PRRES20213812
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED AND UNFINSIHED BASEMENT - COVERED DECK
07/22/2021
08/05/2021
01/19/2022
03/13/2023
Locations
Contacts
NICK ZVACEK CONSTRUCTION LLC, Address:1009 INDUSTRIAL DR, Phone:(816) 213-7204  
Nick Zvacek, Address:1009 Industrial Drive, Phone:(816) 325-3440  
NICK ZVACEK CONSTRUCTION LLC, Address:1009 INDUSTRIAL DR, Phone:(816) 213-7204  
COMFORT SYSTEMS HTG/CLG, Address:17232 BEL-RAY PL, Phone:(816) 322-1013  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
CENTURY PLUMBING, Address:14001 CENTURY LN, Phone:(816) 765-6066  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sewer Connection Fee $570.00 $570.00 Paid 08/05/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 08/05/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 08/05/2021
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 08/05/2021
8350015-Water Meter Fee $479.24 $479.24 Paid 08/05/2021
9110078-Valuation Fee New Single Family $1,622.73 $1,622.73 Paid 08/05/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 03/09/2023
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 03/09/2023
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 03/09/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 8/11/2021 08/11/2021
Informational
08/11/2021
FOOTING APPROVED BY ENGINEER
Sewer Service Inspection - R Passed 8/27/2021 (9:30) 8/27/2021 08/27/2021
Water Service Inspection - R Partial 8/27/2021 (9:30) 8/27/2021 08/27/2021
Water Service Inspection - R Passed 9/1/2021 (11:15) 9/1/2021 09/01/2021
Underslab Plumbing Inspection - Residential Passed 10/5/2021 10/5/2021 10/05/2021
Piers/Caissons Inspection - Residential Passed 10/19/2021 (8:00) 10/19/2021 10/19/2021
Electrical Service Inspection Passed 2/11/2022 2/11/2022 02/11/2022
Gas Service Inspection - Residential Failed 2/11/2022 2/11/2022 02/11/2022
Misc
Corrective Action Required
02/11/2022
Not ready. Complete gas line to fireplace
All Rough Inspection - Residential Failed 2/11/2022 2/11/2022 02/11/2022
Misc
Corrective Action Required
02/10/2022
-Deck posts are required to be notched for beam attachment with two 1/2” through bolts or equivalent. Have engineer address this -Nail garage PFH wall sheathing to sill plate w/ 8d@3” oc and nail to header with 8d@3” grid pattern; block at seam and nail sheathing to blocking w/8d@3” -Solid block joist ends above garage portal header -Shim gap under garage studs -Support 2” DVW at 4 ft or less interval above garage -Complete framing around garage column and anchor column to floor with two 1/2” bolts -Fur out garage/closet wall at return air space for R-13 insulation -Fb garage wall from soffit -Protect laundry plumbing; secure red pex water line -Fb duct/plumbing chase at master bathroom shower from horizontal space. You can use insulation for this. Remove paper facing and just pack it in tight -Protect wiring at master closet/bathroom wall top plate at both sides of wall -Complete gas piping to fireplace and retest. Pressure still not holding -Install plumbing roof boot flashing -Strap pantry wall top plate where bored more than 50% -Protect wiring at rear dining bottom wall plate -Security blocking for deck door; fill in gap at strike plate side with wood -Full support for great room ceiling beam near fireplace -Move smoke alarm min 3 ft from the bathroom door opening 2nd fl -Nail siding at bedroom 3&4 step flashings -Protect wiring at bedroom 3 -Fb basement REC room wall space, including space above windows, vertically at ten ft or less interval; Fb wall in basement bedroom 5 closet wall at I beam web. Use insulation; Fb stair stringer space from ceiling space -Pan off return air from ceiling space outside basement bedroom -Seal penetrations of basement ceiling return air space -Toe nail basement joists to sill and wall top plates per code -Block at cantilevered joists **OK TO INSULATE
All Rough Inspection - Residential Failed 2/15/2022 02/15/2022
Misc
Corrective Action Required
02/11/2022
-Deck posts are required to be notched for beam attachment with two 1/2” through bolts or equivalent. Have engineer address this -Nail garage PFH wall sheathing to sill plate w/ 8d@3” oc and nail to header with 8d@3” grid pattern; block at seam and nail sheathing to blocking w/8d@3” -Solid block joist ends above garage portal header -Shim gap under garage studs -Support 2” DVW at 4 ft or less interval above garage -Complete framing around garage column and anchor column to floor with two 1/2” bolts -Fur out garage/closet wall at return air space for R-13 insulation -Fb garage wall from soffit -Protect laundry plumbing; secure red pex water line -Fb duct/plumbing chase at master bathroom shower from horizontal space. You can use insulation for this. Remove paper facing and just pack it in tight -Protect wiring at master closet/bathroom wall top plate at both sides of wall -Complete gas piping to fireplace and retest. Pressure still not holding -Install plumbing roof boot flashing -Strap pantry wall top plate where bored more than 50% -Protect wiring at rear dining bottom wall plate -Security blocking for deck door; fill in gap at strike plate side with wood -Full support for great room ceiling beam near fireplace -Move smoke alarm min 3 ft from the bathroom door opening 2nd fl -Nail siding at bedroom 3&4 step flashings -Protect wiring at bedroom 3 -Fb basement REC room wall space, including space above windows, vertically at ten ft or less interval; Fb wall in basement bedroom 5 closet wall at I beam web. Use insulation; Fb stair stringer space from ceiling space -Pan off return air from ceiling space outside basement bedroom -Seal penetrations of basement ceiling return air space -Toe nail basement joists to sill and wall top plates per code -Block at cantilevered joists **OK TO INSULATE **2/15/22-THIS IS A 2ND FAILED INSPECTION. 3RD AND SUBSEQUENT FAILED INSPECTION WILL RESULT IN ISSUANCE OF REINSPECTION FEE
All Rough Inspection - Residential Not Ready 2/16/2022 2/16/2022 02/16/2022
Misc
Corrective Action Required
02/15/2022
-Deck posts are required to be notched for beam attachment with two 1/2” through bolts or equivalent. Have engineer address this -Nail garage PFH wall sheathing to sill plate w/ 8d@3” oc and nail to header with 8d@3” grid pattern; block at seam and nail sheathing to blocking w/8d@3” -Solid block joist ends above garage portal header -Shim gap under garage studs -Support 2” DVW at 4 ft or less interval above garage -Complete framing around garage column and anchor column to floor with two 1/2” bolts -Fur out garage/closet wall at return air space for R-13 insulation -Fb garage wall from soffit -Fb duct/plumbing chase at master bathroom shower from horizontal space. You can use insulation for this. Remove paper facing and just pack it in tight -Protect wiring at master closet/bathroom wall top plate at both sides of wall -Install plumbing roof boot flashing -Strap pantry wall top plate where bored more than 50% -Protect wiring at rear dining bottom wall plate -Security blocking for deck door; fill in gap at strike plate side with wood -Full support for great room ceiling beam near fireplace -Move smoke alarm min 3 ft from the bathroom door opening 2nd fl -Nail siding at bedroom 3&4 step flashings -Protect wiring at bedroom 3 -Fb basement REC room wall space, including space above windows, vertically at ten ft or less interval; Fb wall in basement bedroom 5 closet wall at I beam web. Use insulation; Fb stair stringer space from ceiling space -Pan off return air from ceiling space outside basement bedroom -Seal penetrations of basement ceiling return air space -Toe nail basement joists to sill and wall top plates per code -Block at cantilevered joists **OK TO INSULATE **2/15/22-THIS IS A 2ND FAILED INSPECTION. 3RD AND SUBSEQUENT FAILED INSPECTION WILL RESULT IN ISSUANCE OF REINSPECTION FEE **2/16/22-NOT READY FEE ASSESSED
Gas Service Inspection - Residential Passed 2/15/2022 2/16/2022 02/16/2022
Misc
Resolved
02/16/2022
Not ready. Complete gas line to fireplace
All Rough Inspection - Residential Not Ready 2/25/2022 2/25/2022 02/25/2022
Misc
Corrective Action Required
02/16/2022
-Deck posts are required to be notched for beam attachment with two 1/2” through bolts or equivalent. Have engineer address this -Nail garage PFH wall sheathing to sill plate w/ 8d@3” oc and nail to header with 8d@3” grid pattern; block at seam and nail sheathing to blocking w/8d@3” -Solid block joist ends above garage portal header **not done -Complete framing around garage column and anchor column to floor with two 1/2” bolts **anchor column -Fur out garage/closet wall at return air space for R-13 insulation -Fb garage wall from soffit -Install plumbing roof flashings -Security blocking for deck door; fill in gap at strike plate side with wood **fill gap at strike plate side and hinges -Nail all siding at step flashings 2nd floor. If I push the siding out and it moves, you have not nailed the siding properly -Fb basement REC room wall space, including space above windows, vertically at ten ft or less interval; Fb wall in basement bedroom 5 closet wall at I beam web. Use insulation; Fb stair stringer space from ceiling space **ok. Just like other houses, use 3/4” sheathing for fire blocking. Fb gaps at vertical fire blockings. -Pan off return air from ceiling space outside basement bedroom **still open to ceiling space outside basement bathroom -Seal penetrations of basement ceiling return air space **not done -Toe nail basement joists to sill and wall top plates per code **not done -Block at cantilevered joists **not done **OK TO INSULATE **2/15/22-THIS IS A 2ND FAILED INSPECTION. 3RD AND SUBSEQUENT FAILED INSPECTION WILL RESULT IN ISSUANCE OF REINSPECTION FEE **2/16/22-NOT READY FEE ASSESSED **2/25/22-NOT READY FEE ASSESSED
All Rough Inspection - Residential Not Ready 3/1/2022 3/1/2022 03/01/2022
Misc
Corrective Action Required
02/25/2022
-Deck posts are required to be notched for beam attachment with two 1/2” through bolts or equivalent. Have engineer address this -Security blocking for deck door; fill in gap at strike plate side with wood **fill gap at strike plate side and hinges -Nail all siding at step flashings 2nd floor. If I push the siding out and it moves, you have not nailed the siding properly ** bedroom 3 and 4. Please nail the siding to studs per code -Reinstall electrical to receptacle at stair wall in basement **OK TO INSULATE **2/15/22-THIS IS A 2ND FAILED INSPECTION. 3RD AND SUBSEQUENT FAILED INSPECTION WILL RESULT IN ISSUANCE OF REINSPECTION FEE **2/16/22-NOT READY FEE ASSESSED **2/25/22-NOT READY FEE ASSESSED **3/1/22-NOT READY FEE ASSESSED
All Rough Inspection - Residential Passed 3/4/2022 3/4/2022 03/04/2022
Misc
Informational
03/04/2022
**OK TO ROCK **2/15/22-THIS IS A 2ND FAILED INSPECTION. 3RD AND SUBSEQUENT FAILED INSPECTION WILL RESULT IN ISSUANCE OF REINSPECTION FEE **2/16/22-NOT READY FEE ASSESSED **2/25/22-NOT READY FEE ASSESSED **3/1/22-NOT READY FEE ASSESSED
Driveway Inspection Partial 5/19/2022 5/19/2022 05/19/2022
Misc
Informational
05/19/2022
5-19-22AN Forms are in place and aggregate is present and compacted
Driveway Inspection Passed 5/23/2022 5/23/2022 06/01/2022
Misc
Informational
05/19/2022
5-19-22AN Forms are in place and aggregate is present and compacted
Misc
Informational
06/01/2022
6-1-22 AN driveway looks good and has expansion joints at curb and right of way.
