Summary
PRRES20216099
Building Permit - Residential
Temporary Occupancy
MCFARLAND CUSTOM BUILDERS INC
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED AND FINISHED BASEMENT - COVERED DECK STOP WORK ORDER generated on 11/21/2023 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER removed on 11/29/2023 12:00 AM by username 'Khanh Nguyen'. Need to address to close this permit -Deck: provide a graspable handrail no wider than 3.5". You can install a 2x2 as a handrail and return both ends to the newel posts; the ledger board shall be fastened into the floor rim band per code; Cedar posts cannot be buried into soil; Provide hanger support for joists. Google Johnson County Deck Build Guideline. This freely available document will show you how to properly attach deck beam to each post -Splash blocks missing
11/23/2021
02/09/2022
06/25/2022
Locations
Contacts
MCFARLAND CUSTOM BUILDERS, Address:P O BOX 25285, Phone:(816) 215-1660  
MCFARLAND CUSTOM BUILDERS INC, Address:9601 NE BARRY RD STE 130  
Marisa McFarland, Address:suite 130  
MCFARLAND CUSTOM BUILDERS, Address:P O BOX 25285, Phone:(816) 215-1660  
JOE KILOWATT INC, Address:6506 ROYAL, Phone:(816) 792-4888  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sewer Connection Fee $420.00 $420.00 Paid 02/09/2022
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 02/09/2022
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 02/09/2022
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 02/09/2022
8350015-Water Meter Fee $479.24 $479.24 Paid 02/09/2022
9110078-Valuation Fee New Single Family $1,451.11 $1,451.11 Paid 02/09/2022
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 05/14/2024
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 05/14/2024
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 05/14/2024
9110078-Additional Permit Fee $180.75 $180.75 Paid 05/14/2024
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 05/17/2024
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 04/08/2025
9110080-3rd and Subsequent Inspection Fee (Per Hour) $500.00 $500.00 Paid 04/08/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Occupancy Inspection - Codes Residential Pending
Misc
Partial Correction
04/09/2025
-Deck: provide a graspable handrail no wider than 3.5". You can install a 2x2 as a handrail and return both ends to the newel posts; the ledger board shall be fastened into the floor rim band per code; Cedar posts cannot be buried into soil; Provide hanger support for joists. Google Johnson County Deck Build Guideline. This freely available document will show you how to properly attach deck beam to each post **Install two 1/2” through bolts connection of beam to each supporting post; or approved equivalent connection **Nail all hangers. A hanger or approved device is required at each joist connection to ledger board **Cedar posts cannot be buried. Expose posts **A graspable, continuous, and uninterrupted handrail with maximum width of 3.5” shall be installed on one side of stair. Return both ends to newel posts -Splash blocks missing **Provide splash blocks that can direct downspout water min 36” away from building
Sewer Service Inspection - R Passed 6/30/2022 06/30/2022
Underslab Plumbing Inspection - Residential Passed 6/30/2022 6/30/2022 06/30/2022
Water Service Inspection - R Partial 6/30/2022 06/30/2022
Miscellaneous Inspection Failed 6/30/2022 06/30/2022
Misc
Corrective Action Required
06/30/2022
-SUBMIT 3RD PARTY FOOTING INSPECTION TO THE CITY WITHIN TWO DAYS. NO FURTHER INSPECTION UNTIL THE FOOTING APPROVAL IS SUBMITTED
Water Service Inspection - R Passed 7/1/2022 (9:45) 7/1/2022 07/01/2022
Erosion Control Inspection Residential Failed 6/14/2023 06/14/2023
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/14/2023
RESTORE EROSION CONTROL INSTALLATION ALONG THE STREET. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Piers/Caissons Inspection - Residential Failed 6/14/2023 (8:00) 6/14/2023 06/14/2023
Misc
Corrective Action Required
06/14/2023
Deck has been enlarged from approved plan. The enlarged deck joists on the north side are way over-spanned. Submit revised plan for the deck **The three 24” diameter piers on original plan are ok to pour
Driveway Inspection Not Ready 6/14/2023 6/14/2023 06/14/2023
Misc
Corrective Action Required
06/14/2023
6-14-23 DP. Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready.
