Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
No Comments
|
05/11/2022
|
05/11/2022
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $15,637.84
|
|
|
Fire Review
|
Approved with Conditions
|
08/25/2021
|
08/23/2021
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
*Additional fire protection and egress may be required depending on occupancy type.Verified at building permit plan review.
|
|
|
Traffic Review
|
No Comments
|
08/25/2021
|
08/23/2021
|
|
Brad Cooley, P.E., RSPI
|
|
|
Engineering Review
|
Approved with Conditions
|
08/25/2021
|
08/20/2021
|
|
Sue Pyles, P.E.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $15,637.84
|
|
|
Planning Review
|
No Comments
|
08/25/2021
|
08/20/2021
|
|
Victoria Nelson
|
|
Miscellaneous Correction
Parking space length. The new measurements you are showing do not meet the UDO requirements and they need to be revised to meet the 19’ length, measured from the face of the curb, since the sidewalk is less than 6’ wide.
|
|
Miscellaneous Correction
Please pay the $600 applicable fee. This fee must be paid prior to the release of comments on the next resubmittal.
|
|
|
Building Codes Review
|
No Comments
|
08/25/2021
|
08/19/2021
|
|
Joe Frogge
|
|
|
Engineering Review
|
Corrections
|
07/08/2021
|
07/08/2021
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Please update contact information and City related notes on the cover sheet. Several projects designed by your firm have been reviewed recently. Those should provide adequate guidance.
|
|
|
Fire Review
|
Approved with Conditions
|
07/08/2021
|
07/07/2021
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
*Additional fire protection and egress may be required depending on occupancy type.Verified at building permit plan review.
|
|
|
Traffic Review
|
No Comments
|
07/08/2021
|
07/07/2021
|
|
Brad Cooley, P.E., RSPI
|
|
|
Planning Review
|
Corrections
|
07/08/2021
|
07/06/2021
|
|
Victoria Nelson
|
|
Miscellaneous Correction
Parking space measurement. It appears you are measuring to the back of the curb, we ask that you measure to the face of the curb instead. Please re-measure.
|
|
Miscellaneous Correction
Utility easements. Please show widths of U/E’s.
|
|
Miscellaneous Correction
Setback lines. Please show building line and parking lot line setbacks.
|
|
Miscellaneous Correction
Lighting Spec Sheets. Please submit the manufacturer proposed exterior lighting including both parking lot pole mounted and wall fixtures.
|
|
Miscellaneous Correction
Landscaping. All deciduous trees shall be a minimum of 3” caliber. Evergreen trees shall be a minimum of 8’
|
|
Miscellaneous Correction
Shrub count. You say there are 37 BGV plants, I count 35. For CAK, you say 17, I counted 16.
|
|
Miscellaneous Correction
Corrective Action Required
Parking space length. The new measurements you are showing do not meet the UDO requirements and they need to be revised to meet the 19’ length, measured from the face of the curb, since the sidewalk is less than 6’ wide.
|
|
Miscellaneous Correction
Corrective Action Required
Please pay the $600 applicable fee. This fee must be paid prior to the release of comments on the next resubmittal.
|
|
|
Building Codes Review
|
No Comments
|
07/08/2021
|
07/02/2021
|
|
Joe Frogge
|
|
|
Engineering Review
|
Corrections
|
06/18/2021
|
06/18/2021
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
General:
• Please include a cover sheet.
• Please show and label all utility easements throughout the plan set.
• Please submit an Engineer's Estimate of Probable Construction Costs.
|
|
Corrective Action Required
Sheet C1.0: Please differentiate the different types and locations of pavements to match the pavement sections provided in the details.
|
|
Corrective Action Required
Sheet C2.0:
• The proposed contours are shown beyond the expected limits of construction. Please revise.
• Please include existing elevations where the proposed sidewalk will connect to the existing sidewalk at the NE corner of the site.
• Please include specific designs for the proposed ADA-accessible ramps that meet the City’s slope requirements of 1.5% maximum cross-slope and 7.5% maximum longitudinal slope.
|
|
|
Traffic Review
|
No Comments
|
06/18/2021
|
06/16/2021
|
|
Brad Cooley, P.E., RSPI
|
|
Developer may want to look at the on-street parking to the west of proposed drive. May have sight distance conflicts with vehicles exiting.
|
|
|
Planning Review
|
Corrections
|
06/18/2021
|
06/15/2021
|
|
Victoria Nelson
|
|
Miscellaneous Correction
Corrective Action Required
Parking space measurement. It appears you are measuring to the back of the curb, we ask that you measure to the face of the curb instead. Please re-measure.
|
|
Miscellaneous Correction
Corrective Action Required
Utility easements. Please show widths of U/E’s.
|
|
Miscellaneous Correction
Corrective Action Required
Setback lines. Please show building line and parking lot line setbacks.
|
|
Miscellaneous Correction
Corrective Action Required
Lighting Spec Sheets. Please submit the manufacturer proposed exterior lighting including both parking lot pole mounted and wall fixtures.
|
|
Miscellaneous Correction
Corrective Action Required
Landscaping. All deciduous trees shall be a minimum of 3” caliber. Evergreen trees shall be a minimum of 8’
|
|
Miscellaneous Correction
Corrective Action Required
Shrub count. You say there are 37 BGV plants, I count 35. For CAK, you say 17, I counted 16.
|
|
|
Building Codes Review
|
No Comments
|
06/18/2021
|
06/11/2021
|
|
Joe Frogge
|
|
|
Fire Review
|
Approved with Conditions
|
06/18/2021
|
06/07/2021
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
*Additional fire protection and egress may be required depending on occupancy type.Verified at building permit plan review.
|
|
|