Summary


PRSUBD20204839
Public Infrastructure
Final Acceptance
CMH PARKS INC
DEVELOPMENT COMPLETE
Hawthorn Ridge 3rd Plat - subdivision improvements
12/17/2020
04/01/2021
01/24/2025
05/18/2023
Locations
Address
1608 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1604 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1612 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1616 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1620 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1624 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1628 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1632 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1704 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1708 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
3204 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3208 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3212 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3216 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3220 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3224 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3228 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3232 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
1637 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1633 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1629 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1625 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1621 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1617 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1613 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1609 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
1605 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
3221 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3219 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3215 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3211 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3207 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3208 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3212 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3216 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
3224 SW ARBORIDGE CIR, LEES SUMMIT, MO 64082

Address
1628 SW ARBORWAY TER, LEES SUMMIT, MO 64082

Address
3219 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3215 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3211 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3207 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
3203 SW ARBOR SOUND DR, LEES SUMMIT, MO 64082

Address
1617 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1613 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1609 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1605 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Address
1707 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Property
69620032900000000

Property
69620033000000000

Property
69620033100000000

Property
69620033200000000

Property
69620033300000000

Property
69620033400000000

Property
69620033500000000

Property
69620033900000000

Property
69620033600000000

Property
69620033800000000

Property
69620033700000000

Property
69620140200000000

Property
69620140300000000

Property
69620140400000000

Property
69620140500000000

Property
69620140600000000

Property
69620140700000000

Property
69620140900000000

Property
69620140800000000

Property
69620141000000000

Property
69620141100000000

Property
69620141200000000

Property
69620141300000000

Property
69620141400000000

Property
69620141500000000

Property
69620141600000000

Property
69620141700000000

Property
69620141900000000

Property
69620141800000000

Property
69620110800000000

Property
69620111600000000

Property
69620110900000000

Property
69620111500000000

Property
69620111000000000

Property
69620111400000000

Property
69620111100000000

Property
69620111200000000

Property
69620111300000000

Property
69620111700000000

Property
69620111800000000

Property
69620111900000000

Property
69620112000000000

Property
69620112100000000

Property
69620112600000000

Property
69620112500000000

Property
69620112400000000

Property
69620112300000000