Sidewalk Inspection Not Ready 6/14/2023 6/14/2023 06/14/2023
Misc
Corrective Action Required
06/14/2023
Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready.
Erosion Control Inspection Residential Failed 9/8/2023 09/08/2023
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/14/2023
**Restore erosion control along the street **Weed taller than 10" shall be mowed **Failure to correct the deficiencies abovewithin 2 days will result in issuance of a stop-work order
Erosion Control Inspection Residential Passed 9/13/2023 09/13/2023
DCM2 ESC DEFICIENT INSTALLATION
Resolved
09/13/2023
**Restore erosion control along the street **Weed taller than 10" shall be mowed **Failure to correct the deficiencies abovewithin 2 days will result in issuance of a stop-work order
Gas Service Inspection - Residential Passed 11/6/2023 11/6/2023 11/06/2023
All Rough Inspection - Residential Failed 11/6/2023 11/6/2023 11/06/2023
MISC
Corrective Action Required
06/12/2023
FOOTING IS NOT APPROVED, SUBMIT ENGINEER INSPECTION REPORT TO CITY
Misc
Corrective Action Required
11/06/2023
**Post address -Provide flashing above horizontal window trims exposed to rain -The exterior receptacle boxes shall flush with exterior wall siding or install box extensions -Complete plumbing chase at entry closet and Fb as required -Protect water lines inside entry closet -Engineer to address the living room rear wall not strapped per plan. **I will recheck the house on 4813 Jamestown again. I called Andy last week but had problem with cellular signal -Fb all wall plate penetrations ; Fb floor penetrations at plumbing traps -Bond together all EGCs inside boxes with listed devices (wire nuts, crimps, etc) throughout -Complete framing plumbing chase at rear and Fb from joist space -Over-notched joists near plumbing chase (not framed yet) -Nail corner studs w/16d @12” oc or equivalent nailing -Fill in void at deck door strike plate jamb from 12” above to 12” below strike plate; install security blocking -Support rafters to header above rear dining -Rear dining CSPF walls not framed per code -Complete electrical to rear dining receptacles; cannot supply deck receptacle from the dining receptacle 20-amp circuit -Protect wiring at bottom wall plate near gas cooktop; protect home runs at kitchen/garage wall where located within 1.25” of nailing surface -Seal penetrations of return air space throughout house. -Fb garage chase from soffit space -Anchor garage sill plates within 12” of breaks; anchor rear garage wall sill plate no more than 6 ft apart -Move garage receptacle to wall surface -Protect wiring at front garage wall corner -Complete garage electrical (wiring hanging at soffit) -Garage receptacle circuit wiring located outside stud/ceiling space -Install 2”x2” washers at garage PFH wall sill plates -The flexible bath fan duct cannot exceed 14 ft per label. Use combination of flexible duct and rigid duct to meet code requirement -Duct bath fan individually to outdoor. A flexible 4” duct can only handle one fan for a distance but not both fans -Strap rear bedroom wall top plates across cuts -Strap rear J&J bathroom wall plates lapped less than 24” -Have engineer address non-continuous studs at front bedroom gable wall -Complete duct chase in laundry **HOUSE NOT READY FOR INSPECTION. INSPECTION TERMINATED. THE ABOVE LIST IS NOT A COMPLETE LIST
Electrical Service Inspection Failed 11/6/2023 11/6/2023 11/06/2023
Misc
Corrective Action Required
11/06/2023
