Permit Application Status

PRSUBD20232899


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary


PRSUBD20232899
Public Infrastructure
Substantial Completion
DEVELOPMENT COMPLETE
RESIDENCES, RENUNION AND RESERVE AT BLACKWELL - PUBLIC INFRASTRUCTURE ASSOCIATED WITH THE CONSTRUCTION OF THE RESIDENTIAL DEVELOPMENT. THIS INCLUDES THE OVERALL MASS GRADING CONSTRUCTION OF SHENANDOAH DR AND ASSOCIATED STORM SEWER, THE PUBLIC WATER MAIN ALONG SHENANDOAH DR AND PUBLIC SANITARY. STOP WORK ORDER generated on 04/24/2025 12:00 AM by username 'Steve Robbins'. STOP WORK ORDER removed on 04/24/2025 12:00 AM by username 'Steve Robbins'.
06/20/2023
10/16/2024
Locations
Contacts
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
Selby Excavating LLC, Address:16212 Cameron Road  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 06/20/2023 07/24/2023
Mike Weisenborn
Fees
Paid Fees Amount Paid Owing Date Paid
9110071-Site Grading Fee $34,234.71 $34,234.71 Paid 06/23/2023
9110072-Water Test Fee $800.00 $800.00 Paid 10/26/2023
91100C9-Water Insp Fee $9,844.50 $9,844.50 Paid 10/26/2023
9110071-Site Grading Fee $2,176.08 $2,176.08 Paid 08/12/2024
$36,410.79
9110081-Paved Surface Inspection Fee $8,076.78 $8,076.78 Paid 10/15/2024
9110068-Storm Sewer Inspection Fee $2,467.80 $2,467.80 Paid 08/12/2024
91100C8-Sanitary Sewer Insp Fees $10,561.20 $10,561.20 Paid 05/09/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Grading/Excavation/Fill Inspection Pending
Sanitary - Material Verification Pending
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Pavement-Curb Construction Pending
Water Line - Coliform Test 2 Pending
Misc
Informational
03/20/2024
3-20-24 BR 2nd coliform sample was taking on 12'' water main.
Water Line - Coliform Test 2 Pending
Water Line - Construction Inspection Pending
Misc
Informational
04/08/2024
10-23-23 BR Contractor installed 200' of 12'' water main on Sta.14+50 - Sta.12+75 south east side of property. 10-31-23 BR Contractor installed 250' of 12'' water main on Sta.12+75 - Sta.11+00 11-1-23 BR Contractor installed 400' of 12'' water main on Sta. 11+00 - Sta. 7+00 11-6-23 BR Contractor installed 400' of 12'' water main on Sta. 7+00 - Sta. 3+50 11-8-23 BR Contractor installed 300' of 12'' water main on Sta.3+50 - Sta.0+75 11-9-23 BR Contractor installed 100' of 12'' water main line B Sta.0+00 - Sta.1+00 11-16-23 BR Contractor installed 400' of 12'' water main on line B Sta. 1+00 - Sta. 5+00 4-8-24 RH. Contractor started digging up for the 16" water line connection.
Sanitary Sewer Construction Inspection Pending
Misc
Informational
08/06/2024
5-15-24 JMJ Josh crew ran into heavy rock and manage to set MH A-7 and install two stick of pipe. 08-06-24 JMJ installed sanitary 8" SDR-26 pipe, but had to remove seven stick of wrongly align sanitary pipe. Lateral lines were installed on newly installed sanitary pipe.
Water Line - Coliform Test 1 Pending
Fire Line Construction Inspection Pending
Misc
Informational
10/15/2024
10-15-24 BR Contractor (Selby Excavation) replace a damage fire hydrant at Sta. 9+32 due to dirt crew hitting fire hydrant.
Water Line - Construction Inspection Pending
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Water Line - Hydrostatic Test Pending
Water Line - Hydrostatic Test Pending
Water Line - Hydrostatic Test Pending
Water Line - Hydrostatic Test Pending
Pavement-Surface Pending
Misc
Informational
03/27/2025
3-27-25BR Contractor (Seal-o-Matic) laid 2'' type 5 on the reminder roads Wood Ln.,5th ter., 6th st., Bradfree St., Golden Ln., Shenandoah Dr., & Lindberg Ln. 3 party tester on and asphalt base was 95% compaction.
Water Line - Construction Inspection Pending
Sanitary Sewer Construction Inspection Pending
Install Street and Stop Signs Pending
Pavement-Aggregate Base Pending
Pavement-Curb Construction Pending
Pavement-Stabilized Subgrade Pending
Site Visit Pending
Misc
Informational
05/19/2025
11-20-23 Dustin A, No work being done this morning due to rain, Dropping storm boxes off 8-23-24 NS Site visited and crews are working on installing storm boxes for 106 and 107 5-19-25 Dustin A, Not allot of work for us due to rain. Selby is cleaning out a storm inlet that got buried. All erosion control is up where it needs to be.
