Pending
Misc
Corrective Action Required
10/23/2024
-A4.5 FROM 1.3-1.45
Water Line - Coliform Test 1 Pending
Misc
Informational
10/30/2024
10-29-24 DP. Met Floyd onsite and took sample 3 from the 6" fire hydrant line, sample 1 from the domestic service line and the fire line to the building pad. 10-30-24 DP. The 3rd sample from 3 from the 6" fire hydrant line, sample 1 from the domestic service line and the fire line to the building pad all PASSED
Water Line - Coliform Test 2 Pending
Misc
Informational
10/30/2024
10-23-24 DP. Met Floyd onsite and took the second sample for the private 6" line to the single fire hydrant 10-24-24 DP. Second sample failed for TC. Will meet Floyd on Monday for a third sample. 10-30-24 DP. Met Marty onsite with She Digs it and pulled second samples from the 6" private fire hydrant line and also the domestic service line and fire line to the building pad today. All three samples were delivered to Blue Valley Labs.
Detention Basin Pending
Misc
Informational
12/31/2024
10-3-24 DP. Floyds crew set the outflow structure. It looks high for a detention basin. There will be water retained in the bowl. 10-4-24 DP. Floyds crew is onsite cleaning up around the detention basin. It is scheduled to get hydroseeded Monday. McCown Gordon is currently looking into the outflow structure. It is set within a 1/10. The inflow pipe has 1% fall into the basin which is what its called out for. The problem is that with the outflow being so high, water will sit in the pipe 10-10-24 DP. I brought attention again to the outflow structure of the detention basin. They outflow structure will not allow the bottom 3' of the basin to drain. Advised Lindsay with McCown Gordon to have their civil engineer resubmit their fix to the city. There was an email sent today from Lindsay with Correspondence to Scott Ready and Sue Pyles. 12-30-24. I noticed the east side of the detention basin has been disturbed. I was told by a carpenter with McCown Gordon onsite that they replaced the outflow structure in the detention basin. If that is true, no update plans have been resubmitted or approved by the city. We also need to reestablish vegetation around that box and until it's established there needs to be erosion control in place to keep the silt from washing into the detention basin. There was also a decent amount of trash in the detention basin that needs to be removed.
ESC - (Vegetation/Ground Cover) Pending
Misc
Informational
01/15/2025
1-15-25 DP. No ESC issues at this time
Miscellaneous Inspection Pending
Sanitary Sewer - Air Test Pending
Sanitary Sewer - Mandrel Pending
Sanitary Sewer - Vacuum Pending
Pavement-Proof Roll Pending
Misc
Informational
04/10/2025
4-10-25 Dustin A, Proof roll on south end of building for parking and curb , passed
Sidewalk Inspection Pending
Misc
Informational
04/18/2025
4-14-25 DP. Crew poured sidewalk on the north side of the property that connected to existing. They used AB3 and had adequate amount, compacted. They had expansion join laid out where it needed to go and cross slopes looked to be in compliance. I told them with the SW being so wide, that I will confirm cross slopes on final.
Rough Framing Inspection - Commercial Pending
Misc
Corrective Action Required
04/22/2025
ROOMS 206,207 second floor
In-wall Inspection Pending
Misc
Informational
04/24/2025
AREAS APPROVED -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122, 204, 205 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 -intierior of all extiertier walls - first floor bahrooms - dtinking fountain - A201
Misc
Informational
04/24/2025
- elevator shaft wall - first part of elevetor ceiling -
Site Visit Pending
Misc
Informational
05/06/2025
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demoing the water line that runs under the building pad. 9-30-24 DP. Floyds crew is continuing to demo old water pipe from building pad. They are also prepping to run a new line to a fire hydrant. 10-1-24 DP. No work for FEI today. They were just working on digging for the electric company. 12-2-24 DP. No work for FEI, they are just setting steel for the building. 1-15-25 DP. There has been no work on site for FEI since before Thanksgiving
Miscellaneous Correction
Corrective Action Required
05/06/2025
5-6-25 DP. Outside of the construction entrance, there is a blow up in the road. This is needing repairs as it is bad. This will require a full depth repair and need to be replaced from curb to curb.
Pavement-Proof Roll Pending
Footing Inspection - Commercial Pending
Miscellaneous Correction
Corrective Action Required
06/02/2025
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6 Sunken pads @4 1.7-1.9 Footing Northern end A1-A5 Footing East and west 1.1-1.3 Slab ready to pour south East 1.2-1.4 :: A4-A5
Misc
Corrective Action Required
06/02/2025
PHASE 3 FOOING - FOR WELDING ROOM - 2 inteirior steel for pads for coloumns. 6/2/2025
Erosion Control Inspection Pending
Misc
Informational
06/04/2025
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud. 2-11-25 DP. No ESC issues at this time. Rock was added to reestablish the construction entrance. 4-15-25 DP. No ESC issues at this time. 5-6-25 DP. No ESC issues at this time. 6-4-25 DP. No ESC issues at this time. Contractor has been uploading SWPPP reports to the portal.
Piers/Caissons Inspection - Commercial Pending
Misc
Corrective Action Required
06/05/2025
APPROVED - Light pole bases at Norh edge of building, East-West 5 towards parking area Conduits inspected - 4 Light pole bases North East corner of lot Conduit inspected - Light pole base at South of biulding ( conduit not inspected) - 4 Light pole base North West corner of new building
Above Ceiling Inspection Pending
Misc
Informational
06/06/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
06/06/2025
APPROVED AREAS - ALL Hard lid approved - Extierior soffits framing and above ceiling front side all 3
Rated Assembly Inspection Pending
ELEVATOR 1
Corrective Action Required
06/10/2025
approved areas shaft liner first layer back side first layer hat Outside elevator all sides
Sanitary Sewer - Camera Test Pending 3/17/2025
Underground Plumbing Inspection - Commercial Partial 6/5/2024 6/5/2024 06/05/2024
Misc
Informational
06/05/2024
- Floor drains ok - sanitary line comple
Rated Assembly Inspection Partial 6/18/2024 06/18/2024
Misc
Corrective Action Required
06/18/2024
- FIRST LAYER OF INFILL OF SKYLIGHT OK
All Rough Inspection - Commercial Partial 7/15/2024 07/15/2024
Misc
Informational
07/15/2024
- Inspected north wall framing
In-wall Inspection Partial 7/17/2024 7/17/2024 07/17/2024
Misc
Corrective Action Required
07/17/2024
-COLLISION STORAGE VESTABULE, NORTH SIDE, OK - NORTH WALL TOP OUT ,OK - FRAMING FOR SOUTH WALL DOOR BLOCK OUTS,OK
All Rough Inspection - Commercial Partial 7/17/2024 07/17/2024
Misc
Informational
07/15/2024
- Inspected north wall framing
Misc
Corrective Action Required
07/17/2024
- INSPECTED NORTH WALL SINK PLUMBING - INSPECTED SOUTH WALL FRAMING OF DOOR BLOCK OUTS - INSPECTED COLLISION STORAGE VESTABULE ( NEXT TO PAINT BOOTH)
Electrical Service Inspection Failed 7/19/2024 07/19/2024
Misc
Corrective Action Required
07/19/2024
- PROVIDE A SECOND GROUND ROD AT LEAST 6 FOOT APART FRON CURRENT ONE.
Misc
Informational
07/19/2024
THIS IS FOR TEMP SERVICE AT CONSTRUCTION TRAILER.
Underground Plumbing Inspection - Commercial Passed 7/19/2024 07/19/2024
Misc
Informational
06/05/2024
- Floor drains ok - sanitary line comple
Misc
Informational
07/19/2024
- last of floor drains in old paint booth area installed and approved.
Gas Piping Inspection - Commercial Partial 7/19/2024 07/19/2024
Misc
Informational
07/19/2024
GAS PIPING RFI FOR PAINT BOOTH MOVE APPROVED
In-wall Inspection Passed 7/19/2024 07/19/2024
Misc
Informational
07/19/2024
- PRESSURE TEST FOR IN NORTH WALL SINK
Electrical Service Inspection Passed 7/22/2024 07/22/2024
Misc
Resolved
07/22/2024
- PROVIDE A SECOND GROUND ROD AT LEAST 6 FOOT APART FRON CURRENT ONE.
Misc
Resolved
07/22/2024
THIS IS FOR TEMP SERVICE AT CONSTRUCTION TRAILER.
In-wall Inspection Partial 7/24/2024 07/24/2024
Misc
Corrective Action Required
07/17/2024
-COLLISION STORAGE VESTABULE, NORTH SIDE, OK - NORTH WALL TOP OUT ,OK - FRAMING FOR SOUTH WALL DOOR BLOCK OUTS,OK
Misc
Corrective Action Required
07/24/2024
Print West: From F-C lower inspected.
In-wall Inspection Partial 7/26/2024 07/26/2024
Informational
07/26/2024
- INSPECTED FRAMING OF BOTH WALLS ON LINE B, FROM 1.7 TO 1.10. OK TO COVER
All Rough Inspection - Commercial Partial 8/1/2024 08/01/2024
Misc
Informational
07/17/2024
- Inspected north wall framing
Misc
Corrective Action Required
07/17/2024
- INSPECTED NORTH WALL SINK PLUMBING - INSPECTED SOUTH WALL FRAMING OF DOOR BLOCK OUTS - INSPECTED COLLISION STORAGE VESTABULE ( NEXT TO PAINT BOOTH)
MISC
Corrective Action Required
08/01/2024
- INSPECTED NORTH WALL ELECTRICAL PANELS FRAMING.
Rated Assembly Inspection Passed 8/7/2024 08/07/2024
Misc
Resolved
08/07/2024
- FIRST LAYER OF INFILL OF SKYLIGHT OK
Erosion Control Inspection Residential Partial 8/7/2024 08/07/2024
Misc
Corrective Action Required
08/07/2024
Ok at time of inspection
Gas Piping Inspection - Commercial Passed 8/7/2024 08/07/2024
Misc
Informational
07/19/2024
GAS PIPING RFI FOR PAINT BOOTH MOVE APPROVED
Miscellaneous Inspection Passed 8/7/2024 08/07/2024
Misc
Resolved
08/07/2024
- Inspected north wall framing
Misc
Resolved
08/07/2024
- INSPECTED NORTH WALL SINK PLUMBING - INSPECTED SOUTH WALL FRAMING OF DOOR BLOCK OUTS - INSPECTED COLLISION STORAGE VESTABULE ( NEXT TO PAINT BOOTH)
MISC
Resolved
08/07/2024
- INSPECTED NORTH WALL ELECTRICAL PANELS FRAMING.
Miscellaneous Inspection Failed 8/7/2024 08/07/2024
Misc
Corrective Action Required
08/07/2024
- Provide welding cert for steel work - Removal of damper not in use - Close all electrical boxes throughout - Electrical panels and outlets incomplete - Open stand pipe - Provide temp wall to prevent access to paint booth area - Label exhaust fans and label in panel
Alarm Test Passed 8/8/2024 at 2:00 PM 08/08/2024
Sprinkler - Hydrostatic Test Passed 8/7/2024 08/08/2024
Miscellaneous Inspection Passed 8/12/2024 08/12/2024
Misc
Resolved
08/12/2024
- Provide welding cert for steel work - Removal of damper not in use - Close all electrical boxes throughout - Electrical panels and outlets incomplete - Open stand pipe - Provide temp wall to prevent access to paint booth area - Label exhaust fans and label in panel
Occupancy Inspection - Fire Partial 8/12/2024 8/12/2024 08/12/2024
Water Line - Construction Inspection Partial 8/21/2024 8/21/2024 08/22/2024
Misc
Informational
08/22/2024
8-21-24 DP. Floyd with She Digs It was onsite and started excavating and laying the 6" fire line. They Exposed the tie in point at STA 4+95.59 and laid 6" DIP with poly wrap up to STA 4+50. They had proper bedding under the new main.
Miscellaneous Inspection Passed 8/22/2024 08/22/2024
Misc
Informational
08/22/2024
INSPECTION OF ELECTRICAL FOR LIFTS AND MISC EQUIPTMENT.
Water Line - Construction Inspection Partial 8/23/2024 8/23/2024 08/23/2024
Misc
Informational
08/22/2024
8-21-24 DP. Floyd with She Digs It was onsite and started excavating and laying the 6" fire line. They Exposed the tie in point at STA 4+95.59 and laid 6" DIP with poly wrap up to STA 4+50. They had proper bedding under the new main. 8-23-24 DP. She Digs it is on site today and installed 60 more feet of water line and also poured kickers and a thrust block. They are laying water tape as they are backfilling.
Site Visit Partial 8/26/2024 8/26/2024 08/27/2024
Misc
Informational
08/27/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today.
Storm Sewer Construction Inspection Partial 8/28/2024 8/28/2024 08/29/2024
Misc
Informational
08/29/2024
8-28-24 DP. She Digs it is onsite and beginning to install storm pipe.
Water Line - Construction Inspection Partial 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
09/04/2024
9-4-24 DP. Floyds crew was onsite today and poured 1 kicker on a 45.
Site Visit Partial 9/4/2024 9/4/2024 09/04/2024
Misc
Informational
08/27/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day.
Electrical Service Inspection Passed 9/6/2024 09/06/2024
Storm Sewer Construction Inspection Partial 9/6/2024 9/6/2024 09/06/2024
Misc
Informational
08/29/2024
8-28-24 DP. She Digs it is onsite and beginning to install storm pipe. 9-6-24 DP. Floyds crew is onsite and poured a collar around the discharge flume to the detention basin. They also set a nyloplast.
Erosion Control Inspection Partial 9/10/2024 9/10/2024 09/10/2024
Misc
Informational
09/10/2024
9-10-24 DP. No ESC issues.
Occupancy Inspection - Codes Commercial Failed 9/13/2024 9/13/2024 09/13/2024
THE FOLLOWING AREAS ARE APPROVED
Informational
08/12/2024
Approved for Occupancy for -PHASE ONE: COLLISION REPAIR CENTER;
Misc
Corrective Action Required
08/12/2024
-PAINT BOOTH AREA THAT IS FENCED OFF : GRID LINES G- D.2, THIS WILL BE INSPECTED AT A LATER DATE. NO STAFF OF STUDENTS ALLOWED IN THIS AREA UNTIL APPROVAL IS GIVEN BY CODES AND FIRE. -SEAL ROOF OPENING AT PAINT AND PRE PAINT BOOTH VENT - LABEL OUTSIDE VENTING UNITS TO MATCH PANEL LABEL - PROVIDE GFCI PROTECTED SERVICE OUTLET WITHIN 25' OF OUTSIDE UNITS
Water Line - Construction Inspection Partial 9/13/2024 9/13/2024 09/13/2024
Misc
Informational
08/23/2024
8-21-24 DP. Floyd with She Digs It was onsite and started excavating and laying the 6" fire line. They Exposed the tie in point at STA 4+95.59 and laid 6" DIP with poly wrap up to STA 4+50. They had proper bedding under the new main. 8-23-24 DP. She Digs it is on site today and installed 60 more feet of water line and also poured kickers and a thrust block. They are laying water tape as they are backfilling. 9-13-24 DP. Floyds crew was onsite today and installing the 2 inch copper domestic water line today. They will not to the tap until the 6" line is tested and put into service.
Footing Inspection - Commercial Partial 5/27/2025 5/27/2025 09/16/2024
Misc
Partial Correction
09/16/2024
Print S1-1A partial Approved A.5. From 1.15 to 1.2
Fire Line - Hydrostatic Test Partial 9/16/2024 9/16/2024 09/16/2024
Misc
Informational
09/16/2024
9-16-24 DP. Floyds crew is onsite today performing the hydrostatic test on the 6 to 4" fire line. They have it up to 200 psi
Site Visit Partial 9/17/2024 9/17/2024 09/17/2024
Misc
Informational
09/04/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm.