-Replace damaged service entrance conductor -Provide insulating bushing at meter enclosure with #4 copper jumper -Install bonding bushing to bond the metal nipple enclosing the service entrance conductors -Install insulating bushing at feeder entry into service disconnect. Check feeder conductors for damage -Ground service per code -Close opening at bottom of meter enclosure and at top of the service disconnect -Secure SE cable within 12” of service disconnect enclosure; secure SE at max 4.5 ft intervals and within 12” of enclosures -Install insulating bushing at sub-panel -Remove the bonding screw from the grounded bar -Why the ufer grounding electrode conductor goes to the sub-panel??? This needs to go to the service disconnect to ground the service disconnect
Electrical Service Inspection Failed 11/21/2023 11/21/2023 11/21/2023
Misc
Corrective Action Required
11/06/2023
-Ground service per code -Secure SE cable within 12” of service disconnect enclosure; secure SE at max 4.5 ft intervals and within 12” of enclosures -Install insulating bushing at sub-panel -Remove the bonding screw from the grounded bar -Why the ufer grounding electrode conductor goes to the sub-panel??? This needs to go to the service disconnect to ground the service disconnect
All Rough Inspection - Residential Not Ready 11/21/2023 11/21/2023 11/21/2023
MISC
Corrective Action Required
11/06/2023
FOOTING IS NOT APPROVED, SUBMIT ENGINEER INSPECTION REPORT TO CITY NO FURTHER INSPECTION UNTIL 3RD PARTY FOOTING IS UPLOADED AND VERFIED
Misc
Corrective Action Required
11/06/2023
-Complete plumbing chase at entry closet and Fb as required -Protect water lines inside entry closet -Engineer to address the living room rear wall not strapped per plan. **I will recheck the house on 4813 Jamestown again. I called Andy last week but had problem with cellular signal -Fb all wall plate penetrations ; Fb floor penetrations at plumbing traps -Plumbing chase at rear and FB from joist space -Over-notched joists near plumbing chase (not framed yet) -Nail corner studs w/16d @12” oc or equivalent nailing -Fill in void at deck door strike plate jamb from 12” above to 12” below strike plate; install security blocking -Rear dining CSPF walls not framed per code(check nailing) -Complete electrical to rear dining receptacles; cannot supply deck receptacle from the dining receptacle 20-amp circuit -Protect wiring at bottom wall plate near gas cooktop -Fb garage chase from soffit space -Anchor garage sill plates within 12” of breaks; anchor rear garage wall sill plate no more than 6 ft apart -The flexible bath fan duct cannot exceed 14 ft per label. Use combination of flexible duct and rigid duct to meet code requirement -Duct bath fan individually to outdoor. A flexible 4” duct can only handle one fan for a distance but not both fans -Strap rear bedroom wall top plates across cuts -Have engineer address non-continuous studs at front bedroom gable wall -Complete duct chase in laundry and fireblock update plans to show finished basement and have permit changed to finished basement -fireblock all walls at basement bath at bottom of stairs -complete electrical in back bedroom in basement -fire block plum chase in back bedroom in basement -fire block plumbing furr down left or back patio door -provide support for lvl at back wall in basement -provide all steel columns in basement to plans -fire block wall space into furr down
Footing Inspection - Residential Failed - Stop Work 11/21/2023 11/21/2023 11/21/2023
Misc
Corrective Action Required
11/21/2023
Submit 3rd party footing inspection report. inspection report shall be submitted within 48hr of pour.
Footing Inspection - Residential Passed 11/29/2023
Misc
Resolved
11/29/2023
Submit 3rd party footing inspection report. inspection report shall be submitted within 48hr of pour.
Electrical Service Inspection Failed 11/29/2023 11/29/2023
Misc
Corrective Action Required
11/21/2023
-Ground service per code **Inside the service disconnect, connect the ufer grounding conductor to the service grounded bus bar at right side. NEC 250.24 -Install an insulation bushing to the protect the SE cable at entrance into the service disconnect enclosure -Install insulating bushing at sub-panel -Remove the bonding screw from the grounded bar
All Rough Inspection - Residential Failed 11/29/2023 11/29/2023 11/29/2023
MISC
Resolved
11/29/2023
FOOTING IS NOT APPROVED, SUBMIT ENGINEER INSPECTION REPORT TO CITY NO FURTHER INSPECTION UNTIL 3RD PARTY FOOTING IS UPLOADED AND VERFIED
Misc
Corrective Action Required
11/21/2023
-Engineer to address the living room rear wall not strapped per plan. **Page S505/item 3 shows the detail of the number and location of all the straps (total 12, including the foundation hold-down straps) and nailing requirement per PFH detail. The engineer must address whether the current installed strappings meets all the plan design/code requirement -Cannot supply the front outdoor receptacle from the breakfast dining circuit -Rear dining CSPF walls not framed per code **Nail siding to studs @ 3" oc; tie down the CSPF walls to floor joist rim w/ 2 straps for each CSPF wall -Anchor garage wall sill plate no more than 6 ft apart at rear of 3rd car garage -Have engineer address non-continuous studs at front bedroom gable wall **add more straps -Install a support stud under front porch ridge -Update plans to show finished basement and have permit changed to finished basement -Fb walls at basement bath from ceiling space -Provide smoke alarm inside the back basement bedroom and CO&smoke alarm outside bedroom -Anchor sill plates within 12” of break under hose bibb at rear basement bedroom closet
Electrical Service Inspection Failed 12/6/2023 12/06/2023
Misc
Corrective Action Required
11/29/2023
-Ground service per code **Inside the service disconnect, connect the ufer grounding conductor to the service grounded bus bar at right side. NEC 250.24 -Install an insulation bushing to the protect the SE cable at entrance into the service disconnect enclosure -Install insulating bushing at sub-panel
All Rough Inspection - Residential Failed 12/6/2023 12/6/2023 12/06/2023
Misc
Corrective Action Required
11/29/2023
-Rear dining CSPF walls not framed per code **Nail siding to studs @ 3" oc; tie down the CSPF walls to floor joist rim w/ 2 straps for each CSPF wall
Electrical Service Inspection Passed 12/11/2023 12/11/2023
Misc
Resolved
12/11/2023
-Ground service per code **Inside the service disconnect, connect the ufer grounding conductor to the service grounded bus bar at right side. NEC 250.24 -Install an insulation bushing to the protect the SE cable at entrance into the service disconnect enclosure -Install insulating bushing at sub-panel
All Rough Inspection - Residential Failed 12/11/2023 12/11/2023 12/11/2023
Misc
Corrective Action Required
12/06/2023
-Rear dining CSPF walls not framed per code **Nail siding to studs and sill plate @ 3" oc on both floors CSPF walls
All Rough Inspection - Residential Partial 1/4/2024 01/04/2024
Misc
Corrective Action Required
12/11/2023
-Rear dining CSPF walls not framed per code **Nail siding to studs @ 3" oc on both floors CSPF walls **interior braceed wall by GB method-OK
All Rough Inspection - Residential Passed 1/8/2024 1/8/2024 01/08/2024
Misc
Resolved
01/08/2024
-Rear dining CSPF walls not framed per code **Nail siding to studs @ 3" oc on both floors CSPF walls **interior braceed wall by GB method-OK
Driveway Inspection Partial 1/23/2024 01/23/2024
Misc
Corrective Action Required
06/14/2023
6-14-23 DP. Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready. 1-23-24 NS Site visited, no activity due to weather
Piers/Caissons Inspection - Residential Partial 2/2/2024 2/2/2024 02/02/2024
Misc
Corrective Action Required
06/14/2023
Deck has been enlarged from approved plan. The enlarged deck joists on the north side are way over-spanned. Submit revised plan for the deck **The three 24” diameter piers on original plan and two new piers are ok to pour
Erosion Control Inspection Residential Failed 2/2/2024 2/2/2024 02/02/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
02/02/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Clean street and install erosion control along street
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
03/18/2024
3-18-24 Dustin A, EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
Sidewalk Inspection Partial 2/2/2024 2/2/2024 02/02/2024
Misc
Informational
02/02/2024
Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready. 2-2-24 Dustin A, SW is formed and aggregate is being compacted monday morning. Will re check then
Sidewalk Inspection Partial 2/5/2024 2/5/2024 02/05/2024
Misc
Informational
02/05/2024
2-5-24 NS Site visited for pre-pour inspection and it appears that for a pre pour the sidewalk and driveway meet city standards. will come back after they pour.
