Summary
PRCOM20234141
Building Permit - Commercial
Certificate of Occupancy
NEW COMMERCIAL
SWIG - NEW BUILDING FOR DRIVE UP AND WALK IN SERVICE FOR BEVERAGES
08/22/2023
02/02/2024
03/24/2024
12/06/2024
Locations
Contacts
OLIPHANTS HEATING & COOLING INC, Address:208 WOLLARD BLVD, Phone:(816) 470-6444  
READE ELECTRIC LLC, Address:PO BOX 1117 , Phone:(816) 889-8388  
READE ELECTRIC LLC, Address:PO BOX 1117 , Phone:(816) 889-8388  
ALWAYS PLUMBING LLC, Address:807 NASHUA ROAD, Phone:(819) 781-7749  
Olson Architectural Group, Address:1916 NW 79th Terrace, Phone:(816) 225-2660  
NICK READE, Address:1304 SILHOUETTE DR, Phone:(816) 889-8388  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 09/22/2023 10/20/2023
Mike Weisenborn
LC - General Contractor
Resolved
10/20/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent. 9/22/23 - Beggs not currently licensed with us
LC - MEP Subs
Resolved
10/03/2023

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 9/22/23 - Oliphant not currently licensed with us
Health Department Review Approved 10/16/2023
Joe Frogge
Building Plan Review Approved with Conditions 10/12/2023 10/16/2023
Joe Frogge
Misc
Corrective Action Required
10/05/2023

A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is for informational purposes. Fee will be $10,461 9/22/23 - Acknowledged in letter.
Health Dept Review
Resolved
10/16/2023

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is informational. 9/22/23 - Acknowledged in letter.
Health Dept Inspection
Corrective Action Required
10/05/2023

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is informational. 9/22/23 - Acknowledged in letter.
IMC 306.5 Equipment on roofs
Resolved
10/05/2023

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide permanent means of roof access. 9/22/23 - Not compliant as shown. Side railing must extend 30" above parapet.
Engineered truss package
Corrective Action Required
10/05/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide truss package or request deferral. 9/22/23 - Deferred per request
Licensed Contractors Approved 10/05/2023 10/10/2023
Joe Frogge
LC - General Contractor
Resolved
10/10/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent. 9/22/23 - Beggs not currently licensed with us 10/5/23 - Beggs has Class C. A or B required.
Fire Plan Review Approved 10/12/2023 10/05/2023
Joe Frogge
Fire Plan Review Approved 09/22/2023 09/25/2023
Jim Eden
Miscellaneous Correction
Resolved
09/25/2023

Update the Code Analysis. 1. The 2018 International Fire Code with local amendments is the adopted fire code for the City of Lee''s Summit. 2. This is not a fully sprinklered building.
Address numbers required
Resolved
09/25/2023

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).1 Verified at inspection.
Portable fire extinguishers - general
Resolved
09/25/2023

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Provide a minimum of one, 2A,10B,C fire extinguisher near the door. Verified at inpection.
Illumination required
Resolved
09/25/2023

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. Provide emergency illumination of the discharge area with a remote head from the interior emergency light.
Building Plan Review Rejected 09/22/2023 09/22/2023
Joe Frogge
Misc
Corrective Action Required
09/15/2023

A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is for informational purposes. Fee will be $10,461 9/22/23 - Acknowledged in letter.
Health Dept Review
Corrective Action Required
09/15/2023

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is informational. 9/22/23 - Acknowledged in letter.
Health Dept Inspection
Corrective Action Required
09/15/2023

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is informational. 9/22/23 - Acknowledged in letter.
Code analysis required
Resolved
09/22/2023

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Remove reference to fire suppression system. Re: sheet GI001, Project Information and Code Summary, Type of Construction.
ICC A117.1 604.5.1 Fixed side wall grab bars
Resolved
09/22/2023