Footing Inspection - Commercial Partial 9/18/2024 9/18/2024 09/18/2024
Misc
Partial Correction
09/16/2024
Print S1-1A partial Approved -A.5. From 1.15 to 1.2[12-19] - Elevator pit - 4 center column pads- A4- 12,13,14,15
Footing Inspection - Commercial Partial 9/19/2024 09/19/2024
Misc
Partial Correction
09/18/2024
Print S1-1A partial Approved -A.5. From 1.15 to 1.2[12-19] - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls
Water Line - Coliform Test 1 Partial 9/16/2024 9/16/2024 09/20/2024
Misc
Informational
09/20/2024
9-16-24 DP. 4" water line and 6" water lines passed hydrostatic and were chlorinated.
Water Line - Coliform Test 1 Partial 9/17/2024 9/17/2024 09/20/2024
Misc
Informational
09/20/2024
9-16-24 DP. 4" water line and 6" water lines passed hydrostatic and were chlorinated. 9-17-24 DP. Both lines were flushed by Nick Scott
Water Line - Coliform Test 1 Partial 9/18/2024 9/18/2024 09/20/2024
Misc
Informational
09/20/2024
9-16-24 DP. 4" water line and 6" water lines passed hydrostatic and were chlorinated. 9-17-24 DP. Both lines were flushed by Nick Scott 9-18-24 DP. First sample from the 6" and first sample from the 4" were taken and delivered to Blue Valley Labs
Water Line - Coliform Test 1 Partial 9/19/2024 9/19/2024 09/20/2024
Misc
Informational
09/20/2024
9-16-24 DP. 4" water line and 6" water lines passed hydrostatic and were chlorinated. 9-17-24 DP. Both lines were flushed by Nick Scott 9-18-24 DP. First sample from the 6" and first sample from the 4" were taken and delivered to Blue Valley Labs 9-19-24 DP. First sample on both lines passed.
Water Line - Coliform Test 1 Passed 9/20/2024 9/20/2024 09/20/2024
Misc
Informational
09/20/2024
9-16-24 DP. 4" water line and 6" water lines passed hydrostatic and were chlorinated. 9-17-24 DP. Both lines were flushed by Nick Scott 9-18-24 DP. First sample from the 6" and first sample from the 4" were taken and delivered to Blue Valley Labs 9-19-24 DP. First sample on both lines passed.
Water Line - Coliform Test 2 Partial 9/19/2024 9/19/2024 09/20/2024
Misc
Informational
09/20/2024
9-19-24 DP. Second samples were taken from the 6" and 4" water lines and were delivered to Blue Valley Labs
Footing Inspection - Commercial Partial 9/20/2024 09/20/2024
Misc
Partial Correction
09/19/2024
Print S1-1A partial Approved -A.5. From 1.15 to 1.2[12-19] - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10
Water Line - Coliform Test 2 Passed 9/20/2024 9/20/2024 09/21/2024
Misc
Informational
09/20/2024
9-19-24 DP. Second samples were taken from the 6" and 4" water lines and were delivered to Blue Valley Labs 9-20-24 DP. Second samples passed.
Water Line - Construction Inspection Partial 9/21/2024 9/21/2024 09/21/2024
Misc
Informational
09/18/2024
9-4-24 DP. Floyds crew was onsite today and poured 1 kicker on a 45. 9-21-24 DP. We are onsite today and are doing all tie ins. Both samples passed this last week
Water Line - Construction Inspection Passed 9/21/2024 9/21/2024 09/23/2024
Misc
Informational
09/21/2024
9-4-24 DP. Floyds crew was onsite today and poured 1 kicker on a 45. 9-21-24 DP. We are onsite today and are doing all tie ins. Both samples passed this last week 9-21-24 DP. Both the 6" and 4" line has been tied in.
Footing Inspection - Commercial Not Ready 9/24/2024 9/24/2024 09/24/2024
Misc
Corrective Action Required
09/24/2024
NOT READY, NOTHING APPROVED TODAY
Footing Inspection - Commercial Partial 9/26/2024 9/26/2024 09/26/2024
Misc
Corrective Action Required
09/26/2024
Print S1-1A partial Approved -A.5. From 1.15 to 1.2[12-19] - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF
Gas Service Inspection - Commercial Failed 9/26/2024 9/26/2024 09/26/2024
Misc
Resolved
09/26/2024
No pressure or Bonding
Misc
Corrective Action Required
09/26/2024
- TRENCHES ARE CUT, NO PIPING IN TRENCH.
Site Visit Partial 9/26/2024 9/26/2024 09/26/2024
Misc
Informational
09/26/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demo-ing the water line that runs under the building pad.
Piers/Caissons Inspection - Commercial Partial 9/27/2024 9/27/2024 09/27/2024
Misc
Corrective Action Required
09/27/2024
COLUMN PADS APPROVED A5- 1.4, 1.5, 1.6, 1.7, 1.8 5 PADS
Underslab Plumbing Inspection - Commercial Failed 9/27/2024 9/27/2024 09/27/2024
Misc
Corrective Action Required
09/27/2024
- No trace wire - This is on service side of meter, should be inspected by utility. (spire)
Site Visit Partial 9/30/2024 9/30/2024 09/30/2024
Misc
Informational
09/26/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demo-ing the water line that runs under the building pad. 9-30-24 DP. Floyds crew is continuing to demo old water pipe from building pad. They are also prepping to run a new line to a fire hydrant.
Erosion Control Inspection Partial 9/30/2024 9/30/2024 09/30/2024
Misc
Informational
09/10/2024
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues.
Site Visit Partial 10/1/2024 10/1/2024 10/02/2024
Misc
Informational
09/30/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demo-ing the water line that runs under the building pad. 9-30-24 DP. Floyds crew is continuing to demo old water pipe from building pad. They are also prepping to run a new line to a fire hydrant. 10-1-24 DP. No work for FEI today. They were just working on digging for the electric company.
Footing Inspection - Commercial Partial 10/2/2024 10/2/2024 10/02/2024
Miscellaneous Correction
Corrective Action Required
10/02/2024
Print S1-1A partial Approved -A.5. From 1.15 to 1.2[12-19] - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9
Underground Electrical Inspection - Commercial Partial 10/3/2024 10/3/2024 10/03/2024
Misc
Corrective Action Required
10/03/2024
INSPECTED TRENCH AND CONDUIT - A4.5: 1.3-1.6
Footing Inspection - Commercial Partial 10/4/2024 10/4/2024 10/04/2024
Miscellaneous Correction
Corrective Action Required
10/02/2024
Print S1-1A partial Approved -A.5. From 1.15 to 1.2[12-19] - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8
Detention Basin Partial 10/3/2024 10/3/2024 10/04/2024
Misc
Informational
10/04/2024
10-3-24 DP. Floyds crew set the outflow structure. It looks high for a detention basin. There will be water retained in the bowl.
Detention Basin Partial 10/4/2024 10/4/2024 10/04/2024
Misc
Informational
10/04/2024
10-3-24 DP. Floyds crew set the outflow structure. It looks high for a detention basin. There will be water retained in the bowl. 10-4-24 DP. Floyds crew is onsite cleaning up around the detention basin. It is scheduled to get hydroseeded Monday. McCown Gordon is currently looking into the outflow structure. It is set within a 1/10. The inflow pipe has 1% fall into the basin which is what its called out for. The problem is that with the outflow being so high, water will sit in the pipe
Fire Line Construction Inspection Partial 10/7/2024 10/7/2024 10/08/2024
Misc
Informational
10/08/2024
10-7-24 DP. Floyds crew is just excavating and laying the water line that will go to the single fire hydrant.
Underground Electrical Inspection - Commercial Partial 10/8/2024 10/8/2024 10/08/2024
Misc
Corrective Action Required
10/03/2024
INSPECTED TRENCH AND CONDUIT - A4.5: 1.3-1.6
Misc
Corrective Action Required
10/08/2024
Approved to cover - UE from transformer to CT cabinet and 29 out it cabinet ( South West corner)
Underground Electrical Inspection - Commercial Partial 10/10/2024 10/10/2024 10/10/2024
Misc
Corrective Action Required
10/08/2024
INSPECTED TRENCH AND CONDUIT - A4.5: 1.3-1.6
Misc
Corrective Action Required
10/08/2024
Approved to cover - UE from transformer to CT cabinet and 29 out it cabinet ( South West corner) - UE continue from out of CT cabinet to 1.7 then turn to A1 10/10/24
Fire Line Construction Inspection Partial 10/9/2024 10/9/2024 10/11/2024
Misc
Informational
10/08/2024
10-7-24 DP. Floyds crew is just excavating and laying the water line that will go to the single fire hydrant. 10-9-24 DP. Floyds crew laid 60 feet of DIP for the fire line
Fire Line Construction Inspection Partial 10/10/2024 10/10/2024 10/11/2024
Misc
Informational
10/11/2024
10-7-24 DP. Floyds crew is just excavating and laying the water line that will go to the single fire hydrant. 10-9-24 DP. Floyds crew laid 60 feet of DIP for the fire line 10-10-24 DP. Floyds crew laid 40' of DIP for the same fire line.
Detention Basin Partial 10/10/2024 10/10/2024 10/11/2024
Misc
Informational
10/04/2024
10-3-24 DP. Floyds crew set the outflow structure. It looks high for a detention basin. There will be water retained in the bowl. 10-4-24 DP. Floyds crew is onsite cleaning up around the detention basin. It is scheduled to get hydroseeded Monday. McCown Gordon is currently looking into the outflow structure. It is set within a 1/10. The inflow pipe has 1% fall into the basin which is what its called out for. The problem is that with the outflow being so high, water will sit in the pipe 10-10-24 DP. I brought attention again to the outflow structure of the detention basin. They outflow structure will not allow the bottom 3' of the basin to drain. Advised Lindsay with McCown Gordon to have their civil engineer resubmit their fix to the city. There was an email sent today from Lindsay with Correspondence to Scott Ready and Sue Pyles.
Footing Inspection - Commercial Partial 10/11/2024 10/11/2024 10/11/2024
Miscellaneous Correction
Corrective Action Required
10/04/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7
Underslab Plumbing Inspection - Commercial Partial 10/11/2024 10/11/2024
Misc
Resolved
10/11/2024
Misc
Corrective Action Required
10/11/2024
- INSPECTED 2" WATER DOMESTIC - INSPECTED DRAIN TILE AND SEWER ALL SOUTH OF 1.4 - A1 TO A5
Fire Line Construction Inspection Partial 10/11/2024 10/11/2024 10/11/2024
Misc
Informational
10/11/2024
10-7-24 DP. Floyds crew is just excavating and laying the water line that will go to the single fire hydrant. 10-9-24 DP. Floyds crew laid 60 feet of DIP for the fire line 10-10-24 DP. Floyds crew laid 40' of DIP for the same fire line. 10-11-24 DP. Floyds crew finished running the line to the single fire hydrant. They hydrant was set. Next week they will do hydrostatic testing and samples before tying in.
Footing Inspection - Commercial Partial 10/14/2024 10/14/2024 10/14/2024
Miscellaneous Correction
Corrective Action Required
10/11/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8
Underslab Plumbing Inspection - Commercial Partial 10/14/2024 10/14/2024
Misc
Corrective Action Required
10/11/2024
- INSPECTED 2" WATER DOMESTIC - INSPECTED DRAIN TILE AND SEWER
Underground Electrical Inspection - Commercial Partial 10/15/2024 10/15/2024
Misc
Corrective Action Required
10/10/2024
INSPECTED TRENCH AND CONDUIT - A4.5: 1.3-1.6
Misc
Corrective Action Required
10/10/2024
Approved to cover - UE from transformer to CT cabinet and 29 out it cabinet ( South West corner) - UE continue from out of CT cabinet to 1.7 then turn to A1 10/10/24 - 1.7: A2-A4 - A5: 1.4-1.6 AND ACROSS TO A2 10/15
Footing Inspection - Commercial Partial 10/15/2024 10/15/2024 10/15/2024
Miscellaneous Correction
Corrective Action Required
10/14/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24
Footing Inspection - Commercial Partial 10/16/2024 10/16/2024
Miscellaneous Correction
Corrective Action Required
10/15/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector
Water Line - Construction Inspection Partial 10/15/2024 10/15/2024 10/16/2024
Misc
Informational
10/16/2024
10-15-24 DP. Floyds crew got the line to the fire hydrant up to 200 psi. It stayed at 200 psi for 2 hours.
Water Line - Construction Inspection Partial 10/16/2024 10/16/2024 10/16/2024
Misc
Informational
10/16/2024
10-15-24 DP. Floyds crew got the line to the fire hydrant up to 200 psi. It stayed at 200 psi for 2 hours. 10-16-24 DP. Floyds crew got the fire line chlorinated at 10AM today.
Underground Electrical Inspection - Commercial Partial 4/1/2025 10/17/2024
Misc
Corrective Action Required
10/15/2024
INSPECTED TRENCH AND CONDUIT - A4.5: 1.3-1.6
Misc
Corrective Action Required
10/15/2024
Approved to cover - UE from transformer to CT cabinet and 29 out it cabinet ( South West corner) - UE continue from out of CT cabinet to 1.7 then turn to A1 10/10/24 - 1.7: A2-A4 - A5: 1.4-1.6 AND ACROSS TO A2 10/15
Misc
Corrective Action Required
10/17/2024
INSPECTED ELEVATOR CONDUIT OUT TO VARIOUS LOCATIONS - SUMP - FIRE -ELECTRICAL
Underslab Plumbing Inspection - Commercial Partial 10/17/2024 10/17/2024
Misc
Corrective Action Required
10/14/2024
- INSPECTED 2" WATER DOMESTIC - INSPECTED DRAIN TILE AND SEWER
Misc
Corrective Action Required
10/17/2024
inspected main from South end to 1.3 at North end with all branches
Footing Inspection - Commercial Partial 10/17/2024 10/18/2024 10/18/2024
Miscellaneous Correction
Corrective Action Required
10/16/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads
Water Line - Coliform Test 1 Partial 10/18/2024 10/18/2024 10/21/2024
Misc
Informational
10/21/2024
10-18-24 DP. Floyds crew flushed the private 6" to the new fire hydrant today.
Water Line - Coliform Test 1 Partial 10/21/2024 10/21/2024 10/21/2024
Misc
Informational
10/21/2024
10-18-24 DP. Floyds crew flushed the private 6" to the new fire hydrant today. 10-21-24 DP. Met crew onsite to take the first sample on above listed water line today. Nick delivered it to Blue Valley Labs
Water Line - Coliform Test 1 Passed 10/22/2024 10/22/2024 10/23/2024
Misc
Informational
10/21/2024
10-18-24 DP. Floyds crew flushed the private 6" to the new fire hydrant today. 10-21-24 DP. Met crew onsite to take the first sample on above listed water line today. Nick delivered it to Blue Valley Labs 10-22-24 DP. Sample 1 passed
Underslab Electrical Inspection - Commercial Partial 10/23/2024 10/23/2024 10/23/2024
Misc
Corrective Action Required
10/23/2024
-A4.5 FROM 1.3-1.45
Water Line - Coliform Test 2 Partial 10/23/2024 10/23/2024 10/23/2024
Misc
Informational
10/23/2024
10-23-24 DP. Met Floyd onsite and took the second sample for the private 6" line to the single fire hydrant
Footing Inspection - Commercial Partial 10/24/2024 10/24/2024
Miscellaneous Correction
Corrective Action Required
10/18/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6
Water Line - Coliform Test 2 Partial 10/24/2024 10/24/2024 10/24/2024
Misc
Informational
10/23/2024
10-23-24 DP. Met Floyd onsite and took the second sample for the private 6" line to the single fire hydrant 10-24-24 DP. Second sample failed for TC. Will meet Floyd on Monday for a third sample.
Footing Inspection - Commercial Partial 10/28/2024 10/28/2024 10/28/2024
Miscellaneous Correction
Corrective Action Required
10/24/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6
Footing Inspection - Commercial Partial 10/29/2024 10/29/2024 10/29/2024
Miscellaneous Correction
Corrective Action Required
10/28/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6 Sunken pads @4 1.7-1.9 Footing Northern end A1-A5 Footing East and west 1.1-1.3
Erosion Control Inspection Partial 10/30/2024 10/30/2024 10/30/2024
Misc
Informational
09/30/2024
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues
Water Line - Coliform Test 1 Partial 10/29/2024 10/29/2024 10/30/2024
Misc
Informational
10/30/2024
10-29-24 DP. Met Floyd onsite and took sample 3 from the 6" fire hydrant line, sample 1 from the domestic service line and the fire line to the building pad.
Water Line - Coliform Test 1 Partial 10/30/2024 10/30/2024 10/30/2024
Misc
Informational
10/30/2024
10-29-24 DP. Met Floyd onsite and took sample 3 from the 6" fire hydrant line, sample 1 from the domestic service line and the fire line to the building pad. 10-30-24 DP. The 3rd sample from 3 from the 6" fire hydrant line, sample 1 from the domestic service line and the fire line to the building pad all PASSED
Water Line - Coliform Test 2 Partial 10/30/2024 10/30/2024 10/30/2024
Misc
Informational
10/24/2024
10-23-24 DP. Met Floyd onsite and took the second sample for the private 6" line to the single fire hydrant 10-24-24 DP. Second sample failed for TC. Will meet Floyd on Monday for a third sample. 10-30-24 DP. Met Marty onsite with She Digs it and pulled second samples from the 6" private fire hydrant line and also the domestic service line and fire line to the building pad today. All three samples were delivered to Blue Valley Labs.
Fire Line - Hydrostatic Test Passed 9/16/2024 9/16/2024 11/04/2024
Misc
Informational
10/16/2024
9-16-24 DP. Floyds crew is onsite today performing the hydrostatic test on the 6 to 4" fire line. They have it up to 200 psi
Fire Line Construction Inspection Passed 10/11/2024 10/11/2024 11/04/2024
Misc
Informational
10/11/2024
10-7-24 DP. Floyds crew is just excavating and laying the water line that will go to the single fire hydrant. 10-9-24 DP. Floyds crew laid 60 feet of DIP for the fire line 10-10-24 DP. Floyds crew laid 40' of DIP for the same fire line. 10-11-24 DP. Floyds crew finished running the line to the single fire hydrant. They hydrant was set. Next week they will do hydrostatic testing and samples before tying in.
Footing Inspection - Commercial Partial 11/7/2024 11/7/2024 11/07/2024
Miscellaneous Correction
Corrective Action Required
10/29/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6 Sunken pads @4 1.7-1.9 Footing Northern end A1-A5 Footing East and west 1.1-1.3 Slab ready to pour south East 1.2-1.4 :: A4-A5
Underslab Plumbing Inspection - Commercial Passed 11/8/2024 11/8/2024 11/08/2024
Misc
Resolved
11/08/2024
- INSPECTED 2" WATER DOMESTIC - INSPECTED DRAIN TILE AND SEWER
Misc
Resolved
11/08/2024
inspected main from South end to 1.3 at North end with all branches
Misc
Informational
11/08/2024
UNDERSLAB PLUMBING INSPECTIONS COMPLETE INCLUDING STUB OUT FOR GREASE INTERSEPTOR
Site Visit Partial 12/2/2024 12/2/2024 12/02/2024
Misc
Informational
10/02/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demoing the water line that runs under the building pad. 9-30-24 DP. Floyds crew is continuing to demo old water pipe from building pad. They are also prepping to run a new line to a fire hydrant. 10-1-24 DP. No work for FEI today. They were just working on digging for the electric company. 12-2-24 DP. No work for FEI, they are just setting steel for the building.
Underground Plumbing Inspection - Commercial Partial 12/5/2024 12/5/2024 12/05/2024
Misc
Informational
12/05/2024
PIPING AWAY FROM SLAB OUT 20'
Erosion Control Inspection Partial 12/5/2024 12/5/2024 12/05/2024
Misc
Informational
10/30/2024
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week.
Piers/Caissons Inspection - Commercial Partial 12/19/2024 12/19/2024 12/19/2024
Misc
Corrective Action Required
12/19/2024
- Light pole bases at Norh edge of building, East-West 5 towards parking area Conduits not installed
Erosion Control Inspection Partial 12/24/2024 12/24/2024 12/24/2024
Misc
Informational
12/05/2024
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin.
Detention Basin Partial 12/30/2024 12/30/2024 12/31/2024
Misc
Informational
10/11/2024
10-3-24 DP. Floyds crew set the outflow structure. It looks high for a detention basin. There will be water retained in the bowl. 10-4-24 DP. Floyds crew is onsite cleaning up around the detention basin. It is scheduled to get hydroseeded Monday. McCown Gordon is currently looking into the outflow structure. It is set within a 1/10. The inflow pipe has 1% fall into the basin which is what its called out for. The problem is that with the outflow being so high, water will sit in the pipe 10-10-24 DP. I brought attention again to the outflow structure of the detention basin. They outflow structure will not allow the bottom 3' of the basin to drain. Advised Lindsay with McCown Gordon to have their civil engineer resubmit their fix to the city. There was an email sent today from Lindsay with Correspondence to Scott Ready and Sue Pyles. 12-30-24. I noticed the east side of the detention basin has been disturbed. I was told by a carpenter with McCown Gordon onsite that they replaced the outflow structure in the detention basin. If that is true, no update plans have been resubmitted or approved by the city. We also need to reestablish vegetation around that box and until it's established there needs to be erosion control in place to keep the silt from washing into the detention basin. There was also a decent amount of trash in the detention basin that needs to be removed.
ESC - (Vegetation/Ground Cover) Partial 1/15/2025 1/15/2025 01/15/2025
Misc
Informational
01/15/2025
1-15-25 DP. No ESC issues at this time
Site Visit Partial 1/15/2025 1/15/2025 01/15/2025
Misc
Informational
12/02/2024
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demoing the water line that runs under the building pad. 9-30-24 DP. Floyds crew is continuing to demo old water pipe from building pad. They are also prepping to run a new line to a fire hydrant. 10-1-24 DP. No work for FEI today. They were just working on digging for the electric company. 12-2-24 DP. No work for FEI, they are just setting steel for the building. 1-15-25 DP. There has been no work on site for FEI since before Thanksgiving
Underground Plumbing Inspection - Commercial Partial 1/28/2025 1/28/2025 01/28/2025
Misc
Informational
12/05/2024
PIPING AWAY FROM SLAB OUT 20'
Misc
Corrective Action Required
01/28/2025
Tank in and input side complete, ok to cover. Inspection of discharge connection pending
Miscellaneous Inspection Partial 1/28/2025 1/28/2025 01/28/2025
Misc
Informational
01/28/2025
1-28-25 DP. Floyd with She Dig's It was onsite today tying in their grease interceptor. That inspection was completed by Shawn.
Occupancy Inspection - Water Utilities Passed 02/05/2025
Erosion Control Inspection Partial 2/6/2025 2/6/2025 02/06/2025
Misc
Informational
12/24/2024
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud.
Underground Plumbing Inspection - Commercial Partial 2/10/2025 2/10/2025 02/10/2025
Misc
Informational
01/28/2025
PIPING AWAY FROM SLAB OUT 20'
Misc
Informational
02/10/2025
Tank in and input side complete, ok to cover. Inspection of discharge connection pending
Informational
02/10/2025
- sanitary down to back of interseptor, ok to cover
Underground Plumbing Inspection - Commercial Passed 2/11/2025 2/11/2025 02/11/2025
Misc
Resolved
02/11/2025
PIPING AWAY FROM SLAB OUT 20'
Erosion Control Inspection Partial 2/11/2025 2/11/2025 02/11/2025
Misc
Informational
02/06/2025
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud. 2-11-25 DP. No ESC issues at this time. Rock was added to reestablish the construction entrance.
Sanitary Sewer Construction Inspection Passed 2/12/2025 2/12/2025 02/14/2025
Misc
Informational
02/14/2025
2-14-25 DP. Floyds crew connected the sewer pipe from the grease trap to the private sewer main. They tied the wye in to a 6" clay main. They installed tracer wire and also sewer tape.