Erosion Control Inspection Pending
PW-Erosion and Sediment Control
Corrective Action Required
05/27/2025
Your project is in violation of the Erosion and Sediment control policy. Stop Work Order was issue on April 23, 2025.
Misc
Informational
05/27/2025
5-16-25 Dustin A, All erosion control measures that were requested by the city in order to move forward has been met. Erosion control measures need to be maintained throughout project. 5-27-25 Dustin A, ESC are still in place and is functional. I talked with Scott and nick on keeping shenandoah clean, nick is going to have his contractor clean the roads on his side at the end of each working day and get some waddles for the gravel that is piled on the road for the tele-belt.
Site Visit Partial 11/20/2023
Misc
Informational
11/20/2023
11-20-23 Dustin A, No work being done this morning due to rain, Dropping storm boxes off 12-12-23 Dustin A, Working on water main to ne installed so the temp road can go in. Will possibly install 200 ft today, also installing fire t's and putting the domestic sleeves on.
Water Line - Hydrostatic Test Passed 03/14/2024
Misc
Informational
03/13/2024
3-13-24 BR Contractor preformed a hydrostatic test on the public 12'' water main line A and B which it passed.
Water Line - Coliform Test 1 Passed 03/22/2024
Misc
Informational
03/19/2024
3-19-24 BR 1st coliform sample was taking on 12'' water main. 3-22-24 BR 1st coliform sample pass.
Water Line - Coliform Test 2 Passed 03/22/2024
Misc
Informational
03/20/2024
3-20-24 BR 2nd coliform sample was taking on 12'' water main. 3-22-24 BR 2nd coliform sample pass
Sanitary Sewer Construction Inspection Partial 06/11/2024
Misc
Informational
05/16/2024
5-15-24 JMJ Josh crew ran into heavy rock and manage to set MH A-7 and install two stick of pipe. 5-16-24 BR Contractor (selby excavation) installed 100' of 8'' PVC to MH A-8. 5-17-24 BR Contractor (selby excavation) installed MH A-8 structure and 25' of 8'' PVC pipe. 5-21-24 BR Contractor (selby excavation) installed 150' of 8'' PVC to MH A-9 and structure MH A-9 installed. Contractor also have CFS (Crook. Flatt, & Strobel) testing compaction on MH A-7 to MH A-8. 5-22-24 BR Contractor (selby excavation) installed 150' of 8'' PVC pipe from MH A-9. 5-23-24 BR Contractor (selby excavation) installed 100' of service wye from MH A-7 to MH A-9. 5-29-24 BR Contractor (selby excavation) installed 50' of 12'' PVC pipe from MH A-7 before running into heavy rock. Also 2nd crew installed 200' of 8' PVC to MH A-10. 5-30-24 BR Contractor (selby excavation) installed 200'' of 8'' PVC to MH A-10. MH A-10 structure is installed. 6-3-24 BR Contractor (selby excavation) installed 70' of 8'' PVC pipe from MH A-10. CFS tested compaction on MH A-8 to MH A-10. 2nd crew installed 200' of 12'' PVC pipe before running into heavy rock. 6-4-24 BR Contractor (selby excavation) installed 60' of 8'' PVC pipe to MH A-11. MH A-11 structure is installed. 6-11-24 BR Contractor (selby excavation) installed 25' of 12'' PVC pipe heading to MH A-6 well still breaking heavy rock. 6-12-24 BR Contractor (selby excavation) installed 70' of 12'' PVC pipe to MH A-6 and structure is installed.
Water Line - Hydrostatic Test Passed 10/15/2024
Misc
Informational
03/13/2024
3-13-24 BR Contractor preformed a hydrostatic test on the public 12'' water main line A and B which it passed.
Sanitary Sewer - Air Test Passed 12/17/2024 12/17/2024 12/17/2024
Misc
Informational
12/17/2024
12/17/24 Tuesday JMJ (Selby Construction) Air test passed from MH-A10 to A9, A9 to A8, A8 to A7.