Driveway Inspection Partial 2/2/2024 2/2/2024 02/05/2024
Misc
Corrective Action Required
01/23/2024
6-14-23 DP. Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready. 1-23-24 NS Site visited, no activity due to weather 2-2-24 DW is formed to city specs. Aggregate is being compacted monday morning before pour. Will stop by first thing and recheck 2-5-24 Dustin A, Came back by Approach is still not compacted. Contractor on site said they were pouring first thing monday morning (2-5-24), Nobody is on site. Aggregate is soft due to the rain. Cannot pour until doing so, Will need to recall pre pour inspection 2-5-24 NS Site visited for pre-pour inspection and it appears that for a pre pour the sidewalk and driveway meet city standards. will come back after they pour.
Erosion Control Inspection Residential Failed 5/13/2024 05/13/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
02/02/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. Clean street and install erosion control along street
Misc
Corrective Action Required
05/13/2024
EROSION CONTROL FAILED 24HRS TO REPAIR
Occupancy Inspection - Codes Residential Failed 5/13/2024 5/13/2024 05/13/2024
Misc
Corrective Action Required
05/13/2024
-Erosion control failed 24hrs to repair/replace -GFCI’s missing in garage -Label all non GFCI’s in garage -GFCI’s not functioning on 1st floor -Electrical service panel cover missing/not labeled -Final grade and sod not in place -Gutters, downspouts and splash blocks missing -Pay fees
Occupancy Inspection - Codes Residential Ready for Temp CO 5/14/2024 5/14/2024 05/14/2024
Misc
Informational
07/01/2022
SIDEWALK ACROSS THE STREET WAS DAMAGED DURING WATER SERVICE INSTALLATION. SW WILL HAVE TO BE REPAIRED
Misc
Corrective Action Required
05/14/2024
-Provide (2) 1/2” through bolts at post to deck beam connection -Final grade and sod not in place -Gutters, downspouts and splash blocks missing
Occupancy Inspection - Codes Residential Failed 05/17/2024
Misc
Corrective Action Required
05/14/2024
-Needs 1/2 through bolts at post to beam connections at deck -Final grade and sod not in place -Gutters, downspouts and splash blocks missing -Pay fees
Piers/Caissons Inspection - Residential Passed 05/17/2024
Misc
Resolved
05/17/2024
Deck has been enlarged from approved plan. The enlarged deck joists on the north side are way over-spanned. Submit revised plan for the deck **The three 24” diameter piers on original plan and two new piers are ok to pour
Plot Plan Inspection Passed 6/11/2024 06/11/2024
Erosion Control Inspection Residential Failed 6/11/2024 06/11/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
05/13/2024
Clean street and restore erosion control along street and rear flood basin
Sidewalk Inspection Passed 06/11/2024
Misc
Informational
02/05/2024
2-5-24 NS Site visited for pre-pour inspection and it appears that for a pre pour the sidewalk and driveway meet city standards. will come back after they pour. 5-13-24 NS I received a phone call about the erosion control and I will not be doing a final inspection until erosion control is fixed and cleaned up. 6-11-24 NS Site visited to do a final inspection Sidewalk and Driveway pass city standards and ADA. Sidewalk still needs to be cleaned.
Driveway Inspection Passed 2/5/2024 06/11/2024
Misc
Corrective Action Required
02/02/2024
6-14-23 DP. Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready. 1-23-24 NS Site visited, no activity due to weather 2-2-24 DW is formed to city specs. Aggregate is being compacted monday morning before pour. Will stop by first thing and recheck 5-13-24 NS I received a phone call about the erosion control and I will not be doing a final inspection until erosion control is fixed and cleaned up. 6-11-24 NS Site visited to do a final inspection Sidewalk and Driveway pass city standards and ADA. Sidewalk still needs to be cleaned.