Gas Service Inspection - Commercial Passed 2/27/2025 2/27/2025 02/27/2025
Misc
Resolved
02/27/2025
No pressure or Bonding
In-wall Inspection Partial 3/21/2025 3/21/2025 03/21/2025
Misc
Informational
03/21/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107 -A116 -A118B SECOND FLOOR EAST WALL MEZZANINE WALL A208
Piers/Caissons Inspection - Commercial Partial 3/24/2025 3/24/2025 03/24/2025
Misc
Corrective Action Required
12/19/2024
- Light pole bases at Norh edge of building, East-West 5 towards parking area Conduits not installed - 4 Light pole bases North East corner of lot Conduit not ran ( ok to pour)
Erosion Control Inspection Partial 3/26/2025 3/26/2025 03/26/2025
Misc
Informational
02/11/2025
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud. 2-11-25 DP. No ESC issues at this time. Rock was added to reestablish the construction entrance.
In-wall Inspection Partial 3/26/2025 3/26/2025 03/26/2025
Misc
Informational
03/21/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -A208, 118B, A104, A105, A117, A119, A120, A121, A122
Piers/Caissons Inspection - Commercial Partial 4/1/2025 4/1/2025 03/31/2025
Misc
Corrective Action Required
03/24/2025
APPROVED - Light pole bases at Norh edge of building, East-West 5 towards parking area Conduits inspected - 4 Light pole bases North East corner of lot Conduit inspected - Light pole base at South of biulding , conduit inspected
In-wall Inspection Partial 3/31/2025 3/31/2025 03/31/2025
Misc
Informational
03/26/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected.
Above Ceiling Inspection Partial 3/31/2025 03/31/2025
Misc
Informational
03/31/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
In-wall Inspection Partial 4/1/2025 04/01/2025
Misc
Informational
03/31/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected.
In-wall Inspection Partial 4/4/2025 4/4/2025 04/04/2025
Misc
Informational
04/01/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25
In-wall Inspection Partial 4/8/2025 4/8/2025 04/08/2025
Misc
Informational
04/04/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25
In-wall Inspection Partial 4/9/2025 4/9/2025 04/09/2025
Misc
Informational
04/08/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 - North wall
In-wall Inspection Partial 4/10/2025 4/10/2025 04/10/2025
Misc
Informational
04/09/2025
AREAS APPROVED ONE SIDE FRAMING, OK TO COVER ONE SIDE. -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 - South wall - North wall
Pavement-Proof Roll Partial 4/10/2025 4/10/2025 04/10/2025
Misc
Informational
04/10/2025
4-10-25 Dustin A, Proof roll on south end of building for parking and curb , passed
In-wall Inspection Partial 4/14/2025 4/14/2025 04/14/2025
Misc
Informational
04/10/2025
AREAS APPROVED -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 -intierior of all extiertier walls - first floor bahrooms - dtinking fountain
In-wall Inspection Partial 4/15/2025 4/15/2025 04/15/2025
Misc
Informational
04/14/2025
AREAS APPROVED -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 -intierior of all extiertier walls - first floor bahrooms - dtinking fountain - A201
Erosion Control Inspection Partial 4/15/2025 4/15/2025 04/18/2025
Misc
Informational
03/26/2025
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud. 2-11-25 DP. No ESC issues at this time. Rock was added to reestablish the construction entrance. 4-15-25 DP. No ESC issues at this time.
Sidewalk Inspection Partial 4/14/2025 4/14/2025 04/18/2025
Misc
Informational
04/18/2025
4-14-25 DP. Crew poured sidewalk on the north side of the property that connected to existing. They used AB3 and had adequate amount, compacted. They had expansion join laid out where it needed to go and cross slopes looked to be in compliance. I told them with the SW being so wide, that I will confirm cross slopes on final.
In-wall Inspection Partial 4/18/2025 4/18/2025 04/18/2025
Misc
Informational
04/15/2025
AREAS APPROVED -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 -intierior of all extiertier walls - first floor bahrooms - dtinking fountain - A201
Misc
Informational
04/18/2025
- elevator shaft wall - first part of elevetor ceiling
Rough Framing Inspection - Commercial Partial 4/22/2025 4/22/2025 04/22/2025
Misc
Corrective Action Required
04/22/2025
ROOMS 206,207 second floor
Rated Assembly Inspection Partial 4/22/2025 4/22/2025 04/22/2025
ELEVATOR 1
Corrective Action Required
04/22/2025
approved areas shaft liner first layer back side first layer hat
In-wall Inspection Partial 4/24/2025 4/24/2025 04/24/2025
Misc
Informational
04/18/2025
AREAS APPROVED -A107, A116, A118B SECOND FLOOR EAST WALL MEZZANINE WALL -and West wall -A208, 118B, A104, A105, A117, A119, A120, A121, A122, 204, 205 North West corner and West wall 4 bays of electical and framing inspected. A4 1.4-1.6 1.8 W wall Locker room entry way Locker room and changing room -Mitchell Schwarz 04/04/25 -intierior of all extiertier walls - first floor bahrooms - dtinking fountain - A201
Misc
Informational
04/18/2025
- elevator shaft wall - first part of elevetor ceiling -
Above Ceiling Inspection Partial 4/28/2025 4/28/2025 04/28/2025
Misc
Informational
03/31/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
04/28/2025
- Hard lid above stairs approved
Erosion Control Inspection Partial 5/6/2025 5/6/2025 05/06/2025
Misc
Informational
04/18/2025
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud. 2-11-25 DP. No ESC issues at this time. Rock was added to reestablish the construction entrance. 4-15-25 DP. No ESC issues at this time. 5-6-25 DP. No ESC issues at this time.
Site Visit Failed 5/6/2025 5/6/2025 05/06/2025
Misc
Informational
01/15/2025
8-26-24 DP. Crew was on site but working on the building pad. Nothing for FEI today. 9-4-24 DP. Crew was on site locating electric for where the water and storm will run along it. They did this all day. 9-17-24 NS Site visited it and that water main is being flushed today at 4pm. 9-26-24 DP. Floyds crew is onsite today demoing the water line that runs under the building pad. 9-30-24 DP. Floyds crew is continuing to demo old water pipe from building pad. They are also prepping to run a new line to a fire hydrant. 10-1-24 DP. No work for FEI today. They were just working on digging for the electric company. 12-2-24 DP. No work for FEI, they are just setting steel for the building. 1-15-25 DP. There has been no work on site for FEI since before Thanksgiving
Miscellaneous Correction
Corrective Action Required
05/06/2025
5-6-25 DP. Outside of the construction entrance, there is a blow up in the road. This is needing repairs as it is bad. This will require a full depth repair and need to be replaced from curb to curb.
Above Ceiling Inspection Partial 5/8/2025 5/8/2025 05/08/2025
Misc
Informational
04/28/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
04/28/2025
- Hard lid above stairs approved
Misc
Corrective Action Required
05/08/2025
- MC support wire shall not be part of grid support in rooms a110,a112
Above Ceiling Inspection Partial 5/8/2025 5/8/2025 05/08/2025
Misc
Informational
05/08/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/08/2025
- Hard lid above stairs approved - A 110,A 112
Misc
Resolved
05/08/2025
- MC support wire shall not be part of grid support in rooms a110,a112
Above Ceiling Inspection Partial 5/12/2025 05/12/2025
Misc
Informational
05/08/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/08/2025
- Hard lid above stairs approved - A 110,A 112 - Hard lid above main floor mezzanine ok.
Above Ceiling Inspection Partial 5/15/2025 5/15/2025 05/15/2025
Misc
Informational
05/12/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/12/2025
APPROVED AREAS - Hard lid above stairs approved - A 110,A 112 - Hard lid above main floor mezzanine ok. - Extierior soffits framing front side ; South and middle soffit
Above Ceiling Inspection Partial 5/19/2025 05/19/2025
Misc
Informational
05/15/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/15/2025
APPROVED AREAS - Hard lid above stairs approved - A 110,A 112 - Hard lid above main floor mezzanine ok. - Extierior soffits framing front side ; South and middle soffit - 204,205 and hallway East of elevator
Pavement-Aggregate Base Partial 5/19/2025 5/19/2025 05/20/2025
Misc
Informational
05/20/2025
5-19-25 DP. Crew did a proof roll on the dock pad yesterday which did pass. However, it rained over 1/4" last night and will need to be proof rolled again.
