Permit Application Status

PRCOM20210599


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20210599
Building Permit - Commercial
Certificate of Occupancy
CITY OF LEES SUMMIT
NEW COMMERCIAL
NEW BUILDING FOR A RESTAURANT WITH DRIVE-THRU AND PATIO SEATING
02/12/2021
04/05/2021
08/17/2021
12/16/2021
Locations
Contacts
JWM CONTRACTING LLC, Address:420 NE BROCKTON DR, Phone:(913) 530-4205  
CHIEF HEATING & COOLING INC, Address:920 NW TECHNOLOGY DR, Phone:(816) 246-4646  
PRODIGY PLUMBING & MECHANICAL INC, Address:8402 WESTRIDGE RD, Phone:(816) 984-9292  
Bergmeyer Associates, Address:51 Sleeper Street, Suite 600, Phone:(781) 632-5264  
CITY OF LEES SUMMIT, Address:220 SE GREEN ST  
bill@spiegelglass-gc.com, Address:bill@spiegelglass-gc.com  
STACO ELECTRIC CONSTRUCTION COMPANY INC, Address:11030 HICKMAN MILLS DR, Phone:(816) 765-7112  
LARRY BAIR EXCAVATING, Address:2785 W 247TH ST, Phone:(913) 369-6504  
FACILITY SOLUTIONS GROUP INC, Address:17880 W 99TH ST, Phone:(913) 422-8400  
SPIEGELGLASS CONSTRUCTION CO INC, Address:18 WORTHINGTON ACCESS DR, Phone:(314) 569-2300  
Reviews
Review Type Outcome Est. Completion Date Completed
Building Plan Review Approved with Conditions 08/26/2021 08/23/2021
Joe Frogge
Health Dept Inspection
Corrective Action Required
08/19/2021

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes. 3/10/21 - acknowledged in letter
Fire Plan Review Approved with Conditions 08/26/2021 08/20/2021
Michael Weissenbach
Posting of occupant load
Corrective Action Required
08/19/2021

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. (Verified At Inspection) Post occupant load signs in the interior and exterior. Inside 125 Outside 70
Construction documents for fire alarm systems
Corrective Action Required
08/19/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
08/19/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
08/19/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox box at knoxbox.com. Placement to be made by the FDC. 3/10/21 (Verified At Inspection)
Construction documents - Fire protection systems
Corrective Action Required
08/19/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
08/19/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Sprinkler Plan Review Released for Construction 05/27/2021 05/27/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
05/27/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule a hydrostatic and water flow test.
Misc
Corrective Action Required
05/27/2021

(Informational Purposes) Relocate FDC to the North end of the building. FDC to be 100' from hydrant.
Alarm Plan Review Released for Construction 05/12/2021 05/12/2021
Michael Weissenbach
Installation acceptance testing
Corrective Action Required
05/12/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 for testing. Locate outside horn/strobe by FDC
Final Development Plan Review Approved 04/05/2021
Joe Frogge
Building Plan Review Approved with Conditions 03/17/2021 04/04/2021
Joe Frogge
Final Development Plan
Resolved
03/17/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 3/10/21 - approved but waiting on fees to be paid
Misc
Resolved
04/04/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes. 3/10/21 - acknowledged in letter
Health Dept Review
Resolved
03/23/2021

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 847-7070. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is for informational purposes. 3/10/21 - acknowledged in letter
Health Dept Inspection
Corrective Action Required
03/10/2021

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes. 3/10/21 - acknowledged in letter
ICC A117.1 604.5.1 Fixed side wall grab bars
Resolved
03/10/2021

ICC A117.1 604.5.1 Fixed side wall grab bars. Fixed side-wall grab bars shall include a horizontal bar complying with Section 604.5.1.1 and a vertical grab bar complying with Section 604.5.12. The vertical grab bar at water closets primarily for children’s use shall comply with Section 609.4.2. ICC A117.1 604.5.1.1 Horizontal grab bar. A horizontal grab bar 42 inches minimum in length shall be located 12 inches maximum from the rear wall and extending 54 inches minimum from the rear wall. ICC A117.1 604.5.1.2 Vertical grab bar. A vertical grab bar 18 inches minimum in length shall be mounted with the bottom of the bar located 39 inches minimum and 41 inches maximum above the floor, and with the center line of the bar located 39 inches minimum and 41 inches maximum from the rear wall. Action required: Update plans to show installation of required vertical side grab bars.
IPC 403.1 Minimum number of fixtures
Resolved
03/10/2021

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Unable to find mop/utility sink on plans. Clarify.
Licensed Contractors Approved 03/17/2021 04/04/2021
Joe Frogge
LC - General Contractor
Resolved
04/04/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact. 3/10/21 - acknowledged in letter
LC - MEP Subs
Resolved
04/04/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 3/10/21 - acknowledged in letter
Health Department Review Approved 03/23/2021
Joe Frogge
Fire Plan Review Approved with Conditions 03/17/2021 03/10/2021
Michael Weissenbach
Posting of occupant load
Corrective Action Required
03/10/2021

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. (Verified At Inspection) Post occupant load signs in the interior and exterior. Inside 125 Outside 70
Construction documents for fire alarm systems
Corrective Action Required
03/10/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
03/10/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
03/10/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox box at knoxbox.com. Placement to be made by the FDC. 3/10/21 (Verified At Inspection)
Construction documents - Fire protection systems
Corrective Action Required
03/10/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
03/10/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Miscellaneous Correction
Resolved
03/10/2021

(Action Required) Relocate the FDC outside of the patio area.
Miscellaneous Correction
Resolved
03/10/2021

2018 IFC 5307.3 Insulated liquid carbon dioxide systems with more than 100 pounds of carbon dioxide used in beverage dispensing applications shall comply witn section 5307.3.1 (Action Required) Provide specs on tanks. More than 100 pounds will require ventilation or gas detection.
Panic and fire exit hardware
Resolved
03/10/2021

2018 IFC 1010.1.10 Panic and fire exit hardware. Doors serving a Group H occupancy and doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock unless it is a panic hardware or fire exit hardware. (Action Required) Provide panic hardware on the gates leading out of the patio area.
Building Plan Review Rejected 03/01/2021 02/18/2021
Joe Frogge
Final Development Plan
Corrective Action Required
02/18/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Misc
Corrective Action Required
02/18/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
Health Dept Review
Corrective Action Required
02/18/2021

For the Health Department review contact Deb Sees with the Jackson County Public Works Department, Environmental Services Division, at (816) 847-7070. Health Department approval is required prior to receiving any type of building permit from the City of Lee's Summit. Action required: Comment is for informational purposes.
Health Dept Inspection
Corrective Action Required
02/18/2021

For the Health Department inspection contact Deb Sees with the Jackson County Public Works Department, Environmental Health Division at (816) 847-7070. Health Department approval is required prior to receiving any type of Occupancy from the City of Lee's Summit. Action required: Comment is for informational purposes.
ICC A117.1 604.5.1 Fixed side wall grab bars
Corrective Action Required
02/18/2021

ICC A117.1 604.5.1 Fixed side wall grab bars. Fixed side-wall grab bars shall include a horizontal bar complying with Section 604.5.1.1 and a vertical grab bar complying with Section 604.5.12. The vertical grab bar at water closets primarily for children’s use shall comply with Section 609.4.2. ICC A117.1 604.5.1.1 Horizontal grab bar. A horizontal grab bar 42 inches minimum in length shall be located 12 inches maximum from the rear wall and extending 54 inches minimum from the rear wall. ICC A117.1 604.5.1.2 Vertical grab bar. A vertical grab bar 18 inches minimum in length shall be mounted with the bottom of the bar located 39 inches minimum and 41 inches maximum above the floor, and with the center line of the bar located 39 inches minimum and 41 inches maximum from the rear wall. Action required: Update plans to show installation of required vertical side grab bars.
IPC 403.1 Minimum number of fixtures
Corrective Action Required
02/18/2021

2018 IPC 403.1 Minimum number of fixtures. Plumbing fixtures shall be provided in the minimum number shown in Table 403.1, based on the actual use of the building or space. Uses not shown in Table 403.1 shall be considered individually by the code official. The number of occupants shall be determined by the International Building Code. Action required: Unable to find mop/utility sink on plans. Clarify.
Licensed Contractors Rejected 03/01/2021 02/18/2021
Joe Frogge
LC - General Contractor
Corrective Action Required
02/18/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact.
LC - MEP Subs
Corrective Action Required
02/18/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Rejected 03/01/2021 02/17/2021
Michael Weissenbach
Posting of occupant load
Corrective Action Required
02/17/2021

2018 IFC 1004.3- Posting of occupant load. Every room or space that is an assembly occupancy shall have the occupant load of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space. Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or authorized agent. (Verified At Inspection) Post occupant load signs in the interior and exterior. Inside 125 Outside 70
Construction documents for fire alarm systems
Corrective Action Required
02/17/2021

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. (Action Required) Provide PE stamped electronic shop drawings for the fire alarm system to mike.weissenbach@cityofls.net
Address numbers required
Corrective Action Required
02/17/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Knox box required
Corrective Action Required
02/17/2021

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. (Action Required) Order a Knox box at knoxbox.com. Placement to be made by the FDC.
Construction documents - Fire protection systems
Corrective Action Required
02/17/2021

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. (Action Required) Provide PE stamped electronic shop drawings for the fire sprinkler system to mike.weissenbach@cityofls.net
Installation acceptance testing
Corrective Action Required
02/17/2021

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. (Informational Purposes) Call (816)969-1300 to schedule testing.
Miscellaneous Correction
Corrective Action Required
02/17/2021

(Action Required) Relocate the FDC outside of the patio area.
Miscellaneous Correction
Corrective Action Required
02/17/2021

2018 IFC 5307.3 Insulated liquid carbon dioxide systems with more than 100 pounds of carbon dioxide used in beverage dispensing applications shall comply witn section 5307.3.1 (Action Required) Provide specs on tanks. More than 100 pounds will require ventilation or gas detection.
Panic and fire exit hardware
Corrective Action Required
02/17/2021

2018 IFC 1010.1.10 Panic and fire exit hardware. Doors serving a Group H occupancy and doors serving rooms or spaces with an occupant load of 50 or more in a Group A or E occupancy shall not be provided with a latch or lock unless it is a panic hardware or fire exit hardware. (Action Required) Provide panic hardware on the gates leading out of the patio area.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $5,600.00 $5,600.00 Paid 04/05/2021
8331507-Sewer Connection Fee $510.00 $510.00 Paid 03/15/2021
7232302-Commercial License Tax Fee $41,175.00 $41,175.00 Paid 11/29/2021
91100C8-Sanitary Sewer Insp Fees $101.25 $101.25 Paid 03/15/2021
91100C9-Water Insp Fee $1,092.00 $1,092.00 Paid 03/15/2021
9110081-Paved Surface Inspection Fee $6,422.40 $6,422.40 Paid 03/15/2021
9110071-Site Grading Fee $2,550.00 $2,550.00 Paid 03/15/2021
9110072-Water Test Fee $200.00 $200.00 Paid 03/15/2021
8331401-Water Tap Fee $21,486.00 $21,486.00 Paid 03/15/2021
8350015-Water Meter Fee $3,456.47 $3,456.47 Paid 03/15/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 03/15/2021
9110079-After Hours Inspection (Building Codes)(Per Hour) $50.00 $50.00 Paid 11/29/2021
91100C9-Water Insp Fee $195.00 $195.00 Paid 04/22/2021
$1,287.00
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 11/29/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Partial 4/5/2021 4/5/2021 04/05/2021
Misc
Informational
04/02/2021
4-2-21 11:06am On 4-1-21 I met with Nik Torres and Jim Kiffer on site to go over the project. I informed them they needed to get erosion controls in place before grading takes place. They agreed and had erosion controls scheduled. At this time there is no erosion controls in place and they are grading. I spoke again with Nik Torres and he was going to make calls to get the erosion controls in place. If erosion controls are not put in place per plan by the end of today a stop work order will be issued and no further work will be allowed. 11:17am Advanced Erosion Solutions is now on site. 4-5-21 8:09am Erosion controls are in place and working at this time.
Pavement-Proof Roll Partial 04/05/2021
Misc
Informational
04/05/2021
4-5-21 11:55am The developer wants a sub-grade proof roll. There is a third party inspector on site from CFS. 12:35pm Larry Blair is doing the dirt work on site. The proof roll failed in five spots. Corrections will need to be made. CFS will be doing a report.
Site Visit Partial 4/6/2021 04/06/2021
Misc
Informational
04/06/2021
5-6-21 9:24am I checked the geogrid on site and it is on the approved products list.
Pavement-Proof Roll Partial 04/06/2021
Misc
Informational
04/06/2021
4-6-21 9:51am Larry Blair Excavating has made repairs and we are doing another sub-grade proof roll. 10:38am Mike with CFS was on site for the proof roll and he has passed it. LBE will start laying out geogrid and putting down rock. I will collect rock tickets from Nick.
Site Visit Partial 04/06/2021
Misc
Informational
04/06/2021
5-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot.
Site Visit Partial 04/07/2021
Misc
Informational
04/06/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time.
Site Visit Partial 4/9/2021 04/09/2021
Misc
Informational
04/07/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock.
Fire Line Construction Inspection Partial 04/13/2021
Misc
Informational
04/13/2021
Contractor installed fire lane up to the hydrant installation. Contractor will pour backing blocks for fittings tomorrow. I informed contractor that gravel was to be installed under water pipe line as-per Lee’s Summit specifications. Extra fittings will be add near tie in location do to the actual location and size of water line relative to where Backflow valves and vault is located. Contractor will take pictures of bends and fittings that are add.
Fire Line Construction Inspection Partial 4/14/2021 4/14/2021 04/14/2021
Misc
Informational
04/13/2021
Contractor installed fire lane up to the hydrant installation. Contractor will pour backing blocks for fittings tomorrow. I informed contractor that gravel was to be installed under water pipe line as-per Lee’s Summit specifications. Extra fittings will be add near tie in location do to the actual location and size of water line relative to where Backflow valves and vault is located. Contractor will take pictures of bends and fittings that are add. 4-14-21 8:56am I spoke with the Forman with Blair on site. They have the waterline ran to the building and will pour thrust blocks at approximately 11:30am. They have rock under the water line and will cover per spec. 10:32am Bair is setting the vault for the backflow preventer. They are backfilling the waterline.
Fire Line Construction Inspection Partial 4/15/2021 04/15/2021
Misc
Informational
04/14/2021
Contractor installed fire lane up to the hydrant installation. Contractor will pour backing blocks for fittings tomorrow. I informed contractor that gravel was to be installed under water pipe line as-per Lee’s Summit specifications. Extra fittings will be add near tie in location do to the actual location and size of water line relative to where Backflow valves and vault is located. Contractor will take pictures of bends and fittings that are add. 4-14-21 8:56am I spoke with the Forman with Blair on site. They have the waterline ran to the building and will pour thrust blocks at approximately 11:30am. They have rock under the water line and will cover per spec. 10:32am Bair is setting the vault for the backflow preventer. They are backfilling the waterline. 4-15-21 8:55am Bair Excavating are hooking up the fire line inside the vault. They will be pouring kickers at 5pm. 3:30pm They have all of the fire line connected. They will need to put rock under approximately 10’ of the waterline coming out of the south side of the vault.
Fire Line Construction Inspection Partial 04/15/2021
Misc
Informational
04/15/2021
Contractor installed fire lane up to the hydrant installation. Contractor will pour backing blocks for fittings tomorrow. I informed contractor that gravel was to be installed under water pipe line as-per Lee’s Summit specifications. Extra fittings will be add near tie in location do to the actual location and size of water line relative to where Backflow valves and vault is located. Contractor will take pictures of bends and fittings that are add. 4-14-21 8:56am I spoke with the Forman with Blair on site. They have the waterline ran to the building and will pour thrust blocks at approximately 11:30am. They have rock under the water line and will cover per spec. 10:32am Bair is setting the vault for the backflow preventer. They are backfilling the waterline. 4-15-21 8:55am Bair Excavating are hooking up the fire line inside the vault. They will be pouring kickers at 5pm. 3:30pm They have all of the fire line connected. They will need to put rock under approximately 10’ of the waterline coming out of the south side of the vault. 5:23pm No crews are on site. I looked at the collars and kickers before they backfilled. Rain is expected for the overnight and Friday the 16th.
Sanitary Sewer Construction Inspection Partial 4/16/2021 4/16/2021 04/16/2021
Misc
Informational
04/16/2021
4-16-21 8:26am Bair Excavating has installed the sanitary service line from the grease interceptor to the building. They have tracer wire and plenty of rock. They are now digging out for the service line coming out of the interceptor to the main. 11:02am They have approximately 25’ of sanitary service line out of the interceptor.
Pavement-Stabilized Subgrade Passed 04/19/2021
Misc
Corrective Action Required
04/19/2021
CFS was on site for a sub-grade proof roll. Mike with CFS passed it at that time.
Site Visit Partial 4/19/2021 04/19/2021
Misc
Informational
04/09/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary.
Sanitary Sewer Construction Inspection Partial 4/19/2021 4/19/2021 04/19/2021
Misc
Informational
04/16/2021
4-16-21 8:26am Bair Excavating has installed the sanitary service line from the grease interceptor to the building. They have tracer wire and plenty of rock. They are now digging out for the service line coming out of the interceptor to the main. 11:02am They have approximately 25’ of sanitary service line out of the interceptor. 4-19-21 10:31am They have ran the second service line up to the building and will be cutting in the wye to the main.
Sanitary Sewer Construction Inspection Partial 04/19/2021
Misc
Informational
04/19/2021
4-16-21 8:26am Bair Excavating has installed the sanitary service line from the grease interceptor to the building. They have tracer wire and plenty of rock. They are now digging out for the service line coming out of the interceptor to the main. 11:02am They have approximately 25’ of sanitary service line out of the interceptor. 4-19-21 10:31am They have ran the second service line up to the building and will be cutting in the wye to the main. 3:30pm they ran tracer wire for there service line.
Sanitary Sewer Construction Inspection Partial 4/21/2021 4/21/2021 04/21/2021
Misc
Informational
04/19/2021
4-16-21 8:26am Bair Excavating has installed the sanitary service line from the grease interceptor to the building. They have tracer wire and plenty of rock. They are now digging out for the service line coming out of the interceptor to the main. 11:02am They have approximately 25’ of sanitary service line out of the interceptor. 4-19-21 10:31am They have ran the second service line up to the building and will be cutting in the wye to the main. 3:30pm they ran tracer wire for there service line. 4-21-21 Bair is on site waiting on materials. 11:16am They have cut in the wye on the 8” main and are placing the tracer wire and anode. They will be backfilling.
Site Visit Partial 4/22/2021 4/22/2021 04/22/2021
Misc
Informational
04/19/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line.
Underslab Plumbing Inspection - Commercial Partial 4/23/2021 4/22/2021 04/22/2021
THE FOLLOWING AREAS ARE APPROVED
Informational
04/22/2021
- GREASE INTERCEPTOR -
Water Service Inspection Partial 4/23/2021 4/23/2021 04/23/2021
Misc
Informational
04/23/2021
4-23-21 9:30am They have tapped the water line for the irrigation and installed the meter pit. They will be tapping for the fountain next week.
Site Visit Partial 4/26/2021 04/26/2021
Misc
Informational
04/22/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today.
Fire Line Construction Inspection Partial 4/26/2021 4/26/2021 04/26/2021
Misc
Informational
04/15/2021
Contractor installed fire lane up to the hydrant installation. Contractor will pour backing blocks for fittings tomorrow. I informed contractor that gravel was to be installed under water pipe line as-per Lee’s Summit specifications. Extra fittings will be add near tie in location do to the actual location and size of water line relative to where Backflow valves and vault is located. Contractor will take pictures of bends and fittings that are add. 4-14-21 8:56am I spoke with the Forman with Blair on site. They have the waterline ran to the building and will pour thrust blocks at approximately 11:30am. They have rock under the water line and will cover per spec. 10:32am Bair is setting the vault for the backflow preventer. They are backfilling the waterline. 4-15-21 8:55am Bair Excavating are hooking up the fire line inside the vault. They will be pouring kickers at 5pm. 3:30pm They have all of the fire line connected. They will need to put rock under approximately 10’ of the waterline coming out of the south side of the vault. 5:23pm No crews are on site. I looked at the collars and kickers before they backfilled. Rain is expected for the overnight and Friday the 16th. 4-26-21 1:06pm They have poured two kickers for the fire line. They will backfill later today.
Site Visit Partial 4/27/2021 04/27/2021
Misc
Informational
04/26/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit.
Roof Drain Partial 8/20/2021 04/27/2021
Misc
Informational
04/27/2021
4-27-21 2:40pm Bair has ran two storm drain lines up to the pad site. 60’ to the north and 18’ to the south west.
Fire Line - Hydrostatic Test Passed 4/28/2021 4/28/2021 04/28/2021
Misc
Informational
04/28/2021
4-28-21 8:52am Bair is getting set up for the hydrostatic test for the fire line. 9:31am we have started the test. 11:30am The pressure test held at 200 for two hours. It has passed.
Fire Line Construction Inspection Passed 04/29/2021
Misc
Informational
04/26/2021
Contractor installed fire lane up to the hydrant installation. Contractor will pour backing blocks for fittings tomorrow. I informed contractor that gravel was to be installed under water pipe line as-per Lee’s Summit specifications. Extra fittings will be add near tie in location do to the actual location and size of water line relative to where Backflow valves and vault is located. Contractor will take pictures of bends and fittings that are add. 4-14-21 8:56am I spoke with the Forman with Blair on site. They have the waterline ran to the building and will pour thrust blocks at approximately 11:30am. They have rock under the water line and will cover per spec. 10:32am Bair is setting the vault for the backflow preventer. They are backfilling the waterline. 4-15-21 8:55am Bair Excavating are hooking up the fire line inside the vault. They will be pouring kickers at 5pm. 3:30pm They have all of the fire line connected. They will need to put rock under approximately 10’ of the waterline coming out of the south side of the vault. 5:23pm No crews are on site. I looked at the collars and kickers before they backfilled. Rain is expected for the overnight and Friday the 16th. 4-26-21 1:06pm They have poured two kickers for the fire line. They will backfill later today.
Water Line - Construction Inspection Partial 04/29/2021
Misc
Informational
04/29/2021
4-29-21 9:54am The water department has made the tap for the fountain. Bair will start backfilling.
Site Visit Partial 4/30/2021 4/30/2021 04/30/2021
Misc
Informational
04/27/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain.
Underground Electrical Inspection - Commercial Partial 4/30/2021 4/30/2021 04/30/2021
Misc
Informational
04/30/2021
UNDERGROUND CONDUIT (11) LIGHT POLE BASES
Site Visit Partial 5/3/2021 05/03/2021
Misc
Informational
04/30/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade.
Site Visit Partial 5/4/2021 05/04/2021
Misc
Informational
05/03/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time.
Piers/Caissons Inspection - Commercial Partial 5/5/2021 (11:00) 5/5/2021 05/05/2021
Misc
Informational
05/05/2021
(7) LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR EAST SIDE OF BLDG
Piers/Caissons Inspection - Commercial Partial 5/13/2021 5/13/2021 05/13/2021
Misc
Informational
05/13/2021
(7) & (4)LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR.
Pavement-Proof Roll Partial 5/14/2021 5/14/2021 05/14/2021
Misc
Informational
04/06/2021
4-5-21 11:55am The developer wants a sub-grade proof roll. There is a third party inspector on site from CFS. 12:35pm Larry Blair is doing the dirt work on site. The proof roll failed in five spots. Corrections will need to be made. CFS will be doing a report. 5-14-21 8:53am Bair is on site to do a sub grade proof roll. Mike with CFS will be inspecting the proof roll. I will witness. 9:43am Mike has passed the sub grade proof roll. The electricians did not backfill properly or replace the geo grid correctly. Bair has dug out the trenches will back backfill and filled back in with AB3. They have been told to replace the geo grid with a 1 foot overlay on each side on all geo grid that has been cut or damaged. The electricians went under the driving lane for the drive through, it will need repaired as well.
Site Visit Partial 5/14/2021 05/14/2021
Misc
Informational
05/04/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 10:21am Bair is on site laying out geo-grid and base rock. They have to repair all of the geo-grid and backfill done by the electricians.
Site Visit Partial 5/14/2021 5/14/2021 05/14/2021
Misc
Informational
05/14/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now.
Site Visit Partial 5/27/2021 5/27/2021 05/28/2021
Misc
Informational
05/14/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 10:21am Bair is on site laying out geo-grid and base rock. They have to repair all of the geo-grid and backfill done by the electricians. 5-28-21 8:45am Light rain. There is no work taking place on site. The erosion controls are working.
Site Visit Partial 6/1/2021 06/01/2021
Misc
Informational
05/28/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time.
Site Visit Partial 6/2/2021 6/2/2021 06/02/2021
Misc
Informational
06/01/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines.
Curb - Proof Roll Failed 6/2/2021 6/2/2021 06/02/2021
Misc
Informational
06/02/2021
6-2-21 3:47pm Over 90 percent of the proof roll failed. They will be making corrections.
Site Visit Partial 6/3/2021 06/03/2021
Misc
Informational
06/02/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Construction is on site working on the base rock to repair for a curb line proof roll.
Site Visit Partial 6/4/2021 06/04/2021
Misc
Informational
06/03/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock.
Curb - Proof Roll Failed 06/04/2021
Misc
Informational
06/02/2021
6-2-21 3:47pm Over 90 percent of the proof roll failed. They will be making corrections. 6-4-21 11:07am The proof roll failed. Approximately 95 percent did not pass. One island in the center of the north side of the site is good. Corrections will need to be made before the next proof roll.
Curb - Proof Roll Partial 6/7/2021 6/7/2021 06/07/2021
Misc
Informational
06/04/2021
6-2-21 3:47pm Over 90 percent of the proof roll failed. They will be making corrections. 6-4-21 11:07am The proof roll failed. Approximately 95 percent did not pass. One island in the center of the north side of the site is good. Corrections will need to be made before the next proof roll. 6-7-21 2:58pm The Contractor wanted to proof roll at 3:30pm. they have now canceled.
Curb - Proof Roll Partial 6/8/2021 06/08/2021
Misc
Informational
06/07/2021
6-2-21 3:47pm Over 90 percent of the proof roll failed. They will be making corrections. 6-4-21 11:07am The proof roll failed. Approximately 95 percent did not pass. One island in the center of the north side of the site is good. Corrections will need to be made before the next proof roll. 6-7-21 2:58pm The Contractor wanted to proof roll at 3:30pm. they have now canceled. 6-8-21 8:47am The proof roll passed with corrections to be made in a few areas on the site. We will proof roll again at 3:30pm today.
Curb - Proof Roll Partial 6/8/2021 6/8/2021 06/08/2021
Misc
Informational
06/08/2021
6-2-21 3:47pm Over 90 percent of the proof roll failed. They will be making corrections. 6-4-21 11:07am The proof roll failed. Approximately 95 percent did not pass. One island in the center of the north side of the site is good. Corrections will need to be made before the next proof roll. 6-7-21 2:58pm The Contractor wanted to proof roll at 3:30pm. they have now canceled. 6-8-21 8:47am The proof roll passed with corrections to be made in a few areas on the site. We will proof roll again at 3:30pm today. 3:43pm Bair Contractors has not made the completed the corrections. We will try to proof roll at a later date.
Site Visit Partial 6/9/2021 06/09/2021
Misc
Informational
06/04/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today.
Curb - Proof Roll Passed 6/9/2021 06/09/2021
Misc
Informational
06/08/2021
6-2-21 3:47pm Over 90 percent of the proof roll failed. They will be making corrections. 6-4-21 11:07am The proof roll failed. Approximately 95 percent did not pass. One island in the center of the north side of the site is good. Corrections will need to be made before the next proof roll. 6-7-21 2:58pm The Contractor wanted to proof roll at 3:30pm. they have now canceled. 6-8-21 8:47am The proof roll passed with corrections to be made in a few areas on the site. We will proof roll again at 3:30pm today. 3:43pm Bair Contractors has not made the completed the corrections. We will try to proof roll at a later date. 6-9-21 10:44am We are starting the proof roll. The proof roll passed. They will start pouring curb tomorrow the 10th.
Footing Inspection - Commercial Partial 6/10/2021 (10:00) 6/10/2021 06/10/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/10/2021
- TRASH ENCLOSURE -
Commercial Curb Inspection Partial 6/11/2021 6/11/2021 06/11/2021
Misc
Informational
06/11/2021
6-11-21 8:28am Bedrock Concrete are pouring curb. They did not cure the back side of the curb and only had a light coat on the front. I had them re-cure front and back. 10:19am The are on the south side of the site and finishing up with curb. They will setting up the hand pours on Monday the 14th.
Site Visit Partial 6/14/2021 06/14/2021
Misc
Informational
06/09/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time.
Site Visit Partial 06/14/2021
Misc
Informational
06/14/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit.
Commercial Curb Inspection Partial 6/15/2021 6/15/2021 06/15/2021
Misc
Informational
06/11/2021
6-11-21 8:28am Bedrock Concrete are pouring curb. They did not cure the back side of the curb and only had a light coat on the front. I had them re-cure front and back. 10:19am The are on the south side of the site and finishing up with curb. They will setting up the hand pours on Monday the 14th. 6-15-21 10:06am They are setting up hand pours. They will be pouring on Wednesday.
Curb - Proof Roll Partial 6/15/2021 6/15/2021 06/15/2021
Misc
Informational
06/15/2021
6-15-21 11:28am The proof roll passed with two areas they will put flowable fill. They will be good to pour curb.
Commercial Curb Inspection Partial 6/16/2021 6/16/2021 06/16/2021
Misc
Informational
06/15/2021
6-11-21 8:28am Bedrock Concrete are pouring curb. They did not cure the back side of the curb and only had a light coat on the front. I had them re-cure front and back. 10:19am The are on the south side of the site and finishing up with curb. They will setting up the hand pours on Monday the 14th. 6-15-21 10:06am They are setting up hand pours. They will be pouring on Wednesday. 6-16-21 9:07 82 degrees. Bedrock are pouring curb on the north side of the site and the west side. There are three broken panels that will need replaced. One on the east side of the site and two on the south side of the site in the drive through lane. They are pulling forms on the fresh pour. I informed them to cure all exposed concrete.
Curb - Proof Roll Passed 06/17/2021
Misc
Informational
06/15/2021
6-15-21 11:28am The proof roll passed with two areas they will put flowable fill. They will be good to pour curb.
Pavement-Proof Roll Passed 6/17/2021 6/17/2021 06/17/2021
Misc
Informational
06/17/2021
6-17-21 9:45am 81 degrees and full sun. The parking lot has passed the proof roll with three small corrections to be made. They will make the corrections with flowable fill. Two of the corrections are in the drive through lane and the third is between the storm inlets on the NW side of the site. They will be laying asphalt tomorrow 6-18-21.
Pavement-Curb Construction Passed 06/18/2021
Misc
Informational
06/18/2021
6-19-21 6:13am All of the curb is installed.
Pavement-Aggregate Base Passed 06/18/2021
Misc
Informational
06/18/2021
6-19-21 The geo-grid has been placed and the base installed with proof rolls passed.
Pavement-Surface Partial 6/18/2021 6/18/2021 06/18/2021
Misc
Informational
06/18/2021
6-19-21 6:25am 78 degrees and full sun. Updike Paving are on site setting up to lay base asphalt. They are blowing off the curb. 7:30am they have started laying asphalt. Temperatures out of the first truck are 250°. They have not tackled curb and they left a 4 inch gap between the asphalt and the curb. They are using a four tire roller. CFS is on site for testing. The second trucks load Temp is 290°. It is 290 degrees behind the paver. 12:51pm They have a second pass on the drive thru lane then the west side parking spots. 2:45pm They are pulling off the header. They are finished with base and will lay surface Sat. 6-19-21.
Pavement-Surface Passed 6/19/2021 6/19/2021 06/19/2021
Misc
Informational
06/18/2021
6-18-21 6:25am 78 degrees and full sun. Updike Paving are on site setting up to lay base asphalt. They are blowing off the curb. 7:30am they have started laying asphalt. Temperatures out of the first truck are 250°. They have not tackled curb and they left a 4 inch gap between the asphalt and the curb. They are using a four tire roller. CFS is on site for testing. The second trucks load Temp is 290°. It is 290 degrees behind the paver. 12:51pm They have a second pass on the drive thru lane then the west side parking spots. 2:45pm They are pulling off the header. They are finished with base and will lay surface Sat. 6-19-21. 6-19-21 Saturday 6:45am 80 degrees, Contractor was setting up truck to tack the base asphalt. Surface was tack contractor started asphalt at approximately 7:30am at the drive thru a Wedge lift was used approximately 3” to 3”.5 inch. Temperature for the first truck was 280 degrees and the second truck temp reading was 320 degrees for asphalt pile. Third party inspection CFS said all the density were in compliance.
Site Visit Partial 06/21/2021
Misc
Informational
06/14/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor.
Pavement-Surface Failed 06/21/2021
Misc
Informational
06/21/2021
6-21-21 3:08pm There is a 15x14 section of asphalt holding water on the north side of the building pad. See pics. There are ruts along the east side of the lot and the asphalt is higher than the curb. The inside radius of the drive thru lane is not rolled well along with other areas. The asphalt running along the west curb line is not rolled in completely and is high. The overall finish is bad. This is a fail. The manhole was hit on the NW end and has been repaired. They will go back with concrete to the top. Most likely the surface will be damaged when construction starts on the building that will need corrections.
Site Visit Partial 6/22/2021 06/22/2021
Misc
Informational
06/21/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Miscellaneous Inspection Partial 6/22/2021 06/22/2021
Misc
Informational
06/22/2021
TRASH ENCLOSURE SLAB ON GRADE PER PLAN OK TO POUR
Sidewalk Inspection Partial 6/23/2021 6/23/2021 06/23/2021
Misc
Informational
06/23/2021
6-23-21 10:36am They have dug out and set forms on the walking path at the east side of the site. There is no base rock in at this time and no crews are on site.
Footing Inspection - Commercial Partial 7/9/2021 (8:00) 7/9/2021 07/09/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
06/10/2021
- TRASH ENCLOSURE - - BLDG PERIMETER, UFER LOCATED WEST FOOTING NEAR RISER -
Sidewalk Inspection Partial 7/14/2021 7/14/2021 07/14/2021
Misc
Informational
06/23/2021
6-23-21 10:36am They have dug out and set forms on the walking path at the east side of the site. There is no base rock in at this time and no crews are on site. 7-14-21 9:15am They have set forms and have the base rock compacted. They will be pouring at 10am. I informed the contractor to use white cure. They will be pouring the two missing panels at Firebirds as well.
Footing Inspection - Commercial Partial 7/16/2021 07/16/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/09/2021
- TRASH ENCLOSURE - - BLDG PERIMETER, UFER LOCATED WEST FOOTING NEAR RISER - - COLUMN PAD MIDDLE BLDG -
Foundation Inspection - Commercial Partial 7/16/2021 (9:00) 7/16/2021 07/16/2021
Misc
Informational
07/16/2021
PERIMETER FOUNDATION WALLS
Footing Inspection - Commercial Partial 7/23/2021 (10:00) 7/23/2021 07/23/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/16/2021
- TRASH ENCLOSURE - - BLDG PERIMETER, UFER LOCATED WEST FOOTING NEAR RISER - - COLUMN PAD MIDDLE BLDG - - (5) COLUMNS & PADS NORTH SIDE, (2) COLUMNS & PADS EAST SIDE -
Piers/Caissons Inspection - Commercial Partial 7/26/2021 7/26/2021 07/26/2021
Misc
Informational
05/13/2021
(7) & (4)LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR. - (7) COLUMNS FORMED UP W/ BOLT PLATES -
Underslab Electrical Inspection - Commercial Partial 7/26/2021 7/26/2021 07/26/2021
Misc
Informational
04/30/2021
UNDERGROUND CONDUIT (11) LIGHT POLE BASES - CONDUIT FOR BLDG STEEL GROUNDING TO CENTER COLUMN, CONDUIT FOR SELF SERVE KIOSK -
Underslab Plumbing Inspection - Commercial Partial 7/26/2021 7/26/2021 07/26/2021
THE FOLLOWING AREAS ARE APPROVED
Informational
04/22/2021
- GREASE INTERCEPTOR - - SANITARY & GREASE LINES PRESSURE STEADY -
Sidewalk Inspection Passed 7/27/2021 7/27/2021 07/27/2021
Misc
Informational
07/14/2021
6-23-21 10:36am They have dug out and set forms on the walking path at the east side of the site. There is no base rock in at this time and no crews are on site. 7-14-21 9:15am They have set forms and have the base rock compacted. They will be pouring at 10am. I informed the contractor to use white cure. They will be pouring the two missing panels at Firebirds as well. 7-27-21 10:35am They have poured the walks and they are ADA compliant.
Site Visit Partial 8/12/2021 08/12/2021
Misc
Informational
06/22/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/12/2021
No work needing inspections. RP 8-12-21
Site Visit Partial 8/16/2021 8/16/2021 08/16/2021
Misc
Informational
08/12/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/12/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/16/2021
No work needing inspection today. RP 8-16-21
Site Visit Partial 8/18/2021 8/18/2021 08/18/2021
Misc
Informational
08/16/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/16/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/16/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/18/2021
No work needing inspection today. RP 8-18-21
Roof Drain Passed 8/20/2021 8/20/2021 08/20/2021
Misc
Informational
04/27/2021
4-27-21 2:40pm Bair has ran two storm drain lines up to the pad site. 60’ to the north and 18’ to the south west.
Misc
Informational
08/20/2021
Prodigy Plumbing connected the roof drains to the storm line. RP 8-20-21
Site Visit Partial 8/20/2021 8/20/2021 08/20/2021
Misc
Informational
08/18/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/18/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/18/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/18/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
08/20/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Site Visit Partial 8/23/2021 8/23/2021 08/23/2021
Misc
Informational
08/20/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/20/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/20/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/20/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
08/20/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
08/23/2021
No exterior work needing inspection. RP 8-23-21
Rough Framing Inspection - Commercial Partial 8/24/2021 08/24/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/24/2021
- METAL STUD FRAMING ROOF TOP PARAPET WALL -
Site Visit Partial 8/25/2021 8/25/2021 08/25/2021
Misc
Informational
08/23/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/23/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/23/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/23/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
08/23/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
08/23/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
08/25/2021
No exterior work needing inspections today. RP 8-25-21
Site Visit Partial 8/27/2021 8/27/2021 08/27/2021
Misc
Informational
08/25/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/25/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/25/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/25/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
08/25/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
08/25/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
08/25/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
08/27/2021
No exterior work needing inspections today. RP 8-27-21
Site Visit Partial 8/31/2021 8/31/2021 08/31/2021
Misc
Informational
08/27/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/27/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/27/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/27/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
08/27/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
08/27/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
08/27/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
08/27/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
08/31/2021
No exterior work needing inspections today. RP 8-31-21
Site Visit Partial 9/3/2021 9/3/2021 09/03/2021
Misc
Informational
08/31/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
08/31/2021
No work needing inspections. RP 8-12-21
Misc
Informational
08/31/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
08/31/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
08/31/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
08/31/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
08/31/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
08/31/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
08/31/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/03/2021
No exterior work due to storms. RP 9-3-21
Site Visit Partial 9/9/2021 9/9/2021 09/09/2021
Misc
Informational
09/03/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
09/03/2021
No work needing inspections. RP 8-12-21
Misc
Informational
09/03/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
09/03/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
09/03/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
09/03/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
09/03/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/03/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/03/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/03/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
09/09/2021
No exterior work being done today. RP 9-9-21
In-wall Inspection Failed 9/9/2021 9/9/2021 09/09/2021
Miscellaneous Correction
Corrective Action Required
09/09/2021
Secure pex per code Support vertical DWV 2" & smaller at midpoint Secure MC cables per code Provide pigtails at bonding screws Provide boca plates at DWV Secure bottom plate per plan Provide fire rated backing per plan OK TO SHEETROCK BEHIND WALK-IN COOLER
In-wall Inspection Partial 9/14/2021 9/14/2021 09/14/2021
Misc
Informational
09/14/2021
: THE FLLOWING AREAS ARE APPROVED : - OK TO SHEETROCK BEHIND WALK-IN COOLER - - KITCHEN AREA, MANAGERS OFFICE, -
Site Visit Partial 9/17/2021 9/17/2021 09/17/2021
Misc
Informational
09/09/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
09/09/2021
No work needing inspections. RP 8-12-21
Misc
Informational
09/09/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
09/09/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
09/09/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
09/09/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
09/09/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/09/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/09/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/09/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
09/09/2021
No exterior work being done today. RP 9-9-21
Misc
Informational
09/17/2021
No exterior work being done this week needing inspections. RP 9-17-21
Site Visit Partial 9/24/2021 9/20/2021 09/20/2021
Misc
Informational
09/17/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
09/17/2021
No work needing inspections. RP 8-12-21
Misc
Informational
09/17/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
09/17/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
09/17/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
09/17/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
09/17/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/17/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/17/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/17/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
09/17/2021
No exterior work being done today. RP 9-9-21
Misc
Informational
09/17/2021
No exterior work being done this week needing inspections. RP 9-17-21
PW-Misc
Informational
09/20/2021
The contractors are forming up the sidewalks around the buiding.
Site Visit Partial 09/22/2021
Misc
Informational
09/20/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
09/20/2021
No work needing inspections. RP 8-12-21
Misc
Informational
09/20/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
09/20/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
09/20/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
09/20/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
09/20/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/20/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/20/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/20/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
09/20/2021
No exterior work being done today. RP 9-9-21
Misc
Informational
09/20/2021
No exterior work being done this week needing inspections. RP 9-17-21
PW-Misc
Informational
09/20/2021
The contractors are forming up the sidewalks around the buiding.
Misc
Informational
09/22/2021
Contractors are continuing to form and pour sidewalk around the building.
Site Visit Failed 9/24/2021 09/24/2021
Misc
Informational
09/22/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
09/22/2021
No work needing inspections. RP 8-12-21
Misc
Informational
09/22/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
09/22/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
09/22/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
09/22/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
09/22/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/22/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/22/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/22/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
09/22/2021
No exterior work being done today. RP 9-9-21
Misc
Informational
09/22/2021
No exterior work being done this week needing inspections. RP 9-17-21
PW-Misc
Informational
09/22/2021
The contractors are forming up the sidewalks around the buiding.
Misc
Informational
09/22/2021
Contractors are continuing to form and pour sidewalk around the building.
Misc
Corrective Action Required
09/24/2021
The sidewalk around the building has been poured. There seems to be a few panels out of compliance.
Hood/Duct Inspection Partial 9/28/2021 9/28/2021 09/28/2021
Misc
Informational
09/28/2021
- WELDS APPROVED BOTH DUCTS FOR 1ST LAYER OF WRAP -
In-wall Inspection Partial 10/5/2021 10/5/2021 10/05/2021
Misc
Informational
09/14/2021
: THE FLLOWING AREAS ARE APPROVED : - OK TO SHEETROCK BEHIND WALK-IN COOLER - - KITCHEN AREA, MANAGERS OFFICE, - - RESTROOMS, HALLWAY -
Above Ceiling Inspection Partial 10/7/2021 10/07/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/07/2021
HARD LIDS RESTROOMS & HALLWAY, PREP KITCHEN & KITCHEN OK TO DROP TILE. LEAVE HOOD AREA BEHIND COUNTER EXPOSED FOR GREASE DUCT WRAP
Electrical Service Inspection Passed 10/11/2021 10/11/2021 10/11/2021
Hood/Duct Inspection Partial 10/18/2021 10/18/2021 10/18/2021
Misc
Informational
09/28/2021
- WELDS APPROVED BOTH DUCTS FOR 1ST LAYER OF WRAP - - 1ST LAYER WRAP APPROVED FOR 2ND LAYER -
Hood/Duct Inspection Passed 10/20/2021 10/20/2021 10/20/2021
Misc
Informational
10/18/2021
- WELDS APPROVED BOTH DUCTS FOR 1ST LAYER OF WRAP - - 1ST LAYER WRAP APPROVED FOR 2ND LAYER - - 2ND LAYER WRAP APPROVED -
Gas Piping Inspection - Commercial Passed 10/22/2021 10/22/2021 10/22/2021
Gas Service Inspection - Commercial Passed 10/22/2021 10/22/2021 10/22/2021
Above Ceiling Inspection Partial 10/28/2021 10/28/2021 10/28/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/07/2021
HARD LIDS RESTROOMS & HALLWAY, PREP KITCHEN & KITCHEN OK TO DROP TILE. - EXTERIOR PATIO AREA OK TO COVER -
Piers/Caissons Inspection - Commercial Not Ready 11/3/2021 (8:00) 11/3/2021 11/03/2021
Misc
Informational
07/26/2021
(7) & (4)LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR. - (7) COLUMNS FORMED UP W/ BOLT PLATES -
Commercial Curb Inspection Partial 11/9/2021 11/9/2021 11/09/2021
Misc
Informational
06/16/2021
6-11-21 8:28am Bedrock Concrete are pouring curb. They did not cure the back side of the curb and only had a light coat on the front. I had them re-cure front and back. 10:19am The are on the south side of the site and finishing up with curb. They will setting up the hand pours on Monday the 14th. 6-15-21 10:06am They are setting up hand pours. They will be pouring on Wednesday. 6-16-21 9:07 82 degrees. Bedrock are pouring curb on the north side of the site and the west side. There are three broken panels that will need replaced. One on the east side of the site and two on the south side of the site in the drive through lane. They are pulling forms on the fresh pour. I informed them to cure all exposed concrete.
Misc
Informational
11/09/2021
Bedrock Concrete replaced some broken curbing. They replaced it with 4K KCMMB mix. They doweled the existing curbing and treated it with white cure. RP 11-9-21
Piers/Caissons Inspection - Commercial Failed 11/11/2021 (1:00) 11/11/2021 11/11/2021
Misc
Informational
11/03/2021
(7) )LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR. - (7) COLUMNS FORMED UP W/ BOLT PLATES -
Miscellaneous Correction
Corrective Action Required
11/11/2021
PROVIDE CITY STAMPED REVISED PLANS FOR DRIVE THRU & CANOPY PIERS
Piers/Caissons Inspection - Commercial Partial 11/12/2021 (11:00) 11/12/2021 11/12/2021
Misc
Informational
11/11/2021
(7) )LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR. - (7) COLUMNS FORMED UP W/ BOLT PLATES - -(8) PIERS AND CAGES FOR DRIVE THRU MENU, CANOPIES AND CLEARANCE BARS
Miscellaneous Correction
Resolved
11/12/2021
Sprinkler - Hydrostatic Test Failed 11/11/2021 11/15/2021
Sprinkler - Hydrostatic Test Failed 11/12/2021 11/15/2021
Sprinkler - Hydrostatic Test Failed 11/15/2021 11/16/2021
Alternate Protection Systems Inspection Failed 11/16/2021 11/16/2021
Sprinkler - Hydrostatic Test Passed 11/23/2021 11/23/2021
Sprinkler - Flow Test Passed 11/29/2021 11/29/2021
Corrective Action Required
11/29/2021
Change "Tamper" to not report as a water flow. Change Hood to not report as a smoke. Hard pipe air compressor Add Knox Box Support FDC
Alternate Protection Systems Inspection Passed 11/29/2021 11/29/2021
Alarm Test Passed 11/29/2021 11/29/2021
Occupancy Inspection - Engineering Temporary C of O 12/2/2021 12/02/2021
Misc
Informational
12/02/2021
Punch lis to be completed in 30 days. 1. Small dip in the parking lot that holds water. This has been repaired and is better but still holds water. 2. Overtime fees of $50.00.
In-wall Inspection Passed 12/2/2021 12/02/2021
Misc
Informational
10/05/2021
: THE FLLOWING AREAS ARE APPROVED : - OK TO SHEETROCK BEHIND WALK-IN COOLER - - KITCHEN AREA, MANAGERS OFFICE, - - RESTROOMS, HALLWAY -
Miscellaneous Inspection Passed 12/2/2021 12/02/2021
Misc
Informational
06/22/2021
TRASH ENCLOSURE SLAB ON GRADE PER PLAN OK TO POUR
Piers/Caissons Inspection - Commercial Passed 12/2/2021 12/02/2021
Misc
Informational
11/12/2021
(7) )LIGHT POLE BASES CAGE W/ DRIVEN GROUND ROD OK TO POUR. - (7) COLUMNS FORMED UP W/ BOLT PLATES - -(8) PIERS AND CAGES FOR DRIVE THRU MENU, CANOPIES AND CLEARANCE BARS
Rough Framing Inspection - Commercial Passed 12/2/2021 12/02/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
08/24/2021
- METAL STUD FRAMING ROOF TOP PARAPET WALL -
Underground Electrical Inspection - Commercial Passed 12/2/2021 12/02/2021
Misc
Informational
07/23/2021
UNDERGROUND CONDUIT (11) LIGHT POLE BASES
Underslab Electrical Inspection - Commercial Passed 12/2/2021 12/02/2021
Misc
Informational
07/26/2021
UNDERGROUND CONDUIT (11) LIGHT POLE BASES - CONDUIT FOR BLDG STEEL GROUNDING TO CENTER COLUMN, CONDUIT FOR SELF SERVE KIOSK -
Underslab Plumbing Inspection - Commercial Passed 12/2/2021 12/02/2021
THE FOLLOWING AREAS ARE APPROVED
Informational
07/26/2021
- GREASE INTERCEPTOR - - SANITARY & GREASE LINES PRESSURE STEADY -
Above Ceiling Inspection Passed 12/2/2021 12/02/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
10/28/2021
HARD LIDS RESTROOMS & HALLWAY, PREP KITCHEN & KITCHEN OK TO DROP TILE. - EXTERIOR PATIO AREA OK TO COVER -
Footing Inspection - Commercial Passed 12/2/2021 12/02/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
07/23/2021
- TRASH ENCLOSURE - - BLDG PERIMETER, UFER LOCATED WEST FOOTING NEAR RISER - - COLUMN PAD MIDDLE BLDG - - (5) COLUMNS & PADS NORTH SIDE, (2) COLUMNS & PADS EAST SIDE -
Occupancy Inspection - Water Utilities Passed 12/02/2021
Occupancy Inspection - Codes Commercial Failed 12/2/2021 12/2/2021 12/02/2021
Miscellaneous Correction
Corrective Action Required
12/02/2021
OK TO STOCK & TRAIN ONLY ADDRESS BELOW CODE ITEMS & CALL FOR REINSPECT FOR TCO Mens toilet flush valve wring side ADA restroom signs wrong height Install Vertical grab bars restrooms per plan Complete drive thru window
Occupancy Inspection - Fire Temporary C of O 12/2/2021 12/2/2021 12/02/2021
Corrective Action Required
12/02/2021
Knox Box needed above FDC
Occupancy Inspection - Planning Temporary C of O 12/02/2021
Corrective Action Required
12/02/2021
General site clean-up is needed. The large roll-off containers need to be removed.
Corrective Action Required
12/02/2021
The landscaping and sod installation is incomplete.
Corrective Action Required
12/02/2021
The left gate of the trash enclosure needs repair.
Corrective Action Required
12/02/2021
Staff has concerns on the color scheme on the south elevation. The overall appearance of "all white" facade is somewhat concerning on this prominent elevation. Perhaps further discussion is needed.
Occupancy Inspection - Engineering Temporary C of O 12/2/2021 12/02/2021
Misc
Informational
12/02/2021
Punch lis to be completed in 30 days. 1. Small dip in the parking lot that holds water. This has been repaired and is better but still holds water. 2. Overtime fees of $50.00.
Misc
Informational
12/02/2021
Updated Punch List 1. Finish vegetation that was removed for light poles. 2.Make repairs to dip in parking lot where water does not drain and puddles up. 3. Finish installing curb by drivethru. 4. Remove trash bins that are in parking lot. 5. Clean mud and debris off of parking lot. 6. Finish landspaping by curb next to drive thru.
Site Visit Partial 12/6/2021 12/6/2021 12/07/2021
Misc
Informational
09/24/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
09/24/2021
No work needing inspections. RP 8-12-21
Misc
Informational
09/24/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
09/24/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
09/24/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
09/24/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
09/24/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/24/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
09/24/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
09/24/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
09/24/2021
No exterior work being done today. RP 9-9-21
Misc
Informational
09/24/2021
No exterior work being done this week needing inspections. RP 9-17-21
PW-Misc
Informational
09/24/2021
The contractors are forming up the sidewalks around the buiding.
Misc
Informational
09/24/2021
Contractors are continuing to form and pour sidewalk around the building.
Misc
Corrective Action Required
09/24/2021
The sidewalk around the building has been poured. There seems to be a few panels out of compliance.
Misc
Informational
12/07/2021
Met with Dave Olson and Steve Robbins. Owner has accepted the parking lot in it’s current condition. Still needs to vegetate next to the drive thru lane. RP 12-6-21
Water Line - Construction Inspection Passed 12/07/2021
Misc
Informational
04/29/2021
4-29-21 9:54am The water department has made the tap for the fountain. Bair will start backfilling.
Misc
Informational
12/07/2021
Fire hydrant has been painted silver to indicate a private hydrant. RP 12-6-21
Pavement-Surface Passed 12/07/2021
Misc
Informational
12/07/2021
Owner has accepted the parking lot with the small puddles and uneven asphalt around the storm drain. RP 12-6-21
Foundation Inspection - Commercial Passed 12/8/2021 12/08/2021
Misc
Informational
12/08/2021
PERIMETER FOUNDATION WALLS
Occupancy Inspection - Codes Commercial Temporary C of O 12/8/2021 12/8/2021 12/08/2021
Miscellaneous Correction
Corrective Action Required
12/02/2021
CODES COMPLETE TCO EXPIRES 01/07/2022
ESC - (Vegetation/Ground Cover) Passed 12/9/2021 12/9/2021 12/13/2021
Misc
Informational
12/13/2021
Plants and mulch has been placed along the drive thru. Sod has been placed on the curb islands. RP 12-10-21
Occupancy Inspection - Planning Temporary C of O 12/15/2021 12/15/2021 12/15/2021
Resolved
12/16/2021
Sod/Grass is missing on the south property line between the curb and sidewalk. It is primarily dirt/mud at this time.
Erosion Control Inspection Passed 12/13/2021 12/13/2021 12/15/2021
Misc
Informational
12/15/2021
Gutter buddy and silt fence over field inlet have been removed. Everything has been sodded or vegetated. No more need for erosion controls. RP 12-15-21
Grading/Excavation/Fill Inspection Passed 12/15/2021
Site Visit Complete 12/13/2021 12/13/2021 12/15/2021
Misc
Informational
12/07/2021
4-6-21 9:24am I checked the geogrid on site and it is on the approved products list. 4:26pm They laid geogrid and base rock over most of the lot. 4-7-21 10:14am There is no work on site and the erosion controls are in place and working at this time. 4-9-21 9:02am There is no work on site at this time. The site is wet from rain the night before. They have most of the site covered with base rock. 4-19-21 10:29am Bair is on site working on sanitary. 4-22-21 9:06am Bair is on site setting the water meter for the domestic line. 4-26-21 8:55am They are digging out to run the fountain waterline. They will make the tap later today. 4-27-21 11:19am Staco is on site digging for conduit. 4-30-21 10:28am Bair is on site working on the water line for the fountain. 5-3-21 10:19AM I met with Lance Lewis on site to discuss the sewer manhole grade. We will see what the contractor says about final grade. 5-4-21 11:25am There are no inspections needed at this time. 5-5-21 1:27pm Rodriguez is on site setting light pole bases. 5-14-21 12:25pm Bair is on site laying geo-grid and base rock. They are making repairs that the electricians caused. All trench repairs have a 12’’ overlap of geogrid. 2:36pm They have the base rock covered on the north end of the site. They have installed the copper domestic water line for Red ford and are backfilling now. 6-1-21 9:56am There is no work taking place at this time. 6-2-21 10:16am The work taking place on site does not require any inspections at this time. They are setting string lines. 6-3-21 3pm Bair Excavating is on site working on the base rock to repair for a curb line proof roll. 6-4-21 9:03am Bair is on site working on the drive through lane base rock. 6-9-21 9:08am Next To Nature Landscape are on site digging through the base rock to install irrigation lines for the islands. Bair Excavating are still working on the base going through the drive through lane. They have dug up soft spots and installed new geo-grid. I have pics of the repaired geo-grid. They will want to proof roll later today. 6-14-21 8:33am Staco Electric is on site working on the east side of the site. There is no other work taking place at this time. 2:07pm Bedrock Concrete are on site setting up hand pours for curb. They will be pouring in the morning. Bair Excavating are on site digging a cross the driving lane to install conduit. 6-21-21 9:58am light rain and overcast. The surface of the parking lot is completed. There is a 10’ area that is holding water in the parking stalls. i will discuss this with the contractor. 6-22-21 9:51am Bedrock Concrete are on site setting up the walking path on the south side and the two panels on the east side.
Misc
Informational
12/07/2021
No work needing inspections. RP 8-12-21
Misc
Informational
12/07/2021
No work needing inspection today. RP 8-16-21
Misc
Informational
12/07/2021
No work needing inspection today. RP 8-18-21
Misc
Informational
12/07/2021
Roof drains were connected. Told them that Bair Excavating will be coming back to paint the fire hydrant silver since it’s private. RP 8-20-21
Misc
Informational
12/07/2021
No exterior work needing inspection. RP 8-23-21
Misc
Informational
12/07/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
12/07/2021
No exterior work needing inspections today. RP 8-25-21
Misc
Informational
12/07/2021
No exterior work needing inspections today. RP 8-31-21
Misc
Informational
12/07/2021
No exterior work due to storms. RP 9-3-21
Misc
Informational
12/07/2021
No exterior work being done today. RP 9-9-21
Misc
Informational
12/07/2021
No exterior work being done this week needing inspections. RP 9-17-21
PW-Misc
Informational
12/07/2021
The contractors are forming up the sidewalks around the buiding.
Misc
Informational
12/07/2021
Contractors are continuing to form and pour sidewalk around the building.
Misc
Corrective Action Required
12/07/2021
The sidewalk around the building has been poured. There seems to be a few panels out of compliance.
Misc
Informational
12/07/2021
Met with Dave Olson and Steve Robbins. Owner has accepted the parking lot in it’s current condition. Still needs to vegetate next to the drive thru lane. RP 12-6-21
Misc
Informational
12/15/2021
All work concerning field engineering on site has been completed. No further inspections required by field engineer. RP 12-15-21
Occupancy Inspection - Planning Passed 12/16/2021 12/16/2021
Occupancy Inspection - Engineering Passed 1/3/2022 12/16/2021
Misc
Informational
12/02/2021
Punch lis to be completed in 30 days. 1. Small dip in the parking lot that holds water. This has been repaired and is better but still holds water. 2. Overtime fees of $50.00.
Misc
Informational
12/02/2021
Updated Punch List 1. Finish vegetation that was removed for light poles. 2.Make repairs to dip in parking lot where water does not drain and puddles up. 3. Finish installing curb by drivethru. 4. Remove trash bins that are in parking lot. 5. Clean mud and debris off of parking lot. 6. Finish landspaping by curb next to drive thru.
