Review Type |
Outcome |
Est. Completion Date |
Completed |
Engineering Review
|
Approved with Conditions
|
11/30/2021
|
11/30/2021
|
|
Loic Nguinguiri, E.I.
|
|
DE Engineers Estimate
Corrective Action Required
The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit.
|
|
DE Future Repair Work
Corrective Action Required
Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
|
|
DE Contact Field Eng. Inspector
Corrective Action Required
Prior to the commencement of any construction activities, the Contractor shall contact Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference with the assigned Field Engineering Inspector.
|
|
DE C&O #11 Pavement Thickness
Corrective Action Required
Private parking lots shall follow Article 8 of the Unified Development Ordinance for pavement thickness and base requirements.
|
|
|
Fire Review
|
Approved with Conditions
|
11/30/2021
|
11/23/2021
|
|
Jim Eden
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
|
Building Codes Review
|
No Comments
|
11/30/2021
|
11/19/2021
|
|
Mike Weisenborn
|
|
|
Traffic Review
|
No Comments
|
11/30/2021
|
11/19/2021
|
|
Mike Weisenborn
|
|
|
Planning Review
|
No Comments
|
11/30/2021
|
11/19/2021
|
|
Mike Weisenborn
|
|
|
Engineering Review
|
Corrections
|
11/04/2021
|
11/04/2021
|
|
Loic Nguinguiri, E.I.
|
|
Corrective Action Required
Leaders #5, #12, #18 and #25 are not easily visible in plan view of sheet C-100. Revise to make them more visible.
|
|
Corrective Action Required
Add a couple of inlet protection leaders (IP) for the two (2) curb inlets to be protected, shown on both sheets C-400 and C-401.
|
|
Corrective Action Required
In-flow line from CI 200 needs to be 0.2’ minimum higher than the out-flow line, within MH 100.
|
|
Corrective Action Required
The asphalt pavement cross section shown on sheet C-601 is misleading. Please revise, or remove.
|
|
Corrective Action Required
The City requires a 6”-thick minimum layer of granular bedding (aggregate fill) below the edge of utility pipe. Revise the trenching and backfill construction detail accordingly.
|
|
|
Fire Review
|
Approved with Conditions
|
11/04/2021
|
11/02/2021
|
|
Jim Eden
|
|
Code Statement
Corrective Action Required
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Hydrants
Corrective Action Required
IFC 507.5.1 - Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Action required- The nearest hydrant was not shown on the Site or Utility Plans.
|
|
|
Planning Review
|
No Comments
|
11/04/2021
|
11/01/2021
|
|
Victoria Nelson
|
|
Miscellaneous Correction
Setbacks. Please show the required setbacks for building and parking as if the area were zoned CP-2. Refer to UDO Sec. 6.040. Minimum principal building setback Table 6-3. You will have a side yard setback of 10’. Parking setbacks refer to UDO Sec. 8.450.-Design standards-Transition area letter J.
|
|
Miscellaneous Correction
Coordinates. Please provide the State Plane Coordinates for the plat corners.
|
|
Miscellaneous Correction
Measurements. Please do not include the CG-1 curb when showing the measurements for drive aisles and parking spaces. All your drive aisles are measuring less then the required 24’. Refer to the UDO Sec 8.620. Parking lot design.
|
|
Miscellaneous Correction
Trash enclosure concrete pad. The heavy duty concrete pad that is required needs to extend 30’ in front of the gates. Please refer to UDO Sec. 8.620 Parking lot design, letter C, under F. Improvement of Parking and Loading Areas.
|
|
Miscellaneous Correction
Sign. The monument sign exceeds the UDO requirements. This area will follow CP-2 sign regulations, so the monument sign can only be 96 sq. ft. To have a larger monument sign you will need to get approval from Planning Commission. Raceways are not allowed under the UDO, please change it to a wireway or some other mounting. Additional sign information, you are allowed three wall signs anything more will need to get permission from Planning Commission. A wall sign larger than the allowed 10% of façade will need to get permission from Planning Commission. The windmill will also need a permit and it cannot be white, it can be off-white, light tan, light grey, etc. For sign requirements please refer to UDO, Article 9-Signs.
