PRSUBD20242356
Public Infrastructure
Issued
DEVELOPMENT COMPLETE
Sanitary sewer extension of approximately 140 LF. to serve Lot 1 of Village at Discovery Park.
05/10/2024
01/10/2025
08/05/2026
Locations
Contacts
Nolan Dixon, Address:Bldg. 1, Phone:(573) 447-0292  
Matthew Braden, Address:1000 W. Nifong Blvd., Phone:(573) 447-0292  
Brian Maenner - Intrinsic Development, Phone:(573) 881-0280  
Brian Maenner - Intrinsic Development, Phone:(573) 881-0280  
Intrinsic Development, L.L.C., Address:3622 Endeavor Ave., Ste. 101  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Record Drawing Review - Sanitary Accepted 03/26/2026 03/19/2026
Daniel Fernandez
Engineering Record Drawing Review - Sanitary Rejected 02/06/2026 02/05/2026
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
02/05/2026

The as-built information provided indicates that there is inadequate drop through the existing manhole with the new connection. Please verify your information.
Engineering Review - Sanitary No Comments 09/10/2024 09/11/2024
Susan Nelson, P.E.
Engineering Review - Sanitary Corrections 08/08/2024 08/07/2024
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
08/07/2024

The submitted estimate will not satisfy the requirements of the Unified Development Ordinance (Section 3.415) for the required documentation to calculate the Engineering Plan Review and Inspection Fee. This must be an itemized list of unit prices and quantities that includes all materials, labor, equipment and incidental work necessary to complete the entire project. Please resubmit an appropriate signed and sealed estimate. The specific material types must be added to the estimate.
Miscellaneous Correction
Corrective Action Required
08/07/2024

Submit the proposed public sanitary easement documents for review and approval. Please note that this easement must be in place prior to issuance of any permit. The entire legal document that is necessary to record the easement through Jackson County must be submitted for review, not just the exhibits.
Engineering Review - Sanitary Corrections 07/15/2024 07/05/2024
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
07/05/2024

The submitted estimate will not satisfy the requirements of the Unified Development Ordinance (Section 3.415) for the required documentation to calculate the Engineering Plan Review and Inspection Fee. This must be an itemized list of unit prices and quantities that includes all materials, labor, equipment and incidental work necessary to complete the entire project. Please resubmit an appropriate signed and sealed estimate.
Miscellaneous Correction
Corrective Action Required
07/05/2024

Submit the proposed public sanitary easement documents for review and approval. Please note that this easement must be in place prior to issuance of any permit.
Miscellaneous Correction
Corrective Action Required
07/05/2024

Show and document the new public sanitary sewer easement on the plans.
Engineering Review - Sanitary Corrections 05/24/2024 05/24/2024
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Submit an Engineer’s Estimate of Probable Construction Costs.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Submit the proposed public sanitary easement document for review and approval. Please note that the public sanitary sewer easement must be in place prior to issuance of any permit.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Show and document all utility/access easements. Provide stationing to identify the location of the proposed public improvements. Cleary identify the individual lots.
Miscellaneous Correction
Corrective Action Required
05/24/2024

Please add a note to the plans stating: “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
Miscellaneous Correction
Corrective Action Required
05/24/2024

Label Existing MH A2 as 16-108.
Fees
Paid Fees Amount Paid Owing Date Paid
Sanitary Sewer Insp Fees $600.00 $600.00 Paid 10/29/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Punch List Inspection Pending
Site Visit Pending 3/18/2026
Misc
Corrective Action Required
10/31/2025
10-30-25 NS Site visited and it appears that Sewer Lid 16-125 has a storm water and needs to be a sewer lid. 10-31-25 NS Site Visted and it appears that no work is going on.
Erosion Control Inspection Partial 1/25/2025 01/25/2025
Misc
Informational
01/25/2025
1-10-25 NS Site Visited and grass has stopped growing since it is winter 1-16-25 NS Site Visited and grass has stopped growing since it is winter 1-24-25 NS Site Visited and grass has stopped growing since it is winter
Erosion Control Inspection Partial 2/24/2025 02/24/2025
Misc
Informational
01/25/2025
1-10-25 NS Site Visited and grass has stopped growing since it is winter 1-16-25 NS Site Visited and grass has stopped growing since it is winter 1-24-25 NS Site Visited and grass has stopped growing since it is winter 1-31-25 NS Site visited crews are not working because 2-3-25 NS Site Visited and still no erosion control issues 2-10-25 NS Site Visited and still no erosion control issues 2-17-25 NS Site Visited and still no erosion control issues 2-24-25 NS Site Visited and still no erosion control issues
Sanitary Sewer Construction Inspection Partial 2/26/2025 2/26/2025 02/27/2025
Misc
Informational
02/27/2025
2-26-25 DP. Aaron's crew with Advanced Excavation was onsite and began excavating for the sewer extension. They are in deep rock, so will be a slow process.
Sanitary Sewer Construction Inspection Partial 2/27/2025 2/27/2025 02/27/2025
Misc
Informational
02/27/2025
2-27-25 DP. Aaron's crew started the morning breaking rock, but their machine broke down. They are moving onto something else until next week.
Sanitary Sewer Construction Inspection Partial 3/6/2025 3/6/2025 03/06/2025
Misc
Informational
02/27/2025
2-27-25 DP. Aaron's crew started the morning breaking rock, but their machine broke down. They are moving onto something else until next week. 3-6-25 DP. Aaron's crew has started back laying the sewer extension. They have rose above rock so will be moving quicker.
Sanitary Sewer Construction Inspection Partial 3/7/2025 3/7/2025 03/07/2025
Misc
Informational
03/06/2025
2-27-25 DP. Aaron's crew started the morning breaking rock, but their machine broke down. They are moving onto something else until next week. 3-6-25 DP. Aaron's crew has started back laying the sewer extension. They have rose above rock so will be moving quicker. 3-7-25 DP. Aaron's crew finished running A line today. They set A1 and have backfilled while compacting in lifts. Today starts the 30 day wait on the extension before testing can begin.
Sanitary Sewer Construction Inspection Partial 4/18/2025 4/18/2025 04/18/2025
Misc
Informational
03/07/2025
2-27-25 DP. Aaron's crew started the morning breaking rock, but their machine broke down. They are moving onto something else until next week. 3-6-25 DP. Aaron's crew has started back laying the sewer extension. They have rose above rock so will be moving quicker. 3-7-25 DP. Aaron's crew finished running A line today. They set A1 and have backfilled while compacting in lifts. Today starts the 30 day wait on the extension before testing can begin. 4-18-25 DP. Testing can begin any time on the sewer extension. The required 30 day wait has lapsed.
Sanitary Sewer - Air Test Passed 6/12/2025 6/12/2025 06/13/2025
Misc
Informational
06/13/2025
6-12-25 DP. Advanced Excavation came back onsite and tested today. Air pressure test passed passed. It held for the required 7 minutes 34 seconds.
Sanitary - Material Verification Passed 4/1/2025 06/13/2025
Grading/Excavation/Fill Inspection Passed 4/1/2025 06/13/2025
Sanitary Sewer - Mandrel Passed 6/12/2025 6/12/2025 06/13/2025
Misc
Informational
06/13/2025
6-12-25 DP. Advanced Excavation was onsite yesterday and passed the mandrel test.
Sanitary Sewer Construction Inspection Passed 4/1/2025 06/13/2025
Misc
Informational
04/18/2025
2-27-25 DP. Aaron's crew started the morning breaking rock, but their machine broke down. They are moving onto something else until next week. 3-6-25 DP. Aaron's crew has started back laying the sewer extension. They have rose above rock so will be moving quicker. 3-7-25 DP. Aaron's crew finished running A line today. They set A1 and have backfilled while compacting in lifts. Today starts the 30 day wait on the extension before testing can begin. 4-18-25 DP. Testing can begin any time on the sewer extension. The required 30 day wait has lapsed.
Sanitary Sewer - Vacuum Passed 6/13/2025 6/13/2025 06/13/2025
Misc
Informational
06/13/2025
6-12-25 DP. Vacuum testing passed
Sanitary Sewer - Camera Test Partial 6/13/2025 6/13/2025 06/16/2025
Misc
Informational
06/16/2025
6-13-25 DP. Camera test scheduled for early next week.
Site Visit Partial 10/30/2025
Misc
Corrective Action Required
10/30/2025
10-30-25 NS Site visited and it appears that Sewer Lid 16-125 has a storm water and needs to be a sewer lid.
Site Visit Partial 10/30/2025 10/31/2025
Misc
Corrective Action Required
10/30/2025
10-30-25 NS Site visited and it appears that Sewer Lid 16-125 has a storm water and needs to be a sewer lid. 10-31-25 NS Site Visted and it appears that no work is going on.
Punch List Inspection Partial 12/16/2025 02/10/2026
Misc
Informational
02/09/2026
The areas that need attention, that will hold up the project. 1. Steet Names signs 2. Public sidewalks 3. Record Drawing/MDP Discovery Public Punch List. Updated 2-10-26 221 NE ALURA WAY, LEES SUMMIT, MO 64086 PRSUBD20242356 1. Streets & Pavement All street paving complete (Needs parking spots along road need to be installed) Street name signs installed per LS standard (Not completed) Has temp signs up, Needs permanent signs installed) Stripping & markings installed (if required) (PASSED) Curbs and gutters poured and backfilled with no gaps (Once Sidewalk is in and back filled) ADA ramps installed per LS detail and checked for slope (ADA sidewalk needs to be installed) Sidewalks poured, cured, and cleaned – no spalling or trip hazards (Sidewalk needs install) 2. Storm Sewer All inlets, manholes, and pipes installed, cleaned, and flowing (Clean at this time) No standing water in pipes or structures (Passed) Erosion control in place and functioning (Put up as plans say for area & repair any silt fence down) Final grade around inlets complete – (Not completed) Detention/retention basins shaped, seeded, stabilized (Seed was done 12-20-25) 3. Sanitary Sewer (Waiting on Water 2-10-26) Lines tested, televised, and passed (Passed) Manholes adjusted to final grade (Done, needing Waters approval) All punch items from video review corrected (Done, needing Waters approval) All services marked and mapped () 4. Water Main Main passed pressure and bacteria tests (Passed) All valves open and boxes flushed and raised to grade (Done, needing Waters approval) Hydrants installed per plan and painted (red or yellow as required) (passed) As-built water plans submitted to Water Utilities (NEEDED UPLOADED) 5. Grading & Drainage All final grading complete per approved plans (Appears not done until sidewalk is complete) Drainage swales shaped and flowing (Passed) No low spots or ponding around homes or ROW (Passed) Silt fence removed only after site is stabilized (NOT READY) 6. Street Lights Installed, working, and matches approved plans (Not completed) Power company confirmed service is on (N/A) 7. Signage & Striping All stop signs, street name signs, and regulatory signs installed (NEEDED Permeant signs installed) Fire lane striping (if required) complete (NOT REQUIRED) 8. Clean-up Trash, pallets, debris removed from ROW and common areas (active construction site) Silt fences removed once sod/seed is established (NOT REQUIRED) Sidewalks and driveways washed off (sidewalk has not been installed) Construction equipment off site (NOT REQUIRED) 9. As-Builts & Paperwork As-builts submitted and approved (PDF + CAD) (NEEDED) Contractor’s final testing reports submitted (NEEDED) Punchlist items documented and checked off (Not Completed) Request for Substantial Completion submitted in writing (NEEDED)
Documents & Images
Date Uploaded File Type Document Name
05/10/2024 Plans 230286 Village at Discovery Park - Lot 1 Sewer Extension s
05/10/2024 Letter Sewer Extension submittal letter
06/27/2024 Plans Sewer Extension Plans_PRSUBD20242356
06/27/2024 Engineers Estimate Engineers Cost Estimate_PRSUBD20242356
06/27/2024 Letter Response letter_PRSUBD20242356
07/24/2024 Plans Sewer Extension Plans_PRSUBD20242356
07/24/2024 Engineers Estimate Engineers Cost Estimate_PRSUBD20242356
07/24/2024 Letter Response Letter_PRSUBD20242356
07/24/2024 Plans Public Sewer Esmt Exhibit_PRSUBD20242356
08/26/2024 Engineers Estimate Engineers Cost Estimate_PRSUBD20242356
08/26/2024 Recorded Document Signed Sanitary Sewer Easement_PRSUBD20242356
08/26/2024 Letter Response Letter_PRSUBD2024356
09/04/2024 Activity Document Fee Worksheet Revisions_PRSUBD20242356
09/16/2024 Letter MDNR SANITARY CONCURRENCE LETTER_PRSUBD20242356
09/16/2024 Letter SUBD Comment Letter_PRSUBD20242356
09/18/2024 Letter MDNR Concurrence Letter - PRSUBD20242356 Sanitary Village at Discovery - Lot 1
10/29/2024 Receipt Receipt_PRSUBD20242356
11/05/2024 Approved Plans Stamped Approved Plans_PRSUBD20242356
01/25/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/07/2025 Letter INSPECTION SUMMARY
03/07/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
04/18/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/13/2025 Letter INSPECTION SUMMARY
06/16/2025 Letter INSPECTION SUMMARY
01/30/2026 Plans Sewer Extension Asbuilts_PRSUBD20242356
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
02/09/2026 Letter INSPECTION SUMMARY
03/19/2026 Approved Plans Stamped Approved Record Drawings_PRSUBD20242356
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home