Permit Application Status

PRRES20211038


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20211038
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - ROOF TRUSSES - FINISHED AND UNFINISHED BASEMENT
03/09/2021
03/16/2021
09/12/2021
03/01/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
PERMITTING@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 03/18/2021 03/16/2021
Brandon Kalwei
Rear yard dimension
Corrective Action Required
03/16/2021

The rear yard demision(s) must be provided on the plot plan.
Sidewalks
Corrective Action Required
03/16/2021

Sidewalks with dimensions must be provided on the plot plan.
Residential Plan Review Approved 03/18/2021 03/16/2021
Brandon Kalwei
Plot Plan Review Rejected 03/11/2021 03/10/2021
Brandon Kalwei
Rear yard dimension
Corrective Action Required
03/10/2021

The rear yard demision(s) must be provided on the plot plan.
Sidewalks
Corrective Action Required
03/10/2021

Sidewalks with dimensions must be provided on the plot plan.
Residential Plan Review Approved 03/11/2021 03/10/2021
Brandon Kalwei
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,028.89 $1,028.89 Paid 03/16/2021
8331504-EFHB Middle Big Creek, Full $401.76 $401.76 Paid 03/16/2021
8331507-Sewer Connection Fee $360.00 $360.00 Paid 03/16/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 03/16/2021
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 03/16/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 03/16/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 03/16/2021
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 01/04/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 01/04/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 01/04/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Residential Failed 5/21/2021 5/21/2021 05/21/2021
Misc
Corrective Action Required
05/21/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION, UPLOAD ENGINEER REPORT WITHIN 48 HOURS OF INSPECTION (THIRD PARTY REPORT IN PERMIT NOT FOR THIS PERMIT)
Footing Inspection - Residential Failed 5/21/2021 05/21/2021
Misc
Corrective Action Required
05/21/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION, UPLOAD ENGINEER REPORT WITHIN 48 HOURS OF INSPECTION (THIRD PARTY REPORT IN PERMIT NOT FOR THIS PERMIT)
Underslab Plumbing Inspection - Residential Failed 6/4/2021 6/4/2021 06/04/2021
Misc
Corrective Action Required
05/21/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION, UPLOAD ENGINEER REPORT WITHIN 48 HOURS OF INSPECTION (THIRD PARTY REPORT IN PERMIT NOT FOR THIS PERMIT) -Footing requires resolution before proceeding with any further inspections-
Footing Inspection - Residential Passed 6/9/2021 06/09/2021
Misc
Resolved
06/09/2021
Underslab Plumbing Inspection - Residential Passed 6/9/2021 6/9/2021 06/09/2021
Misc
Resolved
06/09/2021
All Rough Inspection - Residential Partial 8/3/2021 8/3/2021 08/03/2021
Misc
Informational
08/03/2021
-GARAGE PORTAL EXTERIOR OK TO COVER
Gas Service Inspection - Residential Passed 9/14/2021 9/14/2021 09/14/2021
All Rough Inspection - Residential Failed 9/22/2021 9/22/2021 09/22/2021
Misc
Informational
08/03/2021
-GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
09/22/2021
-No truss layout detail with plans on site, have at reinspect, corrections subject to change -Strap top plates to connect intersection corner at south garage wall -12” oc nailing at all intersecting braced wall corners -Nail protection plates at NM 1 1/4” or less from end of stud- see garage, pantry, great room -seal all top plate penetrations - see garage, kitchen, finished basement -Anchor bolts required every 6' at garage -Roof boots required at all roof penetrations for DWV, radon -Fireblock around dryer duct at top plate laundry -Land NM to box at master shower, master hall wall -Double top plate requires 24” offset between plate breaks - strap top plates - see kitchen wall, see above fireplace, front bedroom -Install back and front doors -repair front bedroom sub floor -Fireblock all tub and shower traps -Attic access requires 30” vertical clearance -LIB bracing all locations garage per plans -CS-PF design per plans at great room/kitchen exterior wall per plans -(4) 2x4 stud pack at triple girder truss bearing ends at garage wall per plans -seal floor penetration for gas line at fireplace -repair NM at basement stairs for floor receptacle -Fireblock between top plate and foundation wall at basement -Fireblock vertical every 10’ between studs and foundation wall at basement Fireblock vertical to horizontal at furred downs in basement, seal gaps around DWV, etc -2x4 laid flat at furred downs 3’ or more need to be connected to the floor joist above to support the ceiling load -Add joist hangers at sgl to dbl joist connection at fireplace cantilever basement, over 4’ -complete electrical at basement bedroom wall/ceiling
Electrical Service Inspection Passed 9/22/2021 9/22/2021 09/22/2021
All Rough Inspection - Residential Failed 9/28/2021 9/28/2021 09/28/2021
Misc
Informational
09/22/2021
-GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
09/22/2021
-No truss layout detail with plans on site, have at reinspect, corrections subject to change, no truss layout at reinspect -Nail protection plates at NM 1 1/4” or less from end of stud- see pantry, great room -Protection plates at pex for fridge at kitchen -seal all top plate penetrations - see garage, kitchen, finished basement -Fireblock around dryer duct at top plate laundry -Install back and front doors -Fireblock all tub and shower traps -CS-PF design per plans at great room/kitchen exterior wall per plans -Provide attic access per plans -seal floor penetration for gas line at fireplace -protection plate at bottom plate basement office DWV -Fireblock between top plate and foundation wall at basement -If using lumber for fireblock it must be pressure treated where in contact with concrete foundation wall, seal all gaps and penetrations through fireblock -Fireblock vertical every 10’ between studs and foundation wall at basement, If using lumber for fireblock it must be pressure treated where in contact with concrete foundation wall, seal all gaps and penetrations through fireblock
All Rough Inspection - Residential Failed 10/1/2021 10/1/2021 10/01/2021
Misc
Informational
09/28/2021
-GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
09/28/2021
-Nail triple truss girder at front bedroom together per plans -seal all top plate penetrations -finished basement -Shim Jack studs at front door -CS-PF design per plans at great room/kitchen exterior wall per plans
All Rough Inspection - Residential Failed 10/4/2021 10/4/2021 10/04/2021
Misc
Informational
10/01/2021
-GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Corrective Action Required
10/01/2021
-seal all top plate penetrations -see basement office wall -Shim Jack studs at front door
All Rough Inspection - Residential Passed 10/6/2021 10/6/2021 10/06/2021
Misc
Resolved
10/06/2021
-GARAGE PORTAL EXTERIOR OK TO COVER
Misc
Resolved
10/06/2021
Driveway Inspection Passed 10/19/2021 10/19/2021 10/19/2021
Misc
Informational
10/19/2021
On 10/19/2021 I performed a driveway inspection and passed the sub-grade to pour concrete. DJ
Sidewalk Inspection Passed 10/19/2021 10/19/2021 10/19/2021
Misc
Informational
10/19/2021
On 10/19/2021 I performed a sidewalk inspection and passed the sub-grade to pour concrete. DJ
Sewer Service Inspection - R Passed 12/29/2021 12/29/2021
Water Service Inspection - R Passed 12/30/2021 12/30/2021
Erosion Control Inspection Residential Failed 12/30/2021 12/30/2021 12/30/2021
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
12/30/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Occupancy Inspection - Codes Residential Failed 1/4/2022 1/4/2022 01/04/2022
Misc
Corrective Action Required
01/04/2022
-Resolve outstanding inspection fees before final c of o -final grade and sod -splash blocks at all downspout and sump pump discharge locations, min 36" discharge from foundation -seal all penetrations in siding, seal along top of meter can and AC disconnect -Install plate at box front porch exterior receptacle, open around receptacle face -Install deadbolt lock back door -Security screws, Install (2) 3” screws at latch side back exterior door -no setback of box allowed with combustible material- see electrical floor receptacles at great room and foyer -max 1/4” setback allowance at boxes with non combustible material- see electrical receptacles at master bath vanity -attic access cover garage -install set screw on anti siphon at spigot at water shutoff basement and shear off head of set screw -Install ladder basement bedroom egress well
Occupancy Inspection - Codes Residential Temporary C of O 1/5/2022 1/5/2022 01/05/2022
Misc
Corrective Action Required
01/04/2022
-Completed final grade and sod -splash blocks and sump pump discharge to be 36” from foundation -check water meter & siding from ground at time of final grade and sod -obtain irrigation permit -flood light at back of house
Occupancy Inspection - Codes Residential Failed 2/24/2022 2/24/2022 02/24/2022
Misc
Corrective Action Required
01/05/2022
-correct grade at rear of house cantilever, minimum 6" of fall required within first 10' of foundation, grade is at negative slope towards foundation
Erosion Control Inspection Residential Passed 3/1/2022 03/01/2022
DCM1 ESC REQUIRED NO FURTHER INSP
Corrective Action Required
12/30/2021
EROSION CONTROL REQUIRED. NO FURTHER INSPECTIONS WILL BE PERFORMED UNTIL EROSION CONTROL IS INSTALLED AND IN COMPLIANCE.
Plot Plan Inspection Passed 03/01/2022
Occupancy Inspection - Codes Residential Full C of O 3/1/2022 3/1/2022 03/01/2022
Misc
Corrective Action Required
02/24/2022
-correct grade at rear of house cantilever, minimum 6" of fall required within first 10' of foundation, grade is at negative slope towards foundation
Documents & Images
Date Uploaded File Type Document Name
03/09/2021 Application Form APPLICATION
03/09/2021 72 RESERVE AT STONEY CREEK ROOF LAYOUT
03/09/2021 RR #72 - Meadowbrook - Craftsman - Sheets- signed
03/09/2021 LOT 72 FINAL
03/09/2021 210310
03/10/2021 Approved Plans APPROVED PLANS
03/10/2021 Approved Plans APPROVED TRUSS DRAWINGS
03/10/2021 Approved Plans APPROVED TRUSS LAYOUT
03/10/2021 Letter Codes Residential Plan Review
03/16/2021 LOT 72 CITY
03/16/2021 Plot Plan APPROVED PLOT PLAN
03/16/2021 Receipt Receipt for transaction:2021-001311
03/16/2021 Letter DS Building Permit
05/13/2021 Lot 72 Manor at Stoney Creek Footing Inspection
05/21/2021 Letter INSPECTION SUMMARY
05/21/2021 Letter INSPECTION SUMMARY
06/04/2021 Letter INSPECTION SUMMARY
06/08/2021 Lot 72 Reserve at Stoney Creek Foundation Inspection 2
06/08/2021 Lot 72 Reserve at Stoney Creek Footing Inspection
06/09/2021 Letter INSPECTION SUMMARY
06/09/2021 Letter INSPECTION SUMMARY
08/03/2021 Letter INSPECTION SUMMARY
09/14/2021 Letter INSPECTION SUMMARY
09/14/2021 Letter INSPECTION SUMMARY
09/22/2021 Letter INSPECTION SUMMARY
09/22/2021 Letter INSPECTION SUMMARY
09/28/2021 Letter INSPECTION SUMMARY
10/01/2021 Letter INSPECTION SUMMARY
10/04/2021 Letter INSPECTION SUMMARY
10/06/2021 Letter INSPECTION SUMMARY
10/19/2021 Letter INSPECTION SUMMARY
10/19/2021 Letter INSPECTION SUMMARY
12/29/2021 Letter INSPECTION SUMMARY
12/30/2021 Letter INSPECTION SUMMARY
12/30/2021 Letter INSPECTION SUMMARY
01/04/2022 Letter INSPECTION SUMMARY
01/04/2022 Receipt Receipt for transaction:2022-000051
01/05/2022 Letter Codes Temporary Certificate of Occupancy
02/24/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter Field Certificate of Occupancy
03/01/2022 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home