Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
01/10/2025
|
01/08/2025
|
|
Sue Pyles, P.E.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $112,818.45
|
|
|
Engineering Review
|
Corrections
|
10/30/2024
|
11/01/2024
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Please submit an Engineer's Estimate of Probable Construction Costs.
|
|
Corrective Action Required
The standard details that were added, STM-6 and STM-7, are not the current details. Please update (although the info hasn’t changed on STM-7 it was still updated, not sure why).
|
|
Corrective Action Required
The fire lane pavement section was not revised as requested in the previous comment letter. Please revise.
|
|
|
Fire Review
|
Approved with Conditions
|
10/30/2024
|
10/31/2024
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Traffic Review
|
No Comments
|
10/30/2024
|
10/31/2024
|
|
Erin Ralovo
|
|
|
Planning Review
|
No Comments
|
10/30/2024
|
10/28/2024
|
|
Hector Soto Jr.
|
|
|
Building Codes Review
|
No Comments
|
10/30/2024
|
10/25/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
For a 2" meter, piping from main to 10' past meter to be 2" copper. Amend plans.
|
|
Miscellaneous Correction
Specify connection of sanitary to main.
|
|
|
Planning Review
|
Corrections
|
05/06/2024
|
05/07/2024
|
|
Hector Soto Jr.
|
|
Corrective Action Required
LEGAL DESCRIPTION. The legal description provided on Sheet C100 incorrectly identifies the project site as Lot 9 versus Lot 10.
|
|
Corrective Action Required
LOT INFORMATION. The lot line dimensions provided on Sheet C200 are incorrect for the following: the south property line (474.42' instead of 290.94'); the curve length at the SE property corner (134.141' instead of 67.07'); the east property line (375.83' instead of 440.27'); and the northeastern property line (258.89' instead of 187.35').
|
|
Corrective Action Required
STREETS. Dimension the roadway width for north-south street along the western lot boundary.
|
|
Corrective Action Required
DRIVE AISLES. Internal drive aisles serving two-way traffic shall have a minimum pavement width of 24' (excluding curb and gutter). The 24'-wide dimensioned aisles are taken to the face of the curb as currently shown. Revise to meet the 24' width without the curb (i.e. actual asphalt pavement width only).
|
|
Corrective Action Required
PHOTOMETRIC PLAN. The photometric plan only appears to include the parking lot pole-mounted light fixtures. No information is provided for wall-mounted fixtures on the building. The photometric plan shall also include light levels produced by the wall-mounted fixtures. Wall-mounted fixtures shall comply with the fixture standards under UDO Section 8.220, 8.260 and 8.270. Provide specifications for the proposed wall-mounted fixtures.
|
|
Corrective Action Required
MECHANICAL EQUIPMENT. Dash in the roof line and roof-top mechanical equipment on the building elevations to ensure that the proposed building parapet wall heights are of sufficient height to fully screen said equipment from view on all sides. Take into account the added height from any curbs on which the RTUs will sit when designing the parapet wall heights.
|
|
Corrective Action Required
GARAGE PLANS (SHEETS A-100 AND A-101). Dimension the lengths and widths of the standard parking spaces, accessible spaces and accessible access aisle on the garage floor plans. Also dimension the widths of the drive aisles serving the parking garage.
|
|
Corrective Action Required
PLANT MATERIAL SIZE. The caliper size is not provided for most of the trees included in the Plant Schedule. The minimum caliper size for shade trees is 2.5" caliper; the minimum caliper size for ornamental trees is 1.5".
|
|
Corrective Action Required
OPEN YARD LANDSCAPING. In addition to the street frontage tree and shrub planting requirements, open yard landscaping is required to be provided at a rate of 1 tree for every 5,000 sq. ft. of total lot area minus the building footprint square footage. Similarly, 2 shrubs are required to be planted for every 5,000 sq. ft. of total lot area minus the building footprint square footage.
|
|
Corrective Action Required
PARKING LOT SCREENING. Screening to a height of two and one-half feet must be provided along the edge of the parking lot or loading area closest to and parallel to the street along the western lot boundary. Screening shall be decorative and 100 percent opaque to a height of two and one-half feet above the elevation of the parking/loading area or the street, whichever is highest. See UDO Section 8.820.C for the available parking lot screening options.
|
|
Corrective Action Required
STREET TREE LANDSCAPING. One street tree shall be planted along the street frontage along the western lot boundary to satisfy the requirement for 1 tree for every 30' of frontage.
|
|
Corrective Action Required
SITE DATA TABLE. For ease of reference, add a line item for the total number of parking spaces provided (standard + ADA stalls) of 220 spaces.
|
|
Corrective Action Required
TRASH ENCLOSURES. A detailed drawing of enclosure and screening methods to be used in connection with trash storage containers on the property shall be provided. Each trash enclosure shall be constructed of masonry walls or steel architecturally designed walls with either a solid steel opaque gate painted to be compatible with the color of the masonry or steel walls and building it is to serve or a steel framed semi-opaque gate with a screen mesh material approved by the Director that provides an appropriate visual barrier.
|
|
Corrective Action Required
LANDSCAPE ISLAND WIDTH. Tree planting areas shall be no less than 10 feet in width. No tree shall be located less than 4 feet from the back of curb. The islands in the middle of the surface parking lot do not meet the minimum island widths. Also, the trees planted at either ends of these same islands are less than 4' from the back of the curb.
|
|
Corrective Action Required
FAA FORM 7460. Due to the proximity of the project site to the airport, an FAA Form 7460 shall be completed and submitted to the FAA, and comments received back prior to any construction.
|
|
|
Engineering Review
|
Corrections
|
05/06/2024
|
05/07/2024
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Revise “Lot 9” to “Lot 9-1” throughout the plan set.
|
|
Corrective Action Required
30’ of concrete pavement is required to extend from the trash enclosure door. Please revise to meet this requirement.
|
|
Corrective Action Required
Please include the design HGL on all storm sewer Profile views.
|
|
Corrective Action Required
Please replace the Junction Box standard detail with the City’s Curb Inlet standard detail (STM-1).
|
|
Corrective Action Required
Please remove “STM-4” from the Non-Setback Curb Inlet detail as it isn’t a City standard detail.
|
|
Corrective Action Required
Please include the City’s Storm MH Cover (STM-6) and Storm MH Frame (DWG-7) standard details.
|
|
Corrective Action Required
Please revise the Light-Duty Asphalt Section detail to specify KCMMB asphalt Type A2. The minimum lift thickness allowed for Type 2 is 2”, which does not meet the UDO requirements. The UDO will be revised to specify overall pavement thickness. Please either specify the overall thickness or revise lift thicknesses accordingly.
|
|
Corrective Action Required
Please revise the Fire Line Pavement Section to meet the Fire Department requirements, as included in their comments.
|
|
Corrective Action Required
Private easements will be required for the private water mains. Please show throughout the plan set. Coordinate with the developer to determine if these easements will all be platted of by separate document.
|
|
|
Building Codes Review
|
Corrections
|
05/06/2024
|
05/06/2024
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
For a 2" meter, piping from main to 10' past meter to be 2" copper. Amend plans.
|
|
Miscellaneous Correction
Corrective Action Required
Specify connection of sanitary to main.
|
|
|
Fire Review
|
Corrections
|
05/06/2024
|
05/01/2024
|
|
Jim Eden
|
|
|
Traffic Review
|
Corrections
|
05/06/2024
|
05/01/2024
|
|
Erin Ralovo
|
|
Corrective Action Required
The drive approach radii at the street must be 35 FT. Please revise.
|
|
|