Summary
PRCOM20214591
Building Permit - Commercial
Certificate of Occupancy
LSPH INVESTORS LLC
NEW SHELL BUILDING
NEW SHELL BUILDING FOR FUTURE CARRY OUT RESTAURANT STOP WORK ORDER generated on 11/15/2021 12:00 AM by username 'Mark Harding'. STOP WORK ORDER removed on 11/17/2021 12:00 AM by username 'Mark Harding'.
09/01/2021
10/07/2021
03/02/2022
08/03/2022
Locations
Contacts
HARMON CONSTRUCTION INC, Address:18989 WEST 158TH ST, Phone:(913) 962-5888  
gwhite@harmonconst.com, Address:gwhite@harmonconst.com  
TEAGUE ELECTRIC CONSTRUCTION INC, Address:12425 W 92ND ST, Phone:(913) 529-4600  
HEARTLAND PLUMBING INC, Address:800 S CREEKSIDE DR, Phone:(913) 856-5846  
red architecture + planning, Address:589 W Nationwide Blvd, suite b, Phone:(614) 487-8770  
LSPH INVESTORS LLC, Address:3901 W 83RD ST  
SADAM@HARMONCONST.COM  
LOKI ASSET GROUP LLC, Address:8303 MAPLEWOOD LN  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 10/05/2021 10/05/2021
Joe Frogge
LC - General Contractor
Resolved
09/28/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact.
LC - MEP Subs
Resolved
10/05/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors. 9/28/21 - waiting on hvac contractor
Final Development Plan Review Approved 10/01/2021
Joe Frogge
Fire Plan Review Approved 10/05/2021 09/28/2021
Michael Weissenbach
Address numbers required
Resolved
09/28/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Building Plan Review Rejected 10/05/2021 09/28/2021
Joe Frogge
Final Development Plan
Resolved
10/01/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes. 9/28/21 - acknowledged in letter
Misc
Resolved
10/05/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes. 9/28/21 - acknowledged in letter
Engineered truss package
Corrective Action Required
09/28/2021

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide roof truss package or request deferral. 9/28/21 - deferred per request
Misc
Corrective Action Required
09/28/2021

Demolition permit required to remove existing structure on this site. Action required: Comment is for informational purposes. 9/28/21 - acknowledged in letter - to be separate submittal
Building Plan Review Rejected 09/16/2021 09/02/2021
Joe Frogge
Final Development Plan
Corrective Action Required
09/02/2021

The building permit for this project cannot be issued until the Development Services Department has received, approved, and processed the Final Development Plan. Action required: Comment is for informational purposes.
Misc
Corrective Action Required
09/02/2021

A License Tax application completed by the contractor must be submitted to the City of Lee's Summit, Codes Administration Department, and any applicable License Tax paid prior to issuing a building permit. Action required: Comment is for informational purposes.
Engineered truss package
Corrective Action Required
09/02/2021

Copies of the engineered truss package were not provided at the time of permit application. Action required: Provide roof truss package or request deferral.
Misc
Corrective Action Required
09/02/2021

Demolition permit required to remove existing structure on this site. Action required: Comment is for informational purposes.
Licensed Contractors Rejected 09/16/2021 09/02/2021
Joe Frogge
LC - General Contractor
Corrective Action Required
09/02/2021

Lee's Summit Code of Ordinance, Section7-130.10 - Business License. It shall be unlawful for any person to engage in the construction contracting business without first obtaining a business license as required under the applicable provisions of Chapter 28 of the Lee's Summit Code of Ordinances. Action required: Either a Class A or Class B license is required. Provide the name of the licensed general contractor and an email address for the on-site contact.
LC - MEP Subs
Corrective Action Required
09/02/2021

Lee's Summit Code of Ordinance, Section7-130.4 - Business License. (excerpt) No person, other than a licensed contractor or employees of a licensed contractor, shall engage in electrical, plumbing or mechanical business, construction, installation or maintenance unless duly licensed in accordance with this section. Action required: MEP subcontractors are required to be listed on permit. Provide company names of licensed MEP contractors.
Fire Plan Review Approved with Conditions 09/16/2021 09/02/2021
Michael Weissenbach
Address numbers required
Corrective Action Required
09/02/2021

2018 IFC 505.1- Address numbers. New and existing buildings shall have approved address numbers, building numbers or approved building identification placed in a position that is plainly legible and visible from the street or road fronting the property. These numbers shall contrast with their background. In Multi-tenant commercial building where tenants have multiple entrances located on different sides of the building , each door shall be addressed. Address numbers shall be Arabic numerals or alphabet letters. Numbers shall be a minimum of 4 inches (102 mm) high with a minimum stroke width of 0.5 inch (12.7 mm). (Verified At Inspection)
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $339.00 $339.00 Paid 10/07/2021
91100C9-Water Insp Fee $168.00 $168.00 Paid 10/07/2021
9110081-Paved Surface Inspection Fee $1,597.50 $1,597.50 Paid 10/07/2021
9110071-Site Grading Fee $1,005.00 $1,005.00 Paid 10/07/2021
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 10/07/2021
9110078-Valuation Fee for New Shell Building $1,200.00 $1,200.00 Paid 10/07/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Erosion Control Inspection Residential Partial 10/20/2021 10/20/2021 10/20/2021
Misc
Informational
10/20/2021
Construction entrance is using the old existing asphalt. Rieke Grading was digging on the building pad and trucks were transferring some debris into Oldham Parkway. Talked with from Joe from Rieke Grading and Gary White with Harmon Construction about keeping Oldham clean. They also need to add protection for storm flumes. RP 10-20-21
Footing Inspection - Commercial Failed 11/10/2021 11/10/2021
Miscellaneous Correction
Corrective Action Required
11/10/2021
- PROVIDE 3RD PARTY INSPECTION REPORT WITHIN 48 HOURS OF POUR - - CITY INSPECTION REQUIRED ON COMMERCIAL FOOTING -
Miscellaneous Inspection Failed - Stop Work 11/15/2021 11/15/2021
Misc
Corrective Action Required
11/15/2021
Spoke to Gary he was not aware Lee's Summit inspects commercail footings. Not footing inspections until Special inspections are submitted and approved by Lee's Summit.. MARK HARDING 11/15/2021 8:22 AM ready @ 8--- trash encloser. Gary 913-901-6969 Sara Beck 11/12/2021 9:24 AM STOP WORK ORDER generated. This inspection was scheduled for 11/15/2021 12:00 AM and was assigned to 'Patrick Schonfeldt'.
Footing Inspection - Commercial Failed - Stop Work 11/15/2021 (8:00) 11/15/2021 11/15/2021
Miscellaneous Correction
Corrective Action Required
11/10/2021
- PROVIDE 3RD PARTY INSPECTION REPORT WITHIN 48 HOURS OF POUR - - CITY INSPECTION REQUIRED ON COMMERCIAL FOOTING -
Misc
Informational
11/15/2021
11/15/21 - INSPECTED TRASH ENCLOSURE FOOTING
Water Service Inspection Failed 11/16/2021 11/16/2021
Misc
Corrective Action Required
11/16/2021
Doesn’t have 10 feet of copper pipe out of the meter pit. Told contractor that he needs 10 feet and that it can’t be spliced together. RP 11-16-21
Underground Plumbing Inspection - Commercial Passed 11/17/2021 11/17/2021 11/17/2021
Misc
Corrective Action Required
11/16/2021
Doesn’t have 10 feet of copper pipe out of the meter pit. Told contractor that he needs 10 feet and that it can’t be spliced together. RP 11-16-21
Misc
Informational
11/17/2021
Contractor installed new copper pipe over 10 feet long out of the meter. We went to Water Dept and got them a new meter well, since the old one was dug up and in bad shape. RP 11-17-21
Rough Framing Inspection - Commercial Failed 11/18/2021 11/18/2021 11/18/2021
Miscellaneous Correction
Corrective Action Required
11/18/2021
PROVIDE MISSING ANCHOR BOLT REAR WALL NAIL EXTERIOR WALL SHEATHING PER PLAN PROVIDE HANGERS CORNER TRUSSES NAIL HANGER ABOVE REAR DOOR
Footing Inspection - Commercial Failed 11/18/2021 11/18/2021
Miscellaneous Correction
Resolved
11/18/2021
- PROVIDE 3RD PARTY INSPECTION REPORT WITHIN 48 HOURS OF POUR - - CITY INSPECTION REQUIRED ON COMMERCIAL FOOTING -
Misc
Informational
11/15/2021
11/15/21 - INSPECTED TRASH ENCLOSURE FOOTING
Miscellaneous Correction
Corrective Action Required
11/18/2021
PROVIDE APPROVED CLAMP AT UFER ( CONCRETE ENCASED ELECTRODE ) BRASS ON BRASS : UFER LOCATED SOUTH OF REAR DOOR :
Rough Framing Inspection - Commercial Passed 11/19/2021 11/19/2021 11/19/2021
Miscellaneous Correction
Resolved
11/19/2021
Underslab Plumbing Inspection - Commercial Partial 11/19/2021 11/19/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
11/19/2021
STUB OUTS FOR ROOF DRAINS EXITING BLDG PROVIDE BOCA PLATES AT THESE LOCATIONS
Underground Electrical Inspection - Commercial Partial 11/19/2021 11/19/2021 11/19/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
11/19/2021
CONDUIT SLEEVES AT FOOTING REAR WALL NEAR UFER
Footing Inspection - Commercial Passed 11/19/2021 11/19/2021
Misc
Informational
11/18/2021
11/15/21 - INSPECTED TRASH ENCLOSURE FOOTING
Misc
Informational
11/19/2021
- 3RD PARTY FOOTING BY JEFF MARQUEZ @ ALPHA OMEGA GEOTECH INC - - POURED WITHOUT CITY INSPECTION - - UFER LOCATED NEAR REAR WALL SOUTH OF DOOR INSIDE BUILDING -
Miscellaneous Inspection Passed 11/19/2021 11/19/2021 11/19/2021
Misc
Resolved
11/19/2021
Spoke to Gary he was not aware Lee's Summit inspects commercail footings. Not footing inspections until Special inspections are submitted and approved by Lee's Summit.. MARK HARDING 11/15/2021 8:22 AM ready @ 8--- trash encloser. Gary 913-901-6969 Sara Beck 11/12/2021 9:24 AM STOP WORK ORDER generated. This inspection was scheduled for 11/15/2021 12:00 AM and was assigned to 'Patrick Schonfeldt'.
Roof Drain Passed 11/19/2021 11/19/2021 11/19/2021
Misc
Informational
11/19/2021
Roof drains were attached to 4 inch SCH 40 pipe. Ask Gary from Harmon to add a 45 degree bend near the end section to get clearance from a buried water valve. Also informed Water about the buried water valve. RP 11-19-21
Rough Framing Inspection - Commercial Passed 11/24/2021 11/24/2021
Misc
Informational
11/24/2021
TYVEK COMPLETE
Underground Plumbing Inspection - Commercial Partial 12/9/2021 12/9/2021 12/09/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/09/2021
- 12/9/21 GREASE INTERCEPTOR STUB OUT IN BLDG & STUB OUT REAR OF BLDG EXTERIOR, OK TO COVER -
Piers/Caissons Inspection - Commercial Failed 12/9/2021 12/09/2021
Miscellaneous Correction
Corrective Action Required
12/09/2021
- LIGHT POLE BASE PIERS SHALL BE 5'-0" BELOW GRADE PER PLAN -
Piers/Caissons Inspection - Commercial Passed 12/9/2021 (2:00) 12/9/2021 12/09/2021
Misc
Informational
12/09/2021
-(4) LIGHT POLE BASES, DRIVEN GROUND ROD IN PLACE OK TO POUR -
Underground Electrical Inspection - Commercial Partial 12/15/2021 12/15/2021 12/15/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
11/19/2021
CONDUIT SLEEVES AT FOOTING REAR WALL NEAR UFER - UNDERGROUND CONDUIT (2) LIGHT POLE BASES FRONT OF BUILDING (EAST) -
Underground Electrical Inspection - Commercial Partial 12/15/2021 12/15/2021
THE FOLLOWING AREAS ARE APPROVED
Corrective Action Required
12/15/2021
CONDUIT SLEEVES AT FOOTING REAR WALL NEAR UFER - UNDERGROUND CONDUIT (2) LIGHT POLE BASES FRONT OF BUILDING (EAST) - - UNDERGROUND CONDUIT (2) LIGHT POLE BAES REAR OF BUILDING ( WEST), TRANSFORMER TO METER CAN @ TRASH ENCLOSURE -
Site Visit Failed 12/20/2021 12/20/2021 12/21/2021
Misc
Corrective Action Required
12/21/2021
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Pavement-Aggregate Base Partial 12/21/2021 12/21/2021 12/21/2021
Misc
Informational
12/21/2021
They removed the noncompliance curbing and placed Tensar Triax140 geogrid along with 6 inches of APWA Type 5 rock over the asphalt / curb section of the parking lot. RP 12-21-21
Pavement-Proof Roll Passed 12/22/2021 12/22/2021 12/22/2021
Misc
Informational
12/22/2021
Steve Robbins covered the proof roll for the subgrade. He said it passed. RP 12-22-21
Pavement-Aggregate Base Passed 12/22/2021
Misc
Informational
12/21/2021
They removed the noncompliance curbing and placed Tensar Triax140 geogrid along with 6 inches of APWA Type 5 rock over the asphalt / curb section of the parking lot. RP 12-21-21
Pavement-Surface Partial 12/22/2021 12/22/2021 12/22/2021
Misc
Informational
12/22/2021
Hanrahan Asphalt laid down 127 tons 4 inches thick of APWA Type 5 R for the base layer. RP 12-22-21
In-wall Inspection Failed 1/7/2022 01/07/2022
Miscellaneous Correction
Corrective Action Required
01/07/2022
PROVIDE STRUCTURAL STRAPS AT ROOF DRAINS TOP PLATE PROVIDE BOCA PLATES AT ROOF DRAINS FIRE CAULK UPWARD PENETRATIONS : OK TO ROCK ABOVE STORE FRONT WINDOWS :
Site Visit Partial 12/22/2021 12/22/2021 02/04/2022
Misc
Corrective Action Required
12/21/2021
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/04/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Site Visit Partial 2/7/2022 2/7/2022 02/10/2022
Misc
Corrective Action Required
02/04/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/04/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/10/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Underground Plumbing Inspection - Commercial Partial 2/11/2022 02/11/2022
Misc
Informational
02/11/2022
GRINDER PUMP CONNECTED TO GREASE INTERCEPTOR AT NW CORNER OF BUILDING
Site Visit Partial 2/11/2022 2/11/2022 02/14/2022
Misc
Corrective Action Required
02/10/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/10/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/10/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/14/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Sewer Service Inspection Passed 2/14/2022 2/14/2022 02/14/2022
Misc
Informational
02/14/2022
Heartland Plumbing connected the hose off the grinder pump to the service line. Ryan Ratcliff from Water came out to assist me in ensuring the connection was done correctly. RP 2-14-22
Site Visit Partial 2/16/2022 2/16/2022 02/16/2022
Misc
Corrective Action Required
02/14/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/14/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/14/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/14/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
02/16/2022
No exterior work being done today that needs inspection. RP 2-16-22
Erosion Control Inspection Residential Partial 11/16/2021 11/16/2021 02/16/2022
Misc
Informational
02/16/2022
Erosion controls are in place. No erosion issues were spotted. RP 2-16-22
Site Visit Partial 2/17/2022 2/17/2022 02/21/2022
Misc
Corrective Action Required
02/16/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/16/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/16/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/16/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
02/16/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Electrical Service Inspection Failed 2/22/2022 2/22/2022 02/22/2022
Miscellaneous Correction
Corrective Action Required
02/22/2022
PROVIDE GROUNDING ELECTRODE SYSTEM PER PLAN WATER SERVICE ENTRY, BUILDING STEEL, CONCRETE ENCASED ELECTRODE
Site Visit Partial 2/22/2022 2/22/2022 02/22/2022
Misc
Corrective Action Required
02/21/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/21/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/21/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/21/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
02/21/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
No utility or exterior work being done today. RP 2-22-22
Site Visit Partial 2/24/2022 2/24/2022 02/24/2022
Misc
Corrective Action Required
02/22/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/22/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/22/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/22/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
02/22/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/22/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/22/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/24/2022
No work being done today due to the snow. RP 2-24-22
Site Visit Partial 2/25/2022 2/25/2022 02/25/2022
Misc
Corrective Action Required
02/24/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/24/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/24/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/24/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
02/24/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/24/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/24/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/24/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Electrical Service Inspection Passed 3/1/2022 3/1/2022 03/01/2022
Miscellaneous Correction
Resolved
03/01/2022
Site Visit Partial 2/28/2022 2/28/2022 03/02/2022
Misc
Corrective Action Required
02/25/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
02/25/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
02/25/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
02/25/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
02/25/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
02/25/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
02/25/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
02/25/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
02/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/02/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Site Visit Partial 3/3/2022 3/3/2022 03/03/2022
Misc
Corrective Action Required
03/02/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
03/02/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
03/02/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
03/02/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
03/02/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/02/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/02/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/02/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/02/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/02/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
03/03/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Driveway Inspection Partial 3/4/2022 3/4/2022 03/04/2022
Misc
Informational
03/04/2022
R&E Concrete had forms placed and aggregate was present and compacted. They were using KCMMB mix and I informed them about using white cure too. RP 3-4-22
Site Visit Partial 3/4/2022 3/4/2022 03/14/2022
Misc
Corrective Action Required
03/03/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
03/03/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
03/03/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
03/03/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
03/03/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/03/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/03/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/03/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/03/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/03/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
03/03/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
03/14/2022
No exterior work being done on site. RP 3-10-22
Site Visit Partial 03/14/2022
Misc
Corrective Action Required
03/14/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
03/14/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
03/14/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
03/14/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
03/14/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/14/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
03/14/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
03/14/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
03/14/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Driveway Inspection Passed 3/11/2022 3/11/2022 03/14/2022
Misc
Informational
03/04/2022
R&E Concrete had forms placed and aggregate was present and compacted. They were using KCMMB mix and I informed them about using white cure too. RP 3-4-22
Misc
Informational
03/14/2022
Finished driveway meets LS spec. RP 3-14-22
Site Visit Partial 3/21/2022 3/21/2022 03/21/2022
Misc
Corrective Action Required
03/14/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
03/14/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
03/14/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
03/14/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
03/14/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/14/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/14/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
03/14/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
03/14/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
03/14/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
03/21/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Site Visit Partial 3/28/2022 3/28/2022 03/28/2022
Misc
Corrective Action Required
03/21/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
03/21/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
03/21/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
03/21/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
03/21/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/21/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/21/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/21/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/21/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/21/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
03/21/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
03/21/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
03/21/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
03/21/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
03/28/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Pavement-Surface Partial 04/06/2022
Misc
Informational
12/22/2021
Hanrahan Asphalt laid down 127 tons 4 inches thick of APWA Type 5 R for the base layer. RP 12-22-21
Misc
Informational
04/06/2022
Dakota’s crew from Hanrahan laid 75 tons of APWA Type 3 R for the parking lot surface. RP 4-5-22
Site Visit Partial 3/29/2022 3/29/2022 04/06/2022
Misc
Corrective Action Required
03/28/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
03/28/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
03/28/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
03/28/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
03/28/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
03/28/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
03/28/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
03/28/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
03/28/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
03/28/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
03/28/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
03/28/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
03/28/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
03/28/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
03/28/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
04/06/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Pavement-Surface Passed 4/8/2022 04/08/2022
Misc
Informational
04/06/2022
Hanrahan Asphalt laid down 127 tons 4 inches thick of APWA Type 5 R for the base layer. RP 12-22-21
Misc
Informational
04/06/2022
Dakota’s crew from Hanrahan laid 75 tons of APWA Type 3 R for the parking lot surface. RP 4-5-22
Site Visit Partial 4/8/2022 04/08/2022
Misc
Corrective Action Required
04/06/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
04/06/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
04/06/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
04/06/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
04/06/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/06/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/06/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/06/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/06/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/06/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
04/06/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
04/06/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
04/06/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
04/06/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
04/06/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
04/06/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
04/08/2022
Landscaping and seeding was placed. RP 4-8-22
Site Visit Partial 4/11/2022 4/11/2022 04/14/2022
Misc
Corrective Action Required
04/08/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
04/08/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
04/08/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
04/08/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
04/08/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/08/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/08/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/08/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/08/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/08/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
04/08/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
04/08/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
04/08/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
04/08/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
04/08/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
04/08/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
04/08/2022
Landscaping and seeding was placed. RP 4-8-22
Misc
Informational
04/14/2022
No exterior work being done today. RP 4-14-22
Piers/Caissons Inspection - Commercial Passed 4/14/2022 04/14/2022
Site Visit Partial 4/19/2022 4/19/2022 04/19/2022
Misc
Corrective Action Required
04/14/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
04/14/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
04/14/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
04/14/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
04/14/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/14/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/14/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/14/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/14/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/14/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
04/14/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
04/14/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
04/14/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
04/14/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
04/14/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
04/14/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
04/14/2022
Landscaping and seeding was placed. RP 4-8-22
Misc
Informational
04/14/2022
No exterior work being done today. RP 4-14-22
Misc
Informational
04/19/2022
Milled and overlaid the existing asphalt for the parking lot. RP 4-19-22
Site Visit Partial 4/19/2022 4/19/2022 04/19/2022
Misc
Corrective Action Required
04/19/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
04/19/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
04/19/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
04/19/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
04/19/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/19/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/19/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/19/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/19/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/19/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
04/19/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
04/19/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
04/19/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
04/19/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
04/19/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
04/19/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
04/19/2022
Landscaping and seeding was placed. RP 4-8-22
Misc
Informational
04/19/2022
No exterior work being done today. RP 4-14-22
Misc
Informational
04/19/2022
Milled and overlaid the existing asphalt for the parking lot. RP 4-18-22
Misc
Informational
04/19/2022
Parking lot is being striped today. Call Gary from Harmon and asked him to remove his erosion controls. RP 4-19-22
Erosion Control Inspection Residential Partial 2/21/2022 4/19/2022 04/19/2022
Misc
Informational
04/19/2022
Called Gary and informed him that he is good to remove silt fencing and gutter buddies. RP 4-19-22
Site Visit Partial 4/25/2022 4/25/2022 05/25/2022
Misc
Corrective Action Required
04/19/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
04/19/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
04/19/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
04/19/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
04/19/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
04/19/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
04/19/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
04/19/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
04/19/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
04/19/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
04/19/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
04/19/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
04/19/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
04/19/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
04/19/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
04/19/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
04/19/2022
Landscaping and seeding was placed. RP 4-8-22
Misc
Informational
04/19/2022
No exterior work being done today. RP 4-14-22
Misc
Informational
04/19/2022
Milled and overlaid the existing asphalt for the parking lot. RP 4-18-22
Misc
Informational
04/19/2022
Parking lot is being striped today. Call Gary from Harmon and asked him to remove his erosion controls. RP 4-19-22
Misc
Informational
05/25/2022
Currently all utility and paving work has been completed. Will continue to monitor site for any erosion control or other issues. 5/25/22 ES
Erosion Control Inspection Residential Passed 6/9/2022 06/09/2022
Misc
Informational
04/19/2022
Called Gary and informed him that he is good to remove silt fencing and gutter buddies. RP 4-19-22
Misc
Informational
06/09/2022
Silt fence and erosion control measures removed. No erosion issue present as vegetation has been established. 6/9/22 ES
Site Visit Partial 6/9/2022 06/09/2022
Misc
Corrective Action Required
05/25/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
05/25/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
05/25/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
05/25/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
05/25/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
05/25/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
05/25/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
05/25/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
05/25/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
05/25/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
05/25/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
05/25/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
05/25/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
05/25/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
05/25/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
05/25/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
05/25/2022
Landscaping and seeding was placed. RP 4-8-22
Misc
Informational
05/25/2022
No exterior work being done today. RP 4-14-22
Misc
Informational
05/25/2022
Milled and overlaid the existing asphalt for the parking lot. RP 4-18-22
Misc
Informational
05/25/2022
Parking lot is being striped today. Call Gary from Harmon and asked him to remove his erosion controls. RP 4-19-22
Misc
Informational
05/25/2022
Currently all utility and paving work has been completed. Will continue to monitor site for any erosion control or other issues. 5/25/22 ES No erosion issue or open items that need inspections. Should be good for TCO from field engineering side. 5/9/22 ES
Site Visit Complete 6/9/2022 06/09/2022
Misc
Corrective Action Required
06/09/2022
Found out they formed and poured curbing without inspections. No geogrid was placed under curb line. No proof roll was done on the curb line either. They curb line along the asphalt section of the parking lot has to be removed and replaced properly. RP 12-20-21
Misc
Informational
06/09/2022
Stopped by the job site today. No work was being done outside, but a contractor that was working inside came out to see me. He thought I was the building inspector. RP 2-1-22
Misc
Informational
06/09/2022
No exterior work being done today that requires inspections by me. RP 2-10-22
Misc
Informational
06/09/2022
Plumber started installation of a grinder pump for the sanitary service line. Called around to verify who looks at what concerning the pump. It was determined that the building inspector would look at the pump, while the field inspector will look at the connection to the service lateral. RP 2-11-22
Misc
Informational
06/09/2022
No exterior work being done today that needs inspection. RP 2-16-22
Misc
Informational
06/09/2022
No work being done due to the snow storm. RP 2-17-22
Misc
Informational
06/09/2022
No utility or exterior work being done today. RP 2-22-22
Misc
Informational
06/09/2022
No work being done today due to the snow. RP 2-24-22
Misc
Informational
06/09/2022
No work being done today that needs inspection. RP 2-25-22
Misc
Informational
06/09/2022
Subcontractor was digging out the subgrade to prep for the concrete section of the parking lot. We talked about laying a minimum of 4 inches of aggregate and 8 inches of concrete. RP 3-2-22
Misc
Informational
06/09/2022
They put down 4 inches of compacted AB3 for the base. RP 3-3-22
Misc
Informational
06/09/2022
No exterior work being done on site. RP 3-10-22
Misc
Informational
06/09/2022
No exterior work being done on site that needs inspection. RP 3-14-22
Misc
Informational
06/09/2022
Nobody from Harmon was on site. Building contractor getting ready to start tiling the interior. RP 3-21-22
Misc
Informational
06/09/2022
Temperature was too low for Hanrahan to lay surface asphalt today. They will try again at a future date. RP 3-28-22
Misc
Informational
06/09/2022
Stopped by to check for puddling after last night’s storm and found none visible. RP 4-6-22
Misc
Informational
06/09/2022
Landscaping and seeding was placed. RP 4-8-22
Misc
Informational
06/09/2022
No exterior work being done today. RP 4-14-22
Misc
Informational
06/09/2022
Milled and overlaid the existing asphalt for the parking lot. RP 4-18-22
Misc
Informational
06/09/2022
Parking lot is being striped today. Call Gary from Harmon and asked him to remove his erosion controls. RP 4-19-22
Misc
Informational
06/09/2022
Currently all utility and paving work has been completed. Will continue to monitor site for any erosion control or other issues. 5/25/22 ES No erosion issue or open items that need inspections. Should be good for TCO from field engineering side. 6/9/22 ES
Underslab Plumbing Inspection - Commercial Passed 06/16/2022
THE FOLLOWING AREAS ARE APPROVED
Resolved
06/16/2022
STUB OUTS FOR ROOF DRAINS EXITING BLDG PROVIDE BOCA PLATES AT THESE LOCATIONS
Underground Plumbing Inspection - Commercial Passed 06/16/2022
THE FOLLOWING AREAS ARE APPROVED
Informational
06/16/2022
- 12/9/21 GREASE INTERCEPTOR STUB OUT IN BLDG & STUB OUT REAR OF BLDG EXTERIOR, OK TO COVER -
Underground Electrical Inspection - Commercial Passed 06/16/2022
THE FOLLOWING AREAS ARE APPROVED
Informational
06/16/2022
CONDUIT SLEEVES AT FOOTING REAR WALL NEAR UFER - UNDERGROUND CONDUIT (2) LIGHT POLE BASES FRONT OF BUILDING (EAST) - - UNDERGROUND CONDUIT (2) LIGHT POLE BAES REAR OF BUILDING ( WEST), TRANSFORMER TO METER CAN @ TRASH ENCLOSURE -
In-wall Inspection Passed 06/16/2022
Miscellaneous Correction
Resolved
06/16/2022
PROVIDE STRUCTURAL STRAPS AT ROOF DRAINS TOP PLATE PROVIDE BOCA PLATES AT ROOF DRAINS FIRE CAULK UPWARD PENETRATIONS : OK TO ROCK ABOVE STORE FRONT WINDOWS :
Occupancy Inspection - Planning Passed 6/16/2022 06/16/2022
Occupancy Inspection - Engineering Temporary C of O 6/16/2022 06/16/2022
Misc
Informational
06/16/2022
All clear for TCO from FE side. 6/16/22 ES
Occupancy Inspection - Codes Commercial Failed 6/16/2022 6/16/2022 06/16/2022
Misc
Informational
06/16/2022
-CODES COMPLETE -COMPLETE ALL ITEMS FOR OTHER DEPARTMENTS
Occupancy Inspection - Water Utilities Passed 6/17/2022 06/17/2022
Occupancy Inspection - Engineering Passed 6/17/2022 06/17/2022
Misc
Informational
06/16/2022
All clear for TCO from FE side. 6/16/22 ES
Occupancy Inspection - Fire Passed 6/16/2022 6/16/2022 06/17/2022
Occupancy Inspection - Codes Commercial Temporary C of O 6/20/2022 06/20/2022
Misc
Corrective Action Required
06/20/2022
-CODES COMPLETE -COMPLETE ALL ITEMS FOR OTHER DEPARTMENTS Applied for VROW 6/16/22 Tco issued for 3 moths to 9/30/22. 1. Final Development Plan (FDP) Applicant Letter, dated 10/1/21, per Traffic Comment no.1: "The two right-of-way deeds (667242 & 598455) wll need to be vacated, maintaining the necessary easements (utility, access, etc.) prior to final occupancy". Temporary Occupancy will be allowed. This is involves the proposed entrance off SW McClendon Dr. VROW will be required per Planning Commission/City Council process.
Occupancy Inspection - Codes Commercial Temporary C of O 6/20/2022 06/20/2022
Misc
Corrective Action Required
06/20/2022
-CODES COMPLETE -COMPLETE ALL ITEMS FOR OTHER DEPARTMENTS Applied for VROW 6/16/22 Tco issued for 3 moths to 9/30/22. 1. Final Development Plan (FDP) Applicant Letter, dated 10/1/21, per Traffic Comment no.1: "The two right-of-way deeds (667242 & 598455) wll need to be vacated, maintaining the necessary easements (utility, access, etc.) prior to final occupancy". Temporary Occupancy will be allowed. This is involves the proposed entrance off SW McClendon Dr. VROW will be required per Planning Commission/City Council process.
Occupancy Inspection - Codes Commercial Full C of O 8/3/2022 08/03/2022
Misc
Resolved
08/03/2022
-CODES COMPLETE -COMPLETE ALL ITEMS FOR OTHER DEPARTMENTS Applied for VROW 6/16/22 Tco issued for 3 moths to 9/30/22. 1. Final Development Plan (FDP) Applicant Letter, dated 10/1/21, per Traffic Comment no.1: "The two right-of-way deeds (667242 & 598455) wll need to be vacated, maintaining the necessary easements (utility, access, etc.) prior to final occupancy". Temporary Occupancy will be allowed. This is involves the proposed entrance off SW McClendon Dr. VROW will be required per Planning Commission/City Council process.
Documents & Images
Date Uploaded File Type Document Name
09/01/2021 Application Form Commercial Permit Application - SHELL-signed
09/01/2021 Plans Permit Set_S Lee's Summit Shell_090121
09/02/2021 Letter Fire Building Plan Review
09/03/2021 Letter DS P/R Corrections Document
09/23/2021 Letter Response Letter_CMG South Lee's Summit Shell_CAC001_092321
09/23/2021 Plans A301 Address Letters_South Lee's Summit Shell_092321
09/28/2021 Letter Fire Building Plan Review
10/05/2021 Application Form License_Tax_Application.Completed
10/01/2021 Approved Plans Approved FDP-Chipotle-100121
10/06/2021 Approved Plans approved_S Lee's Summit Shell_090121
10/07/2021 Receipt Receipt for transaction:2021-007836
10/07/2021 Letter DS Building Permit
10/20/2021 Letter INSPECTION SUMMARY
11/10/2021 Letter INSPECTION SUMMARY
11/10/2021 Drawing Chipotle_Truss_Layout_11_4-JGA REVIEWED (1)
11/10/2021 Plans Chipotle_Truss_Shops11_4-JGA REVIEWED (1)
11/10/2021 Approved Plans approved truss layout
11/10/2021 Approved Plans approved - truss components
11/15/2021 Engineer Report/Study 2021-10-22 - 21-390F - Chipotle Lee's Summit - Soil Nuclear Gauge
11/15/2021 Engineer Report/Study 2021-10-26 - 21-390F - Chipotle Lee's Summit - 2911 Compressive Strength of Concrete
11/15/2021 Engineer Report/Study 2021-10-26 - 21-390F - Chipotle Lee's Summit - Footing Inspection Report
11/15/2021 Engineer Report/Study 2021-10-26 - 21-390F - Chipotle Lee's Summit - Reinforcing Steel Inspection Report
11/15/2021 Engineer Report/Study 2021-10-28 - 21-390F - Chipotle Lee's Summit - Structural Steel Inspection
11/15/2021 Engineer Report/Study 2021-10-21 - 21-390F - Chipotle Lee's Summit - Proofroll Inspection Report
11/15/2021 Engineer Report/Study 2021-10-20 - 21-390F - Chipotle Lee's Summit - General Observation Report
11/15/2021 Letter Stop Work Order
11/15/2021 Letter Stop Work Order
11/16/2021 Letter INSPECTION SUMMARY
11/16/2021 AOG_Chipotle_Inspections_11_16
11/17/2021 Letter INSPECTION SUMMARY
11/17/2021 Drawing 2021-11-11-21-077 UTILITY PLAN-C4_0 REV4 (1)
11/18/2021 Engineer Report/Study 2021-11-15 - 21-390F - Chipotle Lee's Summit - Reinforcing Steel Inspection Report
11/18/2021 Engineer Report/Study 2021-11-15 - 21-390F - Chipotle Lee's Summit - Footing Inspection Report
11/18/2021 Letter INSPECTION SUMMARY
11/18/2021 Letter INSPECTION SUMMARY
11/18/2021 Letter INSPECTION SUMMARY
11/18/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/19/2021 Letter INSPECTION SUMMARY
11/22/2021 Approved Plans Chipotle Roof Drain Redesign Approved 11.19.21
11/23/2021 2021-11-19 - 21-390F - Chipotle Lee's Summit - Masonry Inspection Report
11/23/2021 2021-11-15 - 21-390F - Chipotle Lee's Summit - 3006 Compressive Strength of Concrete
11/24/2021 chipotle_concrete_test_11_23
11/24/2021 Chipotle_11_23_grout
12/07/2021 Chipotle_Compressivegrout
12/09/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/09/2021 Letter INSPECTION SUMMARY
12/13/2021 Letter INSPECTION SUMMARY
12/14/2021 Compressive Strenght_Trash_Enclosure_Chipotle_28day
12/15/2021 Letter INSPECTION SUMMARY
12/15/2021 Letter INSPECTION SUMMARY
12/21/2021 2021-12-17 - 21-390F - Chipotle Lee's Summit - Proofroll Inspection Report
12/21/2021 Letter INSPECTION SUMMARY
12/21/2021 Letter INSPECTION SUMMARY
12/22/2021 Letter INSPECTION SUMMARY
12/22/2021 Letter INSPECTION SUMMARY
12/22/2021 Letter INSPECTION SUMMARY
12/27/2021 2021-11-19 - 21-390F - Chipotle Lee's Summit - 3041 - Compressive Strength of Grout Prism
12/27/2021 2021-12-21 - 21-390F - Chipotle Lee's Summit - Proofroll Inspection Report
12/28/2021 ASTM D698
12/28/2021 2021-12-21 - 21-390F - Chipotle Lee's Summit - Soil Nuclear Gauge
01/07/2022 Letter INSPECTION SUMMARY
01/07/2022 Letter INSPECTION SUMMARY
02/04/2022 Letter INSPECTION SUMMARY
02/10/2022 Letter INSPECTION SUMMARY
02/11/2022 Drawing 2021-12-22-21-077 UTILITY PLAN-C4_0 REV5
02/11/2022 Approved Plans approved - sewage ejector
02/11/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/21/2022 Letter INSPECTION SUMMARY
02/22/2022 Letter INSPECTION SUMMARY
02/22/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
02/25/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/02/2022 Letter INSPECTION SUMMARY
03/03/2022 Letter INSPECTION SUMMARY
03/04/2022 Letter INSPECTION SUMMARY
03/07/2022 2022-03-02 - 21-390F - Chipotle Lee's Summit - Proofroll Inspection Report
03/14/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/14/2022 Letter INSPECTION SUMMARY
03/21/2022 Letter INSPECTION SUMMARY
03/28/2022 Letter INSPECTION SUMMARY
04/04/2022 K0503G_2020_Mix-Design
04/04/2022 2022-03-08_K0303G_Mix-Design (002)
04/06/2022 Letter INSPECTION SUMMARY
04/06/2022 Letter INSPECTION SUMMARY
04/08/2022 Letter INSPECTION SUMMARY
04/08/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/19/2022 Letter INSPECTION SUMMARY
04/19/2022 Letter INSPECTION SUMMARY
04/19/2022 Letter INSPECTION SUMMARY
05/25/2022 Letter INSPECTION SUMMARY
06/09/2022 Letter INSPECTION SUMMARY
06/09/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/20/2022 Letter Codes Temporary Certificate of Occupancy
06/20/2022 Letter Codes Temporary Certificate of Occupancy
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter Codes Temporary Certificate of Occupancy
08/03/2022 Email Chipotle VROW - TCOCO status update
08/03/2022 Letter Codes Final Certificate of Occupancy
08/03/2022 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home