Planning Application Status

PL2022138




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2022138
Lee's Summit Chipman
Commercial Final Development Plan
Commercial Final Development Plan
Withdrawn
04/07/2022
Site development for new 5,000 square foot multi-tenant commercial building. Mike Weisenborn 07/12/2022 1:20 PM - Application has been withdrawn. See email.
Locations
Contacts
Lees Summit/Chipman Covenant Group LLC, Address:Julie A Margetich, Phone:(951) 582-5745  
HG CONSULT, INC, Address:9007 PINE ST, Phone:(816) 759-2285  
CLARKITECTURE, Address:7701 E KELLOGG DR, STE 630, Phone:(316) 302-4472  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 05/23/2022 05/23/2022
Loic Nguinguiri, E.I.
DE Future Repair Work
Corrective Action Required
05/23/2022

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
DE Contact Field Eng. Inspector
Corrective Action Required
05/23/2022

Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
DE C&O #11 Pavement Thickness
Corrective Action Required
05/23/2022

Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
DE Engineers Estimate
Corrective Action Required
05/23/2022

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $36,173.36
Corrective Action Required
05/23/2022

Additional silt fence is needed along the entire southern property line and at the northeastern point of interest (POI).
Planning Review Corrections 05/23/2022 05/23/2022
Victoria Nelson
Corrective Action Required
05/23/2022

The trash enclosure detail was never uploaded. Please upload it.
Corrective Action Required
05/23/2022

Wall mounted lighting specs where never uploaded. Please upload it.
Fire Review Approved with Conditions 05/23/2022 05/16/2022
Mike Weisenborn
Code Statement
Corrective Action Required
05/16/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code. Additional fire protection systems and assemblies may be required depending on the use of the building.
Imposed Loads
Corrective Action Required
05/16/2022

IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Building Codes Review No Comments 05/23/2022 05/16/2022
Mike Weisenborn
Traffic Review No Comments 05/23/2022 05/16/2022
Mike Weisenborn
Engineering Review Corrections 05/13/2022 05/13/2022
Loic Nguinguiri, E.I.
Corrective Action Required
05/13/2022

Re-evaluate the limits of the area to be disturbed. If above 1 acre, a SWPPP report and a MDNR permit would be required.
Corrective Action Required
05/13/2022

J-hooks are intended to trap the muddy runoff flowing from uphill. Revise the direction(s) of J-hooks accordingly.
Corrective Action Required
05/13/2022

Extend the 10-year HGL upstream, and remove the “install 8” to 10” reducer” statement shown on sheet 5 since no longer needed.
Corrective Action Required
05/13/2022

Indicate the type of Portland Cement Concrete to be used, on sheet 10.
Corrective Action Required
05/13/2022

Revise the language of the trenching and backfill detail. 12 inches (minimum) of bedding aggregate is required above the top of the pipe.
Corrective Action Required
05/13/2022

Include the GEN-3A (ADA ramp) and the type CG-1 curb and gutter construction standard details.
Corrective Action Required
05/13/2022

Draw all the existing public utility lines on the landscape sheet. Provide a 5 feet minimum setback between the existing public utility lines and the proposed overstory trees. Also, there is an existing 20 feet wide U/E along the eastern property line. Only ornamental tree varieties are allowed within public easements.
Corrective Action Required
05/13/2022

Update the Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet. Revise the (unit) price of 4” crushed stone and inlet protections. The quantity for construction entrances and inlet protections need to be revised as well. Also, replace the “connection to existing water main” item with “connection to existing storm inlet”.
Fire Review Approved with Conditions 05/13/2022 05/12/2022
Jim Eden
Code Statement
Corrective Action Required
05/06/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code. Additional fire protection systems and assemblies may be required depending on the use of the building.
Imposed Loads
Corrective Action Required
05/06/2022

IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Planning Review Corrections 05/13/2022 05/12/2022
Victoria Nelson
Corrective Action Required
05/09/2022

This was never uploaded. Trash enclosure. You mentioned the trash enclosure spec are on the architectural plans. This seems to be overlooked. Please upload plans so we can verify that they meet the UDO requirements listed under Sec. 8.180. - Architectural characteristics. G. Trash enclosure.
Corrective Action Required
05/09/2022

This was never uploaded Mechanical equipment. Please show in a dashed line where the mechanical equipment will be. If it is on the roof please show it being behind the parapet wall, or if it is on the ground please show it being screened. For more information refer to UDO Sec. 8.180. - Architectural characteristics.
Corrective Action Required
05/09/2022

This was never uploaded Exterior wall mounted lighting. Please show specifications for all exterior wall lighting. Wall packs shall comply with the design standards of UDO Section 8.260.
Building Codes Review No Comments 05/13/2022 05/11/2022
Joe Frogge
Traffic Review No Comments 05/13/2022 05/09/2022
Brad Cooley, P.E., RSPI
Traffic Review No Comments 04/21/2022 04/21/2022
Brad Cooley, P.E., RSPI
Engineering Review Corrections 04/21/2022 04/21/2022
Loic Nguinguiri, E.I.
Corrective Action Required
04/21/2022

Correct the typo in the Property Description. “…a subdivision no in the City…”
Corrective Action Required
04/21/2022

Correct the typo in General Note 1. “These provisions shall in now way absolve…”
Corrective Action Required
04/21/2022

Include a general note stating that “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a field engineering inspector prior to any land disturbance work at (816) 969-1200”.
Corrective Action Required
04/21/2022

Include a general note stating that “All construction shall follow City of Lee’s Summit’s Design and Construction manual”.
Corrective Action Required
04/21/2022

Correct the drainage easement crossing the lot. Portions were vacated and relocated in the minor plat approved by Jackson County on 11/10/2021.
Corrective Action Required
04/21/2022

Show the existing private drive, located to the NW of the current commercial entrance, directly across the east-west road.
Corrective Action Required
04/21/2022

Show (the footprint of) the existing buildings, located directly west on to the adjacent property.
Corrective Action Required
04/21/2022

On the site grading plan, include a leader or a note that will caution the contractor about the proximity of the public 8” water main running along the southern lot line.
Corrective Action Required
04/21/2022

Instead of an 8”x8”x8” tee with reducer, please consider installing a storm structure, such as a nyloplast drain basin, that will link both 8” inflow pipes (from the south and the west) to the 10” outflow pipe (to the north).
Corrective Action Required
04/21/2022

In plan view of sheet 5, add a leader that indicates the linear footage of the proposed 15” storm pipe that will run from curb inlet 1B to curb inlet 1A.
Corrective Action Required
04/21/2022

As shown in the ESC-03 detail, J-hooks are required within the ESC plan. Given the silt fence 100’ maximum runs for J-hooks, locate the needed J-hooks on sheet 8. Silt fence barrier needs to be installed along the northern lot line, as well.
Corrective Action Required
04/21/2022

ESC measure such as silt dike could be used at the southern cross-access entrance. Also, make sure that the eastern “grate inlet sediment filter” leader points at the right location.
Corrective Action Required
04/21/2022

Show on the utility plan sheet, a 2” pipe running from the reducer to the water main. Make sure to relocate the sanitary lateral information so that the elbow of the domestic water service line is visible. The size of the connecting public water main needs to be indicated, as well.
Corrective Action Required
04/21/2022

Show/label the path(s) of the existing storm drainage lines, located within the private storm easement, on the utility plan sheet.
Corrective Action Required
04/21/2022

Revise the proposed pavement cross sections to meet the minimum pavement requirements as shown in the City’s UDO section 8.620. Also, clearly show on the site plan sheet the proposed whereabout of each pavement section. Remove the pavement cross sections that are not part of the current scope of work.
Corrective Action Required
04/21/2022

Add a general note or revise the typical pavement cross-section(s) drawings to show aggregate base and subgrade of (asphalt and concrete) pavements extending 1’ beyond back of curb.
Corrective Action Required
04/21/2022

Include a pipe trenching and backfill detail. Bedding aggregate is to be placed from a level 6 inches (minimum) below the bottom of the pipe to a level 12 inches (minimum) above the top of the pipe.
Corrective Action Required
04/21/2022

Include the STM-1 (curb inlet), GEN-2 (sidewalk) and applicable ESC construction details. Standard details are accessible through the Design & Construction manual tab located on the City’s website.
Corrective Action Required
04/21/2022

Sidewalk construction must not exceed an 2% cross-slope and an 8.33% running slope. Therefore, it is recommended that the sidewalks be designed to include construction tolerances, which respectively refer to design slopes of 1.5% and 7.5%. Include a note that shares this information.
Corrective Action Required
04/21/2022

Sidewalk would have to connect, a couple of feet south, out of the existing ramp in order to match the design of the other existing ramps at the street intersection. Make sure that the resulting turning space meets ADA requirements.
Corrective Action Required
04/21/2022

Only ornamental tree varieties are allowed within public easements. A 5 to 7 feet setback is also necessary from existing public utility lines to proposed overstory trees. Review and verify that the landscaping plan sheet meets these requirements.
Corrective Action Required
04/21/2022

Please provide an Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet.
Planning Review Corrections 04/21/2022 04/21/2022
Victoria Nelson
Corrective Action Required
04/21/2022

Trash enclosure. The trash enclosure concrete pad only measure 29’. This does not meet the UDO. Please push the trash enclosure back a foot so that it meets the 30' requirement. Refer to UDO Sec 8.620-Parking lot design, C under Improvement of parking and loading areas.
Corrective Action Required
04/21/2022

Trash enclosure. You mentioned the trash enclosure spec are on the architectural plans. This seems to be overlooked. Please upload plans so we can verify that they meet the UDO requirements listed under Sec. 8.180. - Architectural characteristics. G. Trash enclosure.
Corrective Action Required
04/21/2022

Drive-through queue. Show the vehicle stacking from the drive-through pick-up window and from the order box. A minimum 4 vehicle stacking is required from the window and minimum 5 vehicle stacking from the menu board.
Corrective Action Required
04/21/2022

Parking lot light poles. The pole light fixtures exceed the maximum allowable heights under UDO Section 8.250.D.2 and 8.250.D.3.
Corrective Action Required
04/21/2022

Pavement design. The light duty asphalt and concrete pavement details do not meet the minimum standards of UDO Section 8.620.F.1.a
Corrective Action Required
04/21/2022

Landscape island. The landscape island on the east end next to the building only measures 6’,this does not meet the UDO requirements of a minimum of 9'. Please refer to Sec.8.810.B
Corrective Action Required
04/21/2022

Center Line. Please label the center line on NW Donovan Rd.
Corrective Action Required
04/21/2022

Curbing. The minimum width for all two-way drive aisles shall be 24’ of pavement width. None of the two-way aisles around the site meet the minimum width. For example, the south drive connection to the convenience store to the west has a pavement width of only 20’. Since you are proposing a CG-1 curbing, you cannot include the curb or the gutter in the drive aisle width measurements. This includes the drive-thru isle. Please refer to UDO Sec. 8.620. - Parking lot design, E. 4
Corrective Action Required
04/21/2022

Drive thru. The drive thru aisle has to measure a minimum of 10’ again not including CG-1 curb and gutter. Please refer to UDO Sec. 8.570. - Queuing requirements for drive-through facilities. C Design.
Corrective Action Required
04/21/2022

Exterior wall mounted lighting. Please show specifications for all exterior wall lighting. Wall packs shall comply with the design standards of UDO Section 8.260.
Corrective Action Required
04/21/2022

Mechanical equipment. Please show in a dashed line where the mechanical equipment will be. If it is on the roof please show it being behind the parapet wall, or if it is on the ground please show it being screened. For more information refer to UDO Sec. 8.180. - Architectural characteristics.
Corrective Action Required
04/21/2022

Accessible parking spaces sign. Please show the accessible parking spaces signs with dimensions.
Corrective Action Required
04/21/2022

Parking lot screening. The bushes you are proposing only measure to 2’. The UDO requires them to be at least 2.5’ at the time of planting, please see UDO Sec. 8.820. - Screening, parking lot. A.
Corrective Action Required
04/21/2022

Legend. Please show a legend showing all symbols that do not have a label. The legend on sheet 4 has items listed that are not on the plan. Please remove these items if you are not intending to show them.
Building Codes Review No Comments 04/21/2022 04/21/2022
Joe Frogge
Fire Review Approved with Conditions 04/21/2022 04/20/2022
Jim Eden
Code Statement
Corrective Action Required
04/22/2022

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code. Additional fire protection systems and assemblies may be required depending on the use of the building.
Imposed Loads
Corrective Action Required
04/20/2022

IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $725.00 $725.00 Paid 04/07/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.