Property
69620112200000000

Address
1712 SW BUCKTHORN ST, LEES SUMMIT, MO 64082

Contacts
CMH PARKS INC, Address:5000 CLAYTON RD  
OLSSON ASSOCIATES, Address:1301 BURLINGTON, SUITE 100, Phone:(816) 361-1171  
EMERY SAPP AND SONS INC, Address:2301 I-70 DR NW, Phone:(573) 445-8331  
HAWTHORN RIDGE HOMES ASSOCIATION INC, Address:120 SE 30TH ST  
SMITH JAMES B & JULIE A, Address:1708 SW BUCKTHORN DR  
DOMAIN TIMBERLAKE MULTISTATE LLC, Address:590 MADISON AVE FL 13TH  
CLAYTON PROPERTIES GROUP INC, Address:120 SE 30TH ST  
MATIAS STEVEN & KATHRYN, Address:1617 SW BUCKTHORN DR  
JAMES W HART REVOCABLE TRUST, Address:1637 SW ARBORWAY TER  
CURRY CADEN & ASHLEY, Address:3232 SW ARBOR SOUND DR  
HOANG KIM & HUYNH COURTNEY PHUONG, Address:3212 SW ARBOR SOUND DR  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 12/17/2020 04/01/2021
Dawn Bell
Fees
Paid Fees Amount Paid Owing Date Paid
91100C9-Water Insp Fee $4,078.67 $4,078.67 Paid 01/26/2021
9110072-Water Test Fee $800.00 $800.00 Paid 01/26/2021
9110068-Storm Sewer Inspection Fee $4,530.15 $4,530.15 Paid 01/26/2021
9110081-Paved Surface Inspection Fee $6,927.52 $6,927.52 Paid 01/26/2021
$6,927.53
9110071-Site Grading Fee $4,954.45 $4,954.45 Paid 01/26/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 01/26/2021
91100C8-Sanitary Sewer Insp Fees $5,283.91 $5,283.91 Paid 01/26/2021
9110071-Site Grading Fee $9,906.13 $9,906.13 Paid 01/26/2021
$14,860.58
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 4/14/2021 04/14/2021
Misc
Informational
04/14/2021
Core drilled into existing MH 1-6. Used approved boot for 8"pipe to be installed. Started laying 8 sanitary pipe toward MH 3-1. Installed service wyes for lot 184 and 183.
Sanitary Sewer Construction Inspection Partial 4/15/2021 04/15/2021
Misc
Informational
04/14/2021
Core drilled into existing MH 1-6. Used approved boot for 8"pipe to be installed. Started laying 8 sanitary pipe toward MH 3-1. Installed service wyes for lot 184 and 183.
Miscellaneous Correction
Informational
04/15/2021
Still laying pipie toward MH 3-1. Tester was out doing compaction testing on the main and on the 2 service lines.
Misc
Informational
04/22/2021
On Thursday, 4-23-2021. ESS Contractors installed Sanitary Sewer for line 1. The contractor also installed 4 - 4” laterals. The contractor resumed fill grading through out project.
Misc
Informational
04/27/2021
ON Monday and Tuesday, 4-26 and 4-27-2021. The contractor installed MH 1 &2 with approx 140 LF of 8” PVC on line #1 and back filled. On Thursday, 4-29-2021. ESS Excavating resumed Sanitary Sewer installation on line #4. Contractor installed MH #4-1 and placed approx 180 LF of 8” PVC Sewer and back filled. On Friday, 4-30-2021. ESS Excavating resumed Sanitary Sewer installation. Contractor installed the last 4 Laterals lines on line #4 coming into MH #-1 at both sides of the main sewer.
Misc
Informational
04/30/2021
On Friday, 4-30-2021. ESS Excavating resumed Sanitary Sewer installation om line #4. Contractor installed (4) laterals on both sides of the main sewer coming into MH# 4-1 and back filled. KC Testing here taking compaction test.
Misc
Informational
05/05/2021
On Monday, 5-03-2021, ESS Excavating resumed Sanitary Sewer installation. Contractor worked on Line 3 installing 8” PVC sewer from MH-3-1 Towards 3-2. Contractor installed approx.150LF of pipe and back filled. KC Testing provided the compaction testing. On Tuesday, 5-04-2021. ESS Excavating resumed Sanitary Sewer installation. Contractor installed laterals for line #1 towards MH 3-2 and back filled. On Wednesday, 5-05-2021. Contractor resumed sewer installation installing remaining sewer to MH 3-2. Same structure was set and remaining laterals between structure were installed and back filled. KC Testing provided compaction test. Contractor installed approx 60LF of 8” sewer towards MH #3-3 and back filled.
Misc
Informational
05/06/2021
On Monday, 5-03-2021, ESS Excavating resumed Sanitary Sewer installation. Contractor worked on Line 3 installing 8” PVC sewer from MH-3-1 Towards 3-2. Contractor installed approx.150LF of pipe and back filled. KC Testing provided the compaction testing. On Tuesday, 5-04-2021. ESS Excavating resumed Sanitary Sewer installation. Contractor installed laterals for line #1 towards MH 3-2 and back filled. On Wednesday, 5-05-2021. Contractor resumed sewer installation installing remaining sewer to MH 3-2. Same structure was set and remaining laterals between structure were installed and back filled. KC Testing provided compaction test. Contractor installed approx 60LF of 8” sewer towards MH #3-3 and back filled. On Wednesday, 5-05-2021. Contractor resumed Sanitary Sewer installation. Contractor set structure MH#3-3 and placed approx 80LF of pipe. Contractor also placed 4 laterals and back filled. KC Testing preformed soil density’s.
Misc
Informational
05/08/2021
On Monday, 5-03-2021, ESS Excavating resumed Sanitary Sewer installation. Contractor worked on Line 3 installing 8” PVC sewer from MH-3-1 Towards 3-2. Contractor installed approx.150LF of pipe and back filled. KC Testing provided the compaction testing. On Tuesday, 5-04-2021. ESS Excavating resumed Sanitary Sewer installation. Contractor installed laterals for line #1 towards MH 3-2 and back filled. On Wednesday, 5-05-2021. Contractor resumed sewer installation installing remaining sewer to MH 3-2. Same structure was set and remaining laterals between structure were installed and back filled. KC Testing provided compaction test. Contractor installed approx 60LF of 8” sewer towards MH #3-3 and back filled. On Wednesday, 5-05-2021. Contractor resumed Sanitary Sewer installation. Contractor set structure MH#3-3 and placed approx 80LF of pipe. Contractor also placed 4 laterals and back filled. KC Testing preformed soil density’s. On Saturday, 5-08-2021. ESS Excavating resumed Sanitary Sewer installation installing MH 2-2 and laterals 175 and 174. Contractor also continued mass grading throughout project. On Thursday, 6-03-2021. ESS resumed sanitary sewer installation. Contractor placed 8” sewer pipe Between MH 2-1 to 2-2 . On Monday, 6-07-2021. Spalding installed approx 30 LF of 8” sanitary sewer on line #2. Contractor placed approx 40 LF of 8” HDPE pipe. On Tuesday, 6-08-2021. ESS resumed Sanitary Sewer installation.(2) Laterals were installed-for lots 170 & 199 On Wednesday, 6-09-2021. ESS Excavating resumed Sanitary Sewer installation. Contractor layer approx 100 LF of 8” sanitary sewer. Installed Laterals for prop. 171, 172, 198 and 199 on line #2.
Storm Sewer Construction Inspection Partial 04/20/2021
Misc
Informational
04/20/2021
On Monday, 4-19-2021. Emery Sapp Contracting installed 197LF of 54”HDPE pipe and the bottom section of structure JB 2-3 on line line # 1. The contractor also installed approx 122LF of 48” pipe connecting to the bottom section as well.
Misc
Informational
05/10/2021
On Monday, 5-10-2021. The contractor installed approx 300LF of 15” HDPE on line #2 and back filled. On Tuesday, 5-11-2021. ESS resumed installation of line #5 for the storm sewer. The contractor installed structure CI 5-2 and 145 LF of 15” HDPE pipe with flume and placed rip rap and end section for pipe. On Friday, 5-21-2021 and Monday, 5-24-2021. ESS Excavating installed Structure #Ci 3-1, and CI 3-2. Approx 85LF of 24” HDPE Pipe was placed and 115 LF of 15” was laced and back filled. On Wednesday, 5-27-2021. ESS Excavating installed line 4 storm sewer. Including all structures, piping and back fill.for CI 4-1, 4-2, & 4-3 Including 154 LF of 15” HDPE pipe. On Wednesday 6-16-2021 and Thursday, 6-17-2021 ESS Excavating installed Storm Sewer line #5 and poured inverts and dog houses. Contractor backfilled sewer and KC Testing provided the compaction test.
Grading/Excavation/Fill Inspection Partial 04/20/2021
Misc
Informational
04/20/2021
On Monday, 4-19-2021. ESS Contractors continued mass grading over the roadway for Arbor Sound Drive.
Misc
Informational
04/27/2021
On Monday and Tuesday 4-26 and 4-27-2020. ESS Contractors are placing dirt fill at various locations throughout the project.
Misc
Informational
05/06/2021
On Wednesday, 5-06-2021. ESS Contracting resumes fill grading in the south westerly location of the project. Contractor filled approx 3’ of fill at the culvert sac at Arboridge circle. On Thursday, 6-03-2021. ESS completed grading on and around Arbor Sound Drive. On Tuesday, 7-06-2021. ESS Excavating perform top soil grading throughout project. On Wednesday, 7-07-2021. ESS Excavating resumed top soil fill grading throughout project.
Water Line - Construction Inspection Partial 06/03/2021
Misc
Informational
06/03/2021
On Thursday, 6-03-2021. ESS Excavating resumed waterline installation. Contractor installed water line (#3) in Arboridge Circle and installed thrust blocks and straddle blocks for water line bends.
Misc
Informational
06/04/2021
On Friday 6-04-2021. ESS grading various areas around project, On Tuesday, 6-15-2021, ESS Excavating began placing waterline pipe at 21+66 line #2, heading south towards sta 20+00. Contractor back filled.
Sanitary Sewer Construction Inspection Partial 6/10/2021 6/10/2021 08/03/2021
Misc
Informational
04/15/2021
Core drilled into existing MH 1-6. Used approved boot for 8"pipe to be installed. Started laying 8 sanitary pipe toward MH 3-1. Installed service wyes for lot 184 and 183.
Miscellaneous Correction
Informational
04/15/2021
Still laying pipie toward MH 3-1. Tester was out doing compaction testing on the main and on the 2 service lines.
Misc
Informational
06/10/2021
6/10/21- Crew is working towards MH 2-2 but are into heavy shell rock, watering and compacting as they go. Compaction inspected is also on site. Crew is working on digging out the service lines for lots 171, 172, and 173. ON Friday, 6-11-2021. ESS Excavating resumed Sanitary Sewer installation as day before. Watering before back filling was provided as day before. On Friday, 6-18-2021. ESS Excavating preformed a mandrel test on the 8” sewer line between MH holes 1-1 and 1-2 and could not pass the mandrel through. The contractor had to dig up the service and re-compact around a lateral. The location had a clod of dirt laying against the “y” and moved the service ever so slightly. Contractor re-backfilled the location and mandrel passed through. On Friday, 6-18-2021. ESS Excavating began air testing and vacuum testing Sanitary lines that were installed over (30) days. Man Holes 1-2/2-1, 3-1/4-1, 3-1/1-6, 1-2/1-3. These MH’s where vacuumed and mandrel’s between my were passed through connecting man holes. Air testing for approx 600 LF of 8” pvc pipe was passed as well. On Friday, 7-16-2021. ESS Excavating resume Sanitary sewer testing. Man Holes, 2-1,2-2,3-3,3-2, & 3-1 were vacuum tested and passed testing. All sewer between this Man Hole were air tested as well and passed air testing. This was the final sewer testing for the project and the Water Services Dept will be notified the project is ready for videoing. On Monday, 7-27-2021. Water Services sent the results of the Sanitary Sewer video. Video showed (2) locations where the “Y” installed were turned up more angle then they should have and contractor will need to make necessary repairs before stabilizing the roadway.
Misc
Informational
08/03/2021
Emery Sapp began the Water Dept punch list and dug up the “y” installed previously wrong and adjusted the “Y” down to the 45 degree angle specified. This location was not located in the street.
Pavement-Stabilized Subgrade Passed 08/09/2021
Misc
Informational
08/09/2021
On Thursday, 8-05-2021. ESS Excavating completed soil stabilization and compacted subgrade. On Monday, 8-09-2021. ESS Excavating preformed finish grading for sub-grade proof roll. On Wednesday, 8-11-2021. ESS Excavating placed and compacted 6” base rock.
Pavement-Curb Construction Passed 08/20/2021
Misc
Informational
08/12/2021
On Thursday, 8-12-2021. ESS Excavating completed curb proof roll and passed testing. On Monday, 8-16-2021. Emery Sapp Completed a proof roll of the proposed curbing. The contractor began placement of the CS type curb and stopped after placing all CS curb. On Tuesday, The contractor resumed placement of the CG 1 curbing. The contractor also formed and poured throats for approx 6 inverts. On Wednesday, the contractor resumes throat installation for (4) CI’s. Also forms pours small section of CG-1 curb. On Thursday, 8-19-2021. ESS Excavating back filled some of the curbing poured days prior. Also ESS formed and poured (3) CI throats.
Misc
Informational
08/20/2021
On Friday, 8-20-2021. ESS Excavating had Precision drilling cut the tops of (4) CI’s to be placed on grade and throats poured. This will complete curb installation for the project.
Water Line - Construction Inspection Partial 09/07/2021
Misc
Informational
09/02/2021
On Wednesday, 9-01-2021. The Contractor Emery Sapp. Performed a pressure test on the water main that failed to hold the 150 lbs of air introduced. On Thursday,9-02-2021. Another test cycle was held for the air pressure testing and passed holding the 150 lbs for 2 hours. On Thursday, 9-02-2021. Emery Sapp completed chlorination for the water line. On Tuesday, 9-07-2021. Emery Sapp de-chlorinated water line and are waiting on water Services to provide (2) construction taps. On Wednesday, 9-08-2021. Emery Sapp provided water samples that were taking to Key stone Lab for bacteria testing. (4) samples were taken.
Pavement-Surface Partial 09/16/2021
Misc
Informational
08/26/2021
On Thursday, 8-26-2021. Thorn and sons asphalt layer base coarse of asphalt on project. Buckthorn street has (2) lifts of base and contractor will only lay 1st coarse today and finish (2) lift tomorrow. On Friday, 8-27-2021. Thorn Asphalt resumed base asphalt installation on Buckthorn street finishing all base asphalt for project On Monday, 9-13-2021. Emery Sapp completed backfill of water sample test sites.
Misc
Informational
09/16/2021
On Tuesday, 9-14-2021. Emery Sapp saw cut and removed all Man Holes rims and adjusted MH to finish street elevation, then placed steel reinforcing in the 6’x6’ concrete slab to be poured around the man hole.
ADA Inspection Passed 09/16/2021
Site Visit Complete 09/27/2021
Miscellaneous Correction
Informational
03/12/2021
On Thursday, 3-11-2021. Emery Sapp contractor worked removing trees for the project grading.
Misc
Informational
03/12/2021
On Friday, 3-12-2021. Contractor resumes tree removal and grinding and clearing for project.
Misc
Informational
09/27/2021
On Monday, 9-27-2021. Contractor installed seeding at various locations throughout project.
Erosion Control Inspection Failed 07/28/2022
Misc
Corrective Action Required
07/28/2022
7-28-22 RH. Curb inlets need to be cleaned out. Mud build up around multiple.
Erosion Control Inspection Failed 8/4/2022 8/4/2022 08/04/2022
Misc
Corrective Action Required
07/28/2022
7-28-22 RH. Curb inlets need to be cleaned out. Mud build up around multiple. 8-4-22 RH. Curb inlets need to be cleaned out immediately.
Erosion Control Inspection Passed 8/18/2022 8/18/2022 08/12/2022
Misc
Corrective Action Required
08/04/2022
7-28-22 RH. Curb inlets need to be cleaned out. Mud build up around multiple. 8-4-22 RH. Curb inlets need to be cleaned out immediately. 8-12-22 RH curb inlets were cleaned out properly and are now in working order.
Pavement-Proof Roll Passed 05/18/2023
Install Street and Stop Signs Passed 05/18/2023
Pavement-Aggregate Base Passed 05/18/2023
Pavement-Curb Construction Passed 05/18/2023
ESC - (Vegetation/Ground Cover) Passed 05/18/2023
Pavement-Stabilized Subgrade Passed 05/18/2023
Storm Sewer Construction Inspection Passed 5/28/2021 5/28/2021 05/18/2023
Misc
Informational
04/20/2021
On Monday, 4-19-2021. Emery Sapp Contracting installed 197LF of 54”HDPE pipe and the bottom section of structure JB 2-3 on line line # 1. The contractor also installed approx 122LF of 48” pipe connecting to the bottom section as well.
Misc
Informational
05/28/2021
Friday 5-28-21: Installing storm from box C.I 5-3 to C.I 5-4 then to C.I 6-1. Storm pipe has been set with correct base, and properly back filled. Pouring inverts at C.I 6-1 and C.I 5-3 and collars on C.I 5-4. Mud will be here at 1:30PM. Roughly 129 LF of 15” HDPE pipe from C.I 5-3 to C.I 5-4 was laid.
Sanitary Sewer Construction Inspection Passed 6/11/2021 6/11/2021 05/18/2023
Misc
Informational
06/10/2021
Core drilled into existing MH 1-6. Used approved boot for 8"pipe to be installed. Started laying 8 sanitary pipe toward MH 3-1. Installed service wyes for lot 184 and 183.
Miscellaneous Correction
Informational
06/10/2021
Still laying pipie toward MH 3-1. Tester was out doing compaction testing on the main and on the 2 service lines.
Misc
Informational
06/10/2021
6/10/21- Crew is working towards MH 2-2 but are into heavy shell rock, watering and compacting as they go. Compaction inspected is also on site. Crew is working on digging out the service lines for lots 171, 172, and 173.