Above Ceiling Inspection Partial 5/20/2025 05/20/2025
Misc
Informational
05/19/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/19/2025
APPROVED AREAS - Hard lid above stairs approved - A 110,A 112 - Hard lid above main floor mezzanine ok. - Extierior soffits framing front side all 3 - 204,205 and hallway East of elevator
Above Ceiling Inspection Partial 5/23/2025 5/23/2025 05/23/2025
Misc
Informational
05/20/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/20/2025
APPROVED AREAS - Hard lid above stairs approved - A 110,A 112,A203,A203A,A203B - Hard lid above main floor mezzanine ok. - Extierior soffits framing front side all 3 - 204,205 and hallway East of elevator
Footing Inspection - Commercial Partial 5/27/2025 05/27/2025
Miscellaneous Correction
Corrective Action Required
11/07/2024
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6 Sunken pads @4 1.7-1.9 Footing Northern end A1-A5 Footing East and west 1.1-1.3 Slab ready to pour south East 1.2-1.4 :: A4-A5
Misc
Corrective Action Required
05/27/2025
PHASE 3 FOOING FOR WELDING ROOM
Piers/Caissons Inspection - Commercial Partial 5/30/2025 5/30/2025 05/30/2025
Misc
Corrective Action Required
03/31/2025
APPROVED - Light pole bases at Norh edge of building, East-West 5 towards parking area Conduits inspected - 4 Light pole bases North East corner of lot Conduit inspected - Light pole base at South of biulding ( conduit not inspected) - Light pole base North West corner
Above Ceiling Inspection Partial 5/30/2025 5/30/2025 05/30/2025
Misc
Informational
05/23/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/23/2025
APPROVED AREAS - Hard lid above stairs approved - A 110,A 112,A203,A203A,A203B - Hard lid above main floor mezzanine ok. - Extierior soffits framing front side all 3 - 204,205 and hallway East of elevator - framing of hard lid second floor mezzanine
Footing Inspection - Commercial Partial 6/2/2025 6/2/2025 06/02/2025
Miscellaneous Correction
Corrective Action Required
05/27/2025
Print S1-1A partial Approved FOOTING-A.5. From 1.15 to 1.2[12-19] - A3- A1 @ 1.9 UFER LOCATION - Elevator pit floor - 4 center column pads- A4- 12,13,14,15 - Elevator shaft walls - SOUTH SIDE F1-1.10 -A4-1.8 COLOUMN PAD BOTOM HALF - A4-1.9 -A.5-1.1 - CAPS ON A5- 1.5,1.6,1.7,1.8,1.9 - A3: 1.7,1.8 - COLUMN PADS A2 -1.6, 1.7 -A1 1.7-1.8 - F1: 1.5-1.7 10/15/24 - F2 GRADE BEAM/- F1 1.5.5 AND F1 1.7 9 building connector - A1. 1.7-1.3 West side footing and pads Pads 1.3 , 1.4 @ A6 Sunken pads @4 1.7-1.9 Footing Northern end A1-A5 Footing East and west 1.1-1.3 Slab ready to pour south East 1.2-1.4 :: A4-A5
Misc
Corrective Action Required
05/27/2025
PHASE 3 FOOING - FOR WELDING ROOM - 2 inteirior steel for pads for coloumns. 6/2/2025
Erosion Control Inspection Partial 6/4/2025 6/4/2025 06/04/2025
Misc
Informational
05/06/2025
9-10-24 DP. No ESC issues. 9-30-24 DP. No ESC issues. 10-30-24 DP. No ESC issues 12-5-24 DP. Please make sure all erosion control is in place and jobsites are dressed up. DNR audits start next week. 12-24-24 JS. Install silt fence around areas that are not vegetated. Remove trash from detention basin. 2-6-25 DP. No obvious issues with ESC at this time. Please add large rock and reestablish the construction entrance as the rock as been beat into the mud. 2-11-25 DP. No ESC issues at this time. Rock was added to reestablish the construction entrance. 4-15-25 DP. No ESC issues at this time. 5-6-25 DP. No ESC issues at this time. 6-4-25 DP. No ESC issues at this time. Contractor has been uploading SWPPP reports to the portal.
Piers/Caissons Inspection - Commercial Partial 6/5/2025 6/5/2025 06/05/2025
Misc
Corrective Action Required
05/30/2025
APPROVED - Light pole bases at Norh edge of building, East-West 5 towards parking area Conduits inspected - 4 Light pole bases North East corner of lot Conduit inspected - Light pole base at South of biulding ( conduit not inspected) - 4 Light pole base North West corner of new building
Above Ceiling Inspection Partial 6/6/2025 6/6/2025 06/06/2025
Misc
Informational
05/30/2025
- plumbing in wall and above ceiling in: A117, A119 APPROVED SHAFT LINER 6' OK TO COVER at elevator A113 side
Misc
Informational
05/30/2025
APPROVED AREAS - ALL Hard lid approved - Extierior soffits framing and above ceiling front side all 3
Rated Assembly Inspection Partial 6/10/2025 6/10/2025 06/10/2025
ELEVATOR 1
Corrective Action Required
04/22/2025
approved areas shaft liner first layer back side first layer hat Outside elevator all sides
Documents & Images
Date Uploaded File Type Document Name
02/22/2024 Application Form Commercial Permit Application to City
02/22/2024 Plans Drawings_13-23128-00_MCCLongviewAutomotiveInstitute_PermitSet_240216
02/22/2024 Specifications Specs_13-23128-00_MCCLongviewAutomotiveInstitute_BidSet_Volume2of3_240209
02/22/2024 Specifications Specs_13-23128-00_MCCLongviewAutomotiveInstitute_BidSet_Volume3of3_240209
02/26/2024 Letter License Tax Bill
03/08/2024 Letter DS P/R Corrections Document
03/30/2024 Plans Drawings_13-23128-00_MCCLongviewAutomotiveInstitute_PermitSet_240329
03/30/2024 Letter Responses to City Comments_240329
03/30/2024 Engineer Report/Study 338-2484 Geo Report 12_1_2023 - Sealed
04/01/2024 Engineer Report/Study MCC-Longview Automotive Institute - Letter of Special Inspection_240401
04/09/2024 Approved Plans Approved MCC plans
04/16/2024 Receipt Receipt for transaction:2024-002409
04/17/2024 Plans Drawings_13-23128-00_MCCLongviewAutomotiveInstitute_Renovation PermitSet_240417
04/17/2024 Approved Plans Approved plans for Interior Renovations
04/18/2024 Letter DS Building Permit
06/03/2024 Approved Plans Approved plan revisions
06/05/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
07/05/2024 4352CK MCC Auto FS Calcs- PE Stamped
07/05/2024 4352CK MCC Auto FS Plans- PE Stamped
07/15/2024 Letter INSPECTION SUMMARY
07/15/2024 Plans 2024_0708 MCC - LV Automotive FA - JRGCS
07/15/2024 Specifications 2024_0708 MCC - LV Automotive FA Submittal R0 - JRGCS
07/17/2024 Letter INSPECTION SUMMARY
07/17/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/19/2024 Letter INSPECTION SUMMARY
07/22/2024 Approved Plans Approved FDP Full Plan Set_PL2024131_7.22.2024_Administrative
07/22/2024 Letter INSPECTION SUMMARY
07/22/2024 Letter Fire (Sprinkler) Plan Review
07/22/2024 Plans Drawings_13-23128-00_MCCLongviewAutomotiveInstitute_Permit Set_240722
07/24/2024 Letter INSPECTION SUMMARY
07/24/2024 Plans 4352CK MCC Automotive Institute FS Dwg- PE Stamped
07/25/2024 Letter Letter for permit documents_240725
07/25/2024 Plans Drawings_13-23128-00_MCCLongviewAutomotiveInstitute_Permit Set_240725
07/26/2024 Letter INSPECTION SUMMARY
07/29/2024 Receipt Receipt for transaction:2024-006295
07/29/2024 Approved Plans Approved phased construction plans
07/29/2024 Letter Fire (Alarm) Plan Review Notice
07/31/2024 Plans 2024_0730 MCC - LV Automotive FA Dwgs R2 - JRGCS
07/31/2024 2024_0708 MCC - LV Automotive FA Submittal R2 - JRGCS
08/01/2024 Letter INSPECTION SUMMARY
08/05/2024 2024_0730 MCC - LV Automotive FA Dwgs R2 - JRGCS APPROVED
08/05/2024 Letter Fire (Alarm) Plan Review Notice
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/07/2024 Letter INSPECTION SUMMARY
08/08/2024 3RD Party Insp Report Collision Lab - Welding Certification
08/09/2024 224068c Discrepancy Log - Collision Lab
08/12/2024 Letter INSPECTION SUMMARY
08/19/2024 Letter DS Building Permit
08/22/2024 Letter INSPECTION SUMMARY
08/22/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
08/27/2024 Letter INSPECTION SUMMARY
08/28/2024 4352CK MCC Automotive Institute FS Dwg- PE Stamped RFC
08/29/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/04/2024 Letter INSPECTION SUMMARY
09/06/2024 Letter INSPECTION SUMMARY
09/06/2024 Letter INSPECTION SUMMARY
09/10/2024 Letter INSPECTION SUMMARY
09/16/2024 Letter INSPECTION SUMMARY
09/16/2024 Letter License Tax Bill
09/19/2024 Letter INSPECTION SUMMARY
09/20/2024 MCC Longview 4 in and 6 in water samples 1
09/20/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/21/2024 MCC Longview 4 in and 6 in water sample 2
09/21/2024 Letter INSPECTION SUMMARY
09/21/2024 Letter INSPECTION SUMMARY
09/23/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
09/26/2024 Letter INSPECTION SUMMARY
09/26/2024 Letter INSPECTION SUMMARY
09/26/2024 Letter INSPECTION SUMMARY
09/26/2024 Letter INSPECTION SUMMARY
09/26/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
09/27/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
10/02/2024 Letter INSPECTION SUMMARY
10/02/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/04/2024 Letter INSPECTION SUMMARY
10/04/2024 Letter INSPECTION SUMMARY
10/04/2024 Letter INSPECTION SUMMARY
10/08/2024 Letter INSPECTION SUMMARY
10/08/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/11/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
10/15/2024 Letter INSPECTION SUMMARY
10/15/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/18/2024 Letter INSPECTION SUMMARY
10/18/2024 Letter INSPECTION SUMMARY
10/18/2024 Letter INSPECTION SUMMARY
10/21/2024 Letter INSPECTION SUMMARY
10/21/2024 Letter INSPECTION SUMMARY
10/23/2024 Letter INSPECTION SUMMARY
10/23/2024 Letter INSPECTION SUMMARY
10/23/2024 Letter INSPECTION SUMMARY
10/24/2024 Letter INSPECTION SUMMARY
10/24/2024 Letter INSPECTION SUMMARY
10/28/2024 Letter INSPECTION SUMMARY
10/29/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
11/04/2024 MCC Longview Sample 1 for pvt service pvt fire line and pvt hydrant line
11/04/2024 MCC Longview Sample 2 for pvt service pvt fire line and pvt hydrant line
11/04/2024 Letter INSPECTION SUMMARY
11/04/2024 Letter INSPECTION SUMMARY
11/07/2024 Letter INSPECTION SUMMARY
11/08/2024 Letter INSPECTION SUMMARY
12/02/2024 Letter INSPECTION SUMMARY
12/05/2024 Letter INSPECTION SUMMARY
12/05/2024 Letter INSPECTION SUMMARY
12/19/2024 Letter INSPECTION SUMMARY
12/24/2024 Letter INSPECTION SUMMARY
12/31/2024 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/28/2025 Letter INSPECTION SUMMARY
01/28/2025 Letter INSPECTION SUMMARY
01/31/2025 4352CK MCC Auto FS Dwg Rev 2- PE Stamped
01/31/2025 4352CK MCC Auto FS Calc Rev 2- PE Stamped
02/03/2025 4352CK MCC Auto FS Dwg Rev 2- PE Stamped
02/03/2025 MCC-Auto Revision Letter
02/06/2025 Letter INSPECTION SUMMARY
02/07/2025 4352CK MCC Auto FS Dwg Rev 2- PE Stamped0 RFC
02/07/2025 Letter Fire (Sprinkler) Plan Review
02/10/2025 Letter INSPECTION SUMMARY
02/11/2025 Letter INSPECTION SUMMARY
02/11/2025 Letter INSPECTION SUMMARY
02/14/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
03/21/2025 Letter INSPECTION SUMMARY
03/24/2025 Letter INSPECTION SUMMARY
03/26/2025 Letter INSPECTION SUMMARY
03/26/2025 Letter INSPECTION SUMMARY
03/31/2025 Letter INSPECTION SUMMARY
03/31/2025 Letter INSPECTION SUMMARY
04/01/2025 Letter INSPECTION SUMMARY
04/04/2025 Letter INSPECTION SUMMARY
04/04/2025 Letter INSPECTION SUMMARY
04/08/2025 Letter INSPECTION SUMMARY
04/09/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/10/2025 Letter INSPECTION SUMMARY
04/14/2025 Letter INSPECTION SUMMARY
04/15/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
04/22/2025 Letter INSPECTION SUMMARY
04/22/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter INSPECTION SUMMARY
04/28/2025 Letter INSPECTION SUMMARY
05/06/2025 Letter INSPECTION SUMMARY
05/06/2025 Letter INSPECTION SUMMARY
05/08/2025 Letter INSPECTION SUMMARY
05/08/2025 Letter INSPECTION SUMMARY
05/15/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
05/20/2025 Letter INSPECTION SUMMARY
05/20/2025 Letter INSPECTION SUMMARY
05/23/2025 Letter INSPECTION SUMMARY
05/27/2025 SWPPP INSPECTION MCC LONGVIEW 04-07-25
05/27/2025 SWPPP INSPECTION MCC LONGVIEW 04-21-25
05/27/2025 SWPPP INSPECTION MCC LONGVIEW 05-02-25
05/27/2025 SWPPP MCC LONGVIEW 01-08-25
05/27/2025 SWPPP MCC LONGVIEW 01-23-24
05/27/2025 SWPPP MCC LONGVIEW 01-31-25
05/27/2025 SWPPP MCC LONGVIEW 02-21-25
05/27/2025 SWPPP MCC LONGVIEW 02-28-25
05/27/2025 SWPPP MCC LONGVIEW 03-07-25
05/27/2025 SWPPP MCC LONGVIEW 03-14-25
05/27/2025 SWPPP MCC LONGVIEW 03-26-25
05/27/2025 SWPPP MCC LONGVIEW 08-15-24
05/27/2025 SWPPP MCC LONGVIEW 08-25-24
05/27/2025 SWPPP MCC LONGVIEW 09-17-24
05/27/2025 SWPPP MCC LONGVIEW 10-03-24
05/27/2025 SWPPP MCC LONGVIEW 10-09-24
05/27/2025 SWPPP MCC LONGVIEW 10-25-24
05/27/2025 SWPPP MCC LONGVIEW 10-31-24
05/27/2025 SWPPP MCC LONGVIEW 11-05-24
05/27/2025 SWPPP MCC LONGVIEW 11-14-24
05/27/2025 SWPPP MCC LONGVIEW 11-19-24
05/27/2025 SWPPP MCC LONGVIEW 12-10-24
05/27/2025 SWPPP MCC LONGVIEW 12-18-24
05/27/2025 SWPPP MCC LONGVIEW 12-23-24
05/27/2025 Letter INSPECTION SUMMARY
05/30/2025 Letter INSPECTION SUMMARY
05/30/2025 Letter INSPECTION SUMMARY
06/02/2025 Letter INSPECTION SUMMARY
06/04/2025 Letter INSPECTION SUMMARY
06/05/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/10/2025 Letter INSPECTION SUMMARY
06/10/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home