Occupancy Inspection - Codes Commercial Full C of O 12/16/2021
Miscellaneous Correction
Resolved
12/16/2021
CODES COMPLETE TCO EXPIRES 01/07/2022
Documents & Images
Date Uploaded File Type Document Name
02/12/2021 Application Form Building Permit Application - Shake Shack Lee's Summit
02/16/2021 Engineer Report/Study Shake Shack Lee's Summit_Lot 2 - Streets of West Pryor Geotech Report
02/16/2021 Plans Shake Shack Lee's Summit_Permit Set_Combined_Stamped
02/18/2021 Letter DS P/R Corrections Document
03/09/2021 Letter 2020-03-09_Shake Shack Lee's Summit - Permit Comment Responses
03/09/2021 Specifications CO2 Specs
03/09/2021 Plans 2021-03-09_MO_Lees Summit_Addendum 1_Combined
03/10/2021 Approved Plans approved - 2021-03-09_MO_Lees Summit_Addendum 1_Combined
03/15/2021 Receipt Receipt for transaction:2021-001265
03/17/2021 Approved Lot 2 site FDP
03/18/2021 Letter DS Building Permit
03/23/2021 Email New Food Establishment Plan Review - Approved FTG 0001932
03/24/2021 19_9096 Streets of West Pryor Wall E New Section Wall Calculations 3_10_21
03/24/2021 19_9096 Streets of West Pryor Wall E New Section Wall Plans 3_10_21
03/24/2021 19_9096 Streets of West Pryor Wall E New Section Wall Calculations 3_10_21
03/24/2021 19_9096 Streets of West Pryor Wall E New Section Wall Plans 3_10_21
03/30/2021 Application Form Shake Shack #1348 - License Tax Form
04/02/2021 Letter INSPECTION SUMMARY
04/05/2021 Letter License Tax Bill
04/05/2021 Letter INSPECTION SUMMARY
04/05/2021 Receipt Receipt for transaction:2021-001735
04/05/2021 Letter INSPECTION SUMMARY
04/06/2021 Approved geo grid.jpg
04/06/2021 Letter INSPECTION SUMMARY
04/06/2021 Letter INSPECTION SUMMARY
04/07/2021 Letter INSPECTION SUMMARY
04/09/2021 Letter INSPECTION SUMMARY
04/13/2021 Letter INSPECTION SUMMARY
04/14/2021 Letter INSPECTION SUMMARY
04/15/2021 Fire line.jpg
04/15/2021 Water vault .jpg
04/15/2021 Water line needs rock.jpg
04/15/2021 Grease interceptor.jpg
04/15/2021 Letter INSPECTION SUMMARY
04/15/2021 Kickers.jpg
04/15/2021 Kickers and collars .jpg
04/15/2021 Collars .jpg
04/15/2021 Letter INSPECTION SUMMARY
04/16/2021 Sanitary service .jpg
04/16/2021 Letter INSPECTION SUMMARY
04/19/2021 Letter INSPECTION SUMMARY
04/19/2021 Letter INSPECTION SUMMARY
04/19/2021 iSanitary service line .jpg
04/19/2021 Letter INSPECTION SUMMARY
04/19/2021 Sanitary line under water.jpg
04/19/2021 Letter INSPECTION SUMMARY
04/21/2021 Wye cut in.jpg
04/21/2021 Letter INSPECTION SUMMARY
04/22/2021 Receipt Receipt for transaction:2021-002141
04/22/2021 Letter INSPECTION SUMMARY
04/22/2021 Letter INSPECTION SUMMARY
04/23/2021 Letter INSPECTION SUMMARY
04/26/2021 Letter INSPECTION SUMMARY
04/26/2021 Letter INSPECTION SUMMARY
04/27/2021 Letter INSPECTION SUMMARY
02/17/2021 Letter Fire Building Plan Review
04/06/2021 Letter INSPECTION SUMMARY
04/05/2021 Letter DS Building Permit
03/10/2021 Letter Fire Building Plan Review
04/27/2021 Letter INSPECTION SUMMARY
04/28/2021 Letter INSPECTION SUMMARY
04/29/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
05/03/2021 Letter INSPECTION SUMMARY
05/04/2021 Letter INSPECTION SUMMARY
05/12/2021 Shake Shack Lee's Summit - Fire Alarm System Design - Eclipse 2021 - 1
05/12/2021 Letter Fire (Alarm) Plan Review Notice
05/13/2021 Letter INSPECTION SUMMARY
05/14/2021 Letter INSPECTION SUMMARY
05/14/2021 Letter INSPECTION SUMMARY
05/17/2021 Letter 2021-05-17_MO_Lee's Summit_Field Notice 2_Permit ReSubmittal_Narrative
05/17/2021 Plans 2021-05-17_MO_Lees Summit_Field Notice 2_Permit Resubmittal_Combined_reduced
06/02/2021 Letter INSPECTION SUMMARY
06/03/2021 Letter INSPECTION SUMMARY
06/04/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
06/11/2021 Letter INSPECTION SUMMARY
06/14/2021 Letter INSPECTION SUMMARY
06/15/2021 Letter INSPECTION SUMMARY
06/15/2021 Letter INSPECTION SUMMARY
06/16/2021 Letter INSPECTION SUMMARY
06/18/2021 Letter INSPECTION SUMMARY
06/18/2021 Letter INSPECTION SUMMARY
06/19/2021 Letter INSPECTION SUMMARY
06/21/2021 Letter INSPECTION SUMMARY
06/21/2021 Ponding in parking lot.jpg
06/21/2021 Cable on the storm box.jpg
06/21/2021 Asphalt not rolled in and higher than curb.jpg
06/21/2021 Hump by ada.jpg
06/21/2021 Rutting and high asphalt .jpg
06/21/2021 High and not rolled in asphalt .jpg
06/19/2021 image.jpg1
06/19/2021 image.jpg0
06/22/2021 Letter INSPECTION SUMMARY
06/22/2021 Letter INSPECTION SUMMARY
06/23/2021 Letter INSPECTION SUMMARY
07/09/2021 Letter INSPECTION SUMMARY
06/19/2021 image.jpg
07/16/2021 Letter INSPECTION SUMMARY
07/16/2021 Letter INSPECTION SUMMARY
06/18/2021 Letter INSPECTION SUMMARY
06/17/2021 Letter INSPECTION SUMMARY
07/26/2021 Letter INSPECTION SUMMARY
07/26/2021 Letter INSPECTION SUMMARY
07/26/2021 Letter INSPECTION SUMMARY
07/27/2021 Letter INSPECTION SUMMARY
08/09/2021 R1 DTC_1 DT-SGL-LEG-CANOPY-2051 NW Lowenstien Dr_Lee's Summit MO_8-6-21_FINAL (1)
06/17/2021 Letter INSPECTION SUMMARY
08/16/2021 Letter INSPECTION SUMMARY
08/17/2021 Engineer Report/Study Revised DTC_1 - Calcs_Shake Shack_Lee's Summit MO_F (1)
08/17/2021 Approved Plans Revised DTC_1 DT-SGL-LEG-CANOPY-2051
06/14/2021 Letter INSPECTION SUMMARY
08/17/2021 Approved Plans APPROVED - 250360_Lee's Summit MO_Revised Canopy Engineering
08/18/2021 Letter INSPECTION SUMMARY
06/10/2021 Approved Plans approved - 2021-05-17_MO_Lees Summit_Field Notice 2_Permit Resubmittal_Combined_reduced
06/10/2021 Email RE Lee's Summit Shake Shack #1348 - PRCOM20210599 - Revisions - Permit Re-Submission
08/20/2021 Letter INSPECTION SUMMARY
08/20/2021 Letter INSPECTION SUMMARY
08/20/2021 Letter Fire Building Plan Review
08/23/2021 Approved Plans approved - 210819_MO-LEES SUMMIT-1348_Fn3
06/10/2021 Letter INSPECTION SUMMARY
08/24/2021 Letter INSPECTION SUMMARY
08/25/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/31/2021 Letter INSPECTION SUMMARY
06/09/2021 Letter INSPECTION SUMMARY
09/09/2021 Letter INSPECTION SUMMARY
09/09/2021 Letter INSPECTION SUMMARY
09/09/2021 Letter INSPECTION SUMMARY
09/14/2021 Letter INSPECTION SUMMARY
09/15/2021 Plans 2021-09-09_MO_Lees Summit_Field Notice 4_Combined
09/15/2021 Letter 2021-09-09_MO_Lees Summit_Field Notice 4_Narrative
09/17/2021 Letter INSPECTION SUMMARY
09/20/2021 Letter INSPECTION SUMMARY
06/09/2021 Letter INSPECTION SUMMARY
06/09/2021 Geo-grid drive through curve.jpg
06/09/2021 Geo-grid.jpg
06/07/2021 Letter INSPECTION SUMMARY
09/28/2021 Letter INSPECTION SUMMARY
09/28/2021 Letter INSPECTION SUMMARY
10/04/2021 2021-09-28_MO_Lees Summit_Field Notice 5_Narrative
10/04/2021 2021-09-28_MO_Lees Summit_Field Notice 5_Combined
10/05/2021 Letter INSPECTION SUMMARY
06/04/2021 Letter INSPECTION SUMMARY
10/11/2021 Letter INSPECTION SUMMARY
10/18/2021 Letter INSPECTION SUMMARY
10/20/2021 Letter INSPECTION SUMMARY
10/22/2021 Letter INSPECTION SUMMARY
10/22/2021 Letter INSPECTION SUMMARY
10/26/2021 Approved Plans approved - 2021-09-28_MO_Lees Summit_Field Notice 5_Combined
06/02/2021 Letter INSPECTION SUMMARY
11/02/2021 Approved Plans approved sign structures
11/03/2021 Letter INSPECTION SUMMARY
11/09/2021 Letter INSPECTION SUMMARY
11/11/2021 Letter INSPECTION SUMMARY
06/01/2021 Letter INSPECTION SUMMARY
11/12/2021 Plans Shake Shack Lees Summit MO Revised Final 11-12-21
11/12/2021 Approved Plans approved - Shake Shack Lees Summit MO Revised Final 11-12-21
11/29/2021 Letter Fire Loss Reduction Form
11/29/2021 Letter Fire Loss Reduction Form
11/29/2021 Letter Fire Loss Reduction Form
11/29/2021 Receipt Receipt for transaction:2021-008953
05/28/2021 Letter INSPECTION SUMMARY
05/28/2021 Letter INSPECTION SUMMARY
05/28/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
05/28/2021 Letter INSPECTION SUMMARY
05/28/2021 Letter INSPECTION SUMMARY
05/27/2021 Letter Fire (Sprinkler) Plan Review
06/21/2021 Letter INSPECTION SUMMARY
06/21/2021 Letter INSPECTION SUMMARY
07/14/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
07/21/2021 Approved Plans 250360_R11_Shake Shack_Lees Summit, MO_DT Package for Permits_2018 IBC
07/23/2021 Letter INSPECTION SUMMARY
08/12/2021 Letter INSPECTION SUMMARY
08/19/2021 Letter 2021-08-09_MO_Lees Summit_Field Notice 3_Narrative
08/19/2021 Plans 210819_MO-LEES SUMMIT-1348_Fn3
08/23/2021 Letter INSPECTION SUMMARY
09/03/2021 Letter INSPECTION SUMMARY
09/22/2021 Approved Plans Approved_Field Notice 4_Combined
09/22/2021 Letter INSPECTION SUMMARY
09/22/2021 Letter INSPECTION SUMMARY
09/24/2021 Letter INSPECTION SUMMARY
10/07/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/08/2021 Letter INSPECTION SUMMARY
12/08/2021 Letter Codes Temporary Certificate of Occupancy
10/28/2021 Letter INSPECTION SUMMARY
11/12/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/16/2021 Letter Codes Final Certificate of Occupancy
12/20/2021 Letter Field Certificate of Occupancy
12/20/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/02/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter Fire Loss Reduction Form
12/07/2021 Letter Fire Loss Reduction Form
12/07/2021 Letter Fire Loss Reduction Form
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter Fire Loss Reduction Form
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/15/2021 Letter INSPECTION SUMMARY
12/15/2021 Letter INSPECTION SUMMARY
12/15/2021 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home