Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Footing Inspection - Commercial
|
Partial
|
11/3/2023
|
11/3/2023
|
11/03/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/7/2023 (9:00)
|
11/7/2023
|
11/07/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/7/2023 (1:00)
|
11/7/2023
|
11/07/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/8/2023 (1:00)
|
11/8/2023
|
11/08/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/9/2023 (1:00)
|
11/9/2023
|
11/09/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
|
11/13/2023
|
11/13/2023
|
|
Misc
Corrective Action Required
|
Underground Electrical Inspection - Commercial
|
Partial
|
|
11/13/2023
|
11/13/2023
|
|
Misc
|
Footing Inspection - Commercial
|
Partial
|
11/15/2023 (1:00)
|
11/15/2023
|
11/15/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
|
11/17/2023
|
11/17/2023
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
11/17/2023
|
11/17/2023
|
11/17/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
11/28/2023
|
11/28/2023
|
11/28/2023
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
|
11/29/2023
|
11/29/2023
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Failed
|
|
12/1/2023
|
12/01/2023
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Partial
|
12/5/2023
|
12/5/2023
|
12/05/2023
|
|
Misc
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
12/6/2023
|
12/6/2023
|
12/06/2023
|
|
Misc
|
Footing Inspection - Commercial
|
Failed
|
12/7/2023
|
12/7/2023
|
12/07/2023
|
|
Misc
Corrective Action Required
|
Footing Inspection - Commercial
|
Partial
|
12/7/2023
|
12/7/2023
|
12/07/2023
|
|
Misc
Corrective Action Required
|
Underslab Electrical Inspection - Commercial
|
Passed
|
12/11/2023
|
12/11/2023
|
12/11/2023
|
Rough Plumbing Inspection - Commercial
|
Partial
|
3/25/2024
|
3/25/2024
|
03/25/2024
|
|
Misc
|
In-wall Inspection
|
Partial
|
3/25/2024
|
3/25/2024
|
03/25/2024
|
|
Misc
|
Rough Plumbing Inspection - Commercial
|
Partial
|
3/27/2024
|
3/27/2024
|
03/27/2024
|
|
Misc
|
In-wall Inspection
|
Partial
|
3/27/2024
|
3/27/2024
|
03/27/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
In-wall Inspection
|
Partial
|
4/3/2024
|
4/3/2024
|
04/03/2024
|
|
Misc
|
Footing Inspection - Commercial
|
Passed
|
|
|
04/03/2024
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
4/17/2024
|
04/17/2024
|
|
Misc
|
In-wall Inspection
|
Failed
|
4/17/2024
|
4/17/2024
|
04/17/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
4/26/2024
|
4/26/2024
|
04/26/2024
|
|
Misc
|
In-wall Inspection
|
Partial
|
4/26/2024
|
4/26/2024
|
04/26/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Failed
|
5/1/2024
|
5/1/2024
|
05/01/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
In-wall Inspection
|
Partial
|
5/1/2024
|
5/1/2024
|
05/01/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/6/2024
|
5/6/2024
|
05/06/2024
|
|
Misc
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
5/6/2024
|
05/06/2024
|
|
Misc
|
In-wall Inspection
|
Partial
|
5/8/2024
|
5/8/2024
|
05/08/2024
|
|
Misc
|
|
Misc
|
In-wall Inspection
|
Partial
|
5/10/2024
|
5/10/2024
|
05/10/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
In-wall Inspection
|
Partial
|
5/15/2024
|
5/15/2024
|
05/15/2024
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/15/2024
|
5/15/2024
|
05/15/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
5/16/2024
|
5/16/2024
|
05/16/2024
|
|
Misc
|
|
Misc
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
|
05/16/2024
|
In-wall Inspection
|
Partial
|
|
5/22/2024
|
05/22/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
5/31/2024
|
5/31/2024
|
05/31/2024
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/31/2024
|
5/31/2024
|
05/31/2024
|
|
Misc
|
Electrical Service Inspection
|
Partial
|
|
6/6/2024
|
06/06/2024
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
6/6/2024
|
06/06/2024
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
6/7/2024
|
6/7/2024
|
06/07/2024
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
6/11/2024
|
6/11/2024
|
06/11/2024
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
|
6/12/2024
|
06/12/2024
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