Water Line - Construction Inspection Passed 1/27/2025 1/27/2025 01/27/2025
Misc
Informational
11/16/2023
10-23-23 BR Contractor installed 200' of 12'' water main on Sta.14+50 - Sta.12+75 south east side of property. 10-31-23 BR Contractor installed 250' of 12'' water main on Sta.12+75 - Sta.11+00 11-1-23 BR Contractor installed 400' of 12'' water main on Sta. 11+00 - Sta. 7+00 11-6-23 BR Contractor installed 400' of 12'' water main on Sta. 7+00 - Sta. 3+50 11-8-23 BR Contractor installed 300' of 12'' water main on Sta.3+50 - Sta.0+75 11-9-23 BR Contractor installed 100' of 12'' water main line B Sta.0+00 - Sta.1+00 11-16-23 BR Contractor installed 400' of 12'' water main on line B Sta. 1+00 - Sta. 5+00 4-8-24 RH. Contractor started digging up for the 16" water line connection. 1-25-25 NS/BR Contractor lowered 12" water main line B on SHENANDOAH DRIVE at Sta. 1+00 - Sta. 2+55 with 22.5 bend with backing blocks. The line was flush and put back in service.
Water Line - Construction Inspection Passed 01/27/2025
Misc
Informational
10/24/2023
10-23-23 BR Contractor installed 200' of 12'' water main on Sta.14+50 - Sta.12+75 south east side of property. 10-31-23 BR Contractor installed 250' of 12'' water main on Sta.12+75 - Sta.11+00 11-1-23 BR Contractor installed 400' of 12'' water main on Sta. 11+00 - Sta. 7+00 11-6-23 BR Contractor installed 400' of 12'' water main on Sta. 7+00 - Sta. 3+50 11-8-23 BR Contractor installed 300' of 12'' water main on Sta.3+50 - Sta.0+75 11-9-23 BR Contractor installed 100' of 12'' water main line B Sta.0+00 - Sta.1+00 11-16-23 BR Contractor installed 400' of 12'' water main on line B Sta. 1+00 - Sta. 5+00
Water Line - Construction Inspection Passed 01/27/2025
Misc
Informational
10/24/2023
10-23-23 BR Contractor installed 200' of 12'' water main on Sta.14+50 - Sta.12+75 south east side of property. 10-31-23 BR Contractor installed 250' of 12'' water main on Sta.12+75 - Sta.11+00 11-1-23 BR Contractor installed 400' of 12'' water main on Sta. 11+00 - Sta. 7+00 11-6-23 BR Contractor installed 400' of 12'' water main on Sta. 7+00 - Sta. 3+50
Water Line - Construction Inspection Passed 1/30/2025 1/30/2025 02/04/2025
Misc
Informational
11/07/2023
10-23-23 BR Contractor installed 200' of 12'' water main on Sta.14+50 - Sta.12+75 south east side of property. 10-31-23 BR Contractor installed 250' of 12'' water main on Sta.12+75 - Sta.11+00 11-1-23 BR Contractor installed 400' of 12'' water main on Sta. 11+00 - Sta. 7+00 11-6-23 BR Contractor installed 400' of 12'' water main on Sta. 7+00 - Sta. 3+50 11-8-23 BR Contractor installed 300' of 12'' water main on Sta.3+50 - Sta.0+75 11-9-23 BR Contractor installed 100' of 12'' water main line B Sta.0+00 - Sta.1+00 11-16-23 BR Contractor installed 400' of 12'' water main on line B Sta. 1+00 - Sta. 5+00 and fire hydrant was installed at Sta. 4+44. 11-17-23 BR Contractor installed 200' of 12'' water main on line B Sta. 5+00 - Sta. 7+00 2-1-24 BR Contractor installed 230' of 12'' water main on line B Sta. 7+00 - Sta. 9+32 and installed fire hydrant at 9+32. 2-2-24 BR Contractor installed 200' of 12'' water main on line B Sta. 9+32 - 10+89. Contractor installed 12x8 tee at Sta. 10+31 also. 2-9-24 BR I informed the contractor to installed all threats on 12'' water main at were they have 45 bends for more stability at every 45 bends on the water mains. 2-13-24 BR Contractor installed all threats on 45 bends on the water main. Also contractor poured backing blocks at all bends and tees on water main. 2-20-24 BR Contractor installed fire hydrant at STA. 12+02 on the 12'' water main. Also contractor installed air release valve at STA. 10+38 on water main. 2-29-24 BR Contractor installed 300' of 12'' water main to final connection to existing 12'' water main. At STA. 0+19 1st 45 bend was install, STA. 0+14 2nd 45 bend was installed. At STA. 0+05 90 bend was installed for final connection. 3-14-24 BR Contractor started chlorination on 12'' water main. 3-18-24 BR Contractor flush the 12'' water main. 3-26-24 BR Contractor connected new 12'' water main line A to existing 12'' water main at STA. 0+00. 12'' water main line A was flush. 1-29-25 BR Contractor final connected 12'' water main line A to existing 16'' water at Sta. 15+18. The 12'' & 16'' was flush and back in service. Contractor needs to add vertical thrust block to 12'' water bends. 2-3-25 JMJ/BR Contractor installed vertical thrust block on 12'' water main bend.
