Permit Application Status

PRRES20240701


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20240701
Building Permit - Residential
Issued
NEW DUPLEX
NEW DUPLEX. UNFINISHED BASEMENT. STOP WORK ORDER generated on 06/10/2024 12:00 AM by username 'Shawn Hoffman'. STOP WORK ORDER removed on 06/10/2024 12:00 AM by username 'Shawn Hoffman'. STOP WORK ORDER generated on 06/10/2024 12:00 AM by username 'Shawn Hoffman'. STOP WORK ORDER removed on 06/12/2024 12:00 AM by username 'Robb Popp'.
02/19/2024
05/09/2024
Locations
Contacts
ORCHARD PARK DEVELOPMENT LLC, Address:8 SW AA HWY, Phone:(816) 405-6688  
James Edward Tompkins, Address:612 NW Kay Dr, Phone:(816) 525-9833  
CLIMATE RESTORATION SERVICES LLC, Address:PO BOX 574, Phone:(816) 694-8164  
PREMIER ELECTRIC & LIGHTING DESIGN, Address:PO BOX 1311, Phone:(816) 564-7660  
HOWERTON PLUMBING LLC, Address:195 NW AA HWY, Phone:(816) 694-0303  
daburton@mail.com  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Duplex $2,240.42 $2,240.42 Paid 05/09/2024
8331401-Water Tap Fee $7,520.00 $7,520.00 Paid 05/09/2024
8350015-Water Meter Fee $1,360.92 $1,360.92 Paid 05/09/2024
8331507-Sanitary Sewer Development Fee $4,318.00 $4,318.00 Paid 05/09/2024
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 05/09/2024
7232302-Residential License Tax Fee $1,240.32 $1,240.32 Paid 05/09/2024
Outstanding Fees Amount Paid Owing Date Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid
9110080-Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$525.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Foundation Inspection - Commercial Pending
Underslab Electrical Inspection - Residential Pending
Electrical Service Inspection Pending
Occupancy Inspection - Codes Residential Pending
Gas Service Inspection - Residential Pending
Erosion Control Inspection Residential Pending
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/04/2025
2/4/25 EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -Provide erosion control methods at perimeter -Maintain gravel filter with min 6" lift of min 3/4" gravel -Clean silt and debris from street
Rated Assembly Inspection Pending
Misc
Corrective Action Required
03/28/2025
3/13/25 -Inspection for firewall "pre rock" only: *Mechanical chases ok both units *Unit 211 -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 **Incomplete throughout (Required at boxes on both sides of walls, putty packs must cover entire box) *Unit 213 -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 **Incomplete throughout (Required at boxes on both sides of walls, putty packs must cover entire box)
All Rough Inspection - Residential Pending
Misc
Corrective Action Required
03/28/2025
**1/22/25 Inspection incomplete. Correct the following items before further inspections: Unit 211 -Provide properly addressed, complete, updated, stamped plans for inspection -Complete all fireblocking throughout, including fur downs, ceiling lines, between floors and vertically at max 10' oc at double walls per R302.11 -Protect openings in firewall per code at fridge box, electrical boxes etc. per R302.4.2 -Install anchor bolts in middle third of plates -Tighten anchor bolts -Address sole plates not completely bearing on stem walls in garage -Uncover all exterior braced wall panels for inspection -Nail straps at PFH -Correct sheet rock in mechanical chase missing behind duct work, not fastened, gapped greater than 1/4" and missing behind dwv -Strap all over bored top plates per code -Correct joists bored closer than 2" from top or bottom and closer than 2" together -Complete basement bathroom -Complete gas and electrical and schedule associated inspections with all rough
Misc
Corrective Action Required
03/28/2025
***3/28/25 Not Ready. Inspection incomplete. Still no plans on site, these items still not addressed per previous inspection: -Provide properly addressed, complete, updated, stamped plans for inspection -Complete all fireblocking throughout, including fur downs, ceiling lines, between floors and vertically at max 10' oc at double walls per R302.11-Missing at attic space walls, missing at ceiling lines, etc. -Protect openings in firewall per code at fridge box, electrical boxes etc. per R302.4.2 -Address sole plates not completely bearing on stem walls in garage -Uncover all exterior braced wall panels for inspection -Nail straps at PFH -Correct sheet rock in mechanical chase missing behind duct work, not fastened, gapped greater than 1/4" and missing behind dwv -Strap all over bored top plates per code -Correct joists bored closer than 2" from top or bottom and closer than 2" together -Complete gas and electrical and schedule associated inspections with all rough-Inspections not scheduled, only 3lbs of pressure at gas line, electrical not inspected
Underslab Plumbing Inspection - Residential Failed - Stop Work 6/10/2024 6/10/2024 06/10/2024
Misc
Corrective Action Required
06/10/2024
STOP WORK - NO FOOTING INSPECTION ON FILE.
Footing Inspection - Residential Passed 6/12/2024 6/12/2024 06/12/2024
Misc
Informational
06/12/2024
Approved by David Ainsworth on 5/28/24
Erosion Control Inspection Residential Failed 06/12/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/12/2024
6/12/24 DEFICIENT EROSION CONTROL INSTALLATION. -Provide erosion control methods at lot entry to west of building
Underslab Plumbing Inspection - Residential Failed 6/13/2024 6/13/2024 06/13/2024
Misc
Corrective Action Required
06/10/2024
BACKFILL AROUND FOUNDATION FOR ACCESS TO UNDERSLAB PLUMBING
Erosion Control Inspection Residential Failed 06/13/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/12/2024
6/13/24 DEFICIENT EROSION CONTROL INSTALLATION. -Provide erosion control methods at lot entry to west of building
Underslab Plumbing Inspection - Residential Passed 6/18/2024 6/18/2024 06/18/2024
Misc
Resolved
06/18/2024
BACKFILL AROUND FOUNDATION FOR ACCESS TO UNDERSLAB PLUMBING
Erosion Control Inspection Residential Failed 06/18/2024
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
06/13/2024
6/18/24 -Remove loose trash from site -Gravel filter to extend to min of 12 feet and be min 6" lift of min 3/4" gravel
Water Service Inspection - R Partial 12/17/2024 12/17/2024 12/17/2024
Misc
Informational
12/17/2024
Pex ran from foundation both units
Water Service Inspection - R Partial 12/18/2024 12/18/2024 12/18/2024
Misc
Informational
12/17/2024
Pex ran from foundation 213 211 Approved
Sewer Service Inspection - R Passed 12/18/2024 12/18/2024 12/18/2024
Misc
Informational
12/18/2024
211 and 213
Water Service Inspection - R Passed 1/2/2025 1/2/2025 01/02/2025
Misc
Resolved
01/02/2025
Pex ran from foundation 213 211 Approved
Gas Service Inspection - Residential Failed 1/22/2025 01/22/2025
All Rough Inspection - Residential Failed 1/22/2025 1/22/2025 01/22/2025
Misc
Corrective Action Required
01/22/2025
Inspection incomplete. Correct the following items before further inspections: Unit 211 -Provide properly addressed, complete, updated, stamped plans for inspection -Complete all fireblocking throughout, including fur downs, ceiling lines, between floors and vertically at max 10' oc at double walls per R302.11-Missing at attic space -Protect openings in firewall per code at fridge box, electrical boxes etc. per R302.4.2 -Install anchor bolts in middle third of plates -Tighten anchor bolts -Address sole plates not completely bearing on stem walls in garage -Uncover all exterior braced wall panels for inspection -Nail straps at PFH -Correct sheet rock in mechanical chase missing behind duct work, not fastened, gapped greater than 1/4" and missing behind dwv -Strap all over bored top plates per code -Correct joists bored closer than 2" from top or bottom and closer than 2" together -Complete basement bathroom -Complete gas and electrical and schedule associated inspections with all rough
Rated Assembly Inspection Failed 1/28/2025 1/28/2025 01/28/2025
Misc
Corrective Action Required
01/28/2025
-Inspection for firewall "pre rock" only: *Unit 211 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Support hip joist at ridge to bearing wall below in attic space -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly *Unit 213 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly
Rated Assembly Inspection Not Ready 1/30/2025 1/30/2025 01/30/2025
Misc
Corrective Action Required
01/28/2025
-Inspection for firewall "pre rock" only: *Unit 211 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Support hip joist at ridge to bearing wall below in attic space -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly *Unit 213 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly
Misc
Corrective Action Required
01/30/2025
1/30/25 *NOT READY, INSPECTION FOR RATED LAYER IN MECHANICAL CHASE ONLY -Correct all gaps over 1/4" of an inch -Still missing the required layer of sheet rock behind DWV
Erosion Control Inspection Residential Failed 2/4/2025 2/4/2025 02/04/2025
DCM2 ESC DEFICIENT INSTALLATION
Resolved
02/04/2025
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
02/04/2025
2/4/25 EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. -Provide erosion control methods at perimeter -Maintain gravel filter with min 6" lift of min 3/4" gravel -Clean silt and debris from street
Rated Assembly Inspection Not Ready 2/4/2025 2/4/2025 02/04/2025
Misc
Corrective Action Required
01/30/2025
-Inspection for firewall "pre rock" only: *Unit 211 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Support hip joist at ridge to bearing wall below in attic space -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly *Unit 213 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly
Misc
Corrective Action Required
01/30/2025
1/30/25 *NOT READY, INSPECTION FOR RATED LAYER IN MECHANICAL CHASE ONLY -Correct all gaps over 1/4" of an inch -Still missing the required layer of sheet rock behind DWV -Missing screws and sheet rock at joist space 2/4/25 **NOT READY. FEE ASSESSED. -Install compliant erosion control before further inspections
Rated Assembly Inspection Failed 2/6/2025 2/6/2025 02/06/2025
Misc
Corrective Action Required
02/04/2025
-Inspection for firewall "pre rock" only: *Unit 211 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Support hip joist at ridge to bearing wall below in attic space -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly *Unit 213 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly
Misc
Corrective Action Required
02/04/2025
2/6/25 Inspection for mechanical chase at 1st floor only -ok for fire tape -Install compliant erosion control before further inspections
Rated Assembly Inspection Partial 2/12/2025 2/12/2025 02/12/2025
Misc
Corrective Action Required
02/06/2025
-Inspection for firewall "pre rock" only: *Unit 211 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Support hip joist at ridge to bearing wall below in attic space -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly *Unit 213 -Anchor bolts to be in middle third of sole plate -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Missing studs at gable ends in attic space both sides (install and nail 12" oc) -Drywall installed in mechanical chase is not approved- missing behind dwv and not secured properly
Misc
Corrective Action Required
02/06/2025
2/12/25 Inspection for mechanical chase at 1st floor only -Fire tape approved-OK TO REINSTALL HVAC
Rated Assembly Inspection Not Ready 2/25/2025 2/25/2025 02/25/2025
Misc
Corrective Action Required
02/12/2025
-Inspection for firewall "pre rock" only: ***MECHANICAL AT 2ND FLOOR INSTALLED BEFORE WALLS APPROVED IN CHASES *Unit 211 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT BREAKING ON A STUD, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS *Unit 213 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT BREAKING ON A STUD, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS
Misc
Corrective Action Required
02/12/2025
2/12/25 Inspection for mechanical chase at 1st floor only -Fire tape approved-OK TO REINSTALL HVAC
Rated Assembly Inspection Not Ready 3/6/2025 03/06/2025
Misc
Corrective Action Required
02/25/2025
-Inspection for firewall "pre rock" only: ***MECHANICAL AT 2ND FLOOR INSTALLED BEFORE WALLS APPROVED IN CHASES *Unit 211 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT BREAKING ON A STUD, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS *Unit 213 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT BREAKING ON A STUD, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS
Misc
Corrective Action Required
02/25/2025
2/12/25 Inspection for mechanical chase at 1st floor only -Fire tape approved-OK TO REINSTALL HVAC
Misc
Corrective Action Required
03/06/2025
Multiple items not address. No city stamped plans on site.