6/13/2024
|
6/13/2024
|
06/13/2024
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
|
6/14/2024
|
06/14/2024
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Partial
|
6/18/2024
|
6/18/2024
|
06/18/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
6/21/2024
|
06/21/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
|
6/25/2024
|
06/25/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
7/2/2024
|
7/2/2024
|
07/02/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
7/8/2024
|
07/08/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Foundation Inspection - Commercial
|
Passed
|
|
7/8/2024
|
07/08/2024
|
|
|
Above Ceiling Inspection
|
Partial
|
7/12/2024
|
7/12/2024
|
07/12/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
|
7/12/2024
|
07/12/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
7/22/2024
|
7/22/2024
|
07/22/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
7/25/2024
|
7/25/2024
|
07/25/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Pavement-Proof Roll
|
Passed
|
7/26/2024
|
7/26/2024
|
07/26/2024
|
|
Misc
|
Pavement-Aggregate Base
|
Passed
|
7/11/2024
|
7/11/2024
|
07/26/2024
|
|
Misc
|
Sidewalk Inspection
|
Passed
|
7/26/2024
|
7/26/2024
|
07/26/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
7/29/2024
|
07/29/2024
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
7/29/2024
|
07/29/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
7/31/2024
|
07/31/2024
|
|
Misc
|
Gas Service Inspection - Commercial
|
Passed
|
|
7/31/2024
|
07/31/2024
|
Underground Electrical Inspection - Commercial
|
Passed
|
|
|
08/02/2024
|
|
Misc
|
Rough Plumbing Inspection - Commercial
|
Passed
|
|
|
08/02/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
8/2/2024
|
08/02/2024
|
|
Misc
|
Above Ceiling Inspection
|
Partial
|
|
8/7/2024
|
08/07/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Above Ceiling Inspection
|
Partial
|
|
8/9/2024
|
08/09/2024
|
|
Misc
|
|
Misc
Corrective Action Required
|
Driveway Inspection
|
Passed
|
7/22/2024
|
7/22/2024
|
08/28/2024
|
|
Misc
|
Erosion Control Inspection Residential
|
Passed
|
8/15/2024
|
8/15/2024
|
08/28/2024
|
|
Misc
|
Pavement-Curb Construction
|
Passed
|
7/11/2024
|
7/11/2024
|
08/28/2024
|
|
Misc
|
Above Ceiling Inspection
|
Passed
|
|
9/3/2024
|
09/03/2024
|
|
Misc
|
|
Misc
|
In-wall Inspection
|
Passed
|
|
|
09/03/2024
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Passed
|
|
|
09/03/2024
|
|
Misc
|
Miscellaneous Inspection
|
Passed
|
|
10/4/2024
|
10/04/2024
|
|
Misc
|
Alarm Test
|
Passed
|
|
10/10/2024
|
10/10/2024
|
Sprinkler - Flow Test
|
Passed
|
|
10/10/2024
|
10/11/2024
|
Pavement-Surface
|
Passed
|
10/15/2024
|
10/15/2024
|
10/15/2024
|
|
Misc
|
Erosion Control Inspection Residential
|
Passed
|
|
|
10/18/2024
|
|
Misc
|
Occupancy Inspection - Planning
|
Temporary C of O
|
10/18/2024
|
10/18/2024
|
10/18/2024
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Passed
|
6/12/2024
|
|
10/18/2024
|
|
Misc
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
10/18/2024
|
10/18/2024
|
10/18/2024
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Ready for Temp CO
|
10/18/2024
|
10/18/2024
|
10/18/2024
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Water Utilities
|
Passed
|
10/18/2024
|
10/18/2024
|
10/18/2024
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
|
10/18/2024
|
10/18/2024
|
|
Misc
Corrective Action Required
|
|
Miscellaneous Correction
Corrective Action Required
|
Occupancy Inspection - Fire
|
Temporary C of O
|
10/18/2024
|
10/18/2024
|
10/18/2024
|
Record Drawing Review
|
Passed
|
|
10/23/2024
|
10/23/2024
|
|
Misc
|
Occupancy Inspection - Codes Commercial
|
Ready for Temp CO
|
|
11/14/2024
|
11/14/2024
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Planning
|
Passed
|
|
|
11/22/2024
|
|
Misc
|
Occupancy Inspection - Codes Commercial
|
Temporary C of O
|
|
12/3/2024
|
12/03/2024
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Fire
|
Passed
|
|
12/3/2024
|
12/03/2024
|
Occupancy Inspection - Engineering
|
Passed
|
|
|
12/04/2024
|
|
Misc
|
|
Miscellaneous Correction
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
|
12/04/2024
|
|
Misc
|