ICC A117.1 604.5.1 Fixed side wall grab bars. Fixed side-wall grab bars shall include a horizontal bar complying with Section 604.5.1.1 and a vertical grab bar complying with Section 604.5.12. The vertical grab bar at water closets primarily for children’s use shall comply with Section 609.4.2. ICC A117.1 604.5.1.1 Horizontal grab bar. A horizontal grab bar 42 inches minimum in length shall be located 12 inches maximum from the rear wall and extending 54 inches minimum from the rear wall. ICC A117.1 604.5.1.2 Vertical grab bar. A vertical grab bar 18 inches minimum in length shall be mounted with the bottom of the bar located 39 inches minimum and 41 inches maximum above the floor, and with the center line of the bar located 39 inches minimum and 41 inches maximum from the rear wall. Action required: Provide vertical side wall grab bar. (revisions required to AE402 & GI002)
IMC 306.5 Equipment on roofs
Corrective Action Required
09/15/2023

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide permanent means of roof access. 9/22/23 - Not compliant as shown. Side railing must extend 30" above parapet.
Engineered truss package
Corrective Action Required
09/15/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide truss package or request deferral. 9/22/23 - Deferred per request
IBC 1008.3 Emergency power for illumination - at exit discharge
Resolved
09/22/2023

2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at exterior side of exit door.
Building Plan Review Rejected 09/06/2023 09/07/2023
Joe Frogge
Misc
Corrective Action Required
09/07/2023

A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process. Action required: Comment is for informational purposes. Fee will be $10,461
Health Dept Review
Corrective Action Required
09/07/2023

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 797-7162. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is informational.
Health Dept Inspection
Corrective Action Required
09/07/2023

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 797-7162. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is informational.
Code analysis required
Corrective Action Required
09/07/2023

A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed. Action required: Remove reference to fire suppression system. Re: sheet GI001, Project Information and Code Summary, Type of Construction.
ICC A117.1 604.5.1 Fixed side wall grab bars
Corrective Action Required
09/07/2023

ICC A117.1 604.5.1 Fixed side wall grab bars. Fixed side-wall grab bars shall include a horizontal bar complying with Section 604.5.1.1 and a vertical grab bar complying with Section 604.5.12. The vertical grab bar at water closets primarily for children’s use shall comply with Section 609.4.2. ICC A117.1 604.5.1.1 Horizontal grab bar. A horizontal grab bar 42 inches minimum in length shall be located 12 inches maximum from the rear wall and extending 54 inches minimum from the rear wall. ICC A117.1 604.5.1.2 Vertical grab bar. A vertical grab bar 18 inches minimum in length shall be mounted with the bottom of the bar located 39 inches minimum and 41 inches maximum above the floor, and with the center line of the bar located 39 inches minimum and 41 inches maximum from the rear wall. Action required: Provide vertical side wall grab bar. (revisions required to AE402 & GI002)
IMC 306.5 Equipment on roofs
Corrective Action Required
09/07/2023

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide permanent means of roof access.
Engineered truss package
Corrective Action Required
09/07/2023

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide truss package or request deferral.
IBC 1008.3 Emergency power for illumination - at exit discharge
Corrective Action Required
09/07/2023

2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply. 1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Aisles. 2. Corridors. 3. Exit access stairways and ramps. 1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas: 1. Interior exit access stairways and ramps. 2. Interior and exterior exit stairways and ramps. 3. Exit passageways. 4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1. 5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge. 1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas: 1. Electrical equipment rooms. 2. Fire command centers. 3. Fire pump rooms. 4. Generator rooms. 5. Public restrooms with an area greater than 300 square feet. Action required: Provide emergency lighting at exterior side of exit door.
CORRIDOR 2ND FLOOR
Corrective Action Required
09/07/2023

CORRIDOR 3RD FLOOR
Corrective Action Required
09/07/2023

CORRIDOR 4TH FLOOR
Corrective Action Required
09/07/2023

Licensed Contractors Rejected 09/06/2023 09/07/2023
Joe Frogge
LC - General Contractor
Corrective Action Required
09/07/2023

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the company name of the licensed general contractor and an email address & phone number for the on-site contact which is where inspection reports will be sent.
LC - MEP Subs
Corrective Action Required
09/07/2023

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved with Conditions 09/06/2023 09/07/2023
Jim Eden
Miscellaneous Correction
Corrective Action Required
09/07/2023

Update the Code Analysis. 1. The 2018 International Fire Code with local amendments is the adopted fire code for the City of Lee''s Summit. 2. This is not a fully sprinklered building.
Address numbers required
Corrective Action Required
09/07/2023

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm).1 Verified at inspection.
Portable fire extinguishers - general
Corrective Action Required
09/07/2023

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Provide a minimum of one, 2A,10B,C fire extinguisher near the door. Verified at inpection.
Illumination required
Corrective Action Required
09/07/2023

2018 IFC 1008.1 Illumination required. The means of egress, shall be illuminated at all times the building space served by the means of egress is occupied. Provide emergency illumination of the discharge area with a remote head from the interior emergency light.
Final Development Plan Review Approved 09/06/2023 09/06/2023
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $1,600.00 $1,600.00 Paid 02/02/2024
7232302-Commercial License Tax Fee $10,461.00 $10,461.00 Paid 02/02/2024
9110080-Not Ready Inspection Fee $75.00 $75.00 Paid 11/22/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Commercial Failed 2/5/2024 2/5/2024 02/05/2024
Misc
Corrective Action Required
02/05/2024
-Provide #4 copper CEE per plan -Provide 3" min clearance to earth throughout -Remove all loose soil and debris
Footing Inspection - Commercial Passed 2/6/2024 02/06/2024
Misc
Resolved
02/06/2024
-Provide #4 copper CEE per plan -Provide 3" min clearance to earth throughout -Remove all loose soil and debris
Underslab Plumbing Inspection - Commercial Passed 2/27/2024 2/27/2024 02/27/2024
Underground Plumbing Inspection - Commercial Passed 5/10/2024 5/10/2024 05/10/2024
Misc
Resolved
05/10/2024
-Provide exterior cleanouts within 3' of building drain -Complete Grease Interceptor
Rough Plumbing Inspection - Commercial Partial 6/24/2024 6/24/2024 06/24/2024
Misc
Informational
06/24/2024
In wall inspected
Rough Electrical Inspection - Commercial Partial 6/24/2024 6/24/2024 06/24/2024
Misc
Informational
06/24/2024
6/24/24-In wall inspected
Underground Electrical Inspection - Commercial Failed 6/25/2024 6/25/2024 06/25/2024
Misc
Corrective Action Required
06/25/2024
-Pot hole along cover underground conduit for light pole bases. Ensure all Conduit in green space is 18” below grade. -ensure conduit under driving surface to be 24” below sub grade. As discussed on site.
Rough Framing Inspection - Commercial Failed 6/25/2024 6/25/2024 06/25/2024
Misc
Corrective Action Required
06/25/2024
-6x6 posts as required by plans -sister all over notched exterior wall studs for anchor bolts -missing king studs at window opening NE exterior wall corner -install Simpson PHD2-SDS3 hold downs per plans (at each 6x6) -address top plates throughout not tied together -provide web stiffeners for double joist hangered i-joist -have engineer address hold down for iJoist
Underground Electrical Inspection - Commercial Passed 7/9/2024 7/9/2024 07/09/2024
Misc
Resolved
07/09/2024
-Pot hole along cover underground conduit for light pole bases. Ensure all Conduit in green space is 18” below grade. -ensure conduit under driving surface to be 24” below sub grade. As discussed on site.
Underground Electrical Inspection - Commercial Failed 7/30/2024 07/30/2024
Misc
Corrective Action Required
07/30/2024
-Install (6) #6 vertical bars per plan -Pier depth to be min 5'
All Rough Inspection - Commercial Failed 8/2/2024 8/2/2024 08/02/2024
Misc
Corrective Action Required
08/02/2024
-Missing (2) 6x6 posts as required by plans -Sister all over notched exterior wall studs notched greater than 25% -Install Simpson PHD2-SDS3 hold downs per plans (at each 6x6) -Provide web stiffeners for double joist hangered i-joist -Nail exterior corners min of 12" oc Provide engineered corrections for the following: -Corners not connected at top plates -Studs at load bearing exterior walls bored greater than 40% -Provide connection detail for I joists to top plate -Stud packs used in place of 6x6 posts per plan -Missing king studs at header for window at NE corner *Submit sealed, engineered letter for these corrections before scheduling further inspections **NOTED ALSO- I Joists require to be protected from fire
Piers/Caissons Inspection - Commercial Passed 8/15/2024 08/15/2024
All Rough Inspection - Commercial Not Ready 8/26/2024 08/26/2024
Misc
Corrective Action Required
08/02/2024
*INSPECTION FOR WALLS ONLY. ABOVE CEILING NOT READY AT THIS TIME -Install Simpson PHD2-SDS3 hold downs per plans (at each 6x6)-MISSING AT STUD PACK BETWEEN NORTH WINDOWS Provide engineered correction for the following -NAIL STUD PACKS USED IN PLACE OF 6x6 POSTS PER SUBMITTED DOCUMENTS -Studs at load bearing exterior walls bored greater than 40%-NO CORRECTIONS MADE -Provide connection detail for I joists to top plate-PROVIDE LADDER FOR INSPECTION 8/26/24 -Not ready fee assessed
In-wall Inspection Failed 8/26/2024 08/26/2024
Misc
Corrective Action Required
08/26/2024
See All Rough Inspection for correction Items
All Rough Inspection - Commercial Failed 9/16/2024 09/16/2024
Misc
Corrective Action Required
08/26/2024
-Provide connection detail for I joists to top plate (fasten to engineer letter specifications, provide ladder on site to check) Okay to cover walls
Miscellaneous Inspection Passed 10/3/2024 10/03/2024
All Rough Inspection - Commercial Passed 10/03/2024
Misc
Resolved
10/03/2024
Electrical Service Inspection Passed 10/30/2024 10/30/2024
Above Ceiling Inspection Passed 10/30/2024 10/30/2024 10/30/2024
Underground Electrical Inspection - Commercial Passed 11/13/2024
Misc
Resolved
11/13/2024
-Install (6) #6 vertical bars per plan -Pier depth to be min 5'
Verify Final Inspection Status - New Com Development Complete 11/20/2024
Occupancy Inspection - Planning Passed 11/22/2024 11/22/2024
Occupancy Inspection - Fire Failed 11/22/2024 11/22/2024
Occupancy Inspection - Codes Commercial Failed 11/22/2024 11/22/2024
Misc
Corrective Action Required
11/22/2024
-Complete corrections for all other departments -Pay all fees due before occupancy ($75 fee still outstanding) -Install accessible restroom signage -Provide code compliant address at building -Install expansion tank at water heater -Install grab bars at restroom per code/plans -Toilet to be max 16"-18" from side wall -Provide ASSE 1022 backflow device for carbonated beverage machines
Occupancy Inspection - Engineering Passed 11/22/2024 11/22/2024
Misc
Informational
11/22/2024
11/22/24 Friday JMJ Passed occupancy inspection. The one site concern is the no vegetation of island area which will be breaking ground in the near future.
Occupancy Inspection - Water Utilities Passed 11/26/2024 12/02/2024
Occupancy Inspection - Codes Commercial Failed 12/3/2024 12/3/2024 12/03/2024
Misc
Corrective Action Required
11/22/2024
-Provide ASSE 1022 backflow device for carbonated beverage machines
Occupancy Inspection - Fire Passed 12/3/2024 12/3/2024 12/03/2024
Occupancy Inspection - Codes Commercial Full C of O 12/6/2024 12/6/2024 12/06/2024
Misc
Resolved
12/06/2024
-Provide ASSE 1022 backflow device for carbonated beverage machines
Documents & Images
Date Uploaded File Type Document Name
08/22/2023 Application Form APPLICATION
08/23/2023 Approved Plans 230616 Swig - APPROVED SUMMIT ORCHARD LOT 4E2 CIVIL
08/23/2023 Plans 230616 Swig - FINAL Lee's Summit Permit Set
08/23/2023 Engineer Report/Study 230616 Swig - SWIG -LS - Structural Calc Packet
08/23/2023 Engineer Report/Study 230616 Swig - MECH_COMPLIANCE_2018 IECC
08/23/2023 Engineer Report/Study 230616 Swig - ELEC_COMCHECK_2018 IECC
08/23/2023 Engineer Report/Study 230616 Swig - ENVELOPE COMcheck-2018 IECC
09/07/2023 Letter DS P/R Corrections Document
09/15/2023 Letter SwigLSCodeCommentResponseLetter
09/15/2023 Letter SwigLSCodeCommentResponseELECLetter
09/15/2023 Drawing SwigLSCodeCommentResponseCoverSheet
09/15/2023 Drawing SwigLSCodeCommentResponseGI002
09/15/2023 Drawing SwigLSCodeCommentResponseAE202
09/15/2023 Drawing SwigLSCodeCommentResponseAE402
09/15/2023 Drawing SwigLSCodeCommentResponseE601
09/26/2023 Letter DS P/R Corrections Document
10/05/2023 Letter CommentResponseLetterSWIGLeesSummit100223
10/05/2023 Drawing A131ROOFPLANUpdatedforPermit
10/05/2023 Drawing AE202NorthSouthEXTERIORELEVUpdatedPermit
10/05/2023 Letter License Tax Bill
10/13/2023 Letter CommentResponseLetter101223MergedPermitDrawings
10/13/2023 Plans 231010 Swig - FINAL Lee's Summit Merged Permit Set
10/13/2023 Letter HealthDepartmentApproval101323
10/16/2023 Approved Plans approved - 231010 Swig - FINAL Lee's Summit Merged Permit Set
10/16/2023 Email Health approval clarification
02/02/2024 Receipt Receipt for transaction:2024-000562
02/02/2024 Letter DS Building Permit
02/05/2024 Letter INSPECTION SUMMARY
02/06/2024 Letter INSPECTION SUMMARY
02/27/2024 Letter INSPECTION SUMMARY
05/10/2024 Letter INSPECTION SUMMARY
06/24/2024 Letter INSPECTION SUMMARY
06/24/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
07/30/2024 Letter INSPECTION SUMMARY
08/02/2024 Letter INSPECTION SUMMARY
08/05/2024 Drawing 2024-07-31 LED Revised Light Base Detail
08/05/2024 Approved Plans Approved Light Base Detail
08/05/2024 SwIGLeesSummitINSPECTION SUMMARYStamped072624
08/15/2024 Letter INSPECTION SUMMARY
08/23/2024 Engineer Report/Study SWIGLeesSummitResponseINSPECTION SUMMARY9_0822024
08/26/2024 Letter INSPECTION SUMMARY
08/26/2024 Letter INSPECTION SUMMARY
09/05/2024 Letter jackson cty health approval
09/12/2024 Letter Response to INSPECTION SUMMARY 11 091024 with Wall Sketches
09/16/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/03/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
10/30/2024 Letter INSPECTION SUMMARY
11/13/2024 Letter INSPECTION SUMMARY
11/20/2024 3rd Party Permit/Approval Health Department Final Approval
11/22/2024 Letter INSPECTION SUMMARY
11/22/2024 Letter INSPECTION SUMMARY
11/22/2024 Letter INSPECTION SUMMARY
11/22/2024 Receipt Receipt for transaction:2024-009123
12/02/2024 3rd Party Permit/Approval Backflow Certifications
12/03/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/03/2024 Letter INSPECTION SUMMARY
12/06/2024 Letter Codes Final Certificate of Occupancy
12/06/2024 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home