Permit Application Status

PRCOM20204934


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20204934
Building Permit - Commercial
Certificate of Occupancy
STAR ACQUISITIONS & DEVELOPMENT LLC
NEW SHELL BUILDING
NEW SHELL WITH DRIVE-THRU WINDOW - POSSIBLE RESTAURANT AND MERCANTILE STOP WORK ORDER generated on 04/22/2022 12:00 AM by username 'John Jackson'. STOP WORK ORDER removed on 04/28/2022 12:00 AM by username 'John Jackson'. STOP WORK ORDER generated on 09/16/2022 12:00 AM by username 'John Jackson'. STOP WORK ORDER removed on 09/21/2022 12:00 AM by username 'John Jackson'.
12/28/2020
11/15/2021
09/22/2023
Locations
Contacts
BUILDFORCE CONSTRUCTION, Address:1521 ATLANTIC, Phone:(816) 739-8864  
OLIPHANTS HEATING & COOLING INC, Address:208 WOLLARD BLVD, Phone:(816) 470-6444  
Reade Electric LLC, Address:PO Box 1117, Phone:(816) 889-8388  
ALWAYS PLUMBING LLC, Address:807 NASHUA ROAD, Phone:(819) 781-7749  
SCHARHAG ARCHITECTS, Address:6247 BROOKSIDE BLVD STE 204, Phone:(816) 656-5055  
STAR ACQUISITIONS & DEVELOPMENT LLC, Address:244 W MILL STE 101  
aaron@stardevcorp.com, Address:aaron@stardevcorp.com  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 01/12/2021 11/11/2021
Joe Frogge
LC - MEP Subs
Resolved
11/11/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
LC - General Contractor
Resolved
11/11/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact.
Building Plan Review Approved with Conditions 01/12/2021 10/28/2021
Joe Frogge
Miscellaneous Correction
Resolved
10/28/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
Final Development Plan
Resolved
04/14/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Engineered truss package
Corrective Action Required
12/30/2020

Copies of the engineered truss package were not provided at the time of permit application. Action required: Roof truss package submittal deferred to construction. Package must be approved before construction or inspection.
Final Development Plan Review Approved 04/14/2021
Joe Frogge
Fire Plan Review Approved 01/12/2021 12/30/2020
Michael Weissenbach
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Shell Building $1,700.00 $1,700.00 Paid 11/12/2021
8331401-Water Tap Fee $9,549.00 $9,549.00 Paid 11/12/2021
8350015-Water Meter Fee $715.62 $715.62 Paid 11/12/2021
9110068-Storm Fee $731.40 $731.40 Paid 11/12/2021
9110071-Site Grading Fee $883.80 $883.80 Paid 11/12/2021
9110081-Paved Surface Inspection Fee $3,382.29 $3,382.29 Paid 11/12/2021
91100C8-Sanitary Sewer Insp Fees $35.25 $35.25 Paid 11/12/2021
91100C9-Water Insp Fee $28.50 $28.50 Paid 11/12/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 11/30/2021
8350015-Water Meter Fee $3,102.16 $3,102.16 Paid 11/02/2022
$3,817.78
8331401-Water Tap Fee $24,865.00 $24,865.00 Paid 11/02/2022
$34,414.00
8331507-Sanitary Sewer Development Fee $9,230.00 $9,230.00 Paid 11/02/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Failed 11/24/2021 (10:00) 11/24/2021 11/24/2021
Misc
Corrective Action Required
11/24/2021
-Provide city approved, stamped plans -Provide 3" clearance around rebar -Northeast corner of footing not 3' below grade
Footing Inspection - Commercial Not Ready 11/24/2021 (1:00) 11/24/2021 11/24/2021
Misc
Corrective Action Required
11/24/2021
-Provide city approved, stamped plans -Provide 3" clearance around rebar -Northeast corner of footing not 3' below grade
Footing Inspection - Commercial Partial 11/30/2021 (8:00) 11/30/2021 11/30/2021
Misc
Corrective Action Required
11/24/2021
-Northeast corner of footing not 3' below grade - UPLOAD SPECIAL INSPECTION REPORTS TO PERMIT: PLACEMENT OF STEEL,PLACEMENT OF CONCRETE,TESTING OF CONCRETE - - UFER LOCATED NW CORNER OF BLDG - OK TO POUR
Underslab Plumbing Inspection - Commercial Passed 12/10/2021 12/10/2021 12/10/2021
Misc
Corrective Action Required
12/10/2021
MAIN TRUNK WEST END OF BLDG, CLEANOUT NW CORNER
Site Visit Partial 4/5/2022 04/05/2022
Misc
Informational
04/05/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Erosion Control Inspection Residential Partial 4/28/2022 04/28/2022
Misc
Informational
04/28/2022
04/06/22 Wednesday (Star Development - Aaron (816) 807-2502) Silt fence has failed throughout the project. Silt fence needs to be re-staked and repaired. 04/18/22 Monday (Star Development- Aaron) I called contractor and informed him that the erosion control had failed. He expected the erosion fencing company to be out in the next few days. I will check site again to follow up progress on re-establishing erosion control measures. 04/21/22 Thursday (Star Development-Aaron) I again called Aaron about the failed silt fencing around the project. Aaron said he was going to come to the site today with the silt fencing company and re-establish the erosion control. 04/22/22 Friday (Star Development-Aaron) I called Aaron to let him know that there will be No Work on site until erosion control measure are in place. 04/28/22 Thursday Erosion control silt fence was corrected 04/27/22 Wednesday. Contractor resume work on site.
Storm Sewer Construction Inspection Partial 4/28/2022 04/28/2022
Misc
Informational
04/28/2022
04/28/22 Thursday (Sub Contractor For Star Development) Contractor will began work next week. Contractor will be install approximately 200’ of 15” Storm as per plan. 05/05/22 Thursday (Sub Contractor For Star Development) Contractor began work on 5/3/22 Tuesday. On 05/09/22 Monday I will meet with contractor and review all storm sewer construction on site. 05/09/22 Monday Contractor continued storm installation storm box 1,2, & 3 Were set early last week. The last box should be set by tomorrow. Approximately 160’ of 15” Storm pipe HPDE was installed, also last week between the storm boxes. 5/20/22 Friday Contractor laid approximately 70’ (15” green sanitary pipe)the storm pipe from 3 storm box to 4 storm box. Storm box 4 was set last week. See pics of storm line.
Storm Sewer Construction Inspection Partial 5/10/2022 05/10/2022
Misc
Informational
05/10/2022
5-10-22 AN crew is working on pouring some of the inverts for the storm boxes 2 pics
Storm Sewer Construction Inspection Partial 5/11/2022 05/11/2022
Misc
Informational
05/10/2022
5-10-22 AN crew is working on pouring some of the inverts for the storm boxes 2 pics
Misc
Informational
05/11/2022
5-11-22 AN. Storm on the south side is completed and back filled. Need to find out about one of the boxes being buried.
In-wall Inspection Failed 5/11/2022 5/11/2022 05/11/2022
Miscellaneous Correction
Corrective Action Required
05/11/2022
COMPLETE H2.5s NORTH END ROOF NAIL EXTERIOR WALL SHETHING MARKED ON SOUTH END ROOF SHEATHING NAILING APPROVED OK TO COVER PROVIDE CITY APPROVED TRUSS PLANS & LAYOUT
Site Visit Partial 5/12/2022 05/12/2022
Misc
Informational
04/05/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/12/2022
5-12-22 AN no work being done
In-wall Inspection Partial 5/13/2022 5/13/2022 05/13/2022
Miscellaneous Correction
Corrective Action Required
05/11/2022
EXTERIOR WALL SHEATHING OK TO COVER ROOF SHEATHING NAILING APPROVED OK TO COVER PROVIDE CITY APPROVED TRUSS PLANS & LAYOUT NO WINDOW FLASHING ON WOOD SILLS
In-wall Inspection Partial 5/16/2022 05/13/2022
Miscellaneous Correction
Corrective Action Required
05/13/2022
EXTERIOR WALL SHEATHING OK TO COVER ROOF SHEATHING NAILING APPROVED OK TO COVER PROVIDE CITY APPROVED TRUSS PLANS & LAYOUT PROVIDE ANCHOR BOLTS WITHIN 12" OF PLATE BREAKS NORTH WALL NO WINDOW FLASHING ON WOOD SILLS
Site Visit Partial 5/16/2022 05/16/2022
Misc
Informational
05/12/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/12/2022
5-12-22 AN no work being done
Misc
Informational
05/16/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Site Visit Partial 5/16/2022 05/16/2022
Misc
Informational
05/16/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/16/2022
5-12-22 AN no work being done
Misc
Informational
05/16/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
05/16/2022
I
Site Visit Partial 5/17/2022 05/17/2022
Misc
Informational
05/16/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/16/2022
5-12-22 AN no work being done
Misc
Informational
05/16/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
05/16/2022
5-17-22 AN just working on retaining wall
Site Visit Partial 5/18/2022 05/18/2022
Misc
Informational
05/17/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/17/2022
5-12-22 AN no work being done
Misc
Informational
05/17/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
05/17/2022
5-17-22 AN just working on retaining wall 5-18-22 AN crew still working on retaining wall / crew was pumping water
Site Visit Partial 5/18/2022 05/18/2022
Misc
Informational
05/18/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/18/2022
5-12-22 AN no work being done
Misc
Informational
05/18/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
05/18/2022
5-17-22 AN just working on retaining wall 5-18-22 AN crew still working on retaining wall / crew was pumping water
Retaining Wall Inspection Partial 5/20/2022 05/20/2022
Misc
Informational
05/20/2022
5/20/22 Friday (Westland Const.) Contractor has begun working on the installation of retaining wall. Informed Richard and onsite supervisor that they need a 3rd party inspection. 6/13/22 Thursday (Westland Const.) Wall appears to be completed.
In-wall Inspection Partial 6/3/2022 06/03/2022
Miscellaneous Correction
Corrective Action Required
05/13/2022
EXTERIOR WALL SHEATHING OK TO COVER ROOF SHEATHING NAILING APPROVED OK TO COVER
Erosion Control Inspection Residential Failed 08/24/2022
Misc
Informational
04/06/2022
04/06/22 Wednesday (Star Development - Aaron (816) 807-2502) Silt fence has failed throughout the project. Silt fence needs to be re-staked and repaired.
Misc
Corrective Action Required
08/24/2022
Failed Erosion Control.
Pavement-Curb Construction Partial 09/12/2022
Misc
Informational
09/12/2022
09/12/22 Monday JMJ ( Charlie’s Concrete Const. / General contractor Star Development ) Contractor has installed 80% of curbs without the knowledge of inspector. No proof roll was preformed on rock subgrade. I talked with Charlie Ellebracht- Charlie’s Concrete an informed him that proof rolls were required as well as third party inspection. Contractor continues to install curbs.
Site Visit Failed - Stop Work 09/16/2022
Misc
Informational
05/18/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
05/18/2022
5-12-22 AN no work being done
Misc
Informational
05/18/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
05/18/2022
5-17-22 AN just working on retaining wall 5-18-22 AN crew still working on retaining wall / crew was pumping water
Misc
Informational
08/24/2022
09/16/22 Friday JMJ Contractor failed to contact inspector for pours for sidewalks, curbs and, dumpster area. No proof roll was performed at site.
Sidewalk Inspection Partial 09/21/2022
Misc
Informational
09/21/2022
09/21/22 Wednesday JMJ ( Star Development/ Charlie’s Concrete ) Contractor is forming and framing sidewalks.
Sidewalk Inspection Partial 09/21/2022
Misc
Informational
09/21/2022
09/21/22 Wednesday JMJ ( Star Development/ Charlie’s Concrete ) Forms and materials for sidewalks on site passed pre inspection.
Sidewalk Inspection Partial 09/22/2022
Misc
Informational
09/22/2022
09/22/22 Thursday JMJ ( Star Development/ Charlie’s Concrete ) Contractor pour the sidewalk along Southside of project.
Pavement-Aggregate Base Partial 09/28/2022
Misc
Informational
09/28/2022
On Tuesday 9-27-2022. Concrete contractor poured concrete pavement in parking lot. Contractor poured drive thru line and the SE portion of the parking lot. On Wednesday, 9-28-2022. Charlie Concrete Co. resumed pavement installation. Contractor pouring in front of business parking lot. Contractor poured approx. 2500 sf of pavement. Geiger ready-mix was the supplier.
Pavement-Aggregate Base Partial 09/29/2022
Misc
Informational
09/29/2022
On Thursday, 9-29-2022 the contractor resumed concrete pavement installation in front of the building.
Pavement-Surface Partial 09/30/2022
Misc
Informational
09/30/2022
On Friday Concrete contractor resumed installation of the concrete pavement for the parking lot. Contractor poured south center area of the lot completing everything for the lot except back drive through area. Contractor sawed concrete poured day before.
Pavement-Surface Partial 10/05/2022
Misc
Informational
09/30/2022
( JMJ ) 09/23/22 On Friday Concrete contractor resumed installation of the concrete pavement for the parking lot. Contractor poured south center area of the lot completing everything for the lot except back drive through area. Contractor sawed concrete poured day before. 10/05/22 Wednesday JMJ ( Charlie’s Concrete ) Parking lot was completed last week also saw cut were made.
Erosion Control Inspection Partial 10/25/2022
Misc
Informational
10/25/2022
10/25/22 Tuesday JMJ Erosion on site is under control.
Miscellaneous Inspection Passed 10/28/2022 10/28/2022
Misc
Informational
10/28/2022
NEW SUPER KENNETH CARMAN @ STAR DEV / BUILDFORCE 816 465-2129 DISCUSS STATUS OF TO OBTAIN TCO
Sanitary Sewer Construction Inspection Partial 11/01/2022
Misc
Informational
11/01/2022
11/01/22 Tuesday JMJ ( Star Development ) Contractor locating sanitary stub to connect to the building for service.
Sanitary Sewer Construction Inspection Passed 11/01/2022
Misc
Informational
11/01/2022
11/01/22 Tuesday JMJ ( Star Development ) Contractor locating sanitary stub to connect to the building for service. Verified connection to the 6” sanitary with a 6” X4” reducer and approximately 60’ of 4” white colored sanitary private main @ 2:30PM.
Water Service Inspection Passed 11/02/2022
Misc
Informational
11/02/2022
11/02/22 Wednesday ( Star Development ) Contractor laid approximately 28’ of 2” from building.
Pavement-Surface Partial 11/09/2022
Misc
Informational
10/05/2022
( JMJ ) 09/23/22 On Friday Concrete contractor resumed installation of the concrete pavement for the parking lot. Contractor poured south center area of the lot completing everything for the lot except back drive through area. Contractor sawed concrete poured day before. 10/05/22 Wednesday JMJ ( Charlie’s Concrete ) Parking lot was completed last week also saw cut were made.
Misc
Informational
11/09/2022
11/09/22 Wednesday JMJ ( Charlie’s Concrete ) Contractor is grading and setting forms for wrap around driveway for the backside of building.
Pavement-Surface Partial 11/10/2022
Misc
Informational
11/09/2022
( JMJ ) 09/23/22 On Friday Concrete contractor resumed installation of the concrete pavement for the parking lot. Contractor poured south center area of the lot completing everything for the lot except back drive through area. Contractor sawed concrete poured day before. 10/05/22 Wednesday JMJ ( Charlie’s Concrete ) Parking lot was completed last week also saw cut were made.
Misc
Informational
11/09/2022
11/09/22 Wednesday JMJ ( Charlie’s Concrete ) Contractor is grading and setting forms for wrap around driveway for the backside of building. 11/10/22 Thursday JMJ ( Charlie’s Concrete ) Contractor continued grading wrap around drive through.
Water Line - Construction Inspection Partial 11/10/2022
Misc
Informational
11/10/2022
11/10/22 Thursday JMJ ( Star Development ) After LS Water came out to tap water main for 1” irrigation & 2” domestic service lines and found that there was not enough distance from water joint to installed. LS Water Director has approved a installation of fire hydrant and tap the 2” domestic off the newly installed pipe. The new addition has been uploaded to City View.
Water Line - Construction Inspection Partial 12/01/2022
Misc
Informational
11/10/2022
11/10/22 Thursday JMJ ( Star Development ) After LS Water came out to tap water main for 1” irrigation & 2” domestic service lines and found that there was not enough distance from water joint to installed. LS Water Director has approved a installation of fire hydrant and tap the 2” domestic off the newly installed pipe. The new addition has been uploaded to City View. 12/01/22 Thursday JMJ ( Star Development ) Contractor began installation of hydrant that is required by the city. This will allow a tapping point for the domestic and irrigation water main as-per the City of Lee’s Summit. This change will be reflected on the as built.
Site Visit Partial 12/02/2022
Misc
Informational
09/16/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
09/16/2022
5-12-22 AN no work being done
Misc
Informational
09/16/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
09/16/2022
5-17-22 AN just working on retaining wall 5-18-22 AN crew still working on retaining wall / crew was pumping water
Misc
Informational
09/16/2022
09/16/22 Friday JMJ Contractor failed to contact inspector for pours for sidewalks, curbs and, dumpster area. No proof roll was performed at site.
Misc
Informational
12/02/2022
12/02/22 Friday Talked with site supervisor about what could be done to possibly stabilize subgrade. Inclement weather has adverse effected job site in some area.
Water Line - Construction Inspection Partial 12/05/2022
Misc
Informational
12/01/2022
11/10/22 Thursday JMJ ( Star Development ) After LS Water came out to tap water main for 1” irrigation & 2” domestic service lines and found that there was not enough distance from water joint to installed. LS Water Director has approved a installation of fire hydrant and tap the 2” domestic off the newly installed pipe. The new addition has been uploaded to City View. 12/01/22 Thursday JMJ ( Star Development ) Contractor began installation of hydrant that is required by the city. This will allow a tapping point for the domestic and irrigation water main as-per the City of Lee’s Summit. This change will be reflected on the as built. 12/05/22 Monday JMJ ( Star Development ) The contractor are trying to get a two taps on the newly installed water line hydrant ( irrigation & domestic ). Contractor can not find a 1” tap for the irrigation.
Water Line - Construction Inspection Partial 12/06/2022
Misc
Informational
12/05/2022
11/10/22 Thursday JMJ ( Star Development ) After LS Water came out to tap water main for 1” irrigation & 2” domestic service lines and found that there was not enough distance from water joint to installed. LS Water Director has approved a installation of fire hydrant and tap the 2” domestic off the newly installed pipe. The new addition has been uploaded to City View. 12/01/22 Thursday JMJ ( Star Development ) Contractor began installation of hydrant that is required by the city. This will allow a tapping point for the domestic and irrigation water main as-per the City of Lee’s Summit. This change will be reflected on the as built. 12/05/22 Monday JMJ ( Star Development ) The contractor are trying to get a two taps on the newly installed water line hydrant ( irrigation & domestic ). Contractor can not find a 1” tap for the irrigation. 12/06/22 Tuesday JMJ ( Star Development ) The City of Lee’s Summit tap the 1” for irrigation and 2” for domestic water. Contractor installed meter assembly for the irrigation and domestic as well as the copper lines leading to the meter. The newly installed existing copper main running from the building were connnect.
Piers/Caissons Inspection - Commercial Failed 12/6/2022 (2:00) 12/6/2022 12/06/2022
Misc
Corrective Action Required
12/06/2022
Provide stamped pier detail
Piers/Caissons Inspection - Commercial Passed 12/7/2022 (9:00) 12/7/2022 12/07/2022
Misc
Resolved
12/07/2022
Provide stamped pier detail
Misc
Informational
12/07/2022
(3) PIERS WITH GROUND ROD FOR LIGHT POLE BASES
Gas Service Inspection - Commercial Passed 12/8/2022 12/8/2022 12/07/2022
Sidewalk Inspection Partial 12/07/2022
Misc
Informational
09/22/2022
09/22/22 Thursday JMJ ( Star Development/ Charlie’s Concrete ) Contractor pour the sidewalk along Southside of project.
Misc
Informational
12/07/2022
12/07/22 Wednesday JMJ ( Star Development/ Charlie’s Concrete ) Contractor is framing and graveling sidewalk on the backside of property.
Sidewalk Inspection Partial 12/09/2022
Misc
Informational
12/07/2022
09/22/22 Thursday JMJ ( Star Development/ Charlie’s Concrete ) Contractor pour the sidewalk along Southside of project.
Misc
Informational
12/07/2022
12/07/22 Wednesday JMJ ( Star Development/ Charlie’s Concrete ) Contractor is framing and graveling sidewalk on the backside of property.
Misc
Informational
12/09/2022
12/09/22 Friday JMJ ( Star Development/ Charlie’s Concrete ) Contractor poured sidewalk and ADA ramp.
Site Visit Complete 2/1/2023 2/1/2023 02/01/2023
Misc
Informational
12/02/2022
04/05/22 Tuesday Inspection at site will be cover the connection to the sanitary main, proof rolls of parking lot, asphalt, signs, stripping & vegetation. I will check on project for updates for scheduling of inspection.
Misc
Informational
12/02/2022
5-12-22 AN no work being done
Misc
Informational
12/02/2022
5-16-22 AN no work being done.. there is crew working on a retaining wall
Misc
Informational
12/02/2022
5-17-22 AN just working on retaining wall 5-18-22 AN crew still working on retaining wall / crew was pumping water
Misc
Informational
12/02/2022
09/16/22 Friday JMJ Contractor failed to contact inspector for pours for sidewalks, curbs and, dumpster area. No proof roll was performed at site.
Misc
Informational
12/02/2022
12/02/22 Friday Talked with site supervisor about what could be done to possibly stabilize subgrade. Inclement weather has adverse effected job site in some area.
Misc
Informational
02/01/2023
02/01/23 Wednesday JMJ ( Water Department ) Repair 2" Domestic water meter that froze.
In-wall Inspection Failed 3/9/2023 3/9/2023 03/09/2023
Miscellaneous Correction
Corrective Action Required
06/03/2022
EXTERIOR WALL SHEATHING OK TO COVER ROOF SHEATHING NAILING APPROVED OK TO COVER provide truss plans, nail dbl truss, proivde fix on truss at the NE corner of building. recall wehn plans are on site.
ESC - (Vegetation/Ground Cover) Partial 3/10/2023 3/10/2023 03/10/2023
Misc
Informational
03/10/2023
03/10/23 Friday Contractor has been installing shrubs and rocks on project.
Electrical Service Inspection Passed 4/13/2023 4/13/2023 04/13/2023
Misc
Informational
04/13/2023
Service for 1440 white box and 1440 House Panel
Occupancy Inspection - Planning Temporary C of O 5/11/2023 5/11/2023 05/11/2023
MISC
Corrective Action Required
05/11/2023
Install trash enclosure gates per approved plans.
Misc
Informational
05/11/2023
The site has all sod installed, but it is very stressed. Staff will monitor its condition and will require its re-installation should the sod die.
Occupancy Inspection - Water Utilities Passed 5/11/2023 5/11/2023 05/11/2023
Final Inspection - Commercial Failed 5/11/2023 05/11/2023
Miscellaneous Correction
Corrective Action Required
05/11/2023
-Seal all firewall penetrations and perimeter -Nail all truss hold downs -Strap top plate lapped less than 48" at entry door -Secure all mc within 12" of boxes at exterior walls -Secure water service lines -Label RTUs -Remove trash from rooftop -Paint all exterior metallic gas lines with corrosion resistant paint -Provide 30" clearance perpendicular to rungs at rooftop ladder -Complete corrections for all other departments
Occupancy Inspection - Engineering Temporary C of O 5/11/2023 5/11/2023 05/11/2023
Misc
Informational
05/11/2023
05/11/23 Thursday ( Star Development ) 1. 5 and (1/2) half foot curb replacement ( connected to ADA ) at the East entrance on the Westside.
Above Ceiling Inspection Passed 05/11/2023
Footing Inspection - Commercial Passed 05/11/2023
Misc
Resolved
05/11/2023
-Northeast corner of footing not 3' below grade - UPLOAD SPECIAL INSPECTION REPORTS TO PERMIT: PLACEMENT OF STEEL,PLACEMENT OF CONCRETE,TESTING OF CONCRETE - OK TO POUR
Occupancy Inspection - Fire Passed 5/11/2023 5/11/2023 05/11/2023
Occupancy Inspection - Codes Commercial Failed 5/11/2023 5/11/2023 05/11/2023
MISC
Corrective Action Required
05/11/2023
-Seal all firewall penetrations and perimeter -Nail all truss hold downs -Strap top plate lapped less than 48" at entry door -Secure all mc within 12" of boxes at exterior walls -Secure water service lines -Label RTUs -Remove trash from rooftop -Paint all exterior metallic gas lines with corrosion resistant paint -Provide 30" clearance perpendicular to rungs at rooftop ladder -Complete corrections for all other departments
Occupancy Inspection - Engineering Passed 6/8/2023 6/8/2023 06/08/2023
Misc
Informational
05/11/2023
05/11/23 Thursday ( Star Development ) 1. 5 and (1/2) half foot curb replacement ( connected to ADA ) at the East entrance on the Westside. 06/08/23 Thursday JMJ ( Star Development ) Contractor repaired curb to complete the punch list item.
Occupancy Inspection - Codes Commercial Failed 7/20/2023 7/20/2023 07/20/2023
MISC
Corrective Action Required
05/11/2023
-Seal all firewall penetrations and perimeter -Complete corrections for all other departments
Occupancy Inspection - Planning Temporary C of O 07/20/2023
MISC
Corrective Action Required
05/11/2023
The trash enclosure must have either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. The wood fence pickets are not an approved material. Please update the gate material to meet UDO standards.
Occupancy Inspection - Codes Commercial Failed 7/26/2023 7/26/2023 07/26/2023
MISC
Corrective Action Required
07/20/2023
-Complete corrections for planning department: The trash enclosure must have either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. The wood fence pickets are not an approved material. Please update the gate material to meet UDO standards.
Occupancy Inspection - Planning Temporary C of O 09/15/2023
MISC
Corrective Action Required
07/20/2023
The trash enclosure must have either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. Composition wood or real wood fence pickets are not an approved material. Please update the gate material to meet UDO standards.
Occupancy Inspection - Planning Temporary C of O 09/15/2023
MISC
Corrective Action Required
09/15/2023
The trash enclosure must have either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. Composition wood or real wood fence pickets are not an approved material. Please update the gate material to meet UDO standards.
In-wall Inspection Passed 09/18/2023
Occupancy Inspection - Planning Passed 09/22/2023
MISC
Corrective Action Required
09/15/2023
The trash enclosure must have either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. Composition wood or real wood fence pickets are not an approved material. Please update the gate material to meet UDO standards.
Occupancy Inspection - Codes Commercial Full C of O 9/18/2023 09/22/2023
MISC
Resolved
09/22/2023
-Complete corrections for planning department: The trash enclosure must have either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. The wood fence pickets are not an approved material. Please update the gate material to meet UDO standards.
Documents & Images
Date Uploaded File Type Document Name
12/28/2020 Application Form Douglas Road Lot 4 Permit Application 12.28.20
12/28/2020 Engineer Report/Study Douglas Road Lot 4 - Special Inspections 12_28_20
12/28/2020 Engineer Report/Study Douglas Road Lot 4 Structural Calcuations 12_28_20
12/28/2020 Plans Douglas Road Lot 4 Full Plan Set with seal 12_28_20
12/30/2020 Letter Fire Building Plan Review
04/14/2021 Approved Plans approved - Douglas Road Lot 4 Full Plan Set with seal 12_28_20
10/28/2021 Application Form excise tax
10/28/2021 Application Form Permit application
11/09/2021 Engineer Report/Study Oakview Lot 4RWCALC
11/09/2021 Approved Plans approved - 10-14 Oakview Lot 4 Retaining Wall
11/12/2021 Receipt Receipt for transaction:2021-008720
11/22/2021 Approved Plans APPROVED 021-04-06 OAKVIEW LOT 4 SITE PLAN
11/24/2021 Letter INSPECTION SUMMARY
11/24/2021 Letter INSPECTION SUMMARY
11/30/2021 Receipt Receipt for transaction:2021-008969
11/30/2021 Letter INSPECTION SUMMARY
12/08/2021 C20-21-170
12/10/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter DS Building Permit
04/05/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/18/2022 Letter INSPECTION SUMMARY
04/18/2022 Letter INSPECTION SUMMARY
04/21/2022 Letter INSPECTION SUMMARY
04/22/2022 Letter Stop Work Order
04/28/2022 Letter Stop Work Order
04/28/2022 Letter INSPECTION SUMMARY
04/28/2022 Letter INSPECTION SUMMARY
05/03/2022 Letter INSPECTION SUMMARY
05/09/2022 image
05/09/2022 image0
05/09/2022 image1
05/10/2022 Letter INSPECTION SUMMARY
05/10/2022 Storm 1
05/10/2022 Storm 2
05/11/2022 Letter INSPECTION SUMMARY
05/11/2022 Letter INSPECTION SUMMARY
05/12/2022 Letter INSPECTION SUMMARY
05/13/2022 Letter INSPECTION SUMMARY
05/16/2022 Letter INSPECTION SUMMARY
05/16/2022 Engineer Report/Study Douglas Road Lot 4-Engineered Truss Design
05/16/2022 Plans Douglas Road Lot 4-Engineered Truss Layout
05/17/2022 Letter INSPECTION SUMMARY
05/17/2022 Letter INSPECTION SUMMARY
05/17/2022 Letter INSPECTION SUMMARY
05/17/2022 20220517-Window_Installation_Instructions
05/18/2022 20211208_3P_Inspection-Footings
05/18/2022 20220208_3P-Inspections_Steel
05/18/2022 20220421-3P_Inspection-Epoxy-Anchors
05/18/2022 Letter INSPECTION SUMMARY
05/18/2022 Letter INSPECTION SUMMARY
05/20/2022 image2
05/20/2022 image3
05/20/2022 Letter INSPECTION SUMMARY
06/01/2022 Plans Douglas Road Lot #4 Roof Truss Design Package
06/01/2022 Drawing Douglas Road Lot #4 Roof Truss Layout
06/01/2022 Approved Plans approved - Douglas Road Lot #4 Roof Truss Design Package
06/03/2022 Letter INSPECTION SUMMARY
06/06/2022 20220517_Douglas Road Lot 4_Window-Installation
06/09/2022 Letter INSPECTION SUMMARY
08/24/2022 Letter INSPECTION SUMMARY
09/12/2022 Curbs Poured and Forms for Curbs
09/12/2022 Letter INSPECTION SUMMARY
09/16/2022 Letter Stop Work Order
09/21/2022 Letter INSPECTION SUMMARY
09/21/2022 Sidewalks Pre Pour
09/21/2022 Letter INSPECTION SUMMARY
09/22/2022 Letter INSPECTION SUMMARY
09/22/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/28/2022 Letter INSPECTION SUMMARY
09/29/2022 Letter INSPECTION SUMMARY
09/30/2022 Letter INSPECTION SUMMARY
10/05/2022 Letter INSPECTION SUMMARY
10/25/2022 Letter INSPECTION SUMMARY
10/25/2022 Letter INSPECTION SUMMARY
10/25/2022 Letter INSPECTION SUMMARY
10/28/2022 Letter INSPECTION SUMMARY
11/01/2022 Letter INSPECTION SUMMARY
11/01/2022 Letter INSPECTION SUMMARY
11/02/2022 Receipt Receipt for transaction: 2022-008670
11/02/2022 Letter INSPECTION SUMMARY
11/09/2022 Wrap around driveway
11/09/2022 Letter INSPECTION SUMMARY
10/26/2022 Plans 2019.01.02-17-135 SDP UP REV3
11/10/2022 Email RE_ Oakview Lot 4 Water
11/10/2022 Letter INSPECTION SUMMARY
11/10/2022 Letter INSPECTION SUMMARY
11/14/2022 Drive Through & Sidewalk Backside of building
12/01/2022 Letter INSPECTION SUMMARY
12/02/2022 Letter INSPECTION SUMMARY
12/05/2022 Letter INSPECTION SUMMARY
12/06/2022 1”& 2” Taps off Fire Hydrant Assembly
12/06/2022 Installed Irrigation Meter Assembly & 1” Copper PIpe
12/06/2022 Letter INSPECTION SUMMARY
12/06/2022 Letter INSPECTION SUMMARY
12/06/2022 Drawing Oakview Lot 4 (light pole base)
12/07/2022 Approved Plans approved - Oakview Lot 4 (light pole base)
12/07/2022 Letter INSPECTION SUMMARY
12/07/2022 Letter INSPECTION SUMMARY
12/07/2022 Letter INSPECTION SUMMARY
12/09/2022 Letter INSPECTION SUMMARY
02/01/2023 2Domestic Water Meter Break
03/09/2023 Letter INSPECTION SUMMARY
03/10/2023 Letter INSPECTION SUMMARY
04/13/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Curb Repair Required @ East Entrance
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
06/08/2023 Letter INSPECTION SUMMARY
07/20/2023 Letter INSPECTION SUMMARY
07/20/2023 Letter INSPECTION SUMMARY
07/26/2023 Letter INSPECTION SUMMARY
09/18/2023 Letter INSPECTION SUMMARY
09/22/2023 Letter Codes Final Certificate of Occupancy
09/22/2023 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: