Permit Application Status

PRCOM20230813


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRCOM20230813
Building Permit - Commercial
Certificate of Occupancy
LEES SUMMIT RETAIL PARTNERS LLC
NEW COMMERCIAL
NEW BUILDING FOR HARDWARE STORE
02/24/2023
03/30/2023
09/09/2023
11/03/2023
Locations
Contacts
Forge Construction LLC, Address:1307 Union Avenue  
Alex O'Laughlin, Address:1307 Union Ave, Phone:(816) 608-1800  
DAVIDSON ARCHITECTURE & ENGINEERING, Address:4301 INDIAN CREEK PKWY, Phone:(913) 451-9390  
JAKE'S INDUSTRIAL INC, Address:1101 SW 1ST, Phone:(816) 690-3173  
BART'S ELECTRIC COMPANY INC, Address:7103 STEWART RD, Phone:(816) 421-0007  
ACCURATE MECHANICAL LLC, Address:205 E 13TH AVE, Phone:(816) 471-2272  
KANSAS CITY TESTING AND ENGINEERING LLC, Address:1141 SOUTHWEST BLVD, Phone:(913) 321-8100  
Scott Murphy, Phone:(816) 215-2549  
LEES SUMMIT RETAIL PARTNERS LLC, Address:4706 BROADWAY STE 260  
Reviews
Review Type Outcome Est. Completion Date Completed
Sprinkler Plan Review Released for Construction 09/20/2023 09/21/2023
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
09/06/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Stamped plans received 7/28/2023. Revised plans received 9/6/2023 with appropriate correction.
Installation acceptance testing
Corrective Action Required
09/21/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule testing.
Sprinkler Plan Review Rejected 08/11/2023 08/10/2023
Jim Eden
Construction documents - Fire protection systems
Corrective Action Required
08/10/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Stamped plans received 7/28/2023.
Miscellaneous Correction
Corrective Action Required
08/10/2023

A fire department connection (FDC) is not provided on the drawings. Provide the FDC with a 4" storz type connection with elbow.
Fire Plan Review Approved 06/15/2023 06/15/2023
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
05/18/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action required- Provide shop drawings for review and approval.
Construction documents - Fire protection systems
Corrective Action Required
05/18/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action required- Provide shop drawings for review and approval.
Miscellaneous Correction
Informational
05/18/2023

Complete a Hazardous Materials Permit Application for LPG exchange and bottle refilling. Provide information and drawings for the refilling area. 6/14/2023- In process.
Building Plan Review Approved 06/15/2023 06/14/2023
Joe Frogge
Engineering Review Approved 06/15/2023 06/09/2023
Sue Pyles, P.E.
Zoning Review Approved 06/15/2023 06/09/2023
Shannon McGuire
Alarm Plan Review Released for Construction 04/20/2023 04/11/2023
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
04/11/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Stamped plans received 4/5/2023.
Installation acceptance testing
Corrective Action Required
04/11/2023

2018 IFC 901.5- Installation acceptance testing. Fire detection and alarm systems, fire-extinguishing systems, fire hydrant systems, fire standpipe systems, fire pump systems, private fire service mains and all other fire protection systems and appurtenances thereto shall be subject to acceptance tests as contained in the installation standards and as approved by the fire code official. The fire code official shall be notified before any required acceptance testing. The fire code official shall be notified 48 hours before any required acceptance test. Call (816) 969-1300 to schedule an alarm test. Coordinate with sprinkler contractor.
Miscellaneous Correction
Corrective Action Required
04/11/2023

Remove the exterior horn/strobe appliance that is NOT above the FDC. Verified at inspection.
Fire Plan Review Approved with Conditions 03/28/2023 03/29/2023
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
03/21/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action required- Provide shop drawings for review and approval.
Knox box required
Resolved
03/29/2023

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action required- Provide a Knox box 6' AFF over the FDC.
Construction documents - Fire protection systems
Corrective Action Required
03/21/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action required- Provide shop drawings for review and approval.
Miscellaneous Correction
Informational
03/29/2023

Complete a Hazardous Materials Permit Application for LPG exchange and bottle refilling. Provide information and drawings for the refilling area.
Miscellaneous Correction
Resolved
03/29/2023

Provide an exit sign over door 107 hall. Ext signage chevrons shall point to the nearest exit.
Portable fire extinguishers - general
Resolved
03/29/2023

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Action required- Provide an ABC type fire extinguisher at the 107 hallway.
Building Plan Review Approved 03/28/2023 03/24/2023
Joe Frogge
Final Development Plan
Resolved
03/24/2023

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Resolved
03/24/2023

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
IMC 306.5 Equipment on roofs
Resolved
03/24/2023

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide side rail extender at roof hatch ladder.
IBC 1013.1 Where required - exit sign
Resolved
03/24/2023

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide exit sign that leads into Hall 107.
Special Inspections Review Approved 03/24/2023
Joe Frogge
Licensed Contractors Approved 03/28/2023 03/24/2023
Joe Frogge
Final Development Plan Review Approved 03/23/2023 03/23/2023
Scott Ready
Market Street Center Lot - Westlake Ace Hardware
Fire Plan Review Rejected 03/10/2023 03/10/2023
Jim Eden
Construction documents for fire alarm systems
Corrective Action Required
03/10/2023