Site Visit Partial 2/21/2025 2/21/2025 02/21/2025
Misc
Informational
11/20/2023
11-20-23 Dustin A, No work being done this morning due to rain, Dropping storm boxes off 8-23-24 NS Site visited and crews are working on installing storm boxes for 106 and 107 10-29-24 BR Spoke with developer on the items that need to be done before they can start pouring foundation slaps on Reunion section of project. The items are complete and passing sanitary connection and tests with passing water testing of all water main. 2-21-25 BR No activity on site do to weather conditions
Sanitary Sewer - Vacuum Passed 12/17/2024 12/17/2024 02/26/2025
Misc
Informational
12/16/2024
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM. 12/17/24 Tuesday JMJ (Selby Construction) MH-A8 passed on 12/16/24 Monday.
Sanitary Sewer - Vacuum Passed 12/16/2024 12/16/2024 02/26/2025
Misc
Informational
12/16/2024
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM.
Fire Line Construction Inspection Passed 10/16/2024 10/16/2024 02/26/2025
Misc
Informational
10/15/2024
10-15-24 BR Contractor (Selby Excavation) replace a damage fire hydrant at Sta. 9+32 due to dirt crew hitting fire hydrant. 10-16-24 BR Contractor (Selby Excavation) replace a damage fire hydrant at Sta. 11+30 due to dirt crew hitting fire hydrant. 2-25-25 BR Fire hydrant was tested and put back into service.
Sanitary Sewer - Mandrel Partial 3/3/2025 3/3/2025 03/03/2025
Misc
Informational
12/17/2024
12/17/24 Tuesday JMJ (Selby Construction - Tucker) Mandrel test passed MHA-10 to A9, A9 to A8, A8 to A7 2-26-25 BR Selby Excavation preformed a mandrel test on MH B-1 to MH B-2 on 24'' PVC line passed. 3-3-25 BR Selby Excavation preformed a mandrel test on MH B-2 to MH B-3 on 24'' PVC line passed.
Sanitary Sewer - Vacuum Partial 3/3/2025 3/3/2025 03/03/2025
Misc
Informational
12/17/2024
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM. 12/17/24 Tuesday JMJ (Selby Construction) MH-A8 passed on 12/16/24 Monday. 12/18/24 Wednesday JMJ (Selby Construction) MH-A7 passed on 12/17/24 Tuesday. 2-26-25 BR Contractor (Selby Excavation) preformed vacuum test on MH B-2 passed. MH B-1 failed. 2-27-25 BR Contractor (Selby Excavation) preformed vacuum test on MH B-1 passed. 3-3-25 BR Selby Excavation preformed vacuum test on MH B-3 passed.
Pavement-Stabilized Subgrade Partial 3/18/2025 3/18/2025 03/18/2025
Misc
Informational
11/14/2024
11-14-24 BR Contractor installed 9'' subgrade aggregate base on Shenandoah Dr.. 11-19-24 BR Contractor installed 9'' subgrade aggregate base on Lindberg Ln., Golden Ln., 5th Terr., 6th St., Highland Park Dr., wood Ln. 3-18-25 BR Contractor (selby excavation) is recompacting and adding aggregate to base on Shenandoah Dr., Lindberg Ln., Golden Ln., 5th Ter., 6th St., Highland Park Dr., SE Wood Ln., SE Lincoln St.,
Sanitary Sewer Construction Inspection Partial 3/20/2025 3/20/2025 03/20/2025
Misc
Informational
05/16/2024
5-15-24 JMJ Josh crew ran into heavy rock and manage to set MH A-7 and install two stick of pipe. 08-06-24 JMJ installed sanitary 8" SDR-26 pipe, but had to remove seven stick of wrongly align sanitary pipe. Lateral lines were installed on newly installed sanitary pipe. 12-12-24 BR Contractor installed MH B-2 with 100' of 24'' PVC from MH B-2 heading to MH B-1. 12-13-24 BR Contractor installed 200' of 24'' PVC pipe heading to MH B-1. 12-17-24 BR Contractor installed 150' of 24'' PVC pipe before running to heavy rock before the pond outfall basin. 1-15-25 BR Contractor installed 50' of 24' PVC pipe to MH B-2. Also contractor excavated ex. 16'' PVC pipe and cut encasement that was around ex.16'' PVC pipe to get it prepared for connection of bypass pipe. 1-22-25 BR Contractor installed aggerate and rebar to pond outfall on section that was remove to installed 24'' PVC pipe. 1-24-25 BR Contractor poured concrete on pond outfall section and 4 columns that was remove for new 24'' PVC pipe. 2-14-25 BR Contractor installed hard bypass 15'' PVC pipe (for temporary) to remove exiting 15'' PVC pipe for new MH B-1. 2-24-25 BR Contractor installed MH B-1 structure with 25' of 24'' PVC to MH B-1. 2-26-25 BR Contractor remove hard (temporary) bypass and tie-in to MH B-1 to existing manhole with 16" PVC pipe. 2-28-25 BR Contractor (Selby Excavation) installed MH B-3 and connected to existing sewer main all so removed existing MH 65-092 structure plus abandoned ex. 8'' sewer main. 3-11-25 BR Contractor (Selby Excavation) added flowable fill to abandoned 8'' main and grout 8'' main in existing MH 65-226. 3-19-25 BR Contractor (Selby Excavation) added adjusted rings to several manholes on Lindberg Ln., Golden Ln., Highland Park Dr., Wood lane, & 5th Ter.