Sanitary Sewer - Air Test Passed 05/18/2023
Sanitary Sewer - Mandrel Passed 05/18/2023
Sanitary Sewer - Vacuum Passed 05/18/2023
Sanitary Sewer - Camera Test Passed 8/18/2021 05/18/2023
Pavement-Surface Passed 05/18/2023
Misc
Informational
08/26/2021
On Thursday, 8-26-2021. Thorn and sons asphalt layer base coarse of asphalt on project. Buckthorn street has (2) lifts of base and contractor will only lay 1st coarse today and finish (2) lift tomorrow.
Water Line - Hydrostatic Test Passed 05/18/2023
Water Line - Construction Inspection Passed 05/18/2023
Misc
Informational
09/07/2021
On Wednesday, 9-01-2021. The Contractor Emery Sapp. Performed a pressure test on the water main that failed to hold the 150 lbs of air introduced. On Thursday,9-02-2021. Another test cycle was held for the air pressure testing and passed holding the 150 lbs for 2 hours. On Thursday, 9-02-2021. Emery Sapp completed chlorination for the water line. On Tuesday, 9-07-2021. Emery Sapp de-chlorinated water line and are waiting on water Services to provide (2) construction taps.
Record Drawing Review Passed 1/12/2022 05/18/2023
Master Drainage As-built Inspection Passed 1/11/2022 05/18/2023
Water Line - Coliform Test 1 Passed 05/18/2023
Water Line - Hydrostatic Test Passed 05/18/2023
Documents & Images
Date Uploaded File Type Document Name
01/26/2021 Receipt Receipt for transaction: 2021-000388
01/26/2021 Receipt Receipt for transaction: 2021-000389
01/26/2021 Receipt Receipt for transaction: 2021-000390
01/26/2021 Receipt Receipt for transaction: 2021-000400
02/10/2021 Approved Plans Hawthorn Ridge 3rd Plat_Sanitary Plans Approved 2.10.21
02/10/2021 Approved Plans Hawthorn Ridge 3rd Plat_Water Plans Approved 2.10.21
02/10/2021 Approved Plans Hawthorn Ridge 3rd Plat_Street & Storm Plans Approved 2.10.21
02/10/2021 Approved Plans Hawthorn Ridge 3rd Plat_Site Disturbance Plans Approved 2.10.21
04/01/2021 Letter DE-Permit
04/14/2021 Letter INSPECTION SUMMARY
04/15/2021 Letter INSPECTION SUMMARY
04/15/2021 Letter INSPECTION SUMMARY
04/15/2021 Letter INSPECTION SUMMARY
04/15/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
04/30/2021 Letter INSPECTION SUMMARY
05/26/2021 Letter INSPECTION SUMMARY
06/03/2021 Letter INSPECTION SUMMARY
06/08/2021 Letter INSPECTION SUMMARY
06/10/2021 Letter INSPECTION SUMMARY
06/15/2021 Letter INSPECTION SUMMARY
07/19/2021 Letter INSPECTION SUMMARY
08/03/2021 Letter INSPECTION SUMMARY
08/09/2021 Letter INSPECTION SUMMARY
08/09/2021 Letter INSPECTION SUMMARY
08/09/2021 Letter INSPECTION SUMMARY
08/10/2021 Letter INSPECTION SUMMARY
08/12/2021 Letter INSPECTION SUMMARY
08/13/2021 Approved Plans Hawthorn Ridge, 3rd Plat Revised Curb Ramps
08/18/2021 Letter INSPECTION SUMMARY
08/18/2021 Letter INSPECTION SUMMARY
08/20/2021 Letter INSPECTION SUMMARY
08/20/2021 Letter INSPECTION SUMMARY
08/26/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/30/2021 Letter INSPECTION SUMMARY
09/02/2021 Letter INSPECTION SUMMARY
09/07/2021 Letter INSPECTION SUMMARY
09/08/2021 Letter INSPECTION SUMMARY
09/15/2021 Letter INSPECTION SUMMARY
09/14/2021 Hawthorne Ridge 3rd Plat Passing Water Samples
09/16/2021 Letter INSPECTION SUMMARY
09/16/2021 Letter INSPECTION SUMMARY
09/16/2021 Letter INSPECTION SUMMARY
09/20/2021 Letter INSPECTION SUMMARY
01/04/2022 2022-01-04_HR3 Street & Storm Sewer As Built Plans
01/04/2022 21-10-19_Hawthorn Ridge BMP Maintenance Plan
01/04/2022 21-10-19_Hawthorn Ridge BMP Maintenance Plan
01/04/2022 Drawing 2022-01-04_HR3 Water Main As Built Plans
01/04/2022 Drawing 2022-01-04_HR3 Sanitary Sewer As Built Plans
01/04/2022 Drawing 2022-01-04_HR3 Sanitary Sewer As Built Plans
01/24/2022 Letter DE-Certificate of Substantial Completion Multiple Lot
02/24/2022 Letter DE-Punch List
07/28/2022 Letter INSPECTION SUMMARY
08/04/2022 Letter INSPECTION SUMMARY
08/12/2022 Letter INSPECTION SUMMARY
02/17/2023 Hawthorn Ridge 3rd Affidavit
02/21/2023 Hawthorn Ridge 3rd Plat Maintenance Bond
03/13/2023 Hawthorn Ridge 3rd Plat Maintenance bond - dated
05/18/2023 Letter DE-Certificate of Final Acceptance (Commercial)
05/18/2023 Hawthorn Ridge 3rd plat Final Acceptance
10/29/2024 Letter PW ROW Inspections Report
10/29/2024 Email Bond Inspection has Passed
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home