Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Pavement-Curb Construction
|
Pending
|
|
|
|
|
Misc
|
Pavement-Aggregate Base
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
ESC - (Vegetation/Ground Cover)
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Sidewalk Inspection
|
Pending
|
|
|
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Pending
|
|
|
|
|
Misc
|
Water Line - Coliform Test 1
|
Pending
|
|
|
|
Site Visit
|
Pending
|
|
6/3/2025
|
|
|
Misc
|
Sanitary Sewer - Mandrel
|
Pending
|
|
6/19/2025
|
|
Sanitary Sewer - Vacuum
|
Pending
|
|
6/19/2025
|
|
Sanitary Sewer - Camera Test
|
Pending
|
|
6/19/2025
|
|
Pavement-Surface
|
Pending
|
|
6/19/2025
|
|
|
Misc
|
Install Street and Stop Signs
|
Pending
|
|
6/19/2025
|
|
|
Misc
|
Pavement-Stabilized Subgrade
|
Pending
|
|
6/19/2025
|
|
|
Misc
Corrective Action Required
|
Storm Sewer Construction Inspection
|
Pending
|
|
6/19/2025
|
|
|
Misc
|
Erosion Control Inspection
|
Failed
|
|
|
05/16/2023
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
|
05/19/2023
|
|
Misc
Corrective Action Required
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
07/11/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
7/12/2023
|
7/12/2023
|
07/12/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
7/13/2023
|
7/13/2023
|
07/13/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
07/14/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
7/17/2023
|
7/25/2023
|
07/25/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
07/26/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
07/27/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
08/07/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
8/17/2023
|
8/16/2023
|
08/17/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
8/17/2023
|
8/17/2023
|
08/17/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
8/18/2023
|
8/18/2023
|
08/18/2023
|
|
Misc
|
Water Line - Construction Inspection
|
Partial
|
|
|
08/18/2023
|
|
Misc
|
Storm Sewer Construction Inspection
|
Partial
|
|
|
08/24/2023
|
|
Misc
|
Storm Sewer Construction Inspection
|
Partial
|
9/6/2023
|
9/6/2023
|
09/05/2023
|
|
Misc
|
Site Visit
|
Partial
|
|
|
09/14/2023
|
|
Misc
|
Site Visit
|
Complete
|
9/14/2023
|
9/14/2023
|
09/14/2023
|
|
Misc
|
Water Line - Construction Inspection
|
Partial
|
8/21/2023
|
8/21/2023
|
09/19/2023
|
|
Misc
|
Water Line - Construction Inspection
|
Partial
|
|
|
09/20/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
9/27/2023
|
9/27/2023
|
09/27/2023
|
|
Misc
|
Water Line - Construction Inspection
|
Partial
|
|
|
10/09/2023
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Partial
|
|
|
10/16/2023
|
|
Misc
|
Pavement-Proof Roll
|
Partial
|
|
|
10/20/2023
|
|
Misc
Corrective Action Required
|
Pavement-Proof Roll
|
Passed
|
|
|
10/23/2023
|
|
Misc
Corrective Action Required
|
Pavement-Aggregate Base
|
Passed
|
|
|
10/23/2023
|
|
Misc
|
Erosion Control Inspection
|
Failed
|
|
|
10/25/2023
|
|
Misc
Corrective Action Required
|
Pavement-Aggregate Base
|
Partial
|
10/26/2023
|
10/26/2023
|
10/26/2023
|
|
MISC
Corrective Action Required
|
Water Line - Coliform Test 1
|
Partial
|
|
|
10/31/2023
|
|
Misc
|
Sidewalk Inspection
|
Partial
|
|
|
11/27/2023
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
12/18/2023
|
12/18/2023
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
12/20/2023
|
12/20/2023
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
12/22/2023
|
12/22/2023
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
12/28/2023
|
12/28/2023
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
1/2/2024
|
01/03/2024
|
|
Misc
|
Storm Sewer Construction Inspection
|
Partial
|
9/6/2023
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Water Line - Construction Inspection
|
Passed
|
10/10/2023
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Pavement-Aggregate Base
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
MISC
Corrective Action Required
|
Water Line - Coliform Test 1
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Sidewalk Inspection
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
Corrective Action Required
|
Sanitary - Material Verification
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Sanitary Sewer Construction Inspection
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Sanitary Sewer - Air Test
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Sanitary Sewer - Mandrel
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Sanitary Sewer - Vacuum
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Grading/Excavation/Fill Inspection
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Pavement-Surface
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Pavement-Aggregate Base
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
Corrective Action Required
|
Install Street and Stop Signs
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Pavement-Stabilized Subgrade
|
Partial
|
|
1/4/2024
|
01/04/2024
|
|
Misc
Corrective Action Required
|
Storm Sewer Construction Inspection
|
Passed
|
|
1/4/2024
|
01/04/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
1/23/2024
|
01/23/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
2/28/2024
|
02/28/2024
|
|
Misc
|
Site Visit
|
Partial
|
3/6/2024
|
3/6/2024
|
03/06/2024
|
|
Misc
|
Site Visit
|
Partial
|
3/8/2024
|
3/8/2024
|
03/08/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
3/29/2024
|
03/29/2024
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
3/29/2024
|
03/29/2024
|
|
Misc
|
Grading/Excavation/Fill Inspection
|
Passed
|
|
3/29/2024
|
03/29/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
4/18/2024
|
04/18/2024
|
|
Misc
|
Pavement-Curb Construction
|
Partial
|
|
|
04/30/2024
|
|
Misc
|
Pavement-Aggregate Base
|
Partial
|
|
|
04/30/2024
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
4/30/2024
|
04/30/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
6/28/2024
|
06/28/2024
|
|
Misc
|
Site Visit
|
Partial
|
7/19/2024
|
7/19/2024
|
07/19/2024
|
|
Misc
|
Site Visit
|
Partial
|
7/22/2024
|
7/22/2024
|
07/22/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
7/25/2024
|
07/25/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
8/6/2024
|
08/06/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
8/8/2024
|
08/08/2024
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
8/8/2024
|
08/08/2024
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
8/8/2024
|
08/08/2024
|
|
Misc
|
Site Visit
|
Partial
|
8/19/2024
|
8/19/2024
|
08/19/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
8/22/2024
|
08/22/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
8/27/2024
|
08/27/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
8/27/2024
|
08/27/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
9/4/2024
|
09/04/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
9/17/2024
|
09/17/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
9/18/2024
|
09/18/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
9/19/2024
|
09/19/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
9/30/2024
|
09/30/2024
|
|
Misc
|
Erosion Control Inspection
|
Failed
|
|
10/11/2024
|
10/14/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
10/10/2024
|
10/14/2024
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
10/31/2024
|
10/31/2024
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
10/31/2024
|
10/31/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
11/8/2024
|
11/08/2024
|
|
Misc
|
Erosion Control Inspection
|
Failed
|
|
11/13/2024
|
11/13/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
11/21/2024
|
11/21/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
11/26/2024
|
11/26/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
12/13/2024
|
12/13/2024
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
12/13/2024
|
12/13/2024
|
|
Misc
Corrective Action Required
|
Site Visit
|
Partial
|
|
12/13/2024
|
12/13/2024
|
|
Misc
|
Site Visit
|
Partial
|
|
12/31/2024
|
12/31/2024
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
12/31/2024
|
12/31/2024
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
12/31/2024
|
12/31/2024
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
1/25/2025
|
01/25/2025
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
1/25/2025
|
01/25/2025
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
1/31/2025
|
01/31/2025
|
|
Misc
|
Site Visit
|
Partial
|
|
1/31/2025
|
01/31/2025
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
2/24/2025
|
02/24/2025
|
|
Misc
|
ESC - (Vegetation/Ground Cover)
|
Partial
|
|
2/24/2025
|
02/24/2025
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
2/28/2025
|
02/28/2025
|
|
Misc
|
Site Visit
|
Partial
|
|
2/28/2025
|
02/28/2025
|
|
Misc
|
Erosion Control Inspection
|
Partial
|
|
4/23/2025
|
04/24/2025
|
|
Misc
|
Erosion Control Inspection
|
Failed
|
4/29/2025
|
4/29/2025
|
04/29/2025
|
|
Misc
|
Sidewalk Inspection
|
Partial
|
|
5/14/2025
|
05/13/2025
|
|
Misc
Corrective Action Required
|
Erosion Control Inspection
|
Partial
|
|
5/15/2025
|
05/14/2025
|
|
Misc
|
Site Visit
|
Partial
|
|
5/15/2025
|
05/14/2025
|
|
Misc
|
Site Visit
|
Partial
|
|
5/21/2025
|
05/21/2025
|
|
Misc
|
Site Visit
|
Partial
|
|
5/27/2025
|
05/28/2025
|
|
Misc
|
Water Line - Hydrostatic Test
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
Corrective Action Required
|
Sanitary Sewer - Air Test
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
|
Sanitary Sewer - Mandrel
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
|
Sanitary Sewer - Vacuum
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
|
Water Line - Coliform Test 2
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
|
Sanitary Sewer - Camera Test
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
|
Sanitary Sewer - Air Test
|
Passed
|
|
6/19/2025
|
06/20/2025
|
|
Misc
|