Occupancy Inspection - Codes Residential Ready for Temp CO 6/28/2024 06/28/2024
Misc
Corrective Action Required
05/17/2024
-Deck: provide a graspable handrail no wider than 3.5". You can install a 2x2 as a handrail and return both ends to the newel posts; the ledger board shall be fastened into the floor rim band per code; Cedar posts cannot be buried into soil; Provide hanger support for joists; Needs 1/2 through bolts at post to beam connections at deck. Google Johnson County Deck Build Guideline. This freely available document will show you how to properly attach deck beam to each post -Final grade and sod not in place -Gutters, downspouts and splash blocks missing
Erosion Control Inspection Residential Failed 7/1/2024 07/01/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/11/2024
Clean street and restore erosion control along street and rear flood basin
Erosion Control Inspection Residential Failed 08/09/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
07/01/2024
Clean street and restore erosion control along street and rear flood basin 8-9-24 NS Site visited and it appears that storm inlet has a sock that is full of dirt and has grass growing out of them and needs to be cleaned out before 8-19-24 If not I will put a stop work order on this permit.
Occupancy Inspection - Codes Residential Failed 8/9/2024 8/9/2024 08/09/2024
Misc
Partial Correction
08/09/2024
-Deck: provide a graspable handrail no wider than 3.5". You can install a 2x2 as a handrail and return both ends to the newel posts; the ledger board shall be fastened into the floor rim band per code; Cedar posts cannot be buried into soil; Provide hanger support for joists. Google Johnson County Deck Build Guideline. This freely available document will show you how to properly attach deck beam to each post -Splash blocks missing
Erosion Control Inspection Residential Passed 8/19/2024 8/22/2024 08/22/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
08/09/2024
Clean street and restore erosion control along street and rear flood basin 8-9-24 NS Site visited and it appears that storm inlet has a sock that is full of dirt and has grass growing out of them and needs to be cleaned out before 8-19-24 If not I will put a stop work order on this permit. 8-22-24 NS Site Visited and no erosion control issues
Driveway Inspection Passed 9/24/2024 09/24/2024
Misc
Corrective Action Required
05/14/2024
6-14-23 DP. Between Nick and myself we have been out here multiple times today and they are still not ready. Talked to the foreman on site and he said they are going to push it to next week. Told them to recall in for a pre pour inspection when ready. 1-23-24 NS Site visited, no activity due to weather 2-2-24 DW is formed to city specs. Aggregate is being compacted monday morning before pour. Will stop by first thing and recheck 5-13-24 NS I received a phone call about the erosion control and I will not be doing a final inspection until erosion control is fixed and cleaned up. 9-24-24 NS Driveway and Sidewalk pass.
Sidewalk Inspection Passed 09/24/2024
Misc
Informational
05/14/2024
2-5-24 NS Site visited for pre-pour inspection and it appears that for a pre pour the sidewalk and driveway meet city standards. will come back after they pour. 5-13-24 NS I received a phone call about the erosion control and I will not be doing a final inspection until erosion control is fixed and cleaned up. 9-24-24 NS Driveway and Sidewalk pass.
Occupancy Inspection - Codes Residential Failed 4/9/2025 4/9/2025 04/09/2025
Misc
Partial Correction
08/09/2024
-Deck: provide a graspable handrail no wider than 3.5". You can install a 2x2 as a handrail and return both ends to the newel posts; the ledger board shall be fastened into the floor rim band per code; Cedar posts cannot be buried into soil; Provide hanger support for joists. Google Johnson County Deck Build Guideline. This freely available document will show you how to properly attach deck beam to each post **Install two 1/2” through bolts connection of beam to each supporting post; or approved equivalent connection **Nail all hangers. A hanger or approved device is required at each joist connection to ledger board **Cedar posts cannot be buried. Expose posts **A graspable, continuous, and uninterrupted handrail with maximum width of 3.5” shall be installed on one side of stair. Return both ends to newel posts -Splash blocks missing **Provide splash blocks that can direct downspout water min 36” away from building
Documents & Images
Date Uploaded File Type Document Name
12/27/2021 Plot Plan APPROVED PLOT PLAN
12/27/2021 Permit Codes Residential Plan Review
01/18/2022 CORRECTIONS-Codes Residential Plan Review-2
02/03/2022 Approved Plans APPROVED PLANS
02/07/2022 Application Form APPLICATION
02/07/2022 Permit Codes Residential Plan Review
02/09/2022 Permit DS Building Permit
02/09/2022 Receipt Receipt for transaction:2022-000710
06/30/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
06/30/2022 Letter INSPECTION SUMMARY
07/01/2022 Letter INSPECTION SUMMARY
06/14/2023 Letter INSPECTION SUMMARY
06/14/2023 Letter INSPECTION SUMMARY
06/14/2023 Letter INSPECTION SUMMARY
06/14/2023 Letter INSPECTION SUMMARY
09/08/2023 Letter INSPECTION SUMMARY
09/13/2023 Letter INSPECTION SUMMARY
10/20/2023 4728 Jamestowne Dr - framing & strapping
10/25/2023 138 basement drawing
10/25/2023 138 Letter
11/06/2023 Letter INSPECTION SUMMARY
11/06/2023 Letter INSPECTION SUMMARY
11/06/2023 Letter INSPECTION SUMMARY
11/21/2023 Letter INSPECTION SUMMARY
11/21/2023 138 Monticello FTNG
11/21/2023 Letter INSPECTION SUMMARY
11/21/2023 Letter Stop Work Order
11/29/2023 Letter INSPECTION SUMMARY
11/29/2023 Letter INSPECTION SUMMARY
11/29/2023 Letter INSPECTION SUMMARY
11/30/2023 Approved Plans APPROVED BASEMENT FINISH
12/01/2023 4728 Jamestowne Dr - rvised framing & strapping
12/06/2023 Letter INSPECTION SUMMARY
12/06/2023 Letter INSPECTION SUMMARY
12/11/2023 Letter INSPECTION SUMMARY
12/11/2023 Letter INSPECTION SUMMARY
01/04/2024 Letter INSPECTION SUMMARY
01/08/2024 Letter INSPECTION SUMMARY
01/23/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/02/2024 Letter INSPECTION SUMMARY
02/05/2024 Letter INSPECTION SUMMARY
02/05/2024 Letter INSPECTION SUMMARY
02/05/2024 Letter INSPECTION SUMMARY
03/18/2024 Letter INSPECTION SUMMARY
04/12/2024 3RD Party Insp Report Monticello, Lot 138 - deck piers
05/13/2024 Letter INSPECTION SUMMARY
05/13/2024 Letter INSPECTION SUMMARY
05/13/2024 Letter INSPECTION SUMMARY
05/13/2024 Letter INSPECTION SUMMARY
05/14/2024 Letter INSPECTION SUMMARY
05/14/2024 Letter INSPECTION SUMMARY
05/14/2024 Receipt Receipt for transaction:2024-003391
05/17/2024 Certificate/License Codes Temporary Certificate of Occupancy
05/17/2024 Receipt Receipt for transaction:2024-003623
05/17/2024 Letter INSPECTION SUMMARY
06/10/2024 Monticello Lot 138 Asbuilt 24_0607
06/10/2024 Plot Plan approved as graded plot plan
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/28/2024 Letter INSPECTION SUMMARY
07/01/2024 Letter INSPECTION SUMMARY
07/01/2024 Letter INSPECTION SUMMARY
07/01/2024 Letter Codes 10 Day Letter
08/09/2024 Letter INSPECTION SUMMARY
08/09/2024 Letter INSPECTION SUMMARY
08/22/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
09/24/2024 Letter INSPECTION SUMMARY
04/08/2025 Certificate/License Codes Temporary Certificate of Occupancy
04/08/2025 Receipt Receipt for transaction:2025-002162
04/09/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home