Summary
PRRES20213955
Building Permit - Residential
Certificate of Occupancy
NEW DUPLEX
NEW DUPLEX - FINISHED BASEMENT ONLY ON ONE SIDE - UNCOVERED PATIO
07/30/2021
09/01/2021
01/26/2022
08/29/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
JOE@CLOVERANDHIVE.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Duplex $1,495.42 $1,495.42 Paid 09/01/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 09/01/2021
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 09/01/2021
8331507-Sewer Connection Fee $720.00 $720.00 Paid 09/01/2021
8331401-Water Tap Fee $7,310.00 $7,310.00 Paid 09/01/2021
8350015-Water Meter Fee $958.48 $958.48 Paid 09/01/2021
9110078-Valuation Fee for New Duplex $103.80 $103.80 Paid 09/08/2021
$1,599.22
8331504-EFHB Middle Big Creek, Full $803.52 $803.52 Paid 10/22/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 08/02/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 08/02/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 08/02/2022
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 08/03/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 9/30/2021 9/30/2021 09/30/2021
Misc
Informational
09/30/2021
APPROVED PER DAVID P AINSWORTH 9/27/21
Underslab Plumbing Inspection - Residential Passed 10/19/2021 10/19/2021 10/19/2021
Misc
Informational
10/19/2021
2105/2103 Both good.
Sewer Service Inspection - R Failed 1/4/2022 (11:30) 1/4/2022 01/04/2022
Misc
Corrective Action Required
01/04/2022
SEWER LINE OK FOOTING HAS BEEN UNDERMINED FOR SEWER LINE EXCAVATION, DO NOT COVER, HAVE ENGINEER ADDRESS
Footing Inspection - Residential Failed 1/4/2022 1/4/2022 01/04/2022
Misc
Corrective Action Required
01/04/2022
FOOTING HAS BEEN UNDERMINED FOR SEWER LINE EXCAVATION, DO NOT COVER, HAVE ENGINEER ADDRESS
Sewer Service Inspection - R Passed 1/10/2022 (1:00) 1/10/2022 01/10/2022
Misc
Corrective Action Required
01/04/2022
2105,2103 sewer ok
Water Service Inspection - R Failed 1/18/2022 (10:15) 1/18/2022 01/18/2022
Misc
Corrective Action Required
01/18/2022
2103 OK 2105 - ADJUST HEIGHT, 14"-18" FROM TOP OF METER TO TOP OF LID
Water Service Inspection - R Passed 1/18/2022 (1:00) 1/18/2022 01/18/2022
Misc
Informational
01/18/2022
2103 OK 2105 OK
Electrical Service Inspection Passed 3/8/2022 3/8/2022 03/08/2022
Gas Service Inspection - Residential Failed 3/8/2022 3/8/2022 03/08/2022
Misc
Corrective Action Required
03/08/2022
2103 -GAS LINE BOND REQUIRED -PRESSURE AT 0 PSI, MUST MAINTAIN 10 PSI FOR TEST 2105 -GAS LINE BOND REQUIRED *PRESSURE OK*
All Rough Inspection - Residential Failed 3/8/2022 3/8/2022 03/08/2022
Misc
Corrective Action Required
03/08/2022
#2103 -nail exterior sheathing at garage PFH per code R602.10.6.4 -nail exterior sheathing CS-PF per plans at great room windows and master bed windows -clarify UL design for fire rated separation wall at attic space, U336B has 2x4 stud wall with 1/2" rock -top plate to top plate connection as required by code at east garage corner -fireblock between studs of soffit line 2x6 wall garage -repair damaged shaft liner at rated separation wall -fireblock vertical every 10’ between stud and fire rock at rated separation wall -No ridge vent or openings of 4’ fire rated play wood roof deck -(4) 2x studs packs at all girder truss bearing ends per plans -stud shoes at master bath DWV exterior walls -secure all vertical DWV 2” or less at mid point -seal top plate penetration master bath -fireblock between top plates at dbl master shower/bath -install flashing boots all roof penetrations -fireblock between studs at bed#2 closet wall, stair wall side -min (4) 10D nails each side of structural straps -add structural strap at DWV top plate garage wall -install truss hangers TJC37 at J1 hip trusses master bed per plans -(2) 2x12 header continuous corner to corner for CS-PF design at great room windows and master bed windows per plans -LIB bracing per plans at bed#2 wall -nail LIB bracing to top plate at garage wall -add future vent for basement plumbing -add hot water heater circuit -secure SE cable above service panel -gas line bond required -solid shim all trimmer studs cut short of headers throughout #2105 SEE CORRECTIONS LIST FROM 2103 AND ADDITIONAL CORRECTIONS BELOW -Add stud shoe 1st floor bath -Fireblock deadspace bed#2 closet -fireblock vertical every 10’ between foundation wall and studs at finished basement, seal all penetrations through fireblock -fireblock between top plate and foundation throughout finished basement -seal all top plate penetrations at finished basement -fireblock at top plate between furring strips basement bedroom
Gas Service Inspection - Residential Failed 3/21/2022 3/21/2022 03/21/2022
Misc
Corrective Action Required
03/08/2022
2103 -PRESSURE AT 0 PSI, MUST MAINTAIN 10 PSI FOR TEST 2105 *PRESSURE OK*
Rated Assembly Inspection Failed 3/21/2022 3/21/2022 03/21/2022
Misc
Corrective Action Required
03/21/2022
-repair damaged shaft liner at rated separation wall -fireblock vertical every 10’ between stud and fire rock at rated separation wall -No ridge vent or openings of 4’ fire rated play wood roof deck
All Rough Inspection - Residential Not Ready 3/21/2022 3/21/2022 03/21/2022
Misc
Corrective Action Required
03/08/2022
3/21/22 - NOT READY FOR INSPECTION, CORRECTIONS REMAIN, ADDRESS BEFORE RESCHEDULING INSPECTION #2103 -nail exterior sheathing at garage PFH per code R602.10.6.4 -nail exterior sheathing CS-PF per plans at great room windows and master bed windows -clarify UL design for fire rated separation wall at attic space, U336B has 2x4 stud wall with 1/2" rock -top plate to top plate connection as required by code at east garage corner -fireblock between studs of soffit line 2x6 wall garage -repair damaged shaft liner at rated separation wall -fireblock vertical every 10’ between stud and fire rock at rated separation wall -No ridge vent or openings of 4’ fire rated play wood roof deck -(4) 2x studs packs at all girder truss bearing ends per plans -stud shoes at master bath DWV exterior walls -secure all vertical DWV 2” or less at mid point -seal top plate penetration master bath -fireblock between top plates at dbl master shower/bath -install flashing boots all roof penetrations -fireblock between studs at bed#2 closet wall, stair wall side -min (4) 10D nails each side of structural straps -add structural strap at DWV top plate garage wall -install truss hangers TJC37 at J1 hip trusses master bed per plans -(2) 2x12 header continuous corner to corner for CS-PF design at great room windows and master bed windows per plans -LIB bracing per plans at bed#2 wall -nail LIB bracing to top plate at garage wall -add future vent for basement plumbing -add hot water heater circuit -secure SE cable above service panel -gas line bond required -solid shim all trimmer studs cut short of headers throughout #2105 SEE CORRECTIONS LIST FROM 2103 AND ADDITIONAL CORRECTIONS BELOW -Add stud shoe 1st floor bath -Fireblock deadspace bed#2 closet -fireblock vertical every 10’ between foundation wall and studs at finished basement, seal all penetrations through fireblock -fireblock between top plate and foundation throughout finished basement -seal all top plate penetrations at finished basement -fireblock at top plate between furring strips basement bedroom
Gas Service Inspection - Residential Passed 3/22/2022 3/22/2022 03/22/2022
Misc
Resolved
03/22/2022
Footing Inspection - Residential Passed 3/22/2022 3/22/2022 03/22/2022
Misc
Resolved
03/22/2022
Rated Assembly Inspection Passed 3/23/2022 3/23/2022 03/23/2022
Misc
Resolved
03/23/2022
All Rough Inspection - Residential Failed 3/23/2022 3/23/2022 03/23/2022
Misc
Corrective Action Required
03/21/2022
UNIT 2103 -nail exterior sheathing CS-PF per plans at great room windows and master bed windows -(4) 2x studs packs at all girder truss bearing ends per plans -fireblock between top plates at dbl wall master shower/bath -install flashing boots all roof penetrations -fireblock between studs at bed#2 closet wall, stair wall side -min (4) 10D nails each side of structural straps -install truss hangers TJC37 at J1 hip trusses master bed per plans, (the hanger should attach the J1 hip truss to the A1 hip girder and not the box nailer) -(2) 2x12 header continuous corner to corner for CS-PF design at great room windows and master bed windows per plans ,(land and secure all electrical that has been removed for header replacement, address trimmer studs put over top of electrical box at deck, that outlet will need to me moved those trimmer studs need to fill bearing to bottom plate) -LIB bracing per plans at bed#2 wall -add future vent for basement plumbing -secure SE cable above service panel -solid shim all trimmer studs cut short of headers throughout UNIT 2105 -nail exterior sheathing CS-PF per plans at great room windows and master bed windows -install bocca plate at DWV top plate west garage wall -install flashing boots all roof penetrations -(4) 2x studs packs at all girder truss bearing ends per plans -install truss hangers TJC37 at J1 hip trusses master bed per plans, (the hanger should attach the J1 hip truss to the A1 girder and not the box nailer) -(2) 2x12 header continuous corner to corner for CS-PF design at great room windows and master bed windows per plans,(land all electrical wiring to boxes that was removed for this correction) -LIB bracing per plans at bed#2 wall -secure SE cable above service panel -seal all top plate penetrations at finished basement -fireblock at top plate between furring strips basement bedroom
All Rough Inspection - Residential Failed 3/25/2022 3/25/2022 03/25/2022
Misc
Corrective Action Required
03/23/2022
UNIT 2103 -nail exterior sheathing CS-PF per plans at great room windows and master bed windows -(4) 2x studs packs at all girder truss bearing ends per plans, (replace studs added to stud packs have been overnotched) -(2) 2x12 header continuous corner to corner for CS-PF design at great room windows and master bed windows per plans ,(secure all NM per code and replace trimmer studs at CS-PF that have been overnotched) **OK TO INSULATE** UNIT 2105 -nail exterior sheathing CS-PF per plans at great room windows and master bed windows -(4) 2x studs packs at all girder truss bearing ends per plans, (replace studs added to stud packs have been overnotched) -(2) 2x12 header continuous corner to corner for CS-PF design at great room windows and master bed windows per plans ,(secure all NM per code and replace trimmer studs at CS-PF that have been overnotched) -fireblock at top plate between furring strips basement bedroom **OK TO INSULATE**
All Rough Inspection - Residential Passed 3/30/2022 3/30/2022 03/30/2022
Misc
Resolved
03/30/2022
Driveway Inspection Partial 4/26/2022 4/26/2022 04/26/2022
Misc
Informational
04/26/2022
On 4.26.2022 Tuesday I performed a driveway inspection and pass the subgrade to pour concrete. This is one of two driveways and both driveways were inspected and passed.
Sidewalk Inspection Partial 4/26/2022 4/26/2022 04/26/2022
Misc
Informational
04/26/2022
On 4.26.2022 I performed a sidewalk inspection and pass the subgrade to pour concrete.
Sidewalk Inspection Passed 5/3/2022 5/3/2022 05/02/2022
Misc
Informational
04/26/2022
On 4.26.2022 I performed a sidewalk inspection and pass the subgrade to pour concrete.
Occupancy Inspection - Codes Residential Failed 5/31/2022 5/31/2022 05/31/2022
Misc
Corrective Action Required
05/31/2022
UNITS 2103/2105: -Final driveway inspection required, contact development services to schedule -resolve outstanding inspection fees -submit as graded plot plan for review and approval -final grade and sod -downspouts and splash blocks -provide graspable handrail at front stairs 2103: -provide cover at UFER garage wall, open to stud cavity -GFCI protection at dishwasher receptacle -cap and label future vent at basement NO INSPECTION PERFORMED ON UNIT 2105
Driveway Inspection Passed 6/1/2022 06/01/2022
Misc
Informational
04/26/2022
On 4.26.2022 Tuesday I performed a driveway inspection and pass the subgrade to pour concrete.
Occupancy Inspection - Codes Residential Temporary C of O 6/1/2022 6/1/2022 06/01/2022
Misc
Corrective Action Required
05/31/2022
UNITS 2103/2105: -resolve outstanding inspection fees -submit as graded plot plan for review and approval -final grade and sod -downspouts and splash blocks -provide graspable handrail at front stairs **OK FOR TCO, TCO EXPIRES 7/1/22*
Erosion Control Inspection Residential Partial 06/01/2022
Sidewalk Inspection Partial 6/6/2022 6/6/2022 06/06/2022
Misc
Informational
06/06/2022
Sidewalk was framed up with aggregate in and compacted. 6/6/22 ES
Sidewalk Inspection Partial 6/10/2022 6/10/2022 06/14/2022
Misc
Informational
06/06/2022
Sidewalk was framed up with aggregate in and compacted. 6/6/22 ES Sidewalk was still framed up with aggregate in, but still not poured. 6/14/22 ES
Sidewalk Inspection Passed 6/24/2022 6/24/2022 07/06/2022
Misc
Informational
06/14/2022
Sidewalk was framed up with aggregate in and compacted. 6/6/22 ES Sidewalk was still framed up with aggregate in, but still not poured. 6/14/22 ES Sidewalk was inspected and meets LS and ADA specification. 7-6-22 RH
Erosion Control Inspection Residential Passed 8/3/2022 8/3/2022 08/03/2022
Occupancy Inspection - Codes Residential Ready for Temp CO 8/3/2022 8/3/2022 08/03/2022
Misc
Corrective Action Required
06/01/2022
UNITS 2103/2105: -obtain lawn irrigation system permit -submit as graded plot plan for review and approval -splash blocks -provide gravel base water meter pit -provide permanent address tags on disconnects as well as the meter cans -correct grade at unit 2103 front NE corner, negative slope off splash block towards foundation -Unit 2103 uncover water meter lid **TCO HAS EXPIRED, PLEASE PAY $50 TCO FEE TO RENEW TCO EXPIRATION**
Occupancy Inspection - Codes Residential Temporary C of O 08/03/2022
Misc
Corrective Action Required
08/03/2022
UNITS 2103/2105: -obtain lawn irrigation system permit -submit as graded plot plan for review and approval -splash blocks -provide gravel base water meter pit -provide permanent address tags on disconnects as well as the meter cans -correct grade at unit 2103 front NE corner, negative slope off splash block towards foundation -Unit 2103 uncover water meter lid **TCO HAS EXPIRED, PLEASE PAY $50 TCO FEE TO RENEW TCO EXPIRATION**
Occupancy Inspection - Codes Residential Failed 8/18/2022 8/18/2022 08/18/2022
Misc
Corrective Action Required
08/03/2022
UNITS 2103/2105: -submit as graded plot plan for review and approval -provide permanent address tags on disconnects as well as the meter cans, (check address placement)
Plot Plan Inspection Passed 8/29/2022 08/29/2022
Occupancy Inspection - Codes Residential Full C of O 8/29/2022 8/29/2022 08/29/2022
Misc
Resolved
08/29/2022
Documents & Images
Date Uploaded File Type Document Name
07/30/2021 OS #17 - PERMIT APP
07/30/2021 Permit Codes Residential Plan Review
08/03/2021 Plot Plan Approved Plot Plan
08/05/2021 Permit Codes Residential Plan Review
08/31/2021 Approved Plans APPROVED TRUSS LAYOUT
08/31/2021 Approved Plans APPROVED TRUSS PACKAGE
09/01/2021 Permit DS Building Permit
09/01/2021 Receipt Receipt for transaction:2021-007039
09/08/2021 Scope of Work Statement
09/08/2021 Approved Plans Basement Finish Plan
09/08/2021 Receipt Receipt for transaction:2021-007206
09/29/2021 2103 & 2105 SW Osage Dr LSMO Osage Lot 17 Clayton Properties P 2021-3955 3rd Party Footing Inspection Report 9-27-21
09/30/2021 Letter INSPECTION SUMMARY
10/19/2021 Letter INSPECTION SUMMARY
10/22/2021 Receipt Receipt for transaction: 2021-008192
01/04/2022 Letter INSPECTION SUMMARY
01/04/2022 Letter INSPECTION SUMMARY
01/10/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/18/2022 Letter INSPECTION SUMMARY
01/27/2022 Approved Plans Approved Drawings
03/08/2022 Letter INSPECTION SUMMARY
03/08/2022 Letter INSPECTION SUMMARY
03/08/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/22/2022 17 Osage-AB3 Confirmation
03/22/2022 17 Osage-Undermined FTNG
03/22/2022 Letter INSPECTION SUMMARY
03/22/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/23/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/30/2022 Letter INSPECTION SUMMARY
04/26/2022 Letter INSPECTION SUMMARY
04/26/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/31/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter Codes Temporary Certificate of Occupancy
06/01/2022 Letter INSPECTION SUMMARY
06/06/2022 Letter INSPECTION SUMMARY
06/14/2022 Letter INSPECTION SUMMARY
06/21/2022 Approved Plans Approved Drawings
06/21/2022 Plot Plan Approved Plot Plan
07/06/2022 Letter INSPECTION SUMMARY
08/02/2022 Receipt Receipt for transaction:2022-006305
08/03/2022 Letter INSPECTION SUMMARY
08/03/2022 Receipt Receipt for transaction:2022-006370
08/03/2022 Letter Codes Temporary Certificate of Occupancy
08/18/2022 Letter INSPECTION SUMMARY
08/26/2022 Plot Plan Approved As Graded Plot Plan
08/29/2022 Letter INSPECTION SUMMARY
08/29/2022 Letter Field Certificate of Occupancy
08/29/2022 Letter Codes Final Certificate of Occupancy
01/29/2024 LOT 17 ASBUILT
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home