Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Underground Electrical Inspection - Commercial
|
Partial
|
3/16/2017
|
3/16/2017
|
03/16/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
2/21/2017 (9:00)
|
5/11/2017
|
05/11/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
5/12/2017
|
5/12/2017
|
05/12/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Partial
|
5/15/2017
|
5/15/2017
|
05/15/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
|
Misc
Corrective Action Required
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/16/2017
|
5/16/2017
|
05/16/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/19/2017
|
5/19/2017
|
05/19/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/23/2017
|
5/23/2017
|
05/23/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
5/25/2017
|
5/25/2017
|
05/25/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
6/1/2017
|
6/1/2017
|
06/01/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Not Ready
|
6/2/2017
|
6/7/2017
|
06/07/2017
|
Electrical Service Inspection
|
Partial
|
|
6/9/2017
|
06/09/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
6/9/2017
|
6/9/2017
|
06/09/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
5/25/2017
|
6/26/2017
|
06/26/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
6/27/2017
|
6/27/2017
|
06/27/2017
|
|
Misc
Corrective Action Required
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
7/3/2017
|
6/30/2017
|
06/30/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Not Ready
|
|
7/3/2017
|
07/03/2017
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rough Framing Inspection - Commercial
|
Partial
|
7/7/2017
|
7/7/2017
|
07/07/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
7/13/2017
|
7/13/2017
|
07/13/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
7/14/2017
|
7/14/2017
|
07/14/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
7/17/2017
|
7/17/2017
|
07/17/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
7/17/2017
|
7/17/2017
|
07/17/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
7/19/2017
|
7/19/2017
|
07/19/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
7/19/2017
|
07/19/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
7/20/2017
|
07/20/2017
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
7/19/2017
|
7/21/2017
|
07/21/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
7/20/2017
|
7/21/2017
|
07/21/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
7/24/2017
|
7/24/2017
|
07/24/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Not Ready
|
|
7/24/2017
|
07/24/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
7/25/2017
|
7/25/2017
|
07/25/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
7/25/2017
|
7/25/2017
|
07/25/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Not Ready
|
7/27/2017
|
7/27/2017
|
07/27/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
Sprinkler - Hydrostatic Test
|
Passed
|
|
7/28/2017
|
07/28/2017
|
All Rough Inspection - Commercial
|
Failed
|
8/1/2017
|
8/1/2017
|
08/01/2017
|
|
Misc
|
|
Misc
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
8/2/2017
|
08/02/2017
|
|
Misc
|
|
Misc
Corrective Action Required
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/3/2017
|
8/3/2017
|
08/03/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/3/2017
|
8/3/2017
|
08/03/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
8/7/2017
|
08/07/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
8/8/2017
|
08/08/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/14/2017
|
8/14/2017
|
08/14/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/15/2017
|
8/15/2017 at 1:40 PM
|
08/15/2017
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
8/15/2017
|
08/15/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/16/2017
|
8/16/2017 at 1:10 PM
|
08/16/2017
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
8/17/2017 at 1:15 PM
|
08/17/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/17/2017
|
8/17/2017 at 2:25 PM
|
08/17/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/18/2017
|
8/18/2017 at 1:15 PM
|
08/18/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/21/2017
|
8/21/2017 at 12:35 PM
|
08/21/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/24/2017
|
8/24/2017 at 8:15 AM
|
08/24/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/21/2017
|
8/24/2017 at 9:15 AM
|
08/24/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/25/2017
|
8/25/2017 at 10:25 AM
|
08/25/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
8/25/2017 at 11:10 AM
|
08/25/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/28/2017
|
8/28/2017 at 3:05 PM
|
08/28/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
8/29/2017 at 2:20 PM
|
08/29/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
8/29/2017 at 2:35 PM
|
08/29/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
8/30/2017
|
8/30/2017 at 1:00 PM
|
08/30/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Partial
|
8/8/2017
|
8/30/2017 at 1:45 PM
|
08/30/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
8/31/2017
|
8/31/2017 at 1:20 PM
|
08/31/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
|
8/31/2017 at 2:15 PM
|
08/31/2017
|
|
Misc
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
|
9/6/2017 at 12:50 PM
|
09/06/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Partial
|
9/14/2017
|
9/14/2017 at 1:45 PM
|
09/14/2017
|
|
Misc
|
|
Misc
|
Electrical Service Inspection
|
Partial
|
9/26/2017
|
9/26/2017 at 4:00 PM
|
09/26/2017
|
|
Misc
|
|
Misc
|
Electrical Service Inspection
|
Passed
|
10/10/2017
|
10/10/2017 at 3:20 PM
|
10/10/2017
|
|
Misc
|
|
Misc
|
All Rough Inspection - Commercial
|
Passed
|
|
9/14/2017
|
11/08/2017
|
|
Misc
|
|
Misc
|
Underground Electrical Inspection - Commercial
|
Passed
|
5/25/2017
|
3/16/2017
|
11/08/2017
|
|
Misc
|
Rated Assembly Inspection
|
Passed
|
|
9/6/2017
|
11/08/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Rough Framing Inspection - Commercial
|
Passed
|
|
8/30/2017
|
11/08/2017
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
|
Misc
|
Miscellaneous Inspection
|
Partial
|
|
11/8/2017 at 4:00 PM
|
11/08/2017
|
Miscellaneous Inspection
|
Partial
|
|
11/20/2017 at 4:25 PM
|
11/20/2017
|
Miscellaneous Inspection
|
Partial
|
|
11/22/2017 at 11:35 AM
|
11/22/2017
|
Miscellaneous Inspection
|
Partial
|
|
11/27/2017 at 7:30 AM
|
11/27/2017
|
Miscellaneous Inspection
|
Not Ready
|
|
11/29/2017 at 1:55 PM
|
11/29/2017
|
Miscellaneous Inspection
|
Partial
|
|
12/4/2017 at 3:05 PM
|
12/04/2017
|
Miscellaneous Inspection
|
Partial
|
|
12/6/2017 at 7:00 AM
|
12/06/2017
|
Miscellaneous Inspection
|
Partial
|
|
12/7/2017 at 7:00 AM
|
12/07/2017
|
Alarm Test
|
Failed
|
|
12/7/2017
|
12/07/2017
|
Sprinkler - Flow Test
|
Passed
|
|
12/7/2017
|
12/07/2017
|
Miscellaneous Inspection
|
Partial
|
|
12/7/2017 at 9:50 AM
|
12/07/2017
|
|
|
Miscellaneous Inspection
|
Partial
|
|
12/8/2017 at 7:10 AM
|
12/08/2017
|
|
Misc
|
Alarm Test
|
Passed
|
|
12/11/2017
|
12/11/2017
|
Occupancy Inspection - Fire
|
Failed
|
|
12/12/2017
|
12/12/2017
|
Miscellaneous Inspection
|
Partial
|
|
12/12/2017 at 9:15 AM
|
12/12/2017
|
|
Misc
|
Miscellaneous Inspection
|
Partial
|
|
12/12/2017 at 12:25 PM
|
12/12/2017
|
|
Misc
|
Miscellaneous Inspection
|
Passed
|
|
12/12/2017 at 2:00 PM
|
12/12/2017
|
|
Misc
|
Occupancy Inspection - Codes Commercial
|
Failed
|
12/12/2017
|
12/12/2017 at 3:30 PM
|
12/12/2017
|
|
Misc
Corrective Action Required
|
Occupancy Inspection - Codes Commercial
|
Full C of O
|
|
12/13/2017 at 9:35 AM
|
12/13/2017
|
|
Misc
|
Occupancy Inspection - Fire
|
Passed
|
|
12/13/2017
|
12/13/2017
|
Occupancy Inspection - Water Utilities
|
Passed
|
|
|
12/13/2017
|
Occupancy Inspection - Engineering
|
Passed
|
|
|
12/14/2017
|
Occupancy Inspection - Planning
|
Passed
|
|
|
12/14/2017
|