|
|
Miscellaneous Correction
ROW. Please label the ROW width on NW Chipman Rd.
|
|
Miscellaneous Correction
Temporary Asphalt Curb. Please show a temporary asphalt curb on the plans and provided across the drive stub until such time as the abutting lots are developed.
|
|
|
Building Codes Review
|
No Comments
|
11/04/2021
|
10/28/2021
|
|
Joe Frogge
|
|
Miscellaneous Correction
Specify water pipe materials.
|
|
|
Traffic Review
|
No Comments
|
11/04/2021
|
10/28/2021
|
|
Mike Weisenborn
|
|
|
Fire Review
|
Corrections
|
10/19/2021
|
10/19/2021
|
|
Mike Weisenborn
|
|
Code Statement
All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
|
|
Hydrants
IFC 507.5.1 - Where a portion of the facility or building hereafter constructed or moved into or within the jurisdiction is more than 300 feet from a hydrant on a fire apparatus access road, as measured by an approved route around the exterior of the facility or building, on-site fire hydrants and mains shall be provided where required by the fire code official.
Action required- The nearest hydrant was not shown on the Site or Utility Plans.
|
|
|
Engineering Review
|
Corrections
|
10/19/2021
|
10/19/2021
|
|
Loic Nguinguiri, E.I.
|
|
Corrective Action Required
Revise the page reference (sheet number) to C-800 in the lower right-hand corner of the plan sheet showing the existing drainage area map.
|
|
Corrective Action Required
Revise general note 1 to mention that all construction shall be in accordance with the City of Lee’s Summit’s Design and Construction manual.
|
|
Corrective Action Required
Include a note stating that “The contractor shall contact the City’s Development Services Engineering Inspection to schedule a pre-construction meeting with an inspector prior to any land disturbance work at (816) 969-1200”.
|
|
Corrective Action Required
A SWPPP report will not be required for this project since the land disturbance area is below 1 acre. Revise/remove the SWPPP language shown throughout the plans, except if a SWPPP report is intended to be submitted, for review.
|
|
Corrective Action Required
Staff recommends using a different hatching for proposed concrete sidewalk, on the site plan sheet.
|
|
Corrective Action Required
Relocate the proposed monument sign 10’ minimum from the northerly edge of 10’ U/E, on the site plan sheet.
|
|
Corrective Action Required
Show/label a temporary curb across the connection to the western adjacent lot, on the site plan sheet. Include a detail for the temporary curb, as well.
|
|
Corrective Action Required
Relocate the overlapping leaders, shown on both the site plan and grading plan sheets.
|
|
Corrective Action Required
1” domestic water service line connection to 8” water main must be via a 1” tap. Revise the information for U-14 in the table accordingly.
|
|
Corrective Action Required
Staff recommends using two (2) 45-degrees bends instead of one (1) single 90-degrees bend along the proposed domestic water service line.
|
|
Corrective Action Required
Add a U-10 arrow for the unlabeled cleanout located along the proposed domestic sanitary sewer line, in plan view.
|
|
Corrective Action Required
Provide an ESC protection measure, such as silt fence, along both the western and eastern property lines, on sheet C-400. Potential muddy runoff needs to be kept within the site.
|
|
Corrective Action Required
Provide an ESC protection measure, such as inlet protection, to both the northern and southern existing curb inlets. Those will act as secondary ESC protection measures.
|
|
Corrective Action Required
Add a couple of inlet protection leaders (IP) for the curb inlets to be protected along the western property line, in plan view of sheet C-401.
|
|
Corrective Action Required
As shown in the ESC-03 detail, J-hooks are required within the ESC plan. Given the silt fence 100’ maximum runs for J-hooks, please locate the needed J-hooks.
|
|
Corrective Action Required
Show/label the proposed location(s) for ESC blanket/turf on the ESC plan sheet.
|
|
Corrective Action Required
Include area inlet ESC-07 standard detail.
|
|
Corrective Action Required
Detail how MH 100 and CI 200 are intended to connect to the existing 36” private storm line.
|
|
Corrective Action Required
Proposed course thicknesses for medium duty asphalt pavement appear to exceed by far the City’s requirements. Please revise, in accordance with section 8.620 of the City of LS UDO.
|
|
Corrective Action Required
Revise to mention “Chemically stabilized” (base) in the applicable asphalt pavement cross-sectional details, shown on sheet C-600.
|
|
Corrective Action Required
Although 2% cross-slope and 8.33% running slope are allowed, it is recommended that the sidewalks be designed to include construction tolerances. Design slopes of 1.5% and 7.5% are typical. Please note that during the inspection process, sidewalks that exceed the maximum allowable slopes at all will be rejected. There is no allowance given during construction.
|
|
Corrective Action Required
Include the STM-1 curb inlet and GEN-4 curb and gutter details.
|
|
Corrective Action Required
The City requires a 12”-thick minimum layer of granular bedding (aggregate fill) above the edge of utility pipe and a 6”-thick minimum layer below. Revise the trenching and backfill construction details accordingly.
|
|
Corrective Action Required
A 5’ minimum setback is necessary from edge of U/E to edge of overstory tree. Review and verify that the landscaping plan meets this requirement.
|
|
Corrective Action Required
Please provide a stormwater management memorandum.
|
|
Corrective Action Required
Please provide an Engineer’s Opinion of Probable Construction Cost (EOOPCC) sheet.
|
|
|
Traffic Review
|
No Comments
|
10/19/2021
|
10/19/2021
|
|
Brad Cooley, P.E., RSPI
|
|
|
Planning Review
|
Corrections
|
10/19/2021
|
10/19/2021
|
|
Victoria Nelson
|
|
Miscellaneous Correction
Corrective Action Required
Setbacks. Please show the required setbacks for building and parking as if the area were zoned CP-2. Refer to UDO Sec. 6.040. Minimum principal building setback Table 6-3. You will have a side yard setback of 10’. Parking setbacks refer to UDO Sec. 8.450.-Design standards-Transition area letter J.
|
|
Miscellaneous Correction
Corrective Action Required
Coordinates. Please provide the State Plane Coordinates for the plat corners.
|
|
Miscellaneous Correction
Corrective Action Required
Measurements. Please do not include the CG-1 curb when showing the measurements for drive aisles and parking spaces. All your drive aisles are measuring less then the required 24’. Refer to the UDO Sec 8.620. Parking lot design.
|
|
Miscellaneous Correction
Corrective Action Required
Trash enclosure concrete pad. The heavy duty concrete pad that is required needs to extend 30’ in front of the gates. Please refer to UDO Sec. 8.620 Parking lot design, letter C, under F. Improvement of Parking and Loading Areas.
|
|
Miscellaneous Correction
Corrective Action Required
Sign. The monument sign exceeds the UDO requirements. This area will follow CP-2 sign regulations, so the monument sign can only be 96 sq. ft. To have a larger monument sign you will need to get approval from Planning Commission. Raceways are not allowed under the UDO, please change it to a wireway or some other mounting. Additional sign information, you are allowed three wall signs anything more will need to get permission from Planning Commission. A wall sign larger than the allowed 10% of façade will need to get permission from Planning Commission. The windmill will also need a permit and it cannot be white, it can be off-white, light tan, light grey, etc. For sign requirements please refer to UDO, Article 9-Signs.
|
|
Miscellaneous Correction
Corrective Action Required
ROW. Please label the ROW width on NW Chipman Rd.
|
|
Miscellaneous Correction
Corrective Action Required
Temporary Asphalt Curb. Please show a temporary asphalt curb on the plans and provided across the drive stub until such time as the abutting lots are developed.
|
|
|
Building Codes Review
|
Corrections
|
10/19/2021
|
10/14/2021
|
|
Joe Frogge
|
|
Miscellaneous Correction
Corrective Action Required
Specify water pipe materials.
|
|
|