Planning Application Status

PL2021486




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2021486
Cornerstone at Bailey Farms 1st Plat - Public Sanitary
Engineering Plan Review
Engineering Plan Review
Approved
12/21/2021
CLAYTON PROPERTIES GROUP INC
Locations
Contacts
CLAYTON PROPERTIES GROUP INC, Address:120 SE 30TH ST  
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved with Conditions 12/14/2023 12/14/2023
Gene Williams, P.E.
Engineering Review No Comments 11/13/2023 11/13/2023
Gene Williams, P.E.
Engineering Review Approved with Conditions 06/01/2022 06/02/2022
Gene Williams, P.E.
Engineering Review No Comments 05/12/2022 05/13/2022
Gene Williams, P.E.
Traffic Review No Comments 05/10/2022 04/26/2022
Mike Weisenborn
Engineering Review Corrections 02/28/2022 02/28/2022
Gene Williams, P.E.
Corrective Action Required
02/28/2022

Previous submittal showed 12 inch aggregate over top of pipe on the detail, but this submittal shows 6 inches of aggregate over the top of pipe. As previously discussed, the minimum thickness of aggregate over the top of pipe is now 12 inches, as revised in July 2020. Please revise the standard detail.
Engineering Review Corrections 01/10/2022 01/10/2022
Gene Williams, P.E.
Corrective Action Required
01/10/2022

Slope appears deficient between B8 and L1. Please see new standards for 8 inch pipe slope where upstream connections are the governing criteria, with 1.00 percent slope required in many instances, followed by 0.80 percent, and then 0.60 percent as an absolute minimum if 31 or more connections are provided.
Corrective Action Required
01/10/2022

Slope of pipe along Silo street appear deficient. Please see above comment.
Corrective Action Required
01/10/2022

Line L Sheet 5 appears deficient. Please see above comments concerning slope requirements based on upstream lots.
Corrective Action Required
01/10/2022

Sheet 6: Same comments as above apply to the 8 inch line. Slopes appear deficient based on new standards based on upstream lots.
Corrective Action Required
01/10/2022

Please be aware the "new standard" for sanitary sewer slope have been in effect before the Preliminary Plat was submitted and approved. This new requirement went into effect July of 2020.
Hearings

There are no hearings for this planning application.

Documents & Images
Date Uploaded File Type Document Name
12/21/2021 Plans 21-136-SAN(REV0)
01/10/2022 Letter DE-Comment Letter (Engineering Plans)
02/11/2022 Letter Response to DE-Comment Letter - Sanitary Engineering Plans
02/11/2022 Engineer Report/Study EOPC - Cornerstone at Bailey Farms
02/11/2022 Plans 21-136 SAN(REV1)SIGNED
02/11/2022 Engineer Report/Study SWPPP
02/28/2022 Letter DE-Comment Letter (Engineering Plans)
04/26/2022 Plans 21-136 Sanitary(REV2)sealed
04/26/2022 Engineers Estimate 21-136-Cornerstone EOPC(REV1)
04/26/2022 Letter Response to DE-Comment Letter Sanitary
05/19/2022 Plans 21-136 Sanitary(REV3)sealed
05/19/2022 Letter Response to Emailed Comments dated 5-13-2022 Cornerstone at Bailey Farms 1st Plat Sanitary Sewer
05/19/2022 Engineers Estimate 21-136-Cornerstone EOPC(REV2) sealed
05/24/2022 Email PL2021486 Cornerstone at Bailey Farms 1st Plat - Sanitary Sewer Plans Final QAQC Check
05/24/2022 Plans 21-136 Sanitary(REV4)sealed
05/24/2022 Letter Email from Gene with Comments
05/24/2022 Letter Response to Comments Emailed 5-24-2022 Sanitary Sewer Plans Final QA-QC Check - Cornerstone at Bailey Farms 1st Plat
06/02/2022 Email EMAIL TO AMANDA CONCURRENCE JUN2022
06/02/2022 Activity Document FeeWorksheetCornerstoneSanitary
06/06/2023 Letter APPLICATION EXTENSION REQUEST_Rev 0_PL2021431
10/27/2023 Plans 10272023-21-133-SAN-REV(0)sealed
11/14/2023 Activity Document MDNR Concurrence Letter - Cornerstone at Bailey Farms 1st-2022-06-06
11/30/2023 Plans 21-136 San(REV5) sealed
12/14/2023 Activity Document FeeWorksheetCornerstoneSan
12/14/2023 Approved Plans SANITARY - STAMPED CONSTRUCTION PLANS
12/14/2023 Email STKY APPROVAL
02/05/2024 3rd Party Permit/Approval mogc000680-mo0101087-cornerstone-at-bailey-farms-20240201-fa-jackson-wpcb-cw
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New license, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide: