Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Footing Inspection - Commercial
|
Partial
|
6/21/2022 (11:15)
|
6/21/2022
|
06/21/2022
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Footing Inspection - Commercial
|
Passed
|
|
7/15/2022
|
07/15/2022
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Underslab Plumbing Inspection - Commercial
|
Passed
|
7/21/2022
|
7/21/2022
|
07/21/2022
|
|
Misc
Corrective Action Required
|
Foundation Inspection - Commercial
|
Passed
|
7/26/2022 (2:00)
|
7/26/2022
|
07/26/2022
|
All Rough Inspection - Commercial
|
Failed
|
|
9/8/2022
|
09/08/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
Site Visit
|
Partial
|
|
10/20/2022
|
10/20/2022
|
|
Misc
|
Rated Assembly Inspection
|
Partial
|
10/25/2022
|
10/25/2022
|
10/25/2022
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/1/2022
|
11/1/2022
|
11/01/2022
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
All Rough Inspection - Commercial
|
Partial
|
|
11/1/2022
|
11/01/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
11/11/2022
|
11/11/2022
|
11/11/2022
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Rated Assembly Inspection
|
Partial
|
|
11/11/2022
|
11/11/2022
|
|
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
|
Gas Service Inspection - Commercial
|
Passed
|
11/28/2022
|
11/28/2022
|
11/28/2022
|
All Rough Inspection - Commercial
|
Partial
|
|
11/28/2022
|
11/28/2022
|
|
Miscellaneous Correction
Corrective Action Required
|
Water Service Inspection
|
Failed
|
|
1/6/2023
|
01/06/2023
|
|
Miscellaneous Correction
Corrective Action Required
|
Water Service Inspection
|
Failed
|
|
1/6/2023
|
01/06/2023
|
|
Miscellaneous Correction
Corrective Action Required
|
Electrical Service Inspection
|
Failed
|
2/21/2023
|
2/21/2023
|
02/21/2023
|
|
Misc
Corrective Action Required
|
Gas Service Inspection - Commercial
|
Passed
|
|
2/24/2023
|
02/24/2023
|
Gas Piping Inspection - Commercial
|
Passed
|
|
2/24/2023
|
02/24/2023
|
Electrical Service Inspection
|
Failed
|
3/2/2023
|
3/2/2023
|
03/02/2023
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Failed
|
3/7/2023
|
3/7/2023
|
03/07/2023
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Partial
|
3/9/2023
|
3/9/2023
|
03/09/2023
|
|
Misc
Corrective Action Required
|
In-wall Inspection
|
Passed
|
3/30/2023
|
3/30/2023
|
03/30/2023
|
Occupancy Inspection - Engineering
|
Temporary C of O
|
4/5/2023
|
4/5/2023
|
04/05/2023
|
|
Misc
|
Occupancy Inspection - Codes Commercial
|
Failed
|
4/5/2023
|
4/5/2023
|
04/05/2023
|
|
Misc
Corrective Action Required
|
All Rough Inspection - Commercial
|
Passed
|
2/24/2023
|
|
04/05/2023
|
|
Miscellaneous Correction
|
Rated Assembly Inspection
|
Passed
|
2/21/2023
|
|
04/05/2023
|
|
THE FOLLOWING AREAS ARE APPROVED
|
Occupancy Inspection - Fire
|
Failed
|
4/5/2023
|
4/5/2023
|
04/05/2023
|
|
Corrective Action Required
|
Occupancy Inspection - Planning
|
Passed
|
4/5/2023
|
4/5/2023
|
04/05/2023
|
Electrical Service Inspection
|
Failed
|
4/7/2023
|
4/7/2023
|
04/07/2023
|
|
Misc
Corrective Action Required
|
Electrical Service Inspection
|
Passed
|
4/10/2023
|
4/10/2023
|
04/10/2023
|
|
Misc
|
Final Inspection - Commercial
|
Failed
|
4/10/2023
|
4/10/2023
|
04/10/2023
|
|
Miscellaneous Correction
Corrective Action Required
|
Occupancy Inspection - Engineering
|
Passed
|
4/11/2023
|
4/11/2023
|
04/11/2023
|
|
Misc
|
Final Inspection - Commercial
|
Passed
|
4/12/2023
|
4/12/2023
|
04/12/2023
|
|
Miscellaneous Correction
|