Summary


PRSUBD20253174
Public Infrastructure
Substantial Completion
GRIFFIN RILEY INVESTMENTS LLC
DEVELOPMENT COMPLETE
RESIDENCE, REUNION AND RESERVE AT BLACKWELL - CITY STREET LIGHTS LOCATED IN MoDOT ROW
07/29/2025
08/28/2025
Locations
Contacts
MATT BLANN, Address:CAPITAL ELECTRIC, Phone:(816) 215-6693  
GRIFFIN RILEY INVESTMENTS LLC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
GRIFFIN RILEY INVESTMENTS LLC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
Capital Electric Construction Co., Inc., Address:PO Box 410779, Phone:(816) 472-9500  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review - Streetlight Approved with Conditions 08/21/2025 08/07/2025
Mike Weisenborn
Miscellaneous Correction
Resolved
08/07/2025

Provide an estimate of cost, signed and sealed by an egineer, for the installation of the street lights and associated wiring.
Engineering Review - Streetlight Approved with Conditions 08/05/2025 08/05/2025
Mike Weisenborn
Miscellaneous Correction
Corrective Action Required
08/05/2025

Provide an estimate of cost, signed and sealed by an egineer, for the installation of the street lights and associated wiring.
Traffic Review - Streetlight No Comments 08/05/2025 08/05/2025
Mike Weisenborn
Miscellaneous Correction
Resolved
08/05/2025

MoDOT approval will be required before final City approval will be given.
Fees
Paid Fees Amount Paid Owing Date Paid
Paved Surface Inspection Fee $5,014.29 $5,014.29 Paid 08/26/2025
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underground Electrical Inspection - Commercial Pending
Sidewalk Inspection Pending
Misc
Informational
12/27/2025
10-20-25 Dustin A, Will do a final after all sw is in 12-26-25 Dustin A, Allot of sidewalk is out of compliance, and there is some broken pieces.
Punch List Inspection Pending
Misc
Corrective Action Required
03/06/2026
Provide 3 Yr. maintenance bond for 50% of the estimated cost of construction. Street Lights-$167,134.00 Due=$83,567.00 Final affidavit and agreement. Establish 70% vegetation Pay Any Outstanding fees Record Drawings for Street Lights Installed Fix cracked sidewalk panels Replace Unapproved Water Valve Top Hats Complete connection between Blackwell and Blue Pkwy Sidewalk
Erosion Control Inspection Pending
Misc
Corrective Action Required
03/13/2026
12-8-25 Dustin A, Erosion control needs installed due to silt getting on the road, storm inlets need silt removed 3-11-26 Dustin A, Sidewalks, road and roundabout are silted over, All storm inlets need to be cleaned out along blue parkway as well as field inlets. Please have this corrected by Friday 3-13-26 To keep from issuing a Stop Work order. This will be attached to the Apartments failed erosion control inspection issued today as well so both will need to be corrected. 3-13-26 Dustin A, corrections have been made to resume working Scott informed me they have the few items missed scheduled beginning of week
Site Visit Pending
Misc
Partial Correction
03/24/2026
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path 2-6-26 Dustin A, No work being done on site for dev 3-23-26 Dustin A, Selby working on fixing sidewalks
Misc
Corrective Action Required
03/24/2026
1-7-26 Dustin A 2-6-26 Dustin A 2-25-26 Dustin A, No work has been done MoDOT Roundabout Substantial Completion • All water valves that are not on the approved material list need to be switched out • The hydrant and valve (existing) on the east side of the property along Blue Parkway needs to be raised due to changing grade around it. If a water key cannot reach valve after being raised an extension may need to be installed. • All sidewalks need to be in Final Acceptance • 75 % Vegetation • Esc needs to be removed after vegetation (needs to be maintained until) • All sidewalks that have failed need to be fixed • Bond for Sidewalk and Street Lights • Record Drawings for Street Lights 3-18-26 Dustin A, Prepping for the rest of sidewalk
Sidewalk Inspection Partial 08/27/2025
Misc
Informational
08/27/2025
8-25-25 Dustin A, Sw is formed , not compacted, slopes are not in compliance. There are some areas where there is not enough aggregate., Fail 8-25-25 Dustin A, called back out still areas that does not pass. Approved a section of 40 ft to be poured. 8-26-25 Dustin A, sw section around roundabout is formed , slopes are in compliance. Approved to pour that section
Electrical Service Inspection Failed 9/9/2025 9/9/2025 09/09/2025
Misc
Corrective Action Required
09/09/2025
-provide address -provide 3/4” ground rod to plans -breaker sizes are not to plans
Electrical Service Inspection Failed 9/10/2025 9/10/2025 09/10/2025
Misc
Corrective Action Required
09/09/2025
-provide address
Electrical Service Inspection Passed 9/11/2025 9/11/2025 09/11/2025
Misc
Resolved
09/11/2025
-provide address
Site Visit Partial 10/1/2025 10/1/2025 10/01/2025
Misc
Partial Correction
10/01/2025
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments
Sidewalk Inspection Partial 10/10/2025 10/10/2025 10/10/2025
Misc
Informational
08/27/2025
8-25-25 Dustin A, Sw is formed , not compacted, slopes are not in compliance. There are some areas where there is not enough aggregate., Fail 8-25-25 Dustin A, called back out still areas that does not pass. Approved a section of 40 ft to be poured. 8-26-25 Dustin A, sw section around roundabout is formed , slopes are in compliance. Approved to pour that section 10/10/25 Tyler S. ADA ramp and sw has been formed and compacted. Approve to pour.
Sidewalk Inspection Partial 10/20/2025 10/20/2025 10/20/2025
Misc
Informational
10/20/2025
10-20-25 Dustin A, Will do a final after all sw is in
Site Visit Partial 11/07/2025
Misc
Partial Correction
10/01/2025
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished
Site Visit Partial 11/12/2025
Misc
Partial Correction
11/07/2025
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done
Site Visit Partial 11/12/2025
Misc
Partial Correction
11/12/2025
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path
Erosion Control Inspection Failed 12/8/2025 12/8/2025 12/08/2025
Misc
Corrective Action Required
12/08/2025
12-8-25 Dustin A, Erosion control needs installed due to silt getting on the road, storm inlets need silt removed Corrections need to be done within 2 business days
Sidewalk Inspection Failed 12/27/2025
Misc
Informational
10/20/2025
10-20-25 Dustin A, Will do a final after all sw is in 12-26-25 Dustin A, Allot of sidewalk is out of compliance, and there is some broken pieces.
Site Visit Partial 01/07/2026
Misc
Partial Correction
11/12/2025
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path
Misc
Corrective Action Required
01/07/2026
1-7-26 Dustin A MoDOT Roundabout Substantial Completion • All water valves that are not on the approved material list need to be switched out • The hydrant and valve (existing) on the east side of the property along Blue Parkway needs to be raised due to changing grade around it. If a water key cannot reach valve after being raised an extension may need to be installed. • All sidewalks need to be in Final Acceptance • 75 % Vegetation • Esc needs to be removed after vegetation (needs to be maintained until) • All sidewalks that have failed need to be fixed • Bond for Sidewalk and Street Lights • Record Drawings for Street Lights
Site Visit Partial 02/06/2026
Misc
Partial Correction
01/07/2026
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path 2-6-26 Dustin A, No work being done on site for dev
Misc
Corrective Action Required
01/07/2026
1-7-26 Dustin A 2-6-26 Dustin A MoDOT Roundabout Substantial Completion • All water valves that are not on the approved material list need to be switched out • The hydrant and valve (existing) on the east side of the property along Blue Parkway needs to be raised due to changing grade around it. If a water key cannot reach valve after being raised an extension may need to be installed. • All sidewalks need to be in Final Acceptance • 75 % Vegetation • Esc needs to be removed after vegetation (needs to be maintained until) • All sidewalks that have failed need to be fixed • Bond for Sidewalk and Street Lights • Record Drawings for Street Lights
Site Visit Partial 02/26/2026
Misc
Partial Correction
02/06/2026
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path 2-6-26 Dustin A, No work being done on site for dev
Misc
Corrective Action Required
02/06/2026
1-7-26 Dustin A 2-6-26 Dustin A 2-25-26 Dustin A, No work has been done MoDOT Roundabout Substantial Completion • All water valves that are not on the approved material list need to be switched out • The hydrant and valve (existing) on the east side of the property along Blue Parkway needs to be raised due to changing grade around it. If a water key cannot reach valve after being raised an extension may need to be installed. • All sidewalks need to be in Final Acceptance • 75 % Vegetation • Esc needs to be removed after vegetation (needs to be maintained until) • All sidewalks that have failed need to be fixed • Bond for Sidewalk and Street Lights • Record Drawings for Street Lights
Punch List Inspection Partial 03/06/2026
Misc
Corrective Action Required
03/06/2026
Provide 3 Yr. maintenance bond for 50% of the estimated cost of construction. Street Lights-$167,134.00 Due=$83,567.00 Final affidavit and agreement. Establish 70% vegetation Pay Any Outstanding fees Record Drawings for Street Lights Installed Fix cracked sidewalk panels Replace Unapproved Water Valve Top Hats Complete connection between Blackwell and Blue Pkwy Sidewalk
Erosion Control Inspection Failed 03/11/2026
Misc
Corrective Action Required
12/08/2025
12-8-25 Dustin A, Erosion control needs installed due to silt getting on the road, storm inlets need silt removed 3-11-26 Dustin A, Sidewalks, road and roundabout are silted over, All storm inlets need to be cleaned out along blue parkway as well as field inlets. Please have this corrected by Friday 3-13-26 To keep from issuing a Stop Work order. This will be attached to the Apartments failed erosion control inspection issued today as well so both will need to be corrected.
Erosion Control Inspection Partial 3/13/2026 3/13/2026 03/13/2026
Misc
Corrective Action Required
03/11/2026
12-8-25 Dustin A, Erosion control needs installed due to silt getting on the road, storm inlets need silt removed 3-11-26 Dustin A, Sidewalks, road and roundabout are silted over, All storm inlets need to be cleaned out along blue parkway as well as field inlets. Please have this corrected by Friday 3-13-26 To keep from issuing a Stop Work order. This will be attached to the Apartments failed erosion control inspection issued today as well so both will need to be corrected. 3-13-26 Dustin A, corrections have been made to resume working Scott informed me they have the few items missed scheduled beginning of week
Site Visit Partial 03/18/2026
Misc
Partial Correction
02/26/2026
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path 2-6-26 Dustin A, No work being done on site for dev
Misc
Corrective Action Required
02/26/2026
1-7-26 Dustin A 2-6-26 Dustin A 2-25-26 Dustin A, No work has been done MoDOT Roundabout Substantial Completion • All water valves that are not on the approved material list need to be switched out • The hydrant and valve (existing) on the east side of the property along Blue Parkway needs to be raised due to changing grade around it. If a water key cannot reach valve after being raised an extension may need to be installed. • All sidewalks need to be in Final Acceptance • 75 % Vegetation • Esc needs to be removed after vegetation (needs to be maintained until) • All sidewalks that have failed need to be fixed • Bond for Sidewalk and Street Lights • Record Drawings for Street Lights 3-18-26 Dustin A, Prepping for the rest of sidewalk
Site Visit Partial 03/24/2026
Misc
Partial Correction
03/18/2026
9-30-25 Dustin A, SW being formed on east side of round a bout in front of apartments 11-7-25 Dustin A, hydro seeding being done, Sill need sidewalks finished 11-10-25 Dustin A, hydroseeding being done 11-12-25 Dustin A, Crew on site to move communication box out of sidewalk path 2-6-26 Dustin A, No work being done on site for dev 3-23-26 Dustin A, Selby working on fixing sidewalks
Misc
Corrective Action Required
03/18/2026
1-7-26 Dustin A 2-6-26 Dustin A 2-25-26 Dustin A, No work has been done MoDOT Roundabout Substantial Completion • All water valves that are not on the approved material list need to be switched out • The hydrant and valve (existing) on the east side of the property along Blue Parkway needs to be raised due to changing grade around it. If a water key cannot reach valve after being raised an extension may need to be installed. • All sidewalks need to be in Final Acceptance • 75 % Vegetation • Esc needs to be removed after vegetation (needs to be maintained until) • All sidewalks that have failed need to be fixed • Bond for Sidewalk and Street Lights • Record Drawings for Street Lights 3-18-26 Dustin A, Prepping for the rest of sidewalk
Documents & Images
Date Uploaded File Type Document Name
07/29/2025 Plans Street Lighting Plan Blue Pkwy Improvements_REV 0_PRCOM20253174
08/05/2025 Letter SUBD Comment Letter
08/07/2025 3rd Party Permit/Approval MoDOT Streetlights Approval Email_REV 0_PRCOM20253174
08/07/2025 Engineers Estimate Blue Parkway Lighting Accepted Bid_REV 0_PRCOM20253174
08/07/2025 Approved Plans APPROVED BLUE PKWY STREET LIGHTING
08/08/2025 Approved Plans Approved Street and Sidewalk Plans
08/26/2025 Receipt Receipt for transaction:2025-006689
08/27/2025 Letter INSPECTION SUMMARY
09/09/2025 Letter SUBD Building Permit
09/09/2025 Letter INSPECTION SUMMARY
09/10/2025 Blackwell Blue Parkway - Street Lighting Submittals
09/11/2025 Letter INSPECTION SUMMARY
09/11/2025 Letter INSPECTION SUMMARY
10/01/2025 Letter INSPECTION SUMMARY
10/10/2025 Letter INSPECTION SUMMARY
10/20/2025 Letter INSPECTION SUMMARY
11/07/2025 Letter INSPECTION SUMMARY
11/12/2025 Letter INSPECTION SUMMARY
11/12/2025 Letter INSPECTION SUMMARY
12/08/2025 Letter INSPECTION SUMMARY
12/27/2025 Letter INSPECTION SUMMARY
12/27/2025 Letter INSPECTION SUMMARY
01/07/2026 Letter INSPECTION SUMMARY
02/06/2026 Letter INSPECTION SUMMARY
02/26/2026 Letter INSPECTION SUMMARY
03/06/2026 Letter DE-Certificate of Substantial Completion Single Lot
03/06/2026 Letter DE-Punch List
03/06/2026 Letter SUBD Punch List
03/11/2026 Letter INSPECTION SUMMARY
03/11/2026 Letter INSPECTION SUMMARY
03/13/2026 Letter INSPECTION SUMMARY
03/18/2026 Letter INSPECTION SUMMARY
03/24/2026 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents