COBEY CREEK 2ND PLAT - Public Water Line
Engineering Plan Review
Engineering Plan Review
Withdrawn
03/14/2022
JCM DEVELOPMENT LLC
Locations
Contacts
JCM DEVELOPMENT LLC, Address:1314 SW MARKET ST  
Not shown for privacy reasons.
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Corrections 11/04/2022 11/04/2022
Gene Williams, P.E.
Corrective Action Required
11/04/2022

What revisions were made to the latest plans? It appears revisions were made, but it is not obvious what was revised. Please indicate by revision clouds or by written response what was revised on the originally-approvable plans.
Engineering Review No Comments 09/15/2022 09/15/2022
Gene Williams, P.E.
Engineering Review No Comments 07/29/2022 07/29/2022
Gene Williams, P.E.
Engineering Review No Comments 05/25/2022 05/26/2022
Gene Williams, P.E.
Engineering Review Corrections 03/30/2022 03/30/2022
Gene Williams, P.E.
Corrective Action Required
03/30/2022

Water line is shown between lots 33 and 34. This is not allowed by the Design and Construction Manual without specific approval from Water Utilities. Please relocate the water main so it is not located within sideyards.
Corrective Action Required
03/30/2022

Sheet C202: Water main is too deep beneath the sanitary line at sta 8+50. Please revise depth of sanitary line and place line on top of sanitary line. The City is willing to consider 3.0 feet of cover in this instance due to the fact this is not a dead end and water will move continuously during use.
Corrective Action Required
03/30/2022

Water mains 2-FF and 2-GG shall be 12 inch rather than 8 inch as shown. There is a 12 inch water main along Cobey Creek Dr. which was shown in the PDP to be extended to the plat boundary, and as shown, these two lines will not meet the requirements shown in the PDP. Please revise.
Corrective Action Required
03/30/2022

Valves on the new 12 inch line shall be butterfly valves rather than gate valves. This is required for any water main 12 inches and larger. Please review and revise.
Corrective Action Required
03/30/2022

General Layout Sheet: It would be beneficial to show the size of existing water mains and proposed water mains on this sheet. As previously discussed, a 12 inch line exists along Cobey Creek Dr., all the way to the M-150 connection point. This line shall be 12 inch all the way to the plat boundary, and eventually will connect to the property line to the north in a future phase (i.e. the Weaver property). Please revise.
Corrective Action Required
03/30/2022

In addition to the gate valve on the south side of M-150 at the new connection point, an additional gate valve is required on the north side to isolate a break if it occurs beneath the highway. Please revise.
Corrective Action Required
03/30/2022

Sheet C205: The water main is too deep at sta 6+90. Maximum depth of cover is 7 feet as measured to the top of pipe to the finish grade. Either relocate the storm line, and move the water main so it is located on top of the storm line rather than beneath the storm line. The City would consider a lesser cover such as 3.0 feet in this instance since the water main is continuously flowing and not in a dead end situation. Please analyze and revise as appropriate.
Corrective Action Required
03/30/2022

Sheet C207: Please see comment above. This comment also pertains to the water main at sta 12+20. It is too deep. Please review and revise as appropriate.
Corrective Action Required
03/30/2022

Sheet C208: Please see comment above. The same comment pertains to two (2) different locations on the profile view where the water main is shown deeper than 7 feet of cover as measured from the top of pipe to the finish grade. Please review and revise as appropriate.
Corrective Action Required
03/30/2022

Sheet C209: Line JJ is too deep. See previous comments related to this issue and review and revise as appropriate.
Corrective Action Required
03/30/2022

Sheet C210: Please see comment above related to depth issue. This line is too deep beneath the storm line. Please review and revise as appropriate.
Corrective Action Required
03/30/2022

Sheet C212: Please see above comment. A portion of the line is too deep. Please review and revise as appropriate.
Corrective Action Required
03/30/2022

Casing pipe diameter, length, and wall thickness shall be shown on the plan view for the water main crossing. Please review, coordinate with MoDOT, and revise as appropriate.
Corrective Action Required
03/30/2022

An MDNR construction permit shall be required for this project. An MDNR concurrence letter shall be issued after the plans are deemed approvable, along with a model run performed internally by City staff. This comment is for informational purposes only.
Corrective Action Required
03/30/2022

A MoDOT permit shall be required prior to approval of the plans. This comment is for informational purposes only.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
03/14/2022 Plans Cobey Creek 2nd Plat Water Main Plans_Rev0_2022-03-14
03/30/2022 Letter DE-Comment Letter (Engineering Plans)
05/11/2022 2022_05_11 - Cobey Creek 2nd Plat - Water Main Comment Response
05/11/2022 Cobey Creek 2nd Plat - Water Main OPC_Rev0_2022-05-11
05/11/2022 Cobey Creek 2nd Plat - Water Main Plans_Rev1_2022-05-11
07/22/2022 2022_07_22 - Cobey Creek 2nd Plat - Water Main Comment Response
07/22/2022 Cobey Creek 2nd Plat - Water Main Plans_Rev2_2022-07-22
08/11/2022 WU EMAIL COMMENTS AUG2022
08/26/2022 Response to Comments 2022_08_26 - Cobey Creek 2nd Plat - Water Main Comment Response
08/26/2022 EEOPCC Cobey Creek 2nd Plat - Water Main OPC_Rev1_2022-08-26
08/26/2022 Plans Cobey Creek 2nd Plat - Water Main Plans_Rev3_2022-08-26
08/31/2022 Cobey Creek 2nd Plat - Water Main OPC_Rev2_2022-08-30
08/31/2022 Cobey Creek 2nd Plat - Water Main Plans_Rev3_2022-08-30
09/02/2022 Cobey Creek 2nd Plat - Water Main Plans_Rev3_2022-09-02
09/02/2022 WATERMODEL COBEY CREEK 2ND SEPT2022
09/07/2022 MDNR CONC SIGNED SEP2022
09/08/2022 Engineers Estimate Cobey Creek 2nd Plat - Water Main OPC_Rev3_2022-09-08
09/08/2022 Plans Cobey Creek 2nd Plat - Water Main Plans_Rev4_2022-09-08
10/21/2022 Plans Cobey Creek 2nd Plat - Water Main Plans_Rev5_2022-10-11
10/21/2022 Letter MDNR - Waterline Extension Approval 10_13_22
11/04/2022 Email EMAIL COMMENTS NOV2022
11/08/2022 Email MoDOT email correspondence 110822
12/01/2022 Engineers Estimate Cobey Creek 2nd Plat - Water Main OPC_Rev3_2022-09-08
12/02/2022 Activity Document FeeWorksheetCobeyCreek2ndWATER
06/29/2023 Approved Plans APPROVED PLANS STAMPED
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home