Review Type |
Outcome |
Est. Completion Date |
Completed |
Special Inspections Review
|
Approved
|
|
03/03/2025
|
|
Joe Frogge
|
|
|
Building Plan Review
|
Approved with Conditions
|
03/05/2025
|
03/03/2025
|
|
Joe Frogge
|
|
Final Development Plan
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is informational.
1/22/2025 - Not addressed.
3/3/2025 - Acknowledged in letter.
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is for informational purposes. The fee will be $4,44.00
1/22/2025 - Not addressed.
3/3/2025 - Acknowledged in letter.
|
|
IBC 1704.2 Special Inspections
2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions)
Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
1/22/2025 - Not addressed.
|
|
Miscellaneous Correction
Inadequate information to complete review.
Provide the following:
-
-
-
-
-
|
|
Engineered truss package
Copies of the pre-engineered metal building package (PEMB) were not provided at the time of permit application.
Action required: Provide PEMB package or request deferral.
1/22/2025 - Not addressed.
|
|
Gen - Plan submittal documents
**Note added on 1/22/2025**
Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted digitally with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri.
Action required: All plans must be sealed/signed by architect or engineer.
|
|
|
Licensed Contractors
|
Approved
|
03/05/2025
|
03/03/2025
|
|
Joe Frogge
|
|
|
Fire Plan Review
|
Approved with Conditions
|
03/05/2025
|
03/03/2025
|
|
Joe Frogge
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
Action Required: Provide deferred submittal for alarm system.
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
Action Required: Provide deferred submittal for protection system.
|
|
Misc
2018 IFC 1008.3.1 & 3.2 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises' electrical supply. In the event of power supply failure, an emergency electrical system shall automatically illuminate all of the following:
1. Aisles and unenclosed egress stairways in rooms and spaces that require two or mor means of egress.
2. Corridors, interior exit stairways and ramps and exit passageways in buildings required to have two or more exits.
3. Exterior egress components at other than their levels of exit discharge until exit discharge is accomplished for buildings required to have two or more exits.
Provide exterior emergency lighting at all marked exits.
|
|
|
Alarm Plan Review
|
Released for Construction
|
02/21/2025
|
02/21/2025
|
|
Craig Hill
|
|
Alarms connected to automatic sprinkler system
Corrective Action Required
2018 IFC 903.4.2- Alarms. Approved audible and visual devices shall be connected to every automatic sprinkler system. Such sprinkler water-flow alarm devices shall be activated by water flow equivalent to the flow of a single sprinkler of the smallest orifice size installed in the system. Listed alarm notification devices shall be provided on the exterior and interior of the building in an approved location. Where a fire alarm system is installed, actuation of the automatic sprinkler system shall actuate the building fire alarm system.
|
|
Alarm testing.
Corrective Action Required
2018 IFC 904.4.2- Alarm testing. Notification appliances, connections to fire alarm systems, and connections to approved supervising stations shall be tested in accordance with this section and Section 907 to verify proper operation.
Information Only: Call 816-969-1300 to schedule alarm testing, 24 hours in advance. Coordinate with sprinkler testing.
|
|
|
Fire Plan Review
|
Approved
|
01/27/2025
|
01/27/2025
|
|
Craig Hill
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
|
|
|
Final Development Plan Review
|
Approved
|
01/24/2025
|
01/24/2025
|
|
Daniel Fernandez
|
|
|
Building Plan Review
|
Rejected
|
01/27/2025
|
01/22/2025
|
|
Joe Frogge
|
|
Final Development Plan
Corrective Action Required
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is informational.
1/22/2025 - Not addressed.
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is for informational purposes. The fee will be $4,44.00
1/22/2025 - Not addressed.
|
|
IBC 1704.2 Special Inspections
Corrective Action Required
2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions)
Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
1/22/2025 - Not addressed.
|
|
Code analysis required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update Code Notes on cover sheet to show that building is fully sprinklered.
|
|
Miscellaneous Correction
Corrective Action Required
Inadequate information to complete review.
Provide the following:
- Complete construction details for mezzanine. (floor, decking, guard rail, stair geometry, etc.)
1/22/2025 - Incomplete - Details show joists show both wood joists and bar joists, neither of which are sized. How is guard rail attached?
- Complete HVAC design. (furnace spec, outside air calcs, duct sizes, combustion air/vent, RR exhaust, etc.)
1/22/2025 - Incomplete
-
-
-
|
|
Engineered truss package
Corrective Action Required
Copies of the pre-engineered metal building package (PEMB) were not provided at the time of permit application.
Action required: Provide PEMB package or request deferral.
1/22/2025 - Not addressed.
|
|
IBC 1010.1.6 Landings at doors
2018 IBC 1010.1.6 Landings at doors. Landings shall have a width not less than the width of the stairway or the door, whichever is greater. Doors in the fully open position shall not reduce a required dimension by more than 7 inches. Where a landing serves an occupant load of 50 or more, doors in any position shall not reduce the landing to less than one-half its required width. Landings shall have a length measured in the direction of travel of not less than 44 inches. Exception: Landing length in the direction of travel in Groups R-3 and U and within individual units of Group R-2 need not exceed 36 inches.
Action required: Landings required at all exit doors including door on north side of building.
|
|
IBC 1008.3 Emergency power for illumination - at exit discharge
2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply.
1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Aisles.
2. Corridors.
3. Exit access stairways and ramps.
1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Interior exit access stairways and ramps.
2. Interior and exterior exit stairways and ramps.
3. Exit passageways.
4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1.
5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge.
1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas:
1. Electrical equipment rooms.
2. Fire command centers.
3. Fire pump rooms.
4. Generator rooms.
5. Public restrooms with an area greater than 300 square feet.
Action required: Provide emergency lighting at exterior sides of exterior doors. Re: front door.
|
|
NEC Article 210.8 (B) Other than dwelling units GFCI
2017 NEC Article 210.8 (B) Other Than Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(B)(1) through (10) shall have ground-fault circuit-interrupter protection for personnel.
(1) Bathrooms
(2) Kitchens
(3) Rooftops
(4) Outdoors
(5) Sinks - where receptacles are installed within 6 feet of the outside edge of the sink.
(6) Indoor wet locations
(7) Locker rooms with associated showering facilities
(8) Garages, service bays, and similar areas other than vehicle exhibition halls and showrooms.
(9) Crawl spaces – at or below grade level.
(10) Unfinished portions or areas of the basement not intended as habitable rooms.
(refer to code for exceptions)
Action required: Modify drawings to show that all receptacles within 6' of a sink will by GFCI protected.
|
|
IBC 1109.11 Seating at tables, counters and work surfaces - accessibility
2018 IBC 1109.11 Seating at tables, counters and work surfaces. Where seating or standing space at fixed or built-in tables, counters or work surfaces is provided in accessible spaces, at least 5 percent of the seating and standing spaces, but not less than one, shall be accessible. (see code for exception)
Action required: Amend designs to show that breakroom counter top is no taller than 34"
|
|
IPC 305.4 Freezing - protection of potable water
Protection of Potable Water System
2018 IPC 305.4 Freezing. Water, soil, and waste pipes shall not be installed outside of a building, in attics or crawl spaces, concealed in outside walls, or in any other place subjected to freezing temperatures unless adequate provision is made to protect such pipes from freezing by insulation or heat or both. Exterior water supply system piping shall be installed not less than 6” below the frost line (42” below grade) and not less than 12 inches below grade.
Action required: Provide method of heating room/space where water enters building.
|
|
Gen - Plan submittal documents
Corrective Action Required
**Note added on 1/22/2025**
Lee's Summit Code Of Ordinances 7-137. - Submittal Documents. Construction documents, special inspection and structural observation programs, and other data shall be submitted digitally with each application for a permit. A registered design professional licensed by the State of Missouri shall prepare the construction documents. Where special conditions exist, the Building Official is authorized to require additional construction documents to be prepared by a registered design professional licensed by the State of Missouri.
Action required: All plans must be sealed/signed by architect or engineer.
|
|
|
Licensed Contractors
|
Approved
|
01/27/2025
|
01/22/2025
|
|
Joe Frogge
|
|
|
Fire Plan Review
|
Rejected
|
01/03/2025
|
01/03/2025
|
|
Craig Hill
|
|
Construction documents for fire alarm systems
Corrective Action Required
2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions.
|
|
Construction documents - Fire protection systems
Corrective Action Required
2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation.
|
|
Misc
Corrective Action Required
1008.1 Means of egress illumination. Illumination shall be provided in the means of egress in accordance with Section 1008.2. Under emergency power, means of egress illumination shall comply with Section 1008.3
Action required: Provide emergency exterior illumination at all doors exiting the building.
|
|
Miscellaneous Correction
Corrective Action Required
Provide occupant load for the mezzanine.
|
|
Portable fire extinguishers - conspicuous locations
Corrective Action Required
2018 IFC 906.5- Conspicuous location. Portable fire extinguishers shall be located in conspicuous locations where they will be readily accessible and immediately available for use. These locations shall be along normal paths of travel, unless the fire code official determines that the hazard posed indicates the need for placement away from normal paths of travel.
Action Required: Provide location of fire extinguishers.
|
|
|
Building Plan Review
|
Rejected
|
01/03/2025
|
12/30/2024
|
|
Joe Frogge
|
|
Final Development Plan
Corrective Action Required
The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan.
Action required: Comment is informational.
|
|
License Tax - Payment
Corrective Action Required
A one-time impact fee in the form of a license tax must be collected before occupancy can be granted. Please be advised that additional application, review, and inspection fees do apply and additional information pertaining to this will be provided during that stage of your approval process.
Action required: Comment is for informational purposes. The fee will be $4,44.00
|
|
IBC 1704.2 Special Inspections
Corrective Action Required
2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions)
Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
|
|
Code analysis required
Corrective Action Required
A code analysis shall be provided which includes but is not limited to occupancy type, occupant load, construction type, actual area, height and floors, allowable area, height and floors, and the codes to which the project is designed.
Action required: Update Code Notes on cover sheet to show that building is fully sprinklered.
|
|
Miscellaneous Correction
Corrective Action Required
Inadequate information to complete review.
Provide the following:
- Complete construction details for mezzanine. (floor, decking, guard rail, stair geometry, etc.)
- Complete HVAC design. (furnace spec, outside air calcs, duct sizes, combustion air/vent, etc.)
- Coordinate utilities with Civil plans.
- Specify water/sewer entry locations.
- Racking heights (if greater than 12' additional provisions will apply)
|
|
Engineered truss package
Corrective Action Required
Copies of the pre-engineered metal building package (PEMB) were not provided at the time of permit application.
Action required: Provide PEMB package or request deferral.
|
|
IBC 1010.1.6 Landings at doors
Corrective Action Required
2018 IBC 1010.1.6 Landings at doors. Landings shall have a width not less than the width of the stairway or the door, whichever is greater. Doors in the fully open position shall not reduce a required dimension by more than 7 inches. Where a landing serves an occupant load of 50 or more, doors in any position shall not reduce the landing to less than one-half its required width. Landings shall have a length measured in the direction of travel of not less than 44 inches. Exception: Landing length in the direction of travel in Groups R-3 and U and within individual units of Group R-2 need not exceed 36 inches.
Action required: Landings required at all exit doors including door on north side of building.
|
|
IBC 1008.3 Emergency power for illumination - at exit discharge
Corrective Action Required
2018 IBC 1008.3 Emergency power for illumination. The power supply for means of egress illumination shall normally be provided by the premises’ electrical supply.
1008.3.1 General. In the event of power supply failure in rooms and spaces that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Aisles.
2. Corridors.
3. Exit access stairways and ramps.
1008.3.2 Buildings. In the event of power supply failure in buildings that require two or more means of egress, an emergency electrical system shall automatically illuminate all of the following areas:
1. Interior exit access stairways and ramps.
2. Interior and exterior exit stairways and ramps.
3. Exit passageways.
4. Vestibules and areas on the level of discharge used for exit discharge in accordance with Section 1028.1.
5. Exterior landings as required by Section 1010.1.6 for exit doorways that lead directly to the exit discharge.
1008.3.3 Rooms and Spaces. In the event of power supply failure an emergency electrical system shall automatically illuminate all of the following areas:
1. Electrical equipment rooms.
2. Fire command centers.
3. Fire pump rooms.
4. Generator rooms.
5. Public restrooms with an area greater than 300 square feet.
Action required: Provide emergency lighting at exterior sides of exterior doors. Re: front door.
|
|
NEC Article 210.8 (B) Other than dwelling units GFCI
Corrective Action Required
2017 NEC Article 210.8 (B) Other Than Dwelling Units. All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(B)(1) through (10) shall have ground-fault circuit-interrupter protection for personnel.
(1) Bathrooms
(2) Kitchens
(3) Rooftops
(4) Outdoors
(5) Sinks - where receptacles are installed within 6 feet of the outside edge of the sink.
(6) Indoor wet locations
(7) Locker rooms with associated showering facilities
(8) Garages, service bays, and similar areas other than vehicle exhibition halls and showrooms.
(9) Crawl spaces – at or below grade level.
(10) Unfinished portions or areas of the basement not intended as habitable rooms.
(refer to code for exceptions)
Action required: Modify drawings to show that all receptacles within 6' of a sink will by GFCI protected.
|
|
IBC 1109.11 Seating at tables, counters and work surfaces - accessibility
Corrective Action Required
2018 IBC 1109.11 Seating at tables, counters and work surfaces. Where seating or standing space at fixed or built-in tables, counters or work surfaces is provided in accessible spaces, at least 5 percent of the seating and standing spaces, but not less than one, shall be accessible. (see code for exception)
Action required: Amend designs to show that breakroom counter top is no taller than 34"
|
|
IPC 305.4 Freezing - protection of potable water
Corrective Action Required
Protection of Potable Water System
2018 IPC 305.4 Freezing. Water, soil, and waste pipes shall not be installed outside of a building, in attics or crawl spaces, concealed in outside walls, or in any other place subjected to freezing temperatures unless adequate provision is made to protect such pipes from freezing by insulation or heat or both. Exterior water supply system piping shall be installed not less than 6” below the frost line (42” below grade) and not less than 12 inches below grade.
Action required: Provide method of heating room/space where water enters building.
|
|
|
Licensed Contractors
|
Approved
|
12/17/2024
|
12/17/2024
|
|
Joe Frogge
|
|
|
Sprinkler Plan Review
|
Pending
|
|
|
|
Craig Hill
|
|
|