Review Type |
Outcome |
Est. Completion Date |
Completed |
Redesign Review
|
No Comments
|
07/29/2022
|
07/28/2022
|
|
Gene Williams, P.E.
|
|
|
Building Codes Review
|
No Comments
|
01/27/2021
|
01/20/2021
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
01/27/2021
|
01/20/2021
|
|
Mike Weisenborn
|
|
|
Engineering Review
|
Approved with Conditions
|
01/27/2021
|
01/20/2021
|
|
Mike Weisenborn
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $185,883.14
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
A complete set of drawings, with the latest revisions for the water meter vault detail, is required prior to approval of the Final Development Plan.
|
|
|
Planning Review
|
No Comments
|
01/27/2021
|
01/20/2021
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Approved with Conditions
|
01/27/2021
|
01/20/2021
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3 - Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Action required:
1. Fire lanes shall be marked by a combination of RED curbs and signage.
2. Mark the area in front of the new FDC.
|
|
Fire Lanes
Corrective Action Required
IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm)
Action required: The accesses being paved to the farthest east bulding (Ref. C130 Site Plan-North) need to meet this requirement.
12/17/2020- The lanes to and in front of Building E, need to meet this requirement.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
|
Fire Review
|
Corrections
|
01/07/2021
|
01/07/2021
|
|
Mike Weisenborn
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3 - Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Action required:
1. Fire lanes shall be marked by a combination of RED curbs and signage.
2. Mark the area in front of the new FDC.
|
|
Fire Lanes
Corrective Action Required
IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm)
Action required: The accesses being paved to the farthest east bulding (Ref. C130 Site Plan-North) need to meet this requirement.
12/17/2020- The lanes to and in front of Building E, need to meet this requirement.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
|
Engineering Review
|
Approved with Conditions
|
01/07/2021
|
01/07/2021
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $185,883.14
|
|
Corrective Action Required
A complete set of drawings, with the latest revisions for the water meter vault detail, is required prior to approval of the Final Development Plan.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Traffic Review
|
No Comments
|
01/07/2021
|
01/06/2021
|
|
Michael Park
|
|
|
Planning Review
|
No Comments
|
01/07/2021
|
01/04/2021
|
|
Hector Soto Jr.
|
|
|
Building Codes Review
|
No Comments
|
01/07/2021
|
12/30/2020
|
|
Joe Frogge
|
|
Miscellaneous Correction
Site lighting not found.
Action required: Provide complete design or request deferral to building permit submittal.
12/17/20 - Sheets referenced in response letter only show fixture locations. We also need circuitry information and pole base details.
|
|
|
Planning Review
|
No Comments
|
12/23/2020
|
12/27/2020
|
|
Hector Soto Jr.
|
|
|
Engineering Review
|
Corrections
|
12/23/2020
|
12/23/2020
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Please refer to the previous applicant letter. The special meter vault for the 4 inch water meter appears to be showing "note 8" on the various views, but "note 8" is discussing requirements for a strainer rather than the features that are referenced on the various views of the meter vault. Please revise as appropriate.
|
|
Corrective Action Required
Please ensure the valve shown on the bypass is clear in terms of notation, either by a legend or a note. As shown, it might be missed by the contractor.
|
|
|
Traffic Review
|
No Comments
|
12/23/2020
|
12/22/2020
|
|
Michael Park
|
|
|
Fire Review
|
Corrections
|
12/23/2020
|
12/17/2020
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Fire Lanes - Marking
IFC 503.3 - Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Action required:
1. Fire lanes shall be marked by a combination of RED curbs and signage.
2. Mark the area in front of the new FDC.
|
|
Fire Lanes
Corrective Action Required
IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm)
Action required: The accesses being paved to the farthest east bulding (Ref. C130 Site Plan-North) need to meet this requirement.
12/17/2020- The lanes to and in front of Building E, need to meet this requirement.
|
|
Imposed Loads
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
|
Building Codes Review
|
Corrections
|
12/23/2020
|
12/17/2020
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Site lighting not found.
Action required: Provide complete design or request deferral to building permit submittal.
12/17/20 - Sheets referenced in response letter only show fixture locations. We also need circuitry information and pole base details.
|
|
Miscellaneous Correction
Clarify construction/relocation of water meter. Plans show existing meter to remain but also shows an additional new meter.
Provide the following:
- Resolve conflicting information.
- Provide complete water meter vault construction details. (fyi - we do not have a standard detail for your use.)
|
|
|
Fire Review
|
Corrections
|
12/08/2020
|
12/08/2020
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Fire Lanes - Marking
Corrective Action Required
IFC 503.3 - Where required by the fire code official, approved signs or other approved notices or markings that include the words NO PARKING—FIRE LANE shall be provided for fire apparatus access roads to identify such roads or prohibit the obstruction thereof. The means by which fire lanes are designated shall be maintained in a clean and legible condition at all times and be replaced or repaired when necessary to provide adequate visibility.
Action required:
1. Fire lanes shall be marked by a combination of RED curbs and signage.
2. Mark the area in front of the new FDC.
|
|
Fire Lanes
Corrective Action Required
IFC 503.2.1 - Fire apparatus access roads shall have an unobstructed width of not less than 20 feet (6096 mm), exclusive of shoulders, except for approved security gates in accordance with Section 503.6, and an unobstructed vertical clearance of not less than 13 feet 6 inches (4115 mm)
Action required: The accesses being paved to the farthest east bulding (Ref. C130 Site Plan-North) need to meet this requirement.
|
|
Imposed Loads
Corrective Action Required
IFC 503.2.3 - Fire apparatus access roads shall be designed and maintained to support the imposed loads of fire apparatus and shall be surfaced so as to provide all-weather driving capabilities.
|
|
|
Planning Review
|
Corrections
|
12/08/2020
|
12/08/2020
|
|
Hector Soto Jr.
|
|
Corrective Action Required
LAND USE TABLE -- PARKING.
- List the number of existing and proposed resulting number of classrooms to confirm parking adequacy. Minimum parking requirements are based on the number classrooms, calculated at 6 parking spaces required for each classrom for a high school.
- The number of proposed parking spaces listed on Sheets C100 and C1005 do not match, 1154 vs 1159, respectively.
|
|
Corrective Action Required
BLUE PKWY REALIGNMENT. Call out that the Blue Pkwy realignment shown on the plan is not part of this plan but a future improvement by others.
|
|
Corrective Action Required
EXTERIOR MATERIALS. Label the proposed exterior building material colors.
|
|
|
Engineering Review
|
Corrections
|
12/08/2020
|
12/08/2020
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
The public sanitary sewer running from the Highway Patrol property to City manhole #39-155 should be designated as private to avoid conflicts with construction. This would require a new public sanitary sewer extension to the Highway Patrol property from the public sanitary sewer located in the northeast portion of the High School property. In addiition, a portion of the sanitary sewer 39-041 to 39-039 should also be dedicated as private.
|
|
Corrective Action Required
The asphaltic pavement detail should be revised to show aggregate subgrade and chemically-stablized subgrade extending a minimum of 1 foot beyond the back of curb.
|
|
Corrective Action Required
A site-specific design is required for the water meter vault since the City does not supply meter vaults for water meters above 2 inches. The meter vault should include bypass piping. The ring and cover should be a square aluminum hatch, 36” X 36”, centered over the meter and steps. The steps need to be MA Industries copolymer polypropylene plastic coated steel model PS2-PF.
|
|
Corrective Action Required
Sheet C350: Where are the retaining walls in relation to the project? This sheet appears to lack context to the overall project.
|
|
Corrective Action Required
Where and how will the backflow vaults drain? The typical detail for the backflow vault shows a sump, and the notes require that a method be shown how the vault will draiin. This can be via daylighting, connection to a private junction box or inlet, or construction of an infiltration gallery.
|
|
Corrective Action Required
The City will not support waiving the Comprehensive Control Strategy for this project. There did not appear to be any justification for relaxing these requirements in the waiver request.
|
|
Corrective Action Required
On the revised detention basin plans, please provide a prominent note that the basin must be constructed prior to any other improvments on the site, with the exception of erosion and sediment control features.
|
|
Corrective Action Required
Portions of utility easements should be vacated for those portions of the sanitary sewer line to be dedicated as private. Please see comment number 1 for specific information concerning these vacates.
|
|
Corrective Action Required
Please ensure that all private sanitary sewer lines are connected to public mains via a wye rather than a direct manhole connection. This applies for all sanitary sewer lines less than 8 inches in diameter.
|
|
|
Traffic Review
|
No Comments
|
12/08/2020
|
12/03/2020
|
|
Michael Park
|
|
|
Building Codes Review
|
Corrections
|
12/08/2020
|
11/24/2020
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Site lighting not found.
Action required: Provide complete design or request deferral to building permit submittal.
|
|
Miscellaneous Correction
Corrective Action Required
Clarify construction/relocation of water meter. Plans show existing meter to remain but also shows an additional new meter.
Provide the following:
- Resolve conflicting information.
- Provide complete water meter vault construction details. (fyi - we do not have a standard detail for your use.)
|
|
|