Occupancy Inspection - Codes Residential Failed 10/26/2022 10/26/2022 10/26/2022
Misc
Corrective Action Required
10/25/2022
-Not ready fees must be paid before any occupancy can be issued -The back corner of lot not draining properly -Install splash blocks -Provide sewer clean out plug per code -Provide sewer tracer wire port at grade -Seal exterior wall penetrations, seal above meter, AC disconnect, seal exterior lights, etc -Deck beam is not attached to outer posts with two 1/2” bolts or equivalent -Secure AC whip within 12” of disconnect -Install tamper-proof caps at AC valves -Provide sump pump discharge min 3 ft from foundation wall -Garage door not self-closing -Provide handrail at garage stair -Provide a luminaire for stair that does not protrude more than 4” from wall -Check the grounding connection to the ufer rebar. Is the insulation removed? -Remove all foundation wall ties -Support water pex line every 32” or less -Fb floor opening under master bathroom tub -Screw the exterior door embedded jamb brace into studs -No power to basement bathroom receptacle
Occupancy Inspection - Codes Residential Failed 3/10/2023 3/10/2023 03/10/2023
Misc
Corrective Action Required
10/26/2022
-The back corner of lot not draining properly**There is still standing water; also fill in soil at eroded area at sump pump discharge pipe -Install splash block at rear -Fb floor opening under master bathroom tub **pack tight with insulation
Plot Plan Inspection Passed 3/13/2023 03/13/2023
Occupancy Inspection - Codes Residential Full C of O 3/13/2023 3/13/2023 03/13/2023
Misc
Resolved
03/13/2023
-The back corner of lot not draining properly**There is still standing water; also fill in soil at eroded area at sump pump discharge pipe -Install splash block at rear -Fb floor opening under master bathroom tub **pack tight with insulation
Documents & Images
Date Uploaded File Type Document Name
07/23/2021 Lot 149 Residental Permit Application_1
07/23/2021 Lot 149 License_Tax_Application
07/23/2021 Permit Codes Residential Plan Review
08/04/2021 Approved Plans APPROVED PLOT PLAN
08/04/2021 Permit Codes Residential Plan Review
08/05/2021 Permit DS Building Permit
08/05/2021 Receipt Receipt for transaction: 2021-006266
08/11/2021 4728 NE Freehold Dr LSMO MC Lot 149 NZC Permit 2021-3812 3rd Party Footing Inspection Report 8-10-21
08/11/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
08/27/2021 Letter INSPECTION SUMMARY
09/01/2021 Letter INSPECTION SUMMARY
09/21/2021 Lot 149 Revised Blue Print 9-21
09/21/2021 Approved Plans approved plans
10/05/2021 Letter INSPECTION SUMMARY
10/19/2021 Letter INSPECTION SUMMARY
02/11/2022 Letter INSPECTION SUMMARY
02/11/2022 Letter INSPECTION SUMMARY
02/11/2022 Letter INSPECTION SUMMARY
02/15/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/25/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/04/2022 Letter INSPECTION SUMMARY
05/19/2022 Letter INSPECTION SUMMARY
06/01/2022 Letter INSPECTION SUMMARY
08/31/2022 Plot Plan APPROVED AS GRADED PLOT PLAN
10/26/2022 Letter INSPECTION SUMMARY
03/09/2023 Receipt Receipt for transaction:2023-001327
03/10/2023 Lot 149 As-Built 2022-08-31
03/10/2023 Letter INSPECTION SUMMARY
03/10/2023 Plot Plan APPROVED AS GRADED PLOT PLAN
03/13/2023 Letter INSPECTION SUMMARY
03/13/2023 Letter Field Certificate of Occupancy
03/13/2023 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home