Rated Assembly Inspection Not Ready 3/13/2025 3/13/2025 03/13/2025
Misc
Corrective Action Required
03/06/2025
3/13/25 -Inspection for firewall "pre rock" only: ***MECHANICAL AT 2ND FLOOR INSTALLED BEFORE WALLS APPROVED IN CHASES *Unit 211 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS-SMART TRIM AND SMART SIDING ARE NOT APPROVED FIREBLOCKING MATERIALS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT BREAKING ON A STUD, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS *Unit 213 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS-SMART TRIM AND SMART SIDING ARE NOT APPROVED FIREBLOCKING MATERIALS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS
Misc
Resolved
03/13/2025
2/12/25 Inspection for mechanical chase at 1st floor only -Fire tape approved-OK TO REINSTALL HVAC
Misc
Resolved
03/13/2025
Rated Assembly Inspection Not Ready 3/20/2025 3/19/2025 03/20/2025
Misc
Corrective Action Required
03/13/2025
3/13/25 -Inspection for firewall "pre rock" only: ***MECHANICAL AT 2ND FLOOR INSTALLED BEFORE WALLS APPROVED IN CHASES *Unit 211 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Seal top plate penetration at garage door lv wire -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS-SMART TRIM AND SMART SIDING ARE NOT APPROVED FIREBLOCKING MATERIALS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT BREAKING ON A STUD, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS *Unit 213 -Nail intersecting studs 12" oc at first and second floor (studs to exterior wall) -Fireblock gap at top of double wall at first and second floor-SEAL ALL GAPS-SMART TRIM AND SMART SIDING ARE NOT APPROVED FIREBLOCKING MATERIALS -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Drywall installed in mechanical chase on 2nd floor is not approved-LARGE HOLES IN ROCK, SHORT OF TOP PLATES, NOT SECURED AT EDGES, NOT CONTINIOUS BEHIND INTERSECTING WALLS
Misc
Corrective Action Required
03/20/2025
3/20/25 -No access. Have job site unlocked or leave lockbox and provide lockbox code with inspection request
Rated Assembly Inspection Failed 3/21/2025 3/21/2025 03/21/2025
Misc
Corrective Action Required
03/20/2025
3/13/25 -Inspection for firewall "pre rock" only: *Unit 211 -Seal top plate penetration at garage door lv wire -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Fire tape and seal penetrations and call for re inspection before reinstalling mechanical at chase *Unit 213 -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 -Fire tape and seal penetrations and call for re inspection before reinstalling mechanical at chase
Misc
Resolved
03/21/2025
3/20/25 -No access. Have job site unlocked or leave lockbox and provide lockbox code with inspection request
Driveway Inspection Partial 3/24/2025 3/24/2025 03/24/2025
Misc
Informational
03/24/2025
03/24/25 Monday JMJ Pre-inspection Driveway forms and materials appeared to passed.
Rated Assembly Inspection Failed 3/25/2025 3/25/2025 03/25/2025
Misc
Corrective Action Required
03/21/2025
3/13/25 -Inspection for firewall "pre rock" only: *Unit 211 -Seal top plate penetration at garage door lv wire -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 **Incomplete throughout (Required at boxes on both sides of walls, putty packs must cover entire box) -Fire tape and seal penetrations and call for re inspection before reinstalling mechanical at chase **Rock and tape top plate per on site conversation, seal penetrations and gaps *Unit 213 -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 **Incomplete throughout (Required at boxes on both sides of walls, putty packs must cover entire box) -Fire tape and seal penetrations and call for re inspection before reinstalling mechanical at chase **Rock and tape top plate per on site conversation, seal penetrations and gaps
Driveway Inspection Passed 03/26/2025
Misc
Informational
03/24/2025
03/24/25 Monday JMJ Pre-inspection Driveway forms and materials appeared to passed. 03/26/25 Wednesday JMJ Driveway passed final inspection.
Rated Assembly Inspection Failed 3/28/2025 3/28/2025 03/28/2025
Misc
Corrective Action Required
03/25/2025
3/13/25 -Inspection for firewall "pre rock" only: *Mechanical chases ok both units *Unit 211 -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 **Incomplete throughout (Required at boxes on both sides of walls, putty packs must cover entire box) *Unit 213 -Protect all penetrations (electrical boxes and fridge water supply box) per R302.4.2 **Incomplete throughout (Required at boxes on both sides of walls, putty packs must cover entire box)
All Rough Inspection - Residential Not Ready 3/28/2025 3/28/2025 03/28/2025
Misc
Corrective Action Required
01/22/2025
**1/22/25 Inspection incomplete. Correct the following items before further inspections: Unit 211 -Provide properly addressed, complete, updated, stamped plans for inspection -Complete all fireblocking throughout, including fur downs, ceiling lines, between floors and vertically at max 10' oc at double walls per R302.11 -Protect openings in firewall per code at fridge box, electrical boxes etc. per R302.4.2 -Install anchor bolts in middle third of plates -Tighten anchor bolts -Address sole plates not completely bearing on stem walls in garage -Uncover all exterior braced wall panels for inspection -Nail straps at PFH -Correct sheet rock in mechanical chase missing behind duct work, not fastened, gapped greater than 1/4" and missing behind dwv -Strap all over bored top plates per code -Correct joists bored closer than 2" from top or bottom and closer than 2" together -Complete basement bathroom -Complete gas and electrical and schedule associated inspections with all rough
Misc
Corrective Action Required
03/28/2025
***3/28/25 Not Ready. Inspection incomplete. Still no plans on site, these items still not addressed per previous inspection: -Provide properly addressed, complete, updated, stamped plans for inspection -Complete all fireblocking throughout, including fur downs, ceiling lines, between floors and vertically at max 10' oc at double walls per R302.11-Missing at attic space walls, missing at ceiling lines, etc. -Protect openings in firewall per code at fridge box, electrical boxes etc. per R302.4.2 -Address sole plates not completely bearing on stem walls in garage -Uncover all exterior braced wall panels for inspection -Nail straps at PFH -Correct sheet rock in mechanical chase missing behind duct work, not fastened, gapped greater than 1/4" and missing behind dwv -Strap all over bored top plates per code -Correct joists bored closer than 2" from top or bottom and closer than 2" together -Complete gas and electrical and schedule associated inspections with all rough-Inspections not scheduled, only 3lbs of pressure at gas line, electrical not inspected
Documents & Images
Date Uploaded File Type Document Name
02/19/2024 License_Tax_Application #2
05/09/2024 Approved Plans APPROVED PLANS
05/09/2024 Plot Plan APPROVED PLOT PLAN
05/09/2024 Permit Codes Residential Plan Review
05/09/2024 Permit DS Building Permit
05/09/2024 Receipt Receipt for transaction: 2024-003210
05/09/2024 Application Form APPLICATION
06/10/2024 Letter Stop Work Order
06/11/2024 M L Crose 211 & 213 NW Orchard Ct LSMO 3rd Party Footing Inspection Report 5-28-24
06/12/2024 Letter INSPECTION SUMMARY
06/12/2024 Letter INSPECTION SUMMARY
06/13/2024 Letter INSPECTION SUMMARY
06/13/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
11/04/2024 211 NW Orchard Court APPROVED PLANS 11-3-24
12/17/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
12/18/2024 Letter INSPECTION SUMMARY
01/02/2025 Letter INSPECTION SUMMARY
01/22/2025 Letter INSPECTION SUMMARY
01/22/2025 Letter INSPECTION SUMMARY
01/28/2025 Letter INSPECTION SUMMARY
01/30/2025 Letter INSPECTION SUMMARY
02/04/2025 Letter INSPECTION SUMMARY
02/04/2025 Letter INSPECTION SUMMARY
02/06/2025 Letter INSPECTION SUMMARY
02/12/2025 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
02/25/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/06/2025 Letter INSPECTION SUMMARY
03/13/2025 Letter INSPECTION SUMMARY
03/20/2025 Letter INSPECTION SUMMARY
03/21/2025 Letter INSPECTION SUMMARY
03/24/2025 Letter INSPECTION SUMMARY
03/25/2025 Letter INSPECTION SUMMARY
03/28/2025 Letter INSPECTION SUMMARY
03/28/2025 Letter INSPECTION SUMMARY
04/04/2025 211-213 ORCHARD CT INSPECTION RESPONSE 4-3-25
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home