Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
04/10/2025
|
04/10/2025
|
|
Gene Williams, P.E.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap, meter setup, and sanitary impact fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $70,726.20
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a project coordination meeting with the assigned Field Engineering Inspector.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
|
Fire Review
|
Approved with Conditions
|
04/10/2025
|
04/08/2025
|
|
Jim Eden
|
|
Miscellaneous Correction
Corrective Action Required
The FDC Storz connection shall be 4 inch and not the 6 inch that is shown.
|
|
|
Building Codes Review
|
Approved with Conditions
|
03/12/2025
|
03/12/2025
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural/structural/MEP plans provided are not part of this review.
1/15/2025 - Acknowledged in letter.
|
|
|
Engineering Review
|
Corrections
|
03/12/2025
|
03/10/2025
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Sheet C119: 1. PVC water line is called-out, but C900 DR18 pipe is required. Correction required. 2. See comments related to the end of the line at N1017940.27/E2825902.43. A "clean" end of line pointing due west is required with a plug and a valve to facilitate easy extension in the future. Correction required. 3. Stationing was not provided on the plan view to coincide with the stationing shown on the profile view on Sheet C121. Correction required to show basic stationing on the public water main and private fire line. 4. PVC private sanitary sewer lateral was shown but not called-out in terms of DR. Minimum shall be SDR 26 for private sanitary sewer laterals, and shall be shown on the plan view and/or profile view (callout also missing on plan view on Sheet C121). 5. Missing domestic water line pipe material (8 inch copper is called-out, but see previous comments related to this issue). Assuming the line will be approximately 2 inch copper due to the short length and the fact copper is required from main to meter, and minimum 10 feet beyond meter which is very close to the building. Evaluation of pipe size and material required. 6. Connection to the water main shall be a threaded connection (i.e., corporation stop) to be installed by Water Utilities staff for all connections 2 inches and smaller, and shall be a tee for connections greater than 2 inches. Show the appropriate connection method and connection point to the main via notation and stationing on the plan view.
|
|
Corrective Action Required
Sheet C121: 1. Refer to previous applicant letter concerning the profile view of water line W-1. PVC line is called-out, but the City requires C900 DR18 line, not PVC. Correction required. 2. Profile shows a 2 inch domestic water meter, but plan view on Sheet C119 shows a 2.5 inch meter. Reconcile the meter size on the plans, while recognizing the City does not sell a 2.5 inch water meter and does not allow 2.5 inch meters. 3. 8 inch public line west of coordinate 1017940.27/E2825902.43 should be extended to a point due west where a plug and valve can be installed creating a "clean" end of line (i.e., ending in a straight line) rather than as shown. This will allow for a future extension of the public water line with minimal impact. 4. You are not allowed to install a 90 degree fitting and direct-connect an 8 inch main to the water meter as shown. Correction required in accordance with the above comments. 5. Profile view for water line W-1 does not make sense. See comments above about prohibition of connecting an 8 inch public main to a water meter. 6. There are callouts for the copper line on the profile view that do not make sense. This profile view of this line shall be revised to show the extent of the public line to the end of the line, and there should be no 90 degree fittings, "terminal tie-ins", or other shown not in accordance with the plan view. 7. The "8 inch copper waterline pipe" note on the plans is shown on the public portion of the water line and is not allowed. C900 DR18 line is required. 8. Profile view of FS-1 is showing PVC line. The City requires C900 DR18, not PVC. 9. Profile view W-1 has a note specifying "connect to existing fire hydrant". Connecting to a fire hydrant is not allowed. 9. Recommend contacting me. There appear to be misunderstandings on water meter installation requirements specific to the City of Lee's Summit.
|
|
Corrective Action Required
Submit a pdf version of the cost estimate with signature and seal by a design professonal registered in the State of Missouri. The following items shall be required: 1. grading to establish proper drainage, 2. grading and compaction of the parking area, 3. pavement and curb and gutter, 4, aggregate base, including the area one (1) foot beyond the back of curb, 5. geogrid if applicable, including the area one (1) foot beyond the back of curb, 6. storm drainage structures such as inlets, junction boxes, and manholes, 7. storm lines greater than 10 inches diameter, 8. fire line, 9. domestic water line, 10. public water line extension, gates valves, fire hydrant relocation, 11. private sanitary sewer line, 12. private sanitary sewer manhole, 13. wye connection, 14. water main connections via tee or corporation stop, 15. erosion and sediment control devices, 16. final restoration including sodding, seeding, mulch, topsoil, and fertilizer.
|
|
|
Fire Review
|
Approved with Conditions
|
03/12/2025
|
03/05/2025
|
|
Jim Eden
|
|
Miscellaneous Correction
Corrective Action Required
The FDC Storz connection shall be 4 inch and not the 6 inch that is shown.
|
|
|
Fire Review
|
No Comments
|
02/26/2025
|
03/05/2025
|
|
Jim Eden
|
|
|
Engineering Review
|
Corrections
|
02/26/2025
|
02/26/2025
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
SWPPP was not signed or sealed by a design professional registered in the State of Missouri. Correction required.
|
|
Corrective Action Required
Stormwater report was not signed or sealed by a design professional registered in the State of Missouri Correction required.
|
|
Corrective Action Required
Sheet C119: See previous comment letter concerning the fire line. You are showing a gas line entering the building with a note calling out an interior backflow device for the fire line. However, this makes no sense. It appears the gas line was misinterpreted as a fire line. Correction required.
|
|
Corrective Action Required
A profile view of the extended 8 inch water main was missing. Correction required.
|
|
Corrective Action Required
A profile view of the fire line was missing Correction required.
|
|
Corrective Action Required
See previous comments related to fire line sizing and materials. These features shall be shown on the plan. Correction required,
|
|
Corrective Action Required
See previous comments related to domestic water line. A complete notation of materials and pipe size shall be shown on the plans, including the copper line from the main to the meter, and a minimum of ten (10) feet beyond the meter. All of this shall be copper. The remainder may be other materials as allowed by building code. Correction required
|
|
|
Building Codes Review
|
Approved with Conditions
|
02/26/2025
|
02/25/2025
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Architectural/structural/MEP plans provided are not part of this review.
1/15/2025 - Acknowledged in letter.
|
|
|
Planning Review
|
No Comments
|
02/26/2025
|
02/24/2025
|
|
Hector Soto Jr.
|
|
|
Traffic Review
|
No Comments
|
01/17/2025
|
01/21/2025
|
|
Grant White
|
|
|
Engineering Review
|
Corrections
|
01/17/2025
|
01/16/2025
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
Refer to comment #1 in previous applicant letter. We are still missing the stormwater memorandum. Correction required.
|
|
Corrective Action Required
Refer to comment #3 in previous applicant letter. A SWPPP was not submitted. Correction required.
|
|
Corrective Action Required
Refer to comment #4 in previous applicant letter. You are still showing the 4 inch private sanitary sewer lateral connecting directly to manhole MH-6. A wye connection is required, and shall be shown a minimum of 4.0 feet from the outside of the manhole to the beginning portion of the wye. Correction required.
|
|
Corrective Action Required
Refer to comment #5 in the previous applicant letter. Sheet C119 does not make sense. You are showing two undefined water lines with no legend or label showing what each line represents including material and sizing, and you are showing a label for a 2 inch meter which points to nothing. You are showing the two undefined lines beneath a monument sign, which is not good practice. Correction required.
|
|
Corrective Action Required
FS-1 and WL-1 shall be explicitly defined on Sheet C119 by legend or other appropriate method. Correction required.
|
|
Corrective Action Required
You are showing an extension of the 8 inch water main to the west, and relocation of the fire hydrant. Wouldn't it be easier to connect the domestic and fire line to this 8 inch line rather than the 12 inch line to the east? It is quite a bit less distance. You will need to confirm the sizing is adequate for fire flow. Corrections required.
|
|
Corrective Action Required
You will need to install a backflow vault with backflow device on the fire line if the water main is greater than 50 feet from the building. Correction required.
|
|
Corrective Action Required
You will need to show how the backflow vault drains at the sump, either by daylighting or connection to storm structure, or installation of sump pump.
|
|
Corrective Action Required
Missing the materials used for domestic line and fire line. Correction required.
|
|
Corrective Action Required
Wouldn't it be easier to install the water meter to the 8 inch line, similar to the fire line? Correction required.
|
|
Corrective Action Required
Missing the sizing of the fire line and domestic line. Correction required.
|
|
Corrective Action Required
Cost estimate shall be signed and sealed by a design professional registered in the State of Missouri. Correction required.
|
|
|
Building Codes Review
|
Approved with Conditions
|
01/17/2025
|
01/15/2025
|
|
Joe Frogge
|
|
Miscellaneous Correction
2" sprinkler and 6" domestic? Assuming this is just typos, relabel.
|
|
Miscellaneous Correction
Specify types of water pipe connections at main.
|
|
Miscellaneous Correction
Specify water and sanitary piping materials.
|
|
Miscellaneous Correction
Corrective Action Required
Architectural/structural/MEP plans provided are not part of this review.
1/15/2025 - Acknowledged in letter.
|
|
|
Fire Review
|
Complete
|
01/17/2025
|
01/14/2025
|
|
Jim Eden
|
|
FDC
IFC 903.3.7 - Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
Show the location of the FDC on the building.
|
|
|
Planning Review
|
Corrections
|
01/17/2025
|
01/13/2025
|
|
Hector Soto Jr.
|
|
Corrective Action Required
ACCESSIBLE PARKING SPACES/ACCESSIBLE ROUTE. 1) The site plan (Sheet C105) appears to show the bollard in which the ADA signs will be posted located approximately 2' in from the head of the stall, which reduces the effective stall depth so as not to comply with City's minimum 19' stall depth. 2) The site plan show wheel stops at the head of the parking spaces. City ordinance does not allow the use of wheel stops, except at the head of accessible parking spaces when they are adjacent to a pedestrian walkway with no raised curb.
The two previously made comments have been addressed on some plan sheets, but not others. Revise Sheets C105, C129 and L100 accordingly.
|
|
Corrective Action Required
PARKING SPACE DIMENSIONS. The double-row of parking spaces are dimensioned on sheet C131 as having a total depth of 36', which is 18' depth per stall. City ordinance requires a minimum 19' stall depth for all parking spaces, except that stall depth may be reduced by 2' (i.e. 17' stall depth) where the head of the space(s) is/are adjacent to a minimum 6'-wide sidewalk or open area. To illustrate, the easternmost row of parking that fronts onto the landscape area can be reduced from 19' (as currently dimensioned) to 17'.
The previously made comment above has been addressed on some plan sheets, but not others. Revise Sheets C105, C129 and L100 accordingly.
|
|
|
Engineering Review
|
Corrections
|
12/13/2024
|
12/13/2024
|
|
Gene Williams, P.E.
|
|
Corrective Action Required
A stormwater memorandum is required. It shall discuss the regional detention basin under construction, and whether the detention basin will be sufficient to manage stormwater detention for this site in accordance with Section 5600 detention requirements. Correction required.
|
|
Corrective Action Required
Parking lot shall provide sufficient detail to determine whether it meets ADA-accessibility standards. This includes slope callouts, elevation callouts, dimensions, etc. Correction required.
|
|
Corrective Action Required
If greater than 1 acre disturbed area, a SWPPP is required. Informational comment.
|
|
Corrective Action Required
Direct connection of private sanitary sewer laterals cannot be made to the public manholes. A cut-in tee is required. Corrections required on all.
|
|
Corrective Action Required
Domestic water and fire line plans do not appear to make sense. You are showing a 2 inch fire line which is less than the minimum 4 inches (more if supported by your water model). You are showing a 6 inch domestic line which is excessive. Correction required.
|
|
Corrective Action Required
I would like to see better contrast between existing and proposed, especially on the utility plan. Either make the existing features lighter in lineweight, or the proposed features bolder, or both. Correction required.
|
|
Corrective Action Required
Water line plans do not appear to make sense. For instance, you are showing a 6 inch water main extension for domestic line which is excessive. Correction required.
|
|
Corrective Action Required
No further review of the water main plans were conducted due to significant discrepancies described above. Recommend a Teams meeting be setup to discuss briefly.
|
|
Corrective Action Required
Cost estimate for sitework required prior to formal approval. Informational comment.
|
|
Corrective Action Required
New frame and lid detail is required for all storm lids. Use the new standard detail STM-6 showing the stenciled design to be used for all public and private storm lids. Correction required.
|
|
|
Building Codes Review
|
Corrections
|
12/13/2024
|
12/11/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
2" sprinkler and 6" domestic? Assuming this is just typos, relabel.
|
|
Miscellaneous Correction
Corrective Action Required
Specify types of water pipe connections at main.
|
|
Miscellaneous Correction
Corrective Action Required
Specify water and sanitary piping materials.
|
|
Miscellaneous Correction
Corrective Action Required
Architectural/structural/MEP plans provided are not part of this review.
|
|
|
Planning Review
|
Corrections
|
12/13/2024
|
12/09/2024
|
|
Hector Soto Jr.
|
|
Corrective Action Required
FLOODPLAIN. Add a note to the plans stating the site's location relative to the 100-year floodplain. Cite the FIRM Panel number and date used to make the determination.
|
|
Corrective Action Required
OIL AND GAS WELLS. Add a note on the plans as to the presence of any active, inactive or capped oil or gas wells on the subject property. Cite the source of the information used to make that determination. MoDNR maintains an online database of wells that may be used and referenced.
|
|
Corrective Action Required
ACCESSIBLE PARKING SPACES/ACCESSIBLE ROUTE. 1) The site plan (Sheet C105) appears to show the bollard in which the ADA signs will be posted located approximately 2' in from the head of the stall, which reduces the effective stall depth so as not to comply with City's minimum 19' stall depth. 2) The site plan show wheel stops at the head of the parking spaces. City ordinance does not allow the use of wheel stops, except at the head of accessible parking spaces when they are adjacent to a pedestrian walkway with no raised curb. 3) Label the accessible route from the ADA parking spaces to the terminal entrance. Label the slope and cross-slope of said accessible route(s).
|
|
Corrective Action Required
PARKING SPACE DIMENSIONS. The double-row of parking spaces are dimensioned on sheet C131 as having a total depth of 36', which is 18' depth per stall. City ordinance requires a minimum 19' stall depth for all parking spaces, except that stall depth may be reduced by 2' (i.e. 17' stall depth) where the head of the space(s) is/are adjacent to a minimum 6'-wide sidewalk or open area. To illustrate, the easternmost row of parking that fronts onto the landscape area can be reduced from 19' (as currently dimensioned) to 17'.
|
|
Corrective Action Required
MECHANICAL SCREENING. Show/dash-in the location of all ground-mounted and roof-top (RTUs) mechanical units on the site plan and building elevations as is appropriate. Ground units shall be fully screened from view from all directions using evergreen landscaping or masonry walls of a height at least as tall as the units being screened. RTUs shall be fully screened from view using parapet walls of a height at least as tall as the units being screened. Please take into consideration any additional height from any curbs on which the RTUs will sit. Small vent pipes or other roof penetrations shall be painted to blend into the building.
|
|
Corrective Action Required
TRASH ENCLOSURE. Is there any need for an outdoor trash dumpster to serve the terminal? If so, each trash enclosure shall be constructed of masonry walls or steel architecturally designed walls with either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier. Provide a trash enclosure if one will be employed on the site.
|
|
Corrective Action Required
LANDSCAPE ISLANDS. The landscape plans shows that trees will be planted in certain landscape islands/areas. All tree planting areas shall be a minimum 10' wide, with no tree planted within 4' from the edge of any landscape island/area curb border.
|
|
Corrective Action Required
AIRPORT NAME. Update the drawings to show the new airport name of Kansas City-Lee's Summit Regional" on the building and other signage.
|
|
|
Traffic Review
|
No Comments
|
12/13/2024
|
12/09/2024
|
|
Erin Ralovo
|
|
|
Fire Review
|
Approved with Conditions
|
12/13/2024
|
12/04/2024
|
|
Jim Eden
|
|
FDC
IFC 903.3.7 - Fire department connections. The location of fire department connections shall be approved by the fire code official. Connections shall be a 4 inch Storz type fitting and located within 100 feet of a fire hydrant, or as approved by the code official.
Show the location of the FDC on the building.
|
|
|