Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
05/02/2023
|
05/02/2023
|
|
Sue Pyles, P.E.
|
|
Miscellaneous Correction
Please submit an Engineer's Estimate of Probable Construction Costs.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee of $2,028.00 (which is based on 3% of the total infrastructure cost) must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
|
|
|
Engineering Review
|
Approved with Conditions
|
03/01/2023
|
03/02/2023
|
|
Sue Pyles, P.E.
|
|
Miscellaneous Correction
Corrective Action Required
Please submit an Engineer's Estimate of Probable Construction Costs.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $xxx.xx
|
|
|
Planning Review
|
No Comments
|
03/01/2023
|
03/02/2023
|
|
Hector Soto Jr.
|
|
|
Building Codes Review
|
Approved with Conditions
|
03/01/2023
|
02/22/2023
|
|
Scott Ready
|
|
Miscellaneous Correction
Corrective Action Required
This site has been assigned the address of 160 NW Oldham Pkwy. Please update your records and inform your client.
|
|
|
Traffic Review
|
No Comments
|
03/01/2023
|
02/22/2023
|
|
Scott Ready
|
|
|
Fire Review
|
No Comments
|
03/01/2023
|
02/22/2023
|
|
Scott Ready
|
|
|
Engineering Review
|
Corrections
|
02/09/2023
|
02/09/2023
|
|
Sue Pyles, P.E.
|
|
Corrective Action Required
Please submit an Engineer's Estimate of Probable Construction Costs.
|
|
Corrective Action Required
Show location of all oil/gas wells, or indicate none are present, and cite the source.
|
|
Corrective Action Required
Show and label the location and limits of the one percent annual chance flood, as set forth on the current FEMA maps, with reference to the panel number and effective date. Elevations shall be provided if shown on the FEMA map.
|
|
Corrective Action Required
Please add a note stating: “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with a Field Engineering Inspector prior to any land disturbance work at (816) 969-1200.”
|
|
Corrective Action Required
The City requires the use of CG-1 curb and gutter. Pllease include the City's standard detail.
|
|
|
Planning Review
|
Corrections
|
02/09/2023
|
02/09/2023
|
|
Hector Soto Jr.
|
|
Corrective Action Required
APPLICATION.
- Provide a copy of the application form signed by the property owner and applicant.
- Provide a completed and signed copy of the Ownership Affidavit acknowledging and granting permission for submittal of the subject application.
|
|
Corrective Action Required
PHOTOMETRIC PLAN/LIGHTING.
- Provide a photometric plan that complies with the required light levels cited from UDO Section 6.230 that is included on Sheet C1.1. Regarding the lighting requirements, see UDO Section 8.280.D for the specific foot-candle requirements.
- In accordance with UDO Section 8.280.B, canopy light fixtures shall be recessed so that the lens cover is flush with the bottom surface of the canopy. Lights shall not be mounted on the top or sides of the canopy.
|
|
Corrective Action Required
PARKING LOT DESIGN AND CIRCULATION.
- The travel aisle adjacent to the proposed ATM is shown on Sheet C1.1 as measuring 22' from the face of curb on the ATM side of the aisle to an unidentified line on the other side of the aisle to the northwest. Is this unidentified line the back of curb, face of curb or does it represent the edge of pavement where it meets the curb and gutter? To meet minimum requirements for two-way traffic, the adjacent drive aisle must have 20' of pavement width (to the exclusion of curb and gutter). If a minimum of 20' of actual pavement width is maintained, the aisle can remain a two-way drive. If the minimum 20' of actual pavement width cannot be maintained, then the aisle must be a one-way aisle that will then trigger the installation of appropriate signage and pavement markings directing counter-clockwise circulation through this parking area.
- The minimum ATM service drive width shall be 10' (to the exclusion of curb and gutter), meaning 14' from back-of-curb to back-of-curb.
|
|
Corrective Action Required
PARKING SPACE COUNT.
- General Note #21 on Sheet C1.0 states that no parking spaces will be lost due to the ATM construction. However, it appears that two spaces will be lost. Delete the note.
- List the number of existing parking spaces for this parking area and the number of proposed parking spaces for this parking area.
|
|
Corrective Action Required
PAVEMENT DETAIL. The asphalt pavement detail provided on Sheet C2.0 does not meet the City's minimum design standard. Refer to Table 8-5 under UDO Section 8.260 for minimum pavement design.
|
|
Corrective Action Required
SIGNAGE. A separate sign permit application is required for the ATM signage. For your information over-canopy signage is limited to 6 sq. ft. Signage shown on the elevations appear to be twice the allowed sign area.
|
|
|
Building Codes Review
|
Approved with Conditions
|
02/09/2023
|
02/08/2023
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
This site has been assigned the address of 160 NW Oldham Pkwy. Please update your records and inform your client.
|
|
|
Traffic Review
|
No Comments
|
02/09/2023
|
02/08/2023
|
|
Brad Cooley, P.E., RSPI
|
|
|
Fire Review
|
No Comments
|
02/09/2023
|
02/07/2023
|
|
Jim Eden
|
|
|