Permit Application Status

PRCOM20225614


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20225614
Building Permit - Commercial
Certificate of Occupancy
SALLEE REAL ESTATE INVESTMENTS LLC
NEW COMMERCIAL
NEW SELF STORAGE BUILDING
11/08/2022
04/12/2023
07/24/2023
01/21/2025
Locations
Contacts
STRICKLAND CONSTRUCTION CO INC, Address:720 S ROGERS RD STE B, Phone:(913) 764-7000  
KENNY@STRICKLANDCONSTRUCTION.COM  
HERNLY ASSOCIATES INC, Address:1100 RHODE ISLAND STREET, Phone:(785) 749-5806  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
TEAGUE ELECTRIC CONSTRUCTION INC, Address:12425 W 92ND ST, Phone:(913) 529-4600  
HEARTLAND PLUMBING INC, Address:800 S CREEKSIDE DR, Phone:(913) 856-5846  
SALLEE REAL ESTATE INVESTMENTS LLC, Address:PO BOX 6437  
Rone Engineering Services, Address:8908 Ambassador Row, Phone:(214) 630-9745  
Reviews
Review Type Outcome Est. Completion Date Completed
Special Inspections Review Approved 09/09/2024
Mike Weisenborn
Sprinkler Plan Review Released for Construction 02/28/2024 02/28/2024
Jim Eden
Miscellaneous Correction
Resolved
02/28/2024

Provide a one-way check valve at the base of the riser manifold to prevent churning when the system (FDC) is supplied by a private hydrant after the backflow.
Construction documents - Fire protection systems
Corrective Action Required
02/21/2024

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Revised stamped plans received 2/21/2024.
Miscellaneous Correction
Resolved
02/28/2024

Provide a 4 inch Storz connection on the FDC.
Installation acceptance testing
Corrective Action Required
02/21/2024

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule hydrostatic and flow tests.
Sprinkler Plan Review Rejected 10/18/2023 10/18/2023
Jim Eden
Miscellaneous Correction
Corrective Action Required
10/18/2023

Provide a one-way check valve at the base of the riser manifold to prevent churning when the system (FDC) is supplied by a private hydrant after the backflow.
Miscellaneous Correction
Corrective Action Required
10/18/2023

Provide a 4 inch Storz connection on the FDC.
Construction documents - Fire protection systems
Corrective Action Required
10/18/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Stamped plans received 10/4/2023.
Installation acceptance testing
Corrective Action Required
10/18/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test.
Alarm Plan Review Released for Construction 07/20/2023 07/17/2023
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
07/17/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Stamped plans received.
Installation acceptance testing
Corrective Action Required
07/17/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule a test. Coordinated with sprinkler contractor.
Misc
Corrective Action Required
07/17/2023

907.5.2.3.1 Public use areas and common use areas. Visible alarm notification appliances shall be provided in public use areas and common use areas. Provide visible notification appliances in the second floor bathrooms. Verified at inspection.
Building Plan Review Approved with Conditions 02/27/2023 03/01/2023
Joe Frogge
IBC 1704.2 Special Inspections
Resolved
02/23/2023

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Actions required: - - Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 1/25/23 - Not found.
Elevator Equipment Permit
Corrective Action Required
02/17/2023

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational. 1/25/23 - acknowledged in letter
Elevator Equipment Inspection
Corrective Action Required
02/17/2023

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational. 1/25/23 - acknowledged in letter
Elevator Certificate of Inspection
Corrective Action Required
02/17/2023

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational. 1/25/23 - acknowledged in letter
Planning - Screening of rooftop equipment
Resolved
03/01/2023

Unified Development Ordinance Article 8, Section 8.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. Provide verification that parapets are at least as tall as condensing units. 2/28/23 - deferred to Planning Dept
Misc
Resolved
02/23/2023

Inadequate information to complete review. Provide the following: - Complete roof hatch detail. (fyi - 30" side rail extension required) 1/25/23 - side rail extension not found. (guards are diffeent issue) - - - - Roof dead load 1/25/23 - Not found. - Wind speed criteria 1/25/23 - Not found.
Fire Plan Review Approved 02/27/2023 02/27/2023
Jim Eden
Construction documents for fire alarm systems
Resolved
02/27/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action Required: Send shop drawings to Lee's Summit Fire for Review. Acknowledged in letter 3 JAN 23
Knox box required
Resolved
02/27/2023

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action Required: Knox box required above FDC. Acknowledged in letter 3 JAN 23 veriied at inspection
Construction documents - Fire protection systems
Resolved
02/27/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Send shop drawings to Lee's Summit Fire for review. Acknowledged in letter 3 JAN 23
Installation acceptance testing
Resolved
02/27/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Action Required: Informational call 816-969-1300 for acceptance testing of alarm and sprinkler system.Acknowledged in letter 3 JAN 23
Portable fire extinguishers - conspicuous locations
Resolved
02/27/2023

2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel. Action Required: Verified at inspection. Acknowledged in letter 3 JAN 23
Key boxes for non-standardized fire service elevator keys
Resolved
02/27/2023

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Action Required: Knox box with elevator key next to first floor elevator. Verified upon inspection. Acknowledged in letter 3 JAN 23
Illumination required
Resolved
02/27/2023

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. Action Required: Supply exit signage and ilumination at at areas reqiured. Front sales area.
Misc
Corrective Action Required
02/17/2023

Provide additional exit sign at first floor door #10 at Stair B.
Licensed Contractors Approved 02/27/2023 02/23/2023
Joe Frogge
Fire Plan Review Rejected 01/25/2023 01/25/2023
Ben Hicks
Construction documents for fire alarm systems
Corrective Action Required
01/18/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action Required: Send shop drawings to Lee's Summit Fire for Review. Acknowledged in letter 3 JAN 23
Knox box required
Corrective Action Required
01/18/2023