Pavement-Proof Roll Passed 3/20/2025 3/20/2025 03/20/2025
Misc
Informational
03/20/2025
3-20-25 BR Contractor preformed a proof roll on Shenandoah Dr., Lindberg Ln., 5th Ter., Highland Park Dr., SE Wood Ln., with a pass.
Pavement-Aggregate Base Passed 3/26/2025 3/26/2025 03/27/2025
Misc
Informational
03/24/2025
3-21-25 DP/BR Contactor (Seal-o-Matic) 4'' type 5 on Wood Ln. & 1/2 of 5th Ter. Contractor did have 3rd party tester on site and base compaction was 95%. 3-26-25nBR Contractor (Seal-o-Matic) laid 4'' type 5 on the reminder roads Wood Ln.,5th ter., 6th st., Bradfree St., Golden Ln., Shenandoah Dr., & Lindberg Ln. 3 party tester on and asphalt base was 95% compaction.
Pavement-Surface Partial 3/27/2025 3/27/2025 03/27/2025
Misc
Informational
03/27/2025
3-27-25BR Contractor (Seal-o-Matic) laid 2'' type 5 on the reminder roads Wood Ln.,5th ter., 6th st., Bradfree St., Golden Ln., Shenandoah Dr., & Lindberg Ln. 3 party tester on and asphalt base was 95% compaction.
Sanitary Sewer - Air Test Partial 4/16/2025 4/16/2025 04/16/2025
Misc
Informational
02/26/2025
2-26-25 BR Contractor (Selby Excavation) preformed air test on 24'' PVC pipe between MH B-1 to MH B-2 passed. 3-3-25 BR Contractor (Selby Excavation) preformed air test on 24'' PVC between MH B-2 to MH B-3 passed. 4-16-25 BR Contractor (Selby Excavation) preformed air test on 12'' PVC between MH A-6 to MH A-5, MH A-5 to MH A-4 pass.
Erosion Control Inspection Failed - Stop Work 4/24/2025 04/24/2025
PW-Erosion and Sediment Control
Corrective Action Required
04/24/2025
Your project is in violation of the Erosion and Sediment control policy. Stop Work Order was issue on April 23, 2025.
Sanitary Sewer - Vacuum Partial 04/29/2025
Misc
Informational
12/18/2024
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM. 12/17/24 Tuesday JMJ (Selby Construction) MH-A8 passed on 12/16/24 Monday. 12/18/24 Wednesday JMJ (Selby Construction) MH-A7 passed on 12/17/24 Tuesday. 4-28-25 RH. Selby Construction MH-A6 Passed MH-A5 Failed MH-A4 Passe MH-A3 Top is Offset and needs to be fixed prior to testing
Sanitary Sewer - Mandrel Partial 04/29/2025
Misc
Informational
12/17/2024
12/17/24 Tuesday JMJ (Selby Construction - Tucker) Mandrel test passed MHA-10 to A9, A9 to A8, A8 to A7 4-28-25 RH. Selby MH A6-A7 Passed MH A5-A6 Passed MH A4-A5 Passed MH A3-A4 Passed MH A2-A3 Failed. Mandrel got stuck 5' into the test.
Sanitary Sewer - Air Test Partial 04/29/2025
Misc
Informational
02/26/2025
2-26-25 BR Contractor Selby Excavation preformed air test on 24'' PVC pipe between MH A-1 to MH A-2 passed. 4-28-25 RH MH A3-A4 Passed MH A2-A3 not tested due to mandrel fail
Sanitary Sewer - Vacuum Partial 05/02/2025
Misc
Informational
04/29/2025
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM. 12/17/24 Tuesday JMJ (Selby Construction) MH-A8 passed on 12/16/24 Monday. 12/18/24 Wednesday JMJ (Selby Construction) MH-A7 passed on 12/17/24 Tuesday. 4-28-25 RH. Selby Construction MH-A6 Passed MH-A5 Failed MH-A4 Passe MH-A3 Top is Offset and needs to be fixed prior to testing 5-2-25 RH Selby Constuction MH-A1 Passed MH-A2 Passed Contractor is now going to be working on fixing failures form 4-28-25
Sanitary Sewer - Mandrel Partial 05/02/2025
Misc
Informational
04/29/2025
12/17/24 Tuesday JMJ (Selby Construction - Tucker) Mandrel test passed MHA-10 to A9, A9 to A8, A8 to A7 4-28-25 RH. Selby MH A6-A7 Passed MH A5-A6 Passed MH A4-A5 Passed MH A3-A4 Passed MH A2-A3 Failed. Mandrel got stuck 5' into the test. 5-2-25 RH. Selby MH A1-A0 Passed MH A2-A1 Passed
Sanitary Sewer - Air Test Partial 05/02/2025
Misc
Informational
04/29/2025
2-26-25 BR Contractor Selby Excavation preformed air test on 24'' PVC pipe between MH A-1 to MH A-2 passed. 4-28-25 RH MH A3-A4 Passed MH A2-A3 not tested due to mandrel fail 5-2-25 RH MH A1-A0 Passed MH A2-A1 Passed
Sanitary Sewer - Vacuum Partial 05/06/2025
Misc
Informational
05/02/2025
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM. 12/17/24 Tuesday JMJ (Selby Construction) MH-A8 passed on 12/16/24 Monday. 12/18/24 Wednesday JMJ (Selby Construction) MH-A7 passed on 12/17/24 Tuesday. 4-28-25 RH. Selby Construction MH-A6 Passed MH-A5 Failed MH-A4 Passe MH-A3 Top is Offset and needs to be fixed prior to testing 5-2-25 RH Selby Constuction MH-A1 Passed MH-A2 Passed Contractor is now going to be working on fixing failures form 4-28-25 MH-A5 Passed
Sanitary Sewer - Air Test Passed 05/07/2025
Misc
Informational
05/02/2025
2-26-25 BR Contractor Selby Excavation preformed air test on 24'' PVC pipe between MH A-1 to MH A-2 passed. 4-28-25 RH MH A3-A4 Passed MH A2-A3 not tested due to mandrel fail 5-2-25 RH MH A1-A0 Passed MH A2-A1 Passed 5-7-25 Dustin A, MH A2-A3 has passed air test
Sanitary Sewer - Mandrel Passed 5/7/2025 5/7/2025 05/07/2025
Misc
Informational
05/02/2025
12/17/24 Tuesday JMJ (Selby Construction - Tucker) Mandrel test passed MHA-10 to A9, A9 to A8, A8 to A7 4-28-25 RH. Selby MH A6-A7 Passed MH A5-A6 Passed MH A4-A5 Passed MH A3-A4 Passed MH A2-A3 Failed. Mandrel got stuck 5' into the test. 5-2-25 RH. Selby MH A1-A0 Passed MH A2-A1 Passed 5-7-25 Dustin A, MH A2-A3 has passed
Sanitary Sewer - Vacuum Passed 5/7/2025 5/7/2025 05/07/2025
Misc
Informational
05/06/2025
12/13/24 Friday JMJ (Selby) MH-A10 passed around 12:00PM. MH-A9 passed @ 1:35PM. 12/17/24 Tuesday JMJ (Selby Construction) MH-A8 passed on 12/16/24 Monday. 12/18/24 Wednesday JMJ (Selby Construction) MH-A7 passed on 12/17/24 Tuesday. 4-28-25 RH. Selby Construction MH-A6 Passed MH-A5 Failed MH-A4 Passe MH-A3 Top is Offset and needs to be fixed prior to testing 5-2-25 RH Selby Constuction MH-A1 Passed MH-A2 Passed Contractor is now going to be working on fixing failures form 4-28-25 MH-A5 Passed 5-7-25 Dustin A, MH A2-A3 has passed
Storm Sewer Construction Inspection Passed 05/08/2025
Misc
Informational
05/08/2025
All storm sewer is in.
Erosion Control Inspection Partial 5/13/2025 5/13/2025 05/13/2025
Misc
Corrective Action Required
05/13/2025
5-13-25 Dustin A, curb lines and streets still need to be cleaned. Still some trash and debris throughout site. Trash still in some of the ponds. Green storage tank still not protected.
Erosion Control Inspection Partial 5/16/2025 5/16/2025 05/16/2025
PW-Erosion and Sediment Control
Corrective Action Required
05/13/2025
Your project is in violation of the Erosion and Sediment control policy. Stop Work Order was issue on April 23, 2025.
Misc
Informational
05/16/2025
5-16-25 Dustin A, All erosion control measures that were requested by the city in order to move forward has been met. Erosion control measures need to be maintained throughout project.
Site Visit Partial 5/19/2025 5/19/2025 05/19/2025
Misc
Informational
08/23/2024
11-20-23 Dustin A, No work being done this morning due to rain, Dropping storm boxes off 8-23-24 NS Site visited and crews are working on installing storm boxes for 106 and 107 5-19-25 Dustin A, Not allot of work for us due to rain. Selby is cleaning out a storm inlet that got buried. All erosion control is up where it needs to be.
Erosion Control Inspection Partial 5/27/2025 5/27/2025 05/27/2025
PW-Erosion and Sediment Control
Corrective Action Required
05/16/2025
Your project is in violation of the Erosion and Sediment control policy. Stop Work Order was issue on April 23, 2025.
Misc
Informational
05/16/2025
5-16-25 Dustin A, All erosion control measures that were requested by the city in order to move forward has been met. Erosion control measures need to be maintained throughout project. 5-27-25 Dustin A, ESC are still in place and is functional. I talked with Scott and nick on keeping shenandoah clean, nick is going to have his contractor clean the roads on his side at the end of each working day and get some waddles for the gravel that is piled on the road for the tele-belt.
Water Line - Coliform Test 1 Partial 6/9/2025 6/9/2025 06/09/2025
Misc
Informational
03/19/2024
3-19-24 BR 1st coliform sample was taking on 12'' water main. 06-09-25 Jamie S, Preformed 6 water samples at site on new construction taps and delivered to Blue Valley Labs.
Documents & Images
Date Uploaded File Type Document Name
06/20/2023 Approved Plans RELEASED FOR CONSTRUCTION
06/23/2023 Receipt Receipt for transaction: 2023-004770
07/24/2023 Letter DE-Permit
10/18/2023 Approved Plans STAMPED CONSTRUCTION PLANS
10/24/2023 Letter INSPECTION SUMMARY
10/26/2023 Receipt Receipt for transaction:2023-008086
10/26/2023 Letter DE-Permit
10/31/2023 Letter INSPECTION SUMMARY
11/07/2023 Letter INSPECTION SUMMARY
11/10/2023 Letter INSPECTION SUMMARY
11/16/2023 Letter INSPECTION SUMMARY
11/20/2023 Letter INSPECTION SUMMARY
11/20/2023 Letter INSPECTION SUMMARY
02/05/2024 Activity Document FeeWorksheetResidencesBlackwellStreetStorm0
02/06/2024 Letter INSPECTION SUMMARY
02/14/2024 Letter INSPECTION SUMMARY
02/20/2024 Letter INSPECTION SUMMARY
02/29/2024 Letter INSPECTION SUMMARY
03/13/2024 Letter INSPECTION SUMMARY
03/14/2024 Letter INSPECTION SUMMARY
03/14/2024 Letter INSPECTION SUMMARY
03/18/2024 Letter INSPECTION SUMMARY
03/19/2024 Letter INSPECTION SUMMARY
03/20/2024 Letter INSPECTION SUMMARY
03/22/2024 Letter INSPECTION SUMMARY
03/22/2024 Letter INSPECTION SUMMARY
03/26/2024 Letter INSPECTION SUMMARY
04/08/2024 Letter INSPECTION SUMMARY
04/10/2024 Water test Sample - 1
04/10/2024 Water test Sample - 2
05/09/2024 Approved Plans APPROVED PUBLIC SANITARY PLANS_REV 0_PL2022416
05/09/2024 Receipt Receipt for transaction:2024-003232
05/10/2024 Letter DE-Permit
05/16/2024 Letter INSPECTION SUMMARY
05/17/2024 Letter INSPECTION SUMMARY
05/21/2024 Letter INSPECTION SUMMARY
05/22/2024 Letter INSPECTION SUMMARY
05/23/2024 Letter INSPECTION SUMMARY
05/29/2024 Letter INSPECTION SUMMARY
05/30/2024 Letter INSPECTION SUMMARY
06/03/2024 Letter INSPECTION SUMMARY
06/04/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
08/06/2024 Letter INSPECTION SUMMARY
08/12/2024 Receipt Receipt for transaction:2024-006811
08/13/2024 Letter DE-Permit
08/23/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
08/23/2024 Letter INSPECTION SUMMARY
10/15/2024 Letter INSPECTION SUMMARY
10/15/2024 Letter INSPECTION SUMMARY
10/15/2024 Receipt Receipt for transaction:2024-008354
10/16/2024 Letter DE-Permit
10/16/2024 Letter INSPECTION SUMMARY
10/16/2024 Letter INSPECTION SUMMARY
10/29/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/14/2024 Letter INSPECTION SUMMARY
11/19/2024 Letter INSPECTION SUMMARY
11/19/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/16/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
12/17/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/15/2025 Letter INSPECTION SUMMARY
01/24/2025 Letter INSPECTION SUMMARY
01/24/2025 Letter INSPECTION SUMMARY
01/27/2025 Letter INSPECTION SUMMARY
01/27/2025 Letter INSPECTION SUMMARY
01/27/2025 Letter INSPECTION SUMMARY
01/27/2025 Letter INSPECTION SUMMARY
01/30/2025 Letter INSPECTION SUMMARY
01/30/2025 Letter INSPECTION SUMMARY
02/04/2025 Letter INSPECTION SUMMARY
02/04/2025 Letter INSPECTION SUMMARY
02/14/2025 Hard bypass pipe 15'' to 16'' pvc on MH B-1 to ex_ MH 65-226
02/14/2025 Letter INSPECTION SUMMARY
02/14/2025 Letter INSPECTION SUMMARY
02/21/2025 Letter INSPECTION SUMMARY
02/21/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/24/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/26/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/27/2025 Letter INSPECTION SUMMARY
02/28/2025 Letter INSPECTION SUMMARY
02/28/2025 Letter INSPECTION SUMMARY
03/03/2025 Letter INSPECTION SUMMARY
03/03/2025 Letter INSPECTION SUMMARY
03/03/2025 Letter INSPECTION SUMMARY
03/03/2025 Letter INSPECTION SUMMARY
03/03/2025 Letter INSPECTION SUMMARY
03/03/2025 Letter INSPECTION SUMMARY
03/11/2025 Letter INSPECTION SUMMARY
03/11/2025 Letter INSPECTION SUMMARY
03/18/2025 Letter INSPECTION SUMMARY
03/18/2025 Letter INSPECTION SUMMARY
03/20/2025 Letter INSPECTION SUMMARY
03/20/2025 Letter INSPECTION SUMMARY
03/20/2025 Letter INSPECTION SUMMARY
03/24/2025 Letter INSPECTION SUMMARY
03/26/2025 Letter INSPECTION SUMMARY
03/26/2025 Letter INSPECTION SUMMARY
03/27/2025 Letter INSPECTION SUMMARY
03/27/2025 Letter INSPECTION SUMMARY
03/27/2025 Letter INSPECTION SUMMARY
04/16/2025 Letter INSPECTION SUMMARY
04/16/2025 Letter INSPECTION SUMMARY
04/24/2025 Letter Stop Work Order
04/29/2025 Letter INSPECTION SUMMARY
04/29/2025 Letter INSPECTION SUMMARY
04/29/2025 Letter INSPECTION SUMMARY
04/29/2025 Letter INSPECTION SUMMARY
04/29/2025 Letter INSPECTION SUMMARY
05/02/2025 Letter INSPECTION SUMMARY
05/02/2025 Letter INSPECTION SUMMARY
05/02/2025 Letter INSPECTION SUMMARY
05/06/2025 Letter INSPECTION SUMMARY
05/07/2025 Letter INSPECTION SUMMARY
05/07/2025 Letter INSPECTION SUMMARY
05/07/2025 Letter INSPECTION SUMMARY
05/08/2025 Letter INSPECTION SUMMARY
05/13/2025 Letter INSPECTION SUMMARY
05/16/2025 Letter INSPECTION SUMMARY
05/19/2025 Letter INSPECTION SUMMARY
05/30/2025 Residences at Blackwell
05/30/2025 Letter DE-Certificate of Substantial Completion Single Lot
06/02/2025 Blackwell ESC inspection 051225 (5_12_2025) KARA
06/02/2025 Blackwell SWPPs Map (5_12_25) WELCH
06/02/2025 Blackwell SWPPs Report (5_12_2025) WELCH
06/02/2025 Blackwell SWPPS Map (5_19_2025) WELCH
06/02/2025 Blackwell SWPPs Rain event (5_20_2025) WELCH
06/02/2025 Blackwell SWPPS Report (5_19_2025) WELCH
06/02/2025 Blackwell SWPPs report 5_27_2025 (WELCH)
06/02/2025 Blackwell ESC inspection 6_2_2025 (KARA)
06/04/2025 Blackwell SWPPs Report 6_2_2025 (Welch)
06/09/2025 Letter INSPECTION SUMMARY
06/09/2025 Blackwell SWPPs Report 6_9_2025 (WELCH)
06/09/2025 Blackwell SWPPs report 6_4_2025 (WELCH)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home