Summary
PRRES20212715
Building Permit - Residential
Notice of Violation
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK -Window adjacent to the master bathroom tub shall be safety tempered **Window to be boarded off until a tempered glass window replacement is installed
05/25/2021
08/09/2021
11/23/2021
Locations
Contacts
NICK ZVACEK CONSTRUCTION LLC, Address:1009 INDUSTRIAL DR, Phone:(816) 213-7204  
Julie Pitts, Address:10707 Indiana Ave  
COMFORT SYSTEMS HTG/CLG, Address:17232 BEL-RAY PL, Phone:(816) 322-1013  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
CENTURY PLUMBING, Address:14001 CENTURY LN, Phone:(816) 765-6066  
JEFF.BOEHM@ZVACEKCONSTRUCTION.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,147.53 $1,147.53 Paid 08/09/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 08/09/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 08/09/2021
8331507-Sewer Connection Fee $570.00 $570.00 Paid 08/09/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 08/09/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 08/09/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 04/25/2024
Outstanding Fees Amount Paid Owing Date Paid
9110078-Temporary Occupancy Fee $50.00 $0.00 $50.00 Not Paid


$50.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Occupancy Inspection - Codes Residential Pending
Misc
Corrective Action Required
04/25/2024
-Window adjacent to the master bathroom tub shall be safety tempered **Window to be boarded off until a tempered glass window replacement is installed
Underslab Plumbing Inspection - Residential Failed 9/22/2021 9/22/2021 09/22/2021
Misc
Corrective Action Required
09/22/2021
-Vent shower trap. FYI: each trap must connect individually to the wet-vented horizontal drain.
Piers/Caissons Inspection - Residential Passed 10/8/2021 (9:00) 10/8/2021 10/08/2021
Sewer Service Inspection - R Passed 10/12/2021 (1:45) 10/12/2021 10/12/2021
Water Service Inspection - R Partial 10/12/2021 (1:45) 10/12/2021 10/12/2021
Erosion Control Inspection Residential Failed 10/13/2021 10/13/2021
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/13/2021
DEFICIENT EROSION CONTROL INSTALLATION. PROVIDE GRAVEL AT LOT ENTRANCE. RE-INSTALL EROSION CONTROL AND CLEAN UP THE STREET AFTER WATER IS DONE NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Underslab Plumbing Inspection - Residential Failed 10/13/2021 10/13/2021
Misc
Corrective Action Required
09/22/2021
-Vent shower trap. FYI: each trap must connect individually to the wet-vented horizontal drain.
Erosion Control Inspection Residential Failed 10/13/2021 10/13/2021 10/13/2021
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/13/2021
DEFICIENT EROSION CONTROL INSTALLATION. PROVIDE GRAVEL AT LOT ENTRANCE. RE-INSTALL EROSION CONTROL AND CLEAN UP THE STREET AFTER WATER IS DONE NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Misc
Corrective Action Required
10/13/2021
Erosion control needs to be put in place!!
Water Service Inspection - R Passed 10/14/2021 (1:00) 10/14/2021 10/14/2021
Underslab Plumbing Inspection - Residential Passed 10/21/2021 10/21/2021 10/21/2021
Misc
Resolved
10/21/2021
-Vent shower trap. FYI: each trap must connect individually to the wet-vented horizontal drain.
All Rough Inspection - Residential Failed 3/15/2022 3/15/2022 03/15/2022
Misc
Corrective Action Required
03/15/2022
**CLEAN GRAVEL AND DIRT OFF THE STREET AND INSTALL EROSION CONTROL ALONG THE STREET. NO FURTHER INSPECTION IF EC IS NOT IN COMPLIANCE -Deck beam over spanned. Provide middle pier for ridge beam and deck beam support -Protect SE cable at bottom wall plate; at master bedroom; front bedroom; throughout house -Connect duct to all bath fans -Fb wall plate penetrations at half bathroom -Protect plumbing at front bedroom bathroom -Fully nail stud shoes at pantry -Strap exterior wall and interior bearing wall top plates where bored more than 50% -Nail rafters and ceiling joists together -Install collar ties at top ridge -Support valley rafter at ridge above great room -Submit change to plan. Slide door installed in place of windows at rear of great room; or provide engineer report for triple 9.25” lvl span -Provide min 1” clearance from fireplace flue -Install connector at wiring entry into fireplace -Fb gap at back wall of fireplace space -Vent master bathroom tub trap -Toe nail joists to sill plates -Remove bonding screw from sub panel neutral bus bar -Complete electrical to basement closet light -Provide stud at basement bedroom 3 no more than 24” apart -Add additional support for flat ceiling 2x4 joists -Front bathroom-vent connection cannot be below shower trap weir -Protect plumbing in basement bathroom -Pan off return air from fur down ceiling space outside rear basement bedroom -Fb rear basement closet wall from ceiling space -Protect plumbing at wet bar -Vertical fire blocking no more than ten ft apart at rear wall of basement rec -Double joist under half bathroom -Install missing I beam support column at bedroom 3 closet wall **DO NOT INSULATE
Electrical Service Inspection Passed 3/15/2022 3/15/2022 03/15/2022
Gas Service Inspection - Residential Failed 3/15/2022 3/15/2022 03/15/2022
Misc
Corrective Action Required
03/15/2022
Provide min ten psi pressure
Erosion Control Inspection Residential Failed 3/15/2022 3/15/2022 03/15/2022
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
10/13/2021
DEFICIENT EROSION CONTROL INSTALLATION. PROVIDE GRAVEL AT LOT ENTRANCE. RE-INSTALL EROSION CONTROL AND CLEAN UP THE STREET NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Misc
Resolved
03/15/2022
Erosion control needs to be put in place!!
All Rough Inspection - Residential Failed 3/18/2022 3/18/2022 03/18/2022
Misc
Corrective Action Required
03/15/2022
-Deck beam over spanned. Provide middle pier for ridge beam and deck beam support -Connect duct to all bath fans -Fb wall plate penetrations at all low voltage cable penetrations -Protect plumbing at front bedroom bathroom -Fully nail stud shoes at pantry -Strap exterior wall and interior bearing wall top plates where bored more than 50% -Nail rafters and ceiling joists together -Install collar ties at top ridge -Support valley rafter at ridge above great room -Submit change to plan. Slide door installed in place of windows at rear of great room; or provide engineer report for triple 9.25” lvl span -Provide min 1” clearance from fireplace flue -Fb gap at back wall of fireplace space -Vent master bathroom tub trap -Toe nail joists to sill plates -Remove bonding screw from sub panel neutral bus bar -Complete electrical to bedroom 3 closet light **staple wiring min 1.25” from nailing surface -Provide stud at basement bedroom 3 no more than 24” apart -Add additional support for flat ceiling 2x4 joists -Front bathroom-vent connection cannot be below shower trap weir -Protect plumbing in basement bathroom -Pan off return air from fur down ceiling space outside rear basement bedroom -Fb rear basement closet wall from ceiling space -Protect plumbing at wet bar -Vertical fire blocking no more than ten ft apart at rear wall of basement rec -Double joist under half bathroom -Install missing I beam support column at bedroom 3 closet wall **DO NOT INSULATE **3/18-THIS IS A 2ND INSPECTION. KOT READY FEE WILL BE ASSESSED FOR EVERY FAILED INSPECTION AFTER 3RD INSPECTION
Gas Service Inspection - Residential Failed 3/18/2022 3/18/2022 03/18/2022
Misc
Corrective Action Required
03/15/2022
Provide min ten psi pressure
Gas Service Inspection - Residential Not Ready 3/25/2022 3/25/2022 03/25/2022
Misc
Corrective Action Required
03/18/2022
Provide min ten psi pressure **3/25-MIN TEN PSI PRESSURE STILL NOT PROVIDED FOR TESTING. NOT READY FEE ASSESSED
All Rough Inspection - Residential Failed 3/28/2022 3/28/2022 03/28/2022
Misc
Corrective Action Required
03/18/2022
-Deck beam over spanned. Provide middle pier for ridge beam and deck beam support -Submit change to plan. Slide door installed in place of windows at rear of great room; or provide engineer report for triple 9.25” lvl span -Vent master bathroom tub trap **the vent connection cannot be below the trap weir. FYI: you can use the sink drain for wet-venting -Remove bonding screw from sub panel neutral bus bar **not done -Complete electrical to bedroom 3 closet light **staple wiring min 1.25” from nailing surface -Front bathroom-vent connection cannot be below shower trap weir **fb floor penetration -Protect plumbing in basement bathroom **not done -Fb rear basement closet wall from ceiling space **not done. The closet wall space is still open to the fur down ceiling space. Pack in insulation at bathroom I beam web -Install missing I beam support column at bedroom 3 closet wall **fb gap at top **DO NOT INSULATE **3/18-THIS IS A 2ND INSPECTION. NOT READY FEE WILL BE ASSESSED FOR EVERY FAILED INSPECTION AFTER 3RD INSPECTION **3/28-NOT READY FEE ASSESSED
Piers/Caissons Inspection - Residential Passed 3/28/2022 (1:00) 3/28/2022 03/28/2022
All Rough Inspection - Residential Failed 4/4/2022 4/4/2022 04/04/2022
Misc
Corrective Action Required
03/28/2022
-Vent master bathroom tub trap **the vent connection cannot be below the trap weir. FYI: you can use the sink drain for wet-venting **I PROTECTED THE BASEMENT BATHROOM PLUMBING FOR YOUR PLUMBER. HE STILL HAS TO CORRECT HIS PLUMBING FOR THE MASTER BATHROOM TUB VENTING. YOU CAN ROCK NOW **3/18-THIS IS A 2ND INSPECTION. NOT READY FEE WILL BE ASSESSED FOR EVERY FAILED INSPECTION AFTER 3RD INSPECTION **3/28-NOT READY FEE ASSESSED
Gas Service Inspection - Residential Passed 4/4/2022 4/4/2022 04/04/2022
Misc
Resolved
04/04/2022
Provide min ten psi pressure **3/25-MIN TEN PSI PRESSURE STILL NOT PROVIDED FOR TESTING. NOT READY FEE ASSESSED
Driveway Inspection Partial 4/14/2022 4/14/2022 04/14/2022
Misc
Informational
04/12/2022
4-12-22 AN. Forms are in place and aggregate is present and compacted
Misc
Corrective Action Required
04/14/2022
Driveway was framed up with aggregate in and compacted. Driveway measured at 36’ 6”. Spoke with contractor and marked curb to shorten wings to bring into tolerance. 4/14/22 ES
Driveway Inspection Passed 4/22/2022 4/22/2022 04/25/2022
Misc
Informational
04/14/2022
4-12-22 AN. Forms are in place and aggregate is present and compacted
Misc
Corrective Action Required
04/14/2022
Driveway was framed up with aggregate in and compacted. Driveway measured at 36’ 6”. Spoke with contractor and marked curb to shorten wings to bring into tolerance. 4/14/22 ES
Misc
Corrective Action Required
04/25/2022
4-25-22 AN driveway looks good and has expansion joints at curb and right of way . Meets Ada spec
Footing Inspection - Residential Passed 06/09/2022
Informational
06/09/2022
FOOTING APPROVED BY ENGINEER
Plot Plan Inspection Failed 9/2/2022 09/02/2022
Misc
Corrective Action Required
09/02/2022
Complete grading
Sidewalk Inspection Failed 4/6/2023 04/06/2023
Misc
Corrective Action Required
04/06/2023
4-6-2023 NS. Site visited the sidewalk needs to be cleaned before I can do a final inspection.
Sidewalk Inspection Passed 4/20/2023 6/5/2023 06/05/2023
Misc
Corrective Action Required
04/06/2023
4-6-2023 NS. Site visited the sidewalk needs to be cleaned before I can do a final inspection. 6-5-23 NS Site visited and it appears that the sidewalk has been cleaned and passed.
Erosion Control Inspection Residential Passed 04/17/2024
DCM2 ESC DEFICIENT INSTALLATION
Resolved
04/17/2024
DEFICIENT EROSION CONTROL INSTALLATION. PROVIDE GRAVEL AT LOT ENTRANCE. RE-INSTALL EROSION CONTROL AND CLEAN UP THE STREET NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED.
Occupancy Inspection - Codes Residential Failed 4/17/2024 4/17/2024 04/17/2024
Misc
Corrective Action Required
04/17/2024
-Not-ready fees not paid -As-graded plot plan is required -Provide swale at rear of lot -Lower water meter flush to grade -Attach deck beam to each post with two 1/2” through bolts/washers/nuts or equivalent connections; at outer posts, use approved post caps (Simpson Strong-tie or other approved products) to attach deck beam to posts -Deck stair handrail shall be graspable on both sides of handrail -Secure LFNC raceway within 12” of radon switch box -Install front outdoor receptacle weatherproof cover -Provide lighting at exterior of entry door -Final grade, sod, downspout and sump pump extension -Seal exterior wall penetrations; seal above meter, AC disconnect, seal exterior lights, etc -Secure AC whip within 12” of disconnect -Install tamper-proof caps at AC valves -Provide access to roof space in front office closet -Garage stair handrail profile not compliant; Provide min 1.5” space around the handrail -Window adjacent to the master bathroom tub shall be safety tempered -Screw the deck door security strike plate to the embedded metal jamb brace with all 4 screws -Screw the exterior door embedded jamb brace into studs -Support duct above near electrical sub panel -Cut off the ufer rebar to safe length -Support lawn irrigation pex line every 32” horizontally -Provide Siemens breaker for radon fan and label breaker -Provide min 12” horizontal clearance from luminaire to closet storage space -Install basement bedroom window crank
All Rough Inspection - Residential Passed 04/17/2024
Misc
Resolved
04/17/2024
-Vent master bathroom tub trap **the vent connection cannot be below the trap weir. FYI: you can use the sink drain for wet-venting **I PROTECTED THE BASEMENT BATHROOM PLUMBING FOR YOUR PLUMBER. HE STILL HAS TO CORRECT HIS PLUMBING FOR THE MASTER BATHROOM TUB VENTING. YOU CAN ROCK NOW **3/18-THIS IS A 2ND INSPECTION. NOT READY FEE WILL BE ASSESSED FOR EVERY FAILED INSPECTION AFTER 3RD INSPECTION **3/28-NOT READY FEE ASSESSED
Plot Plan Inspection Passed 4/25/2024 04/24/2024
Misc
Resolved
04/24/2024
Complete grading
Occupancy Inspection - Codes Residential Failed 4/24/2024 4/24/2024 04/24/2024
Misc
Corrective Action Required
04/17/2024
-Not-ready fees not paid -Provide lighting at exterior of entry door **Is there a circuit wiring installed? Lighting at front entry is required -Window adjacent to the master bathroom tub shall be safety tempered -Screw the deck door security strike plate to the embedded metal jamb brace with all 4 screws **the security plate is the plate behind the black dead bolt plate. It’s not screwed into the metal jamb brace -Support duct above near electrical sub panel -Cut off the ufer rebar to safe length -Provide Siemens breaker for radon fan and label breaker -Provide min 12” horizontal clearance from luminaire to closet storage space
Occupancy Inspection - Codes Residential Ready for Temp CO 4/25/2024 4/25/2024 04/25/2024
Misc
Corrective Action Required
04/24/2024
-Window adjacent to the master bathroom tub shall be safety tempered **Window to be boarded off until a tempered glass window replacement is installed
Documents & Images
Date Uploaded File Type Document Name
05/25/2021 Application Form Permit Application
05/25/2021 Application Form License Tax Form
05/27/2021 Permit Codes Residential Plan Review
07/27/2021 Approved Plans Approved Drawings
08/06/2021 Plot Plan Approved Plot Plan
08/06/2021 Permit Codes Residential Plan Review
08/09/2021 Permit DS Building Permit
08/09/2021 Receipt Receipt for transaction: 2021-006326
09/07/2021 M L Crose 4717 NE Freehold Dr LSMO Monticello Lot 112 NZC P 2021-2715 3rd Party Footing Inspection Report 9-7-21
09/22/2021 Letter INSPECTION SUMMARY
10/08/2021 Letter INSPECTION SUMMARY
10/12/2021 Letter INSPECTION SUMMARY
10/12/2021 Letter INSPECTION SUMMARY
10/12/2021 Letter INSPECTION SUMMARY
10/13/2021 Letter INSPECTION SUMMARY
10/13/2021 Letter INSPECTION SUMMARY
10/13/2021 Letter INSPECTION SUMMARY
10/14/2021 Letter INSPECTION SUMMARY
10/21/2021 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/18/2022 Letter INSPECTION SUMMARY
03/18/2022 Letter INSPECTION SUMMARY
03/25/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
03/30/2022 Lot 112 Engineering report
04/04/2022 Letter INSPECTION SUMMARY
04/04/2022 Letter INSPECTION SUMMARY
04/12/2022 Letter INSPECTION SUMMARY
04/12/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/25/2022 Letter INSPECTION SUMMARY
06/09/2022 Letter INSPECTION SUMMARY
09/01/2022 Plot Plan Approved As Graded Plot Plan
09/02/2022 Letter INSPECTION SUMMARY
04/06/2023 Letter INSPECTION SUMMARY
06/05/2023 Letter INSPECTION SUMMARY
12/22/2023 Letter Codes 180 Day Letter
04/17/2024 Letter INSPECTION SUMMARY
04/17/2024 Letter INSPECTION SUMMARY
04/17/2024 Letter INSPECTION SUMMARY
04/24/2024 Letter INSPECTION SUMMARY
04/24/2024 Plot Plan approved as graded plot plan
04/25/2024 Letter INSPECTION SUMMARY
04/25/2024 Receipt Receipt for transaction: 2024-002654
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home