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action Required: Knox box required above FDC. Acknowledged in letter 3 JAN 23 veriied at inspection
Construction documents - Fire protection systems
Corrective Action Required
01/18/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Send shop drawings to Lee's Summit Fire for review. Acknowledged in letter 3 JAN 23
Installation acceptance testing
Corrective Action Required
01/18/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Action Required: Informational call 816-969-1300 for acceptance testing of alarm and sprinkler system.Acknowledged in letter 3 JAN 23
Portable fire extinguishers - conspicuous locations
Corrective Action Required
01/18/2023

2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel. Action Required: Verified at inspection. Acknowledged in letter 3 JAN 23
Key boxes for non-standardized fire service elevator keys
Corrective Action Required
01/18/2023

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Action Required: Knox box with elevator key next to first floor elevator. Verified upon inspection. Acknowledged in letter 3 JAN 23
Illumination required
Corrective Action Required
01/18/2023

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. Action Required: Supply exit signage and ilumination at at areas reqiured. Front sales area.
Misc
Corrective Action Required
01/25/2023

Provide additional exit sign at first floor door #10 at Stair B.
Building Plan Review Rejected 01/25/2023 01/25/2023
Joe Frogge
Final Development Plan
Resolved
01/24/2023

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Corrective Action Required
01/18/2023

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Actions required: - - Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections. 1/25/23 - Not found.
Elevator Equipment Permit
Corrective Action Required
01/18/2023

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational. 1/25/23 - acknowledged in letter
Elevator Equipment Inspection
Corrective Action Required
01/18/2023

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational. 1/25/23 - acknowledged in letter
Elevator Certificate of Inspection
Corrective Action Required
01/18/2023

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational. 1/25/23 - acknowledged in letter
IPC 403.1 Minimum number of fixtures
Resolved
01/25/2023

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Additional water closets and lavatories required per table.
Planning - Screening of rooftop equipment
Corrective Action Required
01/18/2023

Unified Development Ordinance Article 8, Section 8.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. Provide verification that parapets are at least as tall as condensing units.
Misc
Corrective Action Required
01/18/2023

Inadequate information to complete review. Provide the following: - Complete roof hatch detail. (fyi - 30" side rail extension required) 1/25/23 - side rail extension not found. (guards are diffeent issue) - - - - Roof dead load 1/25/23 - Not found. - Wind speed criteria 1/25/23 - Not found.
IBC 1015.7 Roof access - roof hatch guard
Resolved
01/25/2023

2018 IBC 1015.7 Roof access. Guards shall be provided where the roof hatch opening is located within 10 feet of a roof edge or open side of a walking surface and such edge or open side is located more than 30 inches above the floor, roof or grade below. The guard shall be constructed so as to prevent the passage of a sphere 21 inches in diameter. (see code for exception) Action required: Extend parapet or provide guards near roof hatch which is within 10' of roof edge.
IBC 1013.1 Where required - exit sign
Resolved
01/25/2023

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide additional exit sign at first floor door #10 at Stair B.
Licensed Contractors Approved 01/25/2023 01/25/2023
Joe Frogge
Final Development Plan Review Approved 01/25/2023 01/24/2023
Mike Weisenborn
Fire Plan Review Rejected 11/22/2022 11/22/2022
Ben Hicks
Construction documents for fire alarm systems
Corrective Action Required
11/22/2022

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action Required: Send shop drawings to Lee's Summit Fire for Review
Knox box required
Corrective Action Required
11/22/2022

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action Required: Knox box required above FDC
Construction documents - Fire protection systems
Corrective Action Required
11/22/2022

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action Required: Send shop drawings to Lee's Summit Fire for review
Installation acceptance testing
Corrective Action Required
11/22/2022

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Action Required: Informational call 816-969-1300 for acceptance testing of alarm and sprinkler system.
Portable fire extinguishers - conspicuous locations
Corrective Action Required
11/22/2022

2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel. Action Required: Verified at inspection
Key boxes for non-standardized fire service elevator keys
Corrective Action Required
11/22/2022

2018 IFC 506.1.2 Key boxes for non-standardized fire service elevator keys. Key boxes provided for non-standardized fire service elevator keys shall comply with Section 506.1 and 506.2 or as approved by the fire code official. Action Required: Knox box with elevator key next to first floor elevator. Verified upon inspection
Illumination required
Corrective Action Required
11/22/2022

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. Action Required: Supply exit signage and ilumination at at areas reqiured. Front sales area.
Building Plan Review Rejected 11/22/2022 11/17/2022
Joe Frogge
Final Development Plan
Corrective Action Required
11/17/2022

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Corrective Action Required
11/17/2022

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Actions required: - List required special inspections on plans. - Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
Elevator Equipment Permit
Corrective Action Required
11/17/2022

Prior to the installation or construction of any elevator equipment, an elevator equipment permit shall be obtained from the Missouri Department of Public Safety or its authorized representative. Action required: Comment is informational.
Elevator Equipment Inspection
Corrective Action Required
11/17/2022

Prior to the operation of any new elevator equipment or the issuance of the operating certificate, such elevator equipment shall be inspected by a licensed inspector. Testing must be performed in accordance with these rules and regulations. The testing must be witnessed by a licensed inspector. Action required: Comment is informational.
Elevator Certificate of Inspection
Corrective Action Required
11/17/2022

Elevator Safety Act and Rules 701.361 - Each privately owned or operated installation and each installation owned or operated by the state of Missouri or any political subdivision of the state shall have a certificate of inspection and meet the safety code promulgated pursuant to sections 701.350 to 701.380. Action required: Comment is informational.
IPC 403.1 Minimum number of fixtures
Corrective Action Required
11/17/2022

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Additional water closets and lavatories required per table.
Planning - Screening of rooftop equipment
Corrective Action Required
11/17/2022

Unified Development Ordinance Article 8, Section 8.180.E Roof mounted equipment – All roof-mounted equipment shall be screened entirely from view by using parapet walls at the same height as the mechanical units. For additions to existing buildings that do not meet this standard, individual screens will be permitted, with the design subject to approval by the Director. Action required: Make needed corrections to drawings that provide details as to how mechanical equipment will be screened from all 4 sides per referenced UDO section. Provide verification that parapets are at least as tall as condensing units.
Misc
Corrective Action Required
11/17/2022

Inadequate information to complete review. Provide the following: - Complete roof hatch detail. (fyi - 30" side rail extension required) - Door schedule. - Window schedule. - Finish material schedule. - Roof dead load - Wind speed criteria
IBC 1015.7 Roof access - roof hatch guard
Corrective Action Required
11/17/2022

2018 IBC 1015.7 Roof access. Guards shall be provided where the roof hatch opening is located within 10 feet of a roof edge or open side of a walking surface and such edge or open side is located more than 30 inches above the floor, roof or grade below. The guard shall be constructed so as to prevent the passage of a sphere 21 inches in diameter. (see code for exception) Action required: Extend parapet or provide guards near roof hatch which is within 10' of roof edge.
IBC 1013.1 Where required - exit sign
Corrective Action Required
11/17/2022

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide additional exit sign at first floor door #10 at Stair B.
Licensed Contractors Approved 11/22/2022 11/08/2022
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $32,502.78 $32,502.78 Paid 04/11/2023
7232302-Industrial/Warehouse License Tax Fee $19,085.00 $19,085.00 Paid 04/11/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 10/17/2024
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 11/19/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sewer Service Inspection Partial 05/09/2023
Misc
Informational
05/09/2023
5-9-23 NS Site visited and it appears that the crew tied into the sewer main with a y. I will upload pictures of the work.
Storm Sewer Construction Inspection Partial 05/17/2023
Misc
Informational
05/17/2023
5-17-23 NS Site visited and it appears that work is goin on storm box 935 they have already connected to the public storm water and will need to re grout around the box.
Water Service Inspection Partial 5/18/2023 05/18/2023
Misc
Informational
05/18/2023
5-18-23 NS site visited and today they are boring under port road to put in a new water main. They are assembling the water line and they would like to do a water tie in on Tuesday at 9am. There will be no one effected in this shut down. They did hit a French drain system but they will be putting this back together. They are hitting a lot of rock. what they would like to do is put he water line all the way up to where they think they will attach the water to the building but they are going to do the test from where the valve and meter pit will be.
Water Service Inspection Partial 5/19/2023 5/19/2023 05/18/2023
Misc
Informational
05/18/2023
5-18-23 NS site visited and today they are boring under port road to put in a new water main. They are assembling the water line and they would like to do a water tie in on Tuesday at 9am. There will be no one effected in this shut down. They did hit a French drain system but they will be putting this back together. They are hitting a lot of rock. what they would like to do is put he water line all the way up to where they think they will attach the water to the building but they are going to do the test from where the valve and meter pit will be. 5-18-23 NS Crew is done boring under the road it is deeper then 36 inches. Crews went back to start working on storm water.
Water Line - Construction Inspection Partial 5/23/2023 05/24/2023
Misc
Informational
05/24/2023
4-23-22 NS Site visited they tied into the water main. They put a valve and a kicker I asked them to put more kickers since there is 2 90 degree bends and when I walked up while they where filling in the hole I did not see them. 4-24-23 NS Site visited I asked the Forman if he had put those kickers in that I asked and he said yes. I asked if he had pictures and he said no and will be re-digging up the hole so I have verification.
Water Line - Coliform Test 1 Partial 06/06/2023
Misc
Corrective Action Required
06/06/2023
6-6-23 NS Site visited to do a water test and I took it up to get the test done at key stone. I will not know until tomorrow if it passed or not.
Water Line - Construction Inspection Partial 6/6/2023 06/08/2023
Misc
Informational
05/24/2023
4-23-22 NS Site visited they tied into the water main. They put a valve and a kicker I asked them to put more kickers since there is 2 90 degree bends and when I walked up while they where filling in the hole I did not see them. 4-24-23 NS Site visited I asked the Forman if he had put those kickers in that I asked and he said yes. I asked if he had pictures and he said no and will be re-digging up the hole so I have verification. 6-6-23 NS Site visited and we took the first water test. They did dig up to show me that they poured kickers at the 90 degree angles. 6-8-23 NS Site visited and I got a email saying there first water test passed.
Water Line - Coliform Test 1 Partial 6/8/2023 06/08/2023
Misc
Corrective Action Required
06/06/2023
6-6-23 NS Site visited to do a water test and I took it up to get the test done at key stone. I will not know until tomorrow if it passed or not. 6-8-23 NS Site visited and I got a email saying there first water test passed.
Water Service Inspection Passed 5/19/2023 8/4/2023 08/04/2023
Misc
Informational
05/18/2023
5-18-23 NS site visited and today they are boring under port road to put in a new water main. They are assembling the water line and they would like to do a water tie in on Tuesday at 9am. There will be no one effected in this shut down. They did hit a French drain system but they will be putting this back together. They are hitting a lot of rock. what they would like to do is put he water line all the way up to where they think they will attach the water to the building but they are going to do the test from where the valve and meter pit will be. 5-18-23 NS Crew is done boring under the road it is deeper then 36 inches. Crews went back to start working on storm water. 8-4-23 NS Site visited Crews passed all water test.
Footing Inspection - Commercial Partial 9/15/2023 (1:00) 9/15/2023 09/15/2023
Misc
Informational
09/15/2023
Foundation wall OK: -Elevator pit f. walls
Footing Inspection - Commercial Partial 9/19/2023 (10:30) 9/19/2023 09/19/2023
Misc
Informational
09/15/2023
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/9 to M/27-OK pending confirmation from the engineer of the cross #5 rebar length
Footing Inspection - Commercial Partial 9/21/2023 (3:00) 9/21/2023 09/21/2023
Misc
Informational
09/19/2023
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/8.5 to M/27; continue to A/8.5 **Ufer rebar installed at rear
Footing Inspection - Commercial Partial 9/29/2023 09/29/2023
Misc
Informational
09/21/2023
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/8.5 to M/27; continue to A/8.5 -GB from I/3 to E/3 to E/1; E/3 to E/4 to elevator wall; G/3 to G/4 **Ufer rebar installed at rear
Footing Inspection - Commercial Partial 10/3/2023 10/03/2023
Misc
Informational
09/29/2023
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/8.5 to M/27; continue to A/8.5 -GB from I/3 to E/3 to E/1; E/3 to E/4 to elevator wall; G/3 to G/4 -From A8.5 continue to E3 **Ufer rebar installed at rear
Foundation Inspection - Commercial Passed 10/3/2023 10/3/2023 10/03/2023
Foundation Inspection - Commercial Passed 10/9/2023 10/09/2023
Footing Inspection - Commercial Partial 10/13/2023 (1:00) 10/13/2023 10/13/2023
Misc
Informational
10/03/2023
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/8.5 to M/27; continue to A/8.5 -GB from I/3 to E/3 to E/1; E/3 to E/4 to elevator wall; G/3 to G/4 -From A8.5 continue to E3 **Ufer rebar installed at rear Remainder of perimeter footing
Piers/Caissons Inspection - Commercial Partial 10/13/2023
Misc
Informational
10/13/2023
Entry canopy on east side pier footings
Footing Inspection - Commercial Partial 10/17/2023 10/17/2023
Misc
Informational
10/13/2023
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/8.5 to M/27; continue to A/8.5 -GB from I/3 to E/3 to E/1; E/3 to E/4 to elevator wall; G/3 to G/4 -From A8.5 continue to E3 -Remainder of perimeter footing -Trash enclosure
Underslab Plumbing Inspection - Commercial Failed 10/31/2023 10/31/2023
Misc
Corrective Action Required
10/31/2023
-Test pressure not holding -Gravel support for building drains
Underslab Plumbing Inspection - Commercial Partial 11/1/2023 11/1/2023 11/01/2023
Misc
Informational
11/01/2023
**1st Floor approved
Grading/Excavation/Fill Inspection Passed 12/4/2023 12/05/2023
Misc
Informational
12/05/2023
12-5-23 NS Site visited and all work is done.
Pavement-Aggregate Base Passed 12/4/2023 12/05/2023
Misc
Informational
12/05/2023
12-5-23 NS Site visited and all base has been put in passed
Pavement-Curb Construction Passed 12/4/2023 12/05/2023
Misc
Informational
12/05/2023
12-5-23 NS Site visited curb has been put in passed unless it cracks in the future then the contractor will have to replace it before the bond is up.
Rough Framing Inspection - Commercial Partial 2/15/2024 2/15/2024 02/15/2024
Misc
Informational
02/15/2024
Preliminary walkthrough of the 1st floor. Framing generally ok; however, install studs per plan at NE and SE corners and fasten partition panel at laps @ 6” oc
In-wall Inspection Failed 6/10/2024 6/10/2024 06/10/2024
FIRST FLOOR
Corrective Action Required
06/10/2024
-Install blockings for restroom grab bars -Secure MC within 12" of boxes -Slope drain toward drain
Electrical Service Inspection Failed 6/13/2024 6/13/2024 06/13/2024
Misc
Corrective Action Required
06/13/2024
-Remove the enamel at supply-side service raceway connection to service disconnect enclosure and tighten lock nut -Provide main bonding jumper sized per 250.102 from the bus bar, where the grounding electrode conductors are connected to, to the bus bar where the service grounded conductor is connected to. NEC 250.24(A)(4) -Tape EGC with green tape
Electrical Service Inspection Passed 6/14/2024 6/14/2024 06/14/2024
Misc
Resolved
06/14/2024
-Remove the enamel at supply-side service raceway connection to service disconnect enclosure and tighten lock nut -Provide main bonding jumper sized per 250.102 from the bus bar, where the grounding electrode conductors are connected to, to the bus bar where the service grounded conductor is connected to. NEC 250.24(A)(4) -Tape EGC with green tape
In-wall Inspection Partial 6/14/2024 6/14/2024 06/14/2024
FIRST FLOOR
Corrective Action Required
06/10/2024
-Install blockings for restroom grab bars -Secure MC within 12" of boxes -Slope drain toward drain Rated wall at future elevator-OK to apply 5/8" type X GB
In-wall Inspection Passed 6/26/2024 6/26/2024 06/26/2024
FIRST FLOOR
Resolved
06/26/2024
Erosion Control Inspection Residential Failed 6/28/2024 06/28/2024
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/28/2024
IMMEDIATE STREET CLEANUP REQUIRED. CLEAN SILT&DEBRIS OFF THE STREET. RESTORE EROSION CONTROL ALONG THE STREET. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/28/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Erosion Control Inspection Residential Failed 7/3/2024 07/03/2024
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
06/28/2024
IMMEDIATE STREET CLEANUP REQUIRED. CLEAN SILT&DEBRIS OFF THE STREET. RESTORE EROSION CONTROL ALONG THE STREET. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS.
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/28/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Erosion Control Inspection Residential Partial 7/5/2024 07/05/2024
DCM3 ESC REQUIRED 2 DAY
Informational
07/05/2024
EROSION CONTROL RESTORED. MAINTAIN EROSION CONTROL DURING CONSTRUCTION
DCM2 ESC DEFICIENT INSTALLATION
Resolved
07/05/2024
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Erosion Control Inspection Residential Partial 7/9/2024 07/09/2024
DCM3 ESC REQUIRED 2 DAY
Informational
07/05/2024
EROSION CONTROL RESTORED. MAINTAIN EROSION CONTROL DURING CONSTRUCTION 7/9-STREET IS GENERALLY CLEAN WITH FEW CHUNKS OF DIRT OUT ON THE STREET. THE BUILDER WILL SWEEP THE STREET AT THE END OF THE DAY. EROSION CONTROL IS IN COMPLIANCE
Gas Service Inspection - Commercial Passed 7/10/2024 07/10/2024
Sprinkler - Hydrostatic Test Passed 07/31/2024
Above Ceiling Inspection Failed 8/21/2024 8/21/2024 08/21/2024
Misc
Corrective Action Required
08/21/2024
-Install ceiling lights -Support furnace PVC pipe every 5 ft; plumbing vent every 4 ft -Complete mechanical duct to ceiling register -Complete sprinkler head installation
Site Visit Partial 9/10/2024 9/10/2024 09/10/2024
Misc
Informational
09/10/2024
9-10-24 DP. Stopped by site this morning and spoke with guys from KAT excavation. This was their first day back on the job in months and they were just cleaning up debris piles and grading black dirt. All of the concrete drive except the 1 stretch to the road has been completed. I spoke with the superintendent onsite, Kenny with Strickland Construction, and he said he was unaware of any pre pour inspections or proof rolls that should've been done. He has my number now and also Nicks number. He is suppose to call before pouring the final stretch which will be within the next 2 weeks.
Site Visit Partial 9/18/2024 09/18/2024
Misc
Informational
09/10/2024
9-10-24 DP. Stopped by site this morning and spoke with guys from KAT excavation. This was their first day back on the job in months and they were just cleaning up debris piles and grading black dirt. All of the concrete drive except the 1 stretch to the road has been completed. I spoke with the superintendent onsite, Kenny with Strickland Construction, and he said he was unaware of any pre pour inspections or proof rolls that should've been done. He has my number now and also Nicks number. He is suppose to call before pouring the final stretch which will be within the next 2 weeks. 9-17-24 NS Site visited and it appeared no one was working on the concrete driveway or did I receive a call from Kyle
Site Visit Partial 9/19/2024 09/19/2024
Misc
Informational
09/18/2024
STORAGE PLACE NEXT TO WATER TOWER 9-10-24 DP. Stopped by site this morning and spoke with guys from KAT excavation. This was their first day back on the job in months and they were just cleaning up debris piles and grading black dirt. All of the concrete drive except the 1 stretch to the road has been completed. I spoke with the superintendent onsite, Kenny with Strickland Construction, and he said he was unaware of any pre pour inspections or proof rolls that should've been done. He has my number now and also Nicks number. He is suppose to call before pouring the final stretch which will be within the next 2 weeks. 9-17-24 NS Site visited and it appeared no one was working on the concrete driveway or did I receive a call from Kyle 9-18-24 NS Site visited and it appears no work is being done on the approach. 9-19-24 NS Site visited no work today.
Above Ceiling Inspection Passed 9/20/2024 9/20/2024 09/20/2024
Misc
Resolved
09/20/2024
-Install ceiling lights -Support furnace PVC pipe every 5 ft; plumbing vent every 4 ft -Complete mechanical duct to ceiling register -Complete sprinkler head installation
Site Visit Partial 9/30/2024 09/30/2024
Misc
Informational
09/19/2024
STORAGE PLACE NEXT TO WATER TOWER 9-10-24 DP. Stopped by site this morning and spoke with guys from KAT excavation. This was their first day back on the job in months and they were just cleaning up debris piles and grading black dirt. All of the concrete drive except the 1 stretch to the road has been completed. I spoke with the superintendent onsite, Kenny with Strickland Construction, and he said he was unaware of any pre pour inspections or proof rolls that should've been done. He has my number now and also Nicks number. He is suppose to call before pouring the final stretch which will be within the next 2 weeks. 9-17-24 NS Site visited and it appeared no one was working on the concrete driveway or did I receive a call from Kyle 9-18-24 NS Site visited and it appears no work is being done on the approach. 9-19-24 NS Site visited no work today. 9-30-24 NS Site Visited to do a inspection for the approach that will be poured tomorrow.
Site Visit Partial 10/3/2024 10/03/2024
Misc
Informational
09/30/2024
STORAGE PLACE NEXT TO WATER TOWER 9-10-24 DP. Stopped by site this morning and spoke with guys from KAT excavation. This was their first day back on the job in months and they were just cleaning up debris piles and grading black dirt. All of the concrete drive except the 1 stretch to the road has been completed. I spoke with the superintendent onsite, Kenny with Strickland Construction, and he said he was unaware of any pre pour inspections or proof rolls that should've been done. He has my number now and also Nicks number. He is suppose to call before pouring the final stretch which will be within the next 2 weeks. 9-17-24 NS Site visited and it appeared no one was working on the concrete driveway or did I receive a call from Kyle 9-18-24 NS Site visited and it appears no work is being done on the approach. 9-19-24 NS Site visited no work today. 9-30-24 NS Site Visited to do a inspection for the approach that will be poured tomorrow. 10-1-24 NS Site visited to do a sidewalk inspection. It appears to be ready to pour. 10-2-24 NS site visited for the rest of the sidewalk and the south side with curb and side walk that appears to meet city standards and will be poured next monday.
Alarm Test Passed 10/9/2024 10/10/2024
Sprinkler - Flow Test Failed 10/9/2024 10/10/2024
Site Visit Partial 10/10/2024 10/14/2024
Misc
Informational
10/03/2024
STORAGE PLACE NEXT TO WATER TOWER 9-10-24 DP. Stopped by site this morning and spoke with guys from KAT excavation. This was their first day back on the job in months and they were just cleaning up debris piles and grading black dirt. All of the concrete drive except the 1 stretch to the road has been completed. I spoke with the superintendent onsite, Kenny with Strickland Construction, and he said he was unaware of any pre pour inspections or proof rolls that should've been done. He has my number now and also Nicks number. He is suppose to call before pouring the final stretch which will be within the next 2 weeks. 9-17-24 NS Site visited and it appeared no one was working on the concrete driveway or did I receive a call from Kyle 9-18-24 NS Site visited and it appears no work is being done on the approach. 9-19-24 NS Site visited no work today. 9-30-24 NS Site Visited to do a inspection for the approach that will be poured tomorrow. 10-1-24 NS Site visited to do a sidewalk inspection. It appears to be ready to pour. 10-2-24 NS site visited for the rest of the sidewalk and the south side with curb and side walk that appears to meet city standards and will be poured next monday. 10-14-24 NS Site visited for the final sidewalk that is being installed and it appears that it meets city standards for pre-pour.
Sprinkler - Flow Test Passed 10/14/2024 10/15/2024
Pavement-Proof Roll Passed 10/17/2024 10/17/2024
Misc
Informational
10/17/2024
10-17-24 NS Proof Roll was not called in. It appears that concrete is holding up there is one part of it that has cracked and I asked the contractor to repair it. Passed
Pavement-Stabilized Subgrade Passed 10/17/2024 10/17/2024
Misc
Informational
10/17/2024
10-17-24 NS Proof Roll was not called in. It appears that concrete is holding up there is one part of it that has cracked and I asked the contractor to repair it. Passed
Pavement-Surface Passed 10/17/2024 10/17/2024
Misc
Informational
10/17/2024
10-17-24 NS Proof Roll was not called in. It appears that concrete is holding up there is one part of it that has cracked and I asked the contractor to repair it. Passed
Sanitary Sewer Construction Inspection Passed 10/17/2024 10/17/2024
Miscellaneous Correction
Corrective Action Required
05/09/2023
5-9-23 NS Site visited this morning and the crew dug up the sewer line and cut it and put a new Y in. They are going to dig the new sewer line to the clean out. I will have pictures of the sewer connection. 10-17-24 NS it appears that sewer has passed
Sewer Service Inspection Passed 10/17/2024 10/17/2024
Misc
Informational
05/09/2023
5-9-23 NS Site visited and it appears that the crew tied into the sewer main with a y. I will upload pictures of the work. 10-17-24 NS it appears sewer passed
Footing Inspection - Commercial Passed 10/17/2024
Misc
Resolved
10/17/2024
Foundation wall OK: -Elevator pit f. walls Footing OK below: -Elevator pad (per engineer letter) -From O/8.5 to M/27; continue to A/8.5 -GB from I/3 to E/3 to E/1; E/3 to E/4 to elevator wall; G/3 to G/4 -From A8.5 continue to E3 -Remainder of perimeter footing -Trash enclosure
Underslab Plumbing Inspection - Commercial Passed 10/17/2024
Misc
Resolved
10/17/2024
**1st Floor approved
Storm Sewer Construction Inspection Passed 10/17/2024 10/17/2024
Misc
Informational
05/17/2023
5-17-23 NS Site visited and it appears that work is goin on storm box 935 they have already connected to the public storm water and will need to re grout around the box. 10-17-24 NS appears storm has been put in and passed
Water Line - Hydrostatic Test Passed 10/17/2024 10/17/2024
Misc
Informational
10/17/2024
10-17-24 NS Water test passed
Water Line - Construction Inspection Passed 10/17/2024 10/17/2024
Misc
Informational
06/08/2023
4-23-22 NS Site visited they tied into the water main. They put a valve and a kicker I asked them to put more kickers since there is 2 90 degree bends and when I walked up while they where filling in the hole I did not see them. 4-24-23 NS Site visited I asked the Forman if he had put those kickers in that I asked and he said yes. I asked if he had pictures and he said no and will be re-digging up the hole so I have verification. 6-6-23 NS Site visited and we took the first water test. They did dig up to show me that they poured kickers at the 90 degree angles. 6-8-23 NS Site visited and I got a email saying there first water test passed. 10-17-24 NS Water test passed
Water Line - Coliform Test 1 Passed 10/17/2024 10/17/2024
Misc
Corrective Action Required
06/08/2023
6-6-23 NS Site visited to do a water test and I took it up to get the test done at key stone. I will not know until tomorrow if it passed or not. 6-8-23 NS Site visited and I got a email saying there first water test passed. 10-17-24 NS Water test passed
Occupancy Inspection - Engineering Temporary C of O 10/17/2024 10/17/2024 10/17/2024
Misc
Corrective Action Required
10/17/2024
10-17-24 NS TCO Check List -Sidewalk is cracked in one spot on the Southwest corner. -clean sidewalk off -put vegetation around property and detention basin -put water meter urt outside of the building in closed in a box hanging on the wall with extra cable in the box. - I will come back next time it rains to check detention basin and make sure it drains with in 40 hours after it rains
Occupancy Inspection - Planning Temporary C of O 10/17/2024 10/17/2024 10/17/2024
Misc
Corrective Action Required
10/17/2024
Complete installation of landscaping per approved plan.
Occupancy Inspection - Water Utilities Temporary C of O 10/17/2024 10/17/2024 10/17/2024
Rough Framing Inspection - Commercial Passed 10/17/2024
Misc
Resolved
10/17/2024
Preliminary walkthrough of the 1st floor. Framing generally ok; however, install studs per plan at NE and SE corners and fasten partition panel at laps @ 6” oc
Rated Assembly Inspection Passed 10/17/2024
Piers/Caissons Inspection - Commercial Passed 10/17/2024
Misc
Resolved
10/17/2024
Entry canopy on east side pier footings
Occupancy Inspection - Codes Commercial Ready for Temp CO 10/17/2024 10/17/2024 10/17/2024
Misc
Corrective Action Required
10/17/2024
-Install erosion control along the street -Approval required from: Planning, Fire, FEI, Water -Support water heater expansion tank -Provide mean to clean out the furnace condensate drain without requiring the removal of the drain pipe -Support water PEX lines above mechanical rm per code -Provide box extension for receptacle box at wood finish wall -Address protrusion more than 4” into egress path of corridors -Labels for fire doors; seal around door frames -Sprinkler head in closet 1325 -Support gas piping (3/4” to 1”) at 8 ft intervals **TCO approved for 1st and 2nd floor only
Occupancy Inspection - Fire Temporary C of O 10/17/2024 10/17/2024 10/18/2024
Occupancy Inspection - Codes Commercial Ready for Temp CO 11/19/2024 11/19/2024
Misc
Corrective Action Required
10/17/2024
-Install erosion control along the street -Approval required from: Planning, Fire, FEI, Water -Support water heater expansion tank -Provide mean to clean out the furnace condensate drain without requiring the removal of the drain pipe -Support water PEX lines above mechanical rm per code -Provide box extension for receptacle box at wood finish wall -Address protrusion more than 4” into egress path of corridors -Labels for fire doors; seal around door frames -Sprinkler head in closet 1325 -Support gas piping (3/4” to 1”) at 8 ft intervals **TCO approved for 1st and 2nd floor only
Occupancy Inspection - Codes Commercial Temporary C of O 12/20/2024 12/30/2024 12/30/2024
Misc
Corrective Action Required
11/19/2024
-Approval required from: Planning, Fire, Water **TCO approved
Occupancy Inspection - Planning Passed 12/31/2024
Misc
Corrective Action Required
10/17/2024
Complete installation of landscaping per approved plan.
Occupancy Inspection - Water Utilities Passed 01/13/2025
Occupancy Inspection - Engineering Passed 01/13/2025
Misc
Corrective Action Required
10/17/2024
10-17-24 NS TCO Check List -Sidewalk is cracked in one spot on the Southwest corner. -clean sidewalk off -put vegetation around property and detention basin -put water meter urt outside of the building in closed in a box hanging on the wall with extra cable in the box. - I will come back next time it rains to check detention basin and make sure it drains with in 40 hours after it rains 1-13-25 NS all TCO checklist has been completed. Passed
Occupancy Inspection - Fire Passed 1/17/2025 01/21/2025
Occupancy Inspection - Codes Commercial Full C of O 12/31/2024 1/17/2025 01/21/2025
Misc
Resolved
01/21/2025
-Approval required from Water **TCO approved
Documents & Images
Date Uploaded File Type Document Name
11/08/2022 Application Form Commercial Permit Application
11/08/2022 Engineer Report/Study 18-222-Geotechnical Report-219188G Lakewood Business Park Lot-35
11/08/2022 Plans Elec plans - 22573E
11/08/2022 Plans Mech & Plum plans - 22573MP
11/08/2022 Plans pre-eng bldg - 80861 Strickland-Lakewood (Permit 80) 11-03-22_stamped
11/08/2022 Plans Arch plans - LWS-20221108-ARCHSET
11/08/2022 Engineer Report/Study Storage Calcs-80861 Strickland-3NOV
11/08/2022 Letter License Tax Bill
11/22/2022 Letter DS P/R Corrections Document
11/22/2022 Letter Fire Building Plan Review
01/18/2023 Plans ARCH - LWS-20230103
01/18/2023 Plans ELEC - Updated 1-12-23
01/18/2023 Letter PermitResponseLetter20230103
01/18/2023 Plans PLUMB & MECH - Updated 1-12-23
01/18/2023 Specifications Submittal -MECH Cutsheets - 281890-Lakewood Storage (2)
01/25/2023 Letter Fire Building Plan Review
01/25/2023 Letter DS P/R Corrections Document
02/17/2023 Plans PLUMB & MECH - Updated 2-16-23
02/17/2023 Letter PermitResponseLetter20230217
02/17/2023 Plans LWS-20230210-archset
02/17/2023 Activity Document Lakewood Storage - Special Inspections
02/17/2023 Specifications LadderUP Safety Post, Steel - Yellow - Bilco - AccessDoorsAndPanels
02/17/2023 Plans ELEC - Updated 2-16-23
02/17/2023 Plans 80861 Strickland-Lakewood (Permit 80) 11-03-22_stamped
02/17/2023 Specifications 7-2-Panel-prn-1
03/01/2023 Approved Plans approved - arch
03/01/2023 Approved Plans approved - MEP
03/01/2023 Approved Plans approved - pre-eng metal bldg
04/11/2023 Receipt Receipt for transaction:2023-001998
04/12/2023 Letter DS Building Permit
04/13/2023 Letter INSPECTION SUMMARY53
04/13/2023 Letter INSPECTION SUMMARY52
04/13/2023 Letter INSPECTION SUMMARY51
04/13/2023 Letter INSPECTION SUMMARY50
04/13/2023 Letter INSPECTION SUMMARY49
04/13/2023 Letter INSPECTION SUMMARY48
04/13/2023 Letter INSPECTION SUMMARY47
04/13/2023 Letter INSPECTION SUMMARY46
04/13/2023 Letter INSPECTION SUMMARY45
04/13/2023 Letter INSPECTION SUMMARY44
04/13/2023 Letter INSPECTION SUMMARY43
04/13/2023 Letter INSPECTION SUMMARY42
04/13/2023 Letter INSPECTION SUMMARY41
04/13/2023 Letter INSPECTION SUMMARY40
04/13/2023 Letter INSPECTION SUMMARY39
04/13/2023 Letter INSPECTION SUMMARY38
04/13/2023 Letter INSPECTION SUMMARY37
04/13/2023 Letter INSPECTION SUMMARY36
04/13/2023 Letter INSPECTION SUMMARY35
04/13/2023 Letter INSPECTION SUMMARY34
04/13/2023 Letter INSPECTION SUMMARY33
04/13/2023 Letter INSPECTION SUMMARY32
04/13/2023 Letter INSPECTION SUMMARY31
04/13/2023 Letter INSPECTION SUMMARY30
04/13/2023 Letter INSPECTION SUMMARY29
04/13/2023 Letter INSPECTION SUMMARY28
04/13/2023 Letter INSPECTION SUMMARY27
04/13/2023 Letter INSPECTION SUMMARY26
04/13/2023 Letter INSPECTION SUMMARY25
04/13/2023 Letter INSPECTION SUMMARY24
04/13/2023 Letter INSPECTION SUMMARY23
04/13/2023 Letter INSPECTION SUMMARY22
04/13/2023 Letter INSPECTION SUMMARY21
04/13/2023 Letter INSPECTION SUMMARY20
04/13/2023 Letter INSPECTION SUMMARY19
04/13/2023 Letter INSPECTION SUMMARY18
04/13/2023 Letter INSPECTION SUMMARY17
04/13/2023 Letter INSPECTION SUMMARY16
04/13/2023 Letter INSPECTION SUMMARY15
04/13/2023 Letter INSPECTION SUMMARY14
04/13/2023 Letter INSPECTION SUMMARY13
04/13/2023 Letter INSPECTION SUMMARY12
04/13/2023 Letter INSPECTION SUMMARY11
04/13/2023 Letter INSPECTION SUMMARY10
04/13/2023 Letter INSPECTION SUMMARY9
04/13/2023 Letter INSPECTION SUMMARY8
04/13/2023 Letter INSPECTION SUMMARY7
04/13/2023 Letter INSPECTION SUMMARY6
04/13/2023 Letter INSPECTION SUMMARY5
04/13/2023 Letter INSPECTION SUMMARY4
04/13/2023 Letter INSPECTION SUMMARY3
04/13/2023 Letter INSPECTION SUMMARY2
04/13/2023 Letter INSPECTION SUMMARY1
04/13/2023 Letter INSPECTION SUMMARY0
04/13/2023 Letter INSPECTION SUMMARY
05/09/2023 Photograph Lakewood Storage Sewer 1
05/09/2023 Photograph Lakewood Storage Sewer 2
05/09/2023 Letter INSPECTION SUMMARY
05/09/2023 Lakewood Storage Sewer 1
05/09/2023 Lakewood Storage Sewer 2
09/15/2021 Approved Plans Approved Lakewood Self Storage FDP Plan Set
05/18/2023 Letter INSPECTION SUMMARY
05/18/2023 Letter INSPECTION SUMMARY
05/18/2023 Letter Fire Building Plan Review
05/18/2023 Letter Fire Building Plan Review
05/18/2023 Letter INSPECTION SUMMARY
05/24/2023 Letter INSPECTION SUMMARY
06/01/2023 Photograph 30
06/01/2023 Photograph 31
07/13/2023 Specifications Equipment Submittals
07/13/2023 Plans Lakewood Storage
07/17/2023 Lakewood Storage Approved
07/17/2023 Letter Fire (Alarm) Plan Review Notice
09/19/2023 Engineer Report/Study 00002774_230918_121545
09/19/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter Fire (Alarm) Plan Review Notice
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter Fire Building Plan Review
09/21/2023 Letter Fire Building Plan Review
09/21/2023 Letter Fire Building Plan Review
09/29/2023 Letter INSPECTION SUMMARY
10/03/2023 Letter Fire Building Plan Review
10/03/2023 Letter INSPECTION SUMMARY
10/03/2023 Letter INSPECTION SUMMARY
10/04/2023 Lakeview Calc Area 1
10/04/2023 Lakeview Calc Area 2
10/04/2023 Lakeview Self Storage 001
10/04/2023 Lakeview Self Storage 002
10/04/2023 Lakeview Self Storage 003
10/04/2023 Lakeview Self Storage 004
10/04/2023 Lakeview Self Storage 005
10/09/2023 Letter INSPECTION SUMMARY
10/13/2023 Letter INSPECTION SUMMARY
10/13/2023 Letter INSPECTION SUMMARY
10/17/2023 Letter INSPECTION SUMMARY
10/18/2023 Letter Fire (Sprinkler) Plan Review
10/31/2023 Letter Fire (Sprinkler) Plan Review
10/31/2023 Letter INSPECTION SUMMARY
11/01/2023 Letter INSPECTION SUMMARY
12/05/2023 Letter INSPECTION SUMMARY
12/05/2023 Letter INSPECTION SUMMARY
12/05/2023 Letter INSPECTION SUMMARY
12/19/2023 20231215_205144
12/19/2023 COI - Strickland Construction Company, Inc_ - City of Lee's Summit, Missouri
02/15/2024 Letter INSPECTION SUMMARY
02/21/2024 Lakeview Calc Area 1
02/21/2024 Lakeview Calc Area 2
02/21/2024 Plans Lakeview Self Storage 001
02/21/2024 Plans Lakeview Self Storage 002
02/21/2024 Plans Lakeview Self Storage 003
02/21/2024 Plans Lakeview Self Storage 004
02/21/2024 Plans Lakeview Self Storage 005
02/28/2024 Letter Fire (Sprinkler) Plan Review
06/10/2024 Letter INSPECTION SUMMARY
06/13/2024 Letter INSPECTION SUMMARY
06/14/2024 Letter INSPECTION SUMMARY
06/14/2024 Letter INSPECTION SUMMARY
06/26/2024 Letter INSPECTION SUMMARY
06/28/2024 Letter INSPECTION SUMMARY
07/03/2024 Letter INSPECTION SUMMARY
07/05/2024 Letter INSPECTION SUMMARY
07/09/2024 Letter INSPECTION SUMMARY
07/10/2024 Letter INSPECTION SUMMARY
08/21/2024 Letter INSPECTION SUMMARY
09/09/2024 3rd Party Permit/Approval Special Inspections Approval Letter
09/10/2024 Letter INSPECTION SUMMARY
09/18/2024 Letter INSPECTION SUMMARY
09/19/2024 Letter INSPECTION SUMMARY
09/20/2024 Letter INSPECTION SUMMARY
09/30/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/14/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Letter INSPECTION SUMMARY
10/17/2024 Certificate/License Codes Temporary Certificate of Occupancy
10/17/2024 Receipt Receipt for transaction:2024-008413
10/18/2024 Letter Fire Loss Reduction Form
10/31/2024 Plans Lakeview Self Storage 2 SPR APPROVED
10/31/2024 Plans Lakeview Self Storage 3 SPR APPROVED
10/31/2024 Plans Lakeview Self Storage 4 SPR APPROVED
10/31/2024 Plans Lakeview Self Storage 5 SPR APPROVED
10/31/2024 Plans Lakeview Self Storage 6 SPR APPROVED
11/19/2024 Certificate/License Codes Temporary Certificate of Occupancy
11/19/2024 Receipt Receipt for transaction:2024-009038
12/30/2024 Certificate/License Codes Temporary Certificate of Occupancy
01/06/2025 3RD Party Insp Report BACKFLOW CERTIFICATION - IRRIGATION AND DOMESTIC
01/21/2025 Activity Document Inspection LSFD-INS-2024-0001637-2
01/21/2025 Letter Field Certificate of Occupancy
01/21/2025 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home