2018 IFC 907.1.1- Construction documents. Construction documents for fire alarm systems shall be submitted for review and approval prior to system installation. Construction documents shall include, but not be limited to, all of the following: 1. .A floor plan which indicates the use of all rooms. 2. Locations of alarm-initiating and notification appliances. 3. Alarm control and trouble signaling equipment. 4. Annunciation. 5. Power connection. 6. Battery calculations. 7. Conductor type and sizes. 8. Voltage drop calculations. 9. Manufacturers, model numbers and listing information for equipment, devices and materials. 10. Details of ceiling height and construction. 11. The interface of fire safety control functions. Action required- Provide shop drawings for review and approval.
Knox box required
Corrective Action Required
03/10/2023

2018 IFC 506.1- Where required. Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type and shall contain keys to gain necessary access as required by the fire code official. Action required- Provide a Knox box 6' AFF over the FDC.
Construction documents - Fire protection systems
Corrective Action Required
03/10/2023

2018 IFC 901.2- Construction documents. The fire code official shall have the authority to require construction documents and calculations for all fire protection systems and to require permits be issued for the installation, rehabilitation or modification of any fire protection system. Construction documents for fire protection systems shall be submitted for review and approval prior to system installation. Action required- Provide shop drawings for review and approval.
Miscellaneous Correction
Corrective Action Required
03/10/2023

Complete a Hazardous Materials Permit Application for LPG exchange and bottle refilling. Provide information and drawings for the refilling area.
Miscellaneous Correction
Corrective Action Required
03/10/2023

Provide an exit sign over door 107 hall. Ext signage chevrons shall point to the nearest exit.
Portable fire extinguishers - general
Corrective Action Required
03/10/2023

2018 IFC 906.2- General requirements. Portable fire extinguishers shall be selected, installed and maintained in accordance with this section and NFPA 10. Action required- Provide an ABC type fire extinguisher at the 107 hallway.
Building Plan Review Rejected 03/10/2023 03/09/2023
Joe Frogge
Final Development Plan
Corrective Action Required
03/09/2023

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is informational.
IBC 1704.2 Special Inspections
Corrective Action Required
03/09/2023

2018 IBC 1704.2 Special inspections. Where application is made for construction as described in this section, the owner or the registered design professional in responsible charge acting as the owner’s agent shall employ one or more approved agencies to perform inspections during construction on the types of work listed under Section 1705. These inspections are in addition to the inspections identified in Lee’s Summit Code of Ordinances Chapter 7. (see code section for exceptions) Action required: Provide statement of special inspections / letter of responsibility from company contracted to perform special inspections.
IMC 306.5 Equipment on roofs
Corrective Action Required
03/09/2023

2018 IMC 306.5 Equipment and appliances on roofs or elevated structures. Where equipment requiring access or appliances are located on an elevated structure or the roof of a building such that personnel will have to climb higher than 16 feet above grade to access such equipment or appliances, an interior or exterior means of access shall be provided. Such access shall not require climbing over obstructions greater than 30 inches in height or walking on roofs having a slope greater than 4 units vertical in 12 units horizontal. Such access shall not require the use of portable ladders. Where access involves climbing over parapet walls, the height shall be measured to the top of the parapet wall. Permanent ladders installed to provide the required access shall comply with the following minimum design criteria: 1. The side railing shall extend above the parapet or roof edge not less than 30" (see code section for additional construction requirements) Action required: Provide side rail extender at roof hatch ladder.
IBC 1013.1 Where required - exit sign
Corrective Action Required
03/09/2023

2018 IBC Exit Signs 1013.1 Where Required. Exits and exit access doors shall be marked by an approved exit sign readily visible from any direction of egress travel. The path of egress travel to exits and within exits shall be marked by readily visible exit signs to clearly indicate the direction of egress travel in cases where the exit of the path of egress travel is not immediately visible to the occupants. Intervening means of egress doors within exits shall be marked by exit signs. Exit sign placement shall be such that no point in an exit access corridor or exit passageway is more than 100 feet or the listed viewing distance for the sign, whichever is less, from the nearest visible exit sign. (see code section for exceptions) Action required: Provide exit sign that leads into Hall 107.
Licensed Contractors Approved 02/24/2023 02/27/2023
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee for New Commercial $7,000.00 $7,000.00 Paid 03/27/2023
7232302-Commercial Excise Tax Fee $28,182.00 $28,182.00 Paid 03/27/2023
8331507-Sanitary Sewer Development Fee $3,693.00 $3,693.00 Paid 03/27/2023
8350015-Water Meter Fee $884.21 $884.21 Paid 03/27/2023
8331401-Water Tap Fee $9,945.00 $9,945.00 Paid 03/27/2023
9110071-Site Grading Fee $940.03 $940.03 Paid 03/27/2023
9110081-Paved Surface Inspection Fee $10,366.59 $10,366.59 Paid 03/27/2023
9110068-Storm Sewer Inspection Fee $1,388.40 $1,388.40 Paid 03/27/2023
91100C9-Water Insp Fee $1,782.96 $1,782.96 Paid 03/27/2023
91100C8-Sanitary Sewer Insp Fees $18.65 $18.65 Paid 03/27/2023
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 03/27/2023
9110069-After Hours Inspections (Public Works)(Per Hour) $250.00 $250.00 Paid 10/03/2023
9110078-Temporary Occupancy Fee $50.00 $50.00 Paid 10/26/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Site Visit Partial 3/30/2023 3/30/2023 03/30/2023
Misc
Corrective Action Required
03/30/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17
Site Visit Partial 04/18/2023
Misc
Informational
04/18/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions.
Erosion Control Inspection Residential Partial 04/18/2023
Misc
Informational
04/18/2023
4-18-23 RH. Silt fence is set up on site and in working order.
Site Visit Partial 4/19/2023 4/19/2023 04/19/2023
Misc
Informational
04/18/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today.
Erosion Control Inspection Residential Partial 4/20/2023 4/20/2023 04/20/2023
Misc
Informational
04/20/2023
4-20-23 RH. Erosion control is up and in working order.
Site Visit Partial 4/21/2023 4/21/2023 04/21/2023
Misc
Informational
04/19/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM.
Erosion Control Inspection Residential Partial 4/24/2023 4/24/2023 04/24/2023
Misc
Informational
04/20/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order.
Site Visit Partial 4/24/2023 4/24/2023 04/24/2023
Misc
Informational
04/21/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM.
Site Visit Partial 04/24/2023
Misc
Informational
04/24/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 7-6-23 BR No work on site for development. Contractor working on building framing.
Site Visit Partial 04/25/2023
Misc
Informational
04/24/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM.
Site Visit Partial 4/26/2023 4/26/2023 04/26/2023
Misc
Informational
04/25/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM.
Site Visit Partial 04/27/2023
Misc
Informational
04/26/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development.
Site Visit Partial 04/28/2023
Misc
Informational
04/27/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development.
Erosion Control Inspection Residential Partial 5/1/2023 5/1/2023 05/01/2023
Misc
Informational
04/24/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order. 5-1-23 RH. Erosin Control is up and in working order.
Footing Inspection - Commercial Partial 5/1/2023 (1:00) 5/1/2023 05/01/2023
Miscellaneous Correction
Informational
05/01/2023
This is a partial pass. The footings on the south and west side have passed inspection. The southeast corner of the footing has the cooper ground
Site Visit Partial 05/02/2023
Misc
Informational
04/28/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together.
Site Visit Partial 05/02/2023
Misc
Informational
05/02/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development.
Footing Inspection - Commercial Passed 5/2/2023 (1:00) 5/2/2023 05/02/2023
Miscellaneous Correction
Informational
05/01/2023
The southeast corner of the footing has the cooper ground for the footing
Miscellaneous Inspection Passed 5/2/2023 05/02/2023
Misc
Informational
05/02/2023
The cooper ground for the footing is located at the southeast corner of the building
Site Visit Partial 5/3/2023 5/3/2023 05/03/2023
Misc
Informational
05/02/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today.
Footing Inspection - Commercial Passed 5/3/2023 (1:00) 5/3/2023 05/03/2023
Pavement-Stabilized Subgrade Partial 05/04/2023
Misc
Informational
05/04/2023
5-4-23 RH. The SE side of the building had parking lot graded out. Geo grid was then placed overlapping 1'. Base rock will be brought in later today to go over the top of the geogrid. 8-17-23 RH. Geogrid was place for parking lot and overlapped by 1'. Contractor will continue to lay geogrid and then cover with compacted aggregate tomorrow. 8-25-23 BR Contractor performed a proof roll that was successful ready for asphalt base. 8-30-23 BR Contractor poured curbs with LS specification in parking lot.
Pavement-Aggregate Base Partial 5/5/2023 5/5/2023 05/05/2023
Misc
Informational
05/05/2023
5-5-23 RH. Aggregate base was placed on top of geogrid that was placed on the South East side of the parking lot. 8-10-23 PS Contractor placing and spreading aggregate at rear east side of buliding at dock area 9-13-23 BR Contractor placing 4'' asphalt base (type 1) over compacted subgrade. 9-14-23 BR Contractor placing 2'' asphalt surface (type 3) over asphalt base
Storm Sewer Construction Inspection Partial 05/10/2023
Misc
Informational
05/10/2023
5-10-23 RH. Storm Structus were installed for Line 3 Station 0+00 to 0+75. Correct bedding was placed for structures. Rip Rap still needs to be added to the outlet at 0+00.
Water Service Inspection Partial 5/10/2023 05/10/2023
Misc
Informational
05/10/2023
5-10-23 RH. Copper line was ran from under the footing and out to the future parking lot. Copper line will eventually be ran to the meter and then too the main.
Underslab Plumbing Inspection - Commercial Passed 5/10/2023 5/10/2023 05/10/2023
Underground Electrical Inspection - Commercial Passed 5/11/2023 5/11/2023 05/11/2023
Storm Sewer Construction Inspection Partial 05/12/2023
Misc
Informational
05/10/2023
5-10-23 RH. Storm Structus were installed for Line 3 Station 0+00 to 0+75. Correct bedding was placed for structures. Rip Rap still needs to be added to the outlet at 0+00. 5-12-23 RH. Storm Sturcture 10A for Storm Line 1 was placed over the previously poured line. Sturcture 32 at station 1+09 was placed and poured around. Collars and inlets were poured for the previous placed storm structures.
Erosion Control Inspection Residential Partial 05/12/2023
Misc
Informational
05/01/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order. 5-1-23 RH. Erosin Control is up and in working order. 5-12-23 RH. Erosion control is up and in working order for most of site. Due to Storm line being placed some silt fence was knocked down and will need fixed. Contractor is informed and will fix.
Site Visit Partial 05/15/2023
Misc
Informational
05/03/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today. 5-15-23 RH. No work for development in the AM.
Erosion Control Inspection Residential Partial 05/15/2023
Misc
Informational
05/12/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order. 5-1-23 RH. Erosin Control is up and in working order. 5-12-23 RH. Erosion control is up and in working order for most of site. Due to Storm line being placed some silt fence was knocked down and will need fixed. Contractor is informed and will fix. 5-15-23 RH. Erosion control is up and in working order for most of site. Some silt fence need repaird and contractor is fixing this week. 7-5-23 BR Erosion control is up and working order
Erosion Control Inspection Residential Partial 05/16/2023
Misc
Informational
05/15/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order. 5-1-23 RH. Erosin Control is up and in working order. 5-12-23 RH. Erosion control is up and in working order for most of site. Due to Storm line being placed some silt fence was knocked down and will need fixed. Contractor is informed and will fix. 5-15-23 RH. Erosion control is up and in working order for most of site. Some silt fence need repaird and contractor is fixing this week. 5-16-23 RH. Erosion control is up and in working order other than the silt that needs repaired. 6-19-23 BR Erosion control is up and working order 7-25-23 BR Erosion control is up and working order
Site Visit Partial 05/17/2023
Misc
Informational
05/15/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today. 5-15-23 RH. No work for development in the AM. 5-17-23 RH. Contractor is pouring the bulding pad today. No work for development in the AM.
Site Visit Partial 05/18/2023
Misc
Informational
05/17/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today. 5-15-23 RH. No work for development in the AM. 5-17-23 RH. Contractor is pouring the building pad today. No work for development in the AM. 5-18-23 RH. Contractor poured the building yesterday. No work on site for development in the AM.
Site Visit Partial 05/19/2023
Misc
Informational
05/18/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today. 5-15-23 RH. No work for development in the AM. 5-17-23 RH. Contractor is pouring the building pad today. No work for development in the AM. 5-18-23 RH. Contractor poured the building yesterday. No work on site for development in the AM. 5-19-23 RH. No work on site for development in the AM.
Erosion Control Inspection Residential Partial 05/22/2023
Misc
Informational
05/16/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order. 5-1-23 RH. Erosin Control is up and in working order. 5-12-23 RH. Erosion control is up and in working order for most of site. Due to Storm line being placed some silt fence was knocked down and will need fixed. Contractor is informed and will fix. 5-15-23 RH. Erosion control is up and in working order for most of site. Some silt fence need repaird and contractor is fixing this week. 5-16-23 RH. Erosion control is up and in working order other than the silt that needs repaired. 5-22-23 RH. Erosion control is upa nd in working order.
Site Visit Partial 05/22/2023
Misc
Informational
05/19/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today. 5-15-23 RH. No work for development in the AM. 5-17-23 RH. Contractor is pouring the building pad today. No work for development in the AM. 5-18-23 RH. Contractor poured the building yesterday. No work on site for development in the AM. 5-19-23 RH. No work on site for development in the AM. 5-22-23 RH. Fill is being moved on site to continue grading for future parking lot.
Storm Sewer Construction Inspection Partial 05/22/2023
Misc
Informational
05/12/2023
5-10-23 RH. Storm Structus were installed for Line 3 Station 0+00 to 0+75. Correct bedding was placed for structures. Rip Rap still needs to be added to the outlet at 0+00. 5-12-23 RH. Storm Sturcture 10A for Storm Line 1 was placed over the previously poured line. Sturcture 32 at station 1+09 was placed and poured around. Collars and inlets were poured for the previous placed storm structures. 5-22-23 RH. Storm structure 11 is being lowered to match grade for parking lot. 7-11-23 BR 110' of storm sewer was installed with building gutters tie into storm main on the west side the building.
Water Service Inspection Partial 05/23/2023
Misc
Informational
05/10/2023
5-10-23 RH. Copper line was ran from under the footing and out to the future parking lot. Copper line will eventually be ran to the meter and then too the main. 5-23-23 RH. Contractor exposed water main and started to set up for water line connection tonight at midnight.
Water Service Inspection Partial 05/24/2023
Misc
Informational
05/23/2023
5-10-23 RH. Copper line was ran from under the footing and out to the future parking lot. Copper line will eventually be ran to the meter and then too the main. 5-23-23 RH. Contractor exposed water main and started to set up for water line connection tonight at midnight. 5-24-23 RH. Water main was tied into for fire line.
Water Service Inspection Partial 05/24/2023
Misc
Informational
05/24/2023
5-10-23 RH. Copper line was ran from under the footing and out to the future parking lot. Copper line will eventually be ran to the meter and then too the main. 5-23-23 RH. Contractor exposed water main and started to set up for water line connection tonight at midnight. 5-24-23 RH. Water main was tied into for fire line. Thrust block will be poured tomorrow morning so dry blocks were used to hold the main.
Water Service Inspection Partial 05/25/2023
Misc
Informational
05/24/2023
5-10-23 RH. Copper line was ran from under the footing and out to the future parking lot. Copper line will eventually be ran to the meter and then too the main. 5-23-23 RH. Contractor exposed water main and started to set up for water line connection tonight at midnight. 5-24-23 RH. Water main was tied into for fire line. Thrust block will be poured tomorrow morning so dry blocks were used to hold the main. 5-25-23 RH. Thrust block was poured for water main where connection was made. Contractor is now digging rest of water line towards the building and new fire hydrant.
Erosion Control Inspection Residential Partial 6/5/2023 6/5/2023 06/05/2023
Misc
Informational
05/22/2023
4-20-23 RH. Erosion control is up and in working order. 4-24-23 RH. Erosion control is up and in working order. 5-1-23 RH. Erosin Control is up and in working order. 5-12-23 RH. Erosion control is up and in working order for most of site. Due to Storm line being placed some silt fence was knocked down and will need fixed. Contractor is informed and will fix. 5-15-23 RH. Erosion control is up and in working order for most of site. Some silt fence need repaird and contractor is fixing this week. 5-16-23 RH. Erosion control is up and in working order other than the silt that needs repaired. 5-22-23 RH. Erosion control is upa nd in working order. 6-5-23 BR. Erosion control is up and working order 6-13-23 BR Erosion control is up and working order 6-19-23 BR Erosion control is up and working order 6-27-23 BR Erosion control is up 7-5-23 BR Erosion control is up and workig order
Water Service Inspection Passed 6/1/2023 6/1/2023 06/05/2023
Misc
Informational
05/25/2023
5-10-23 RH. Copper line was ran from under the footing and out to the future parking lot. Copper line will eventually be ran to the meter and then too the main. 5-23-23 RH. Contractor exposed water main and started to set up for water line connection tonight at midnight. 5-24-23 RH. Water main was tied into for fire line. Thrust block will be poured tomorrow morning so dry blocks were used to hold the main. 5-25-23 RH. Thrust block was poured for water main where connection was made. Contractor is now digging rest of water line towards the building and new fire hydrant. 6-1-23 BR Water service line and meter installed
Underground Electrical Inspection - Commercial Failed 7/11/2023 7/11/2023 07/11/2023
Miscellaneous Correction
Informational
07/11/2023
Sweeps for secondary lines at transformer base were installed located on the east side of the lot passed inspection. This is a partial pass only
Underground Electrical Inspection - Commercial Failed 7/14/2023 07/14/2023
Miscellaneous Correction
Informational
07/11/2023
Sweeps for secondary lines at transformer base were installed located on the east side of the lot passed inspection. This is a partial pass only
Miscellaneous Correction
Informational
07/14/2023
Secondary line at transformer to about 20 feet shy of the building passed for underground electrical. This is another partial pass only 07/14/2023. KBEARD
Underground Electrical Inspection - Commercial Failed 7/27/2023 7/27/2023 07/27/2023
Miscellaneous Correction
Informational
07/14/2023
Sweeps for secondary lines at transformer base were installed located on the east side of the lot passed inspection. This is a partial pass only
Miscellaneous Correction
Informational
07/14/2023
Secondary line at transformer to about 20 feet shy of the building passed for underground electrical. This is another partial pass only 07/14/2023. KBEARD
Miscellaneous Correction
Informational
07/27/2023
Secondary line is completed and passed for underground inspection. Light pole underground will be called in at a later date.
In-wall Inspection Failed 7/28/2023 07/28/2023
Miscellaneous Correction
Informational
07/28/2023
Front of building has nine lights in the center and two lights located on either side in the upper facia that passed for pre wiring. Metal studs anchored into the masonry column were also inspected at the time of in wall inspection.
Underground Electrical Inspection - Commercial Failed 8/7/2023 08/07/2023
Miscellaneous Correction
Informational
07/27/2023
Sweeps for secondary lines at transformer base were installed located on the east side of the lot passed inspection. This is a partial pass only
Miscellaneous Correction
Informational
07/27/2023
Secondary line at transformer to about 20 feet shy of the building passed for underground electrical. This is another partial pass only 07/14/2023. KBEARD
Miscellaneous Correction
Informational
07/27/2023
Secondary line is completed and passed for underground inspection. Light pole underground will be called in at a later date.
Misc
Informational
08/07/2023
Under ground electrical for the exterior garden area passed. This is a partial pass only. 08/07/2023 KBEARD
Piers/Caissons Inspection - Commercial Failed 8/7/2023 8/7/2023 08/07/2023
Misc
Informational
08/07/2023
Piers for the exterior garden area passed. This is a partial pass only. 08/07/2023 KBEARD
Underground Electrical Inspection - Commercial Failed 8/8/2023 08/08/2023
Miscellaneous Correction
Informational
08/07/2023
Sweeps for secondary lines at transformer base were installed located on the east side of the lot passed inspection. This is a partial pass only
Miscellaneous Correction
Informational
08/07/2023
Secondary line at transformer to about 20 feet shy of the building passed for underground electrical. This is another partial pass only 07/14/2023. KBEARD
Miscellaneous Correction
Informational
08/07/2023
Secondary line is completed and passed for underground inspection. Light pole underground will be called in at a later date.
Misc
Informational
08/07/2023
Under ground electrical for the exterior garden area passed. This is a partial pass only. 08/07/2023 KBEARD
Miscellaneous Correction
Informational
08/08/2023
This is a partial pass for under ground electric for parking lot light poles only. This is only a partial pass. 08/08/2022 KBEARD
Pavement-Aggregate Base Partial 8/10/2023 8/10/2023 08/10/2023
Misc
Informational
05/05/2023
5-5-23 RH. Aggregate base was placed on top of geogrid that was placed on the South East side of the parking lot. 8-10-23 PS Contractor placing and spreading aggregate at rear east side of buliding at dock area 9-13-23 BR Contractor placing 4'' asphalt base (type 1) over compacted subgrade.
In-wall Inspection Passed 8/15/2023 8/15/2023 08/15/2023
Miscellaneous Correction
Informational
07/28/2023
Front of building has nine lights in the center and two lights located on either side in the upper facia that passed for pre wiring. Metal studs anchored into the masonry column were also inspected at the time of in wall inspection.
Miscellaneous Correction
Informational
08/15/2023
In wall is completed. Okay to insulate and sheetrock. Above ceiling needs to be exposed for inspection.
Gas Service Inspection - Commercial Passed 8/25/2023 8/25/2023 08/25/2023
Footing Inspection - Commercial Passed 8/31/2023 08/31/2023
Miscellaneous Correction
Informational
08/31/2023
This is the footing for the monument sign. No drawing for the footing were included in the blue print. The on site superintendent had detailed notes from the engineer about the footing steel and the size of the concrete slab. There is underground electrical that is in the footing to be poured. Conduit measures 27 inches deep in the footing
Piers/Caissons Inspection - Commercial Passed 9/5/2023 (9:00) 9/5/2023 09/05/2023
Miscellaneous Correction
Informational
09/05/2023
Job site superintendent said this would be the last of the pier inspections
Sprinkler - Hydrostatic Test Passed 9/7/2023 09/07/2023
Site Visit Partial 09/12/2023
Misc
Informational
05/22/2023
3-30-23 PS Construction pre con meeting took place this morning. Contractor estimates site work to begin 4-17 4-18-23 RH. Contractor has put in the construciton entrance. Contractor is on site and is digging some boreholes to check soil conditions. 4-19-23 RH. Contractor is diggin out the building pad today. 4-21-23 RH. No work on site for development in the AM. 4-24-23 RH. Contractor is placing screenings down for building pad. No work for development in the AM. Contractor continued to work on the building pad in the PM. 4-25-23 RH. Contractor continues to place lime screenings for the building pad. No work for development in the AM. 4-26-23 RH. Contractor is not doing any work on site in the AM. 4-27-23 RH. Contractor is starting to tie rebar for footings. No work for development. 4-28-23 RH. Contractor continues to work on footings for the building. No work for development. 5-1-23 RH. Contractor inspected conduit for the electrical going under the future parking lot of enctrance to job site. Conduit was 36" deep and all glued together. 5-2-23 RH. Contractor contiunes to dig trenches for underground electric. No work for development. 5-3-23 RH. Contractor is planning to place geogrid later today. 5-15-23 RH. No work for development in the AM. 5-17-23 RH. Contractor is pouring the building pad today. No work for development in the AM. 5-18-23 RH. Contractor poured the building yesterday. No work on site for development in the AM. 5-19-23 RH. No work on site for development in the AM. 5-22-23 RH. Fill is being moved on site to continue grading for future parking lot. 9-22-23 A.A Checked in with super, pushed asphalt off till tomarrow
Pavement-Stabilized Subgrade Passed 09/19/2023
Misc
Informational
05/04/2023
5-4-23 RH. The SE side of the building had parking lot graded out. Geo grid was then placed overlapping 1'. Base rock will be brought in later today to go over the top of the geogrid. 8-17-23 RH. Geogrid was place for parking lot and overlapped by 1'. Contractor will continue to lay geogrid and then cover with compacted aggregate tomorrow. 8-25-23 BR Contractor performed a proof roll that was successful ready for asphalt base. 8-30-23 BR Contractor poured curbs with LS specification in parking lot. 9-8-23 BR Contractor performed 2nd proof roll on parking lot that was successful ready for asphalt base. 9-15-23 BR Contractor performed stripping on parking lot.
Electrical Service Inspection Failed 9/21/2023 9/21/2023 09/21/2023
Misc
Corrective Action Required
09/21/2023
-Only 1 conductor per lug unless lug is listed for two conductors -Tighten water grounding connection -Provide min #1 copper EGC for each feeder parallel set -Ground service to steel with 2/0 copper GEC -Install 2/0 CU jumper around water line insulating backflow valve
Electrical Service Inspection Passed 9/21/2023 09/21/2023
Misc
Resolved
09/21/2023
-Only 1 conductor per lug unless lug is listed for two conductors -Tighten water grounding connection -Provide min #1 copper EGC for each feeder parallel set -Ground service to steel with 2/0 copper GEC -Install 2/0 CU jumper around water line insulating backflow valve
Underground Electrical Inspection - Commercial Passed 10/5/2023 10/05/2023
Miscellaneous Correction
Informational
08/08/2023
Sweeps for secondary lines at transformer base were installed located on the east side of the lot passed inspection. This is a partial pass only
Miscellaneous Correction
Informational
08/08/2023
Secondary line at transformer to about 20 feet shy of the building passed for underground electrical. This is another partial pass only 07/14/2023. KBEARD
Miscellaneous Correction
Informational
08/08/2023
Secondary line is completed and passed for underground inspection. Light pole underground will be called in at a later date.
Misc
Informational
08/08/2023
Under ground electrical for the exterior garden area passed. This is a partial pass only. 08/07/2023 KBEARD
Miscellaneous Correction
Informational
08/08/2023
This is a partial pass for under ground electric for parking lot light poles only. This is only a partial pass. 08/08/2022 KBEARD
Miscellaneous Correction
Informational
10/05/2023
All under ground electrical has been completed
Above Ceiling Inspection Passed 10/12/2023 10/12/2023 10/12/2023
Storm Sewer Construction Inspection Passed 7/14/2023 7/14/2023 10/25/2023
Misc
Informational
05/22/2023
5-10-23 RH. Storm Structus were installed for Line 3 Station 0+00 to 0+75. Correct bedding was placed for structures. Rip Rap still needs to be added to the outlet at 0+00. 5-12-23 RH. Storm Sturcture 10A for Storm Line 1 was placed over the previously poured line. Sturcture 32 at station 1+09 was placed and poured around. Collars and inlets were poured for the previous placed storm structures. 5-22-23 RH. Storm structure 11 is being lowered to match grade for parking lot. 7-14-23 PS Collar poured and invert poured for storm structure #35 10-25-23 BR Storm structure is installed and working properly.
Sanitary Sewer Construction Inspection Passed 8/10/2023 (1:30) 8/10/2023 10/25/2023
Misc
Informational
08/10/2023
Site visited and it appears that the sewer tie in meets city standards. they are going to pour concrete at 2pm. 10-25-23 BR Sanitary sewer structure is installed and working properly.
Occupancy Inspection - Engineering Temporary C of O 10/25/2023 10/25/2023 10/25/2023
Misc
Corrective Action Required
10/25/2023
10-25-23 BR There is no corrections to be done.
Occupancy Inspection - Codes Commercial Failed 10/25/2023 10/25/2023 10/25/2023
Miscellaneous Correction
Corrective Action Required
10/25/2023
- All departments must pass their inspections (Fire and water). - Label electrical panels - Label roof top RTU’s - Adjust roof hatch to to allow easy lock and unlocking
Gas Piping Inspection - Commercial Passed 10/25/2023 10/25/2023
Sprinkler - Flow Test Passed 10/25/2023 10/25/2023
Alarm Test Passed 10/25/2023 10/25/2023
Occupancy Inspection - Fire Temporary C of O 10/25/2023 10/25/2023 10/25/2023
Occupancy Inspection - Planning Passed 10/25/2023 10/25/2023 10/26/2023
Occupancy Inspection - Engineering Passed 10/26/2023 10/26/2023
Misc
Corrective Action Required
10/25/2023
10-25-23 BR There is no corrections to be done.
Occupancy Inspection - Codes Commercial Ready for Temp CO 10/26/2023 10/26/2023
Miscellaneous Correction
Corrective Action Required
10/25/2023
- All departments must pass their inspections (Fire and water). - Label electrical panels - Label roof top RTU’s
Miscellaneous Correction
Corrective Action Required
10/26/2023
All departments must pass their inspections (Fire and water). - Label electrical panels - Label roof top RTU’s Passed for TCO only KBEARD 10/26/2023
Occupancy Inspection - Codes Commercial Full C of O 11/2/2023 11/3/2023 11/03/2023
Miscellaneous Correction
Resolved
11/03/2023
- All departments must pass their inspections (Fire and water). - Label electrical panels - Label roof top RTU’s
Miscellaneous Correction
Resolved
11/03/2023
All departments must pass their inspections (Fire and water). - Label electrical panels - Label roof top RTU’s Passed for TCO only KBEARD 10/26/2023
Occupancy Inspection - Fire Passed 11/3/2023 11/3/2023 11/03/2023
Documents & Images
Date Uploaded File Type Document Name
02/24/2023 Application Form APPLICATION
02/26/2023 Engineer Report/Study 22-365 Westlake Ace Hardware - Lee's Summit, MO Calculations 2022-12-23
02/26/2023 Engineer Report/Study 2022_04_25 Market Street Center Geotech Report
02/26/2023 Plans 2023-02-24 Westlake 3511 SW Market Permit Drawings
02/27/2023 Letter License Tax Bill
03/10/2023 Letter Fire Building Plan Review
03/13/2023 Letter DS P/R Corrections Document
03/20/2023 Plans 2023-03-20 Westlake 3511 SW Market Permit Drawings rev1
03/20/2023 Letter 2023-03-20 Westlake ACE Plan Review Response Letter
03/20/2023 Engineer Report/Study Westlake Special Inspection Intent Letter
03/23/2023 Approved Plans Approved FDP_032323_2023-03-16 Market Street Center - Lot 2 FDP
03/27/2023 Receipt Receipt for transaction:2023-001710
03/29/2023 Letter Fire Building Plan Review
03/30/2023 Approved Plans Approved - Westlake 3511 SW Market Permit Drawings rev1
03/30/2023 Letter DS Building Permit
03/30/2023 Letter INSPECTION SUMMARY
04/05/2023 28-01 - Fire Alarm Shop Drawings
04/11/2023 Letter Fire (Alarm) Plan Review Notice
04/18/2023 Letter INSPECTION SUMMARY
04/18/2023 Letter INSPECTION SUMMARY
04/19/2023 Letter INSPECTION SUMMARY
04/20/2023 Letter INSPECTION SUMMARY
04/21/2023 Letter INSPECTION SUMMARY
04/24/2023 Letter INSPECTION SUMMARY
04/24/2023 Letter INSPECTION SUMMARY
04/24/2023 Letter INSPECTION SUMMARY
04/25/2023 Letter INSPECTION SUMMARY
04/25/2023 PRCOM20230813 Parking Subgrade RFI Approval
04/26/2023 Letter INSPECTION SUMMARY
04/26/2023 28-01 R1 - REV1 Fire Alarm Shop Drawings
04/27/2023 Letter INSPECTION SUMMARY
04/28/2023 Letter INSPECTION SUMMARY
05/01/2023 Letter INSPECTION SUMMARY
05/01/2023 Letter INSPECTION SUMMARY
05/02/2023 Conduit For Electrical 2
05/02/2023 Conduit For Electrical 3
05/02/2023 Conduit For Electrical
05/02/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/02/2023 Letter INSPECTION SUMMARY
05/03/2023 Letter INSPECTION SUMMARY
05/03/2023 Letter INSPECTION SUMMARY
05/04/2023 Letter INSPECTION SUMMARY
05/05/2023 Letter INSPECTION SUMMARY
05/10/2023 West Lakes Geo Grid 5-5-23
05/10/2023 Fire Line 1
05/10/2023 Fire Line 2
05/10/2023 Fire Line 3
05/10/2023 Fire Line 4
05/10/2023 Letter INSPECTION SUMMARY
05/10/2023 Letter INSPECTION SUMMARY
05/10/2023 Water Line 5-10-23
05/10/2023 Storm Sturcture 31
05/10/2023 Letter INSPECTION SUMMARY
05/11/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
05/12/2023 Letter INSPECTION SUMMARY
05/15/2023 Letter INSPECTION SUMMARY
05/15/2023 Letter INSPECTION SUMMARY
05/16/2023 Letter INSPECTION SUMMARY
05/17/2023 Letter INSPECTION SUMMARY
05/18/2023 Letter INSPECTION SUMMARY
05/19/2023 Letter INSPECTION SUMMARY
05/19/2023 WLS - Propane Haz Mat Application
05/22/2023 Letter INSPECTION SUMMARY
05/22/2023 Letter INSPECTION SUMMARY
05/22/2023 Letter INSPECTION SUMMARY
05/23/2023 Letter INSPECTION SUMMARY
05/24/2023 Letter INSPECTION SUMMARY
05/24/2023 Water Tie In 5-24-23
05/24/2023 Letter INSPECTION SUMMARY
05/25/2023 Letter INSPECTION SUMMARY
05/25/2023 Thrust Block Concrete Ticket
05/25/2023 Backflow Vault
05/25/2023 Backflow Vault Fabric
05/25/2023 Thrust Block on Main
05/26/2023 Backflow Value
05/26/2023 Fire Hydrant
05/26/2023 Staraddle Block
05/26/2023 Backing Block on Tee
05/31/2023 Service line
05/31/2023 Meter Pit
05/31/2023 Water Tap on main
06/05/2023 Letter INSPECTION SUMMARY
06/05/2023 Letter INSPECTION SUMMARY
06/08/2023 Drawing 2023-06-08 Westlake LS Updated Arch A2_1
06/08/2023 Plans 2023-06-08 Westlake LS Updated Civil
06/08/2023 Plans 2023-06-08 Westlake LS Updated structural S1_1 S3_2
06/13/2023 Letter INSPECTION SUMMARY
06/15/2023 Approved Plans approved revisions
06/15/2023 Approved Plans FDP APPROVED CIVIL REVISIONS_2023-06-08 Westlake LS Updated Civil Drawings
06/20/2023 Letter INSPECTION SUMMARY
07/05/2023 Letter INSPECTION SUMMARY
07/07/2023 Letter INSPECTION SUMMARY
07/11/2023 Letter INSPECTION SUMMARY
07/11/2023 Letter INSPECTION SUMMARY
07/14/2023 Letter INSPECTION SUMMARY
07/14/2023 Letter INSPECTION SUMMARY
07/27/2023 Letter INSPECTION SUMMARY
07/28/2023 Westlake Lees summit Stamped FP plans 7-27-23
07/28/2023 Westlake Lees Summit Stamped retail calcs 7-27-23
07/28/2023 Westlake Lees Summit Stamped dry calcs 7-27-23
07/28/2023 Letter INSPECTION SUMMARY
08/07/2023 Letter INSPECTION SUMMARY
08/07/2023 Letter INSPECTION SUMMARY
08/08/2023 Letter INSPECTION SUMMARY
08/10/2023 Letter Fire (Sprinkler) Plan Review
08/10/2023 Letter INSPECTION SUMMARY
08/10/2023 Letter INSPECTION SUMMARY
08/15/2023 Letter INSPECTION SUMMARY
08/17/2023 Geogrid 1
08/17/2023 Geogrid 2
08/17/2023 Letter INSPECTION SUMMARY
08/25/2023 Letter INSPECTION SUMMARY
08/25/2023 Westlake Proof Roll ticket
08/25/2023 Letter INSPECTION SUMMARY
08/30/2023 Letter INSPECTION SUMMARY
08/31/2023 Letter INSPECTION SUMMARY
09/05/2023 Letter INSPECTION SUMMARY
09/06/2023 Westlake Lees summit Stamped FP plans 9-6-23 FDC change
09/06/2023 Grinder Pump 1
09/06/2023 Grinder Pump 2
09/06/2023 Grinder Pump Line 1
09/06/2023 Grinder Pump Line 2
09/06/2023 Grinder Pump Line 3
09/06/2023 Grinder Pump Line 4
09/11/2023 3'' Retaining Wall 2
09/11/2023 3'' Retaining Wall 3
09/11/2023 3'' Retaining Wall
09/11/2023 3'' Retaining Wall 4
09/12/2023 Letter INSPECTION SUMMARY
09/12/2023 Letter INSPECTION SUMMARY
09/13/2023 Letter INSPECTION SUMMARY
09/15/2023 Letter INSPECTION SUMMARY
09/19/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter INSPECTION SUMMARY
09/21/2023 Letter Fire (Sprinkler) Plan Review
09/21/2023 Westlake Lees summit Stamped FP plans 9-6-23 FDC change APPROVED
10/03/2023 Receipt Receipt for transaction:2023-007474
10/03/2023 3rd Party Letter of Acceptance
10/05/2023 Letter INSPECTION SUMMARY
10/12/2023 Letter INSPECTION SUMMARY
10/24/2023 Westlake Lees summit Stamped FP plans 9-6-23 FDC change
10/24/2023 Signed Hydro Static test papers 9-7-23
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 Letter INSPECTION SUMMARY
10/25/2023 WLS - Water Service Backflow Report
10/26/2023 Letter INSPECTION SUMMARY
10/26/2023 Certificate/License Codes Temporary Certificate of Occupancy
10/26/2023 Receipt Receipt for transaction:2023-008077
11/01/2023 WLS - Fire Backflow Reports
11/03/2023 Letter Codes Final Certificate of Occupancy
11/03/2023 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home