Planning Application Status

PL2021278




 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PL2021278
Lakewood Self Storage
Commercial Final Development Plan
Commercial Final Development Plan
Approved
07/20/2021
SALLEE REAL ESTATE INVESTMENTS LLC
Development of a climate controlled storage facility
Locations
Contacts
SALLEE REAL ESTATE INVESTMENTS LLC, Address:PO BOX 6437  
LAKEWOOD SELF STORAGE, LLC, Address:1220 WASHINGTON, SUITE 300, Phone:(816) 268-4241  
SCHLAGEL & ASSOCIATES, Address:14920 W 107TH ST, Phone:(913) 492-5158  
STRICKLAND CONSTRUCTION CO INC, Address:720 S ROGERS RD STE B, Phone:(913) 764-7000  
Reviews
Review Type Outcome Est. Completion Date Completed
Record Drawings Review No Comments 12/20/2024 12/23/2024
Sue Pyles, P.E.
Planning Review No Comments 01/25/2023 01/24/2023
Shannon McGuire
Building Codes Review No Comments 01/25/2023 01/18/2023
Mike Weisenborn
Traffic Review No Comments 01/25/2023 01/18/2023
Mike Weisenborn
Fire Review Approved with Conditions 01/25/2023 01/18/2023
Mike Weisenborn
Code Statement
Corrective Action Required
01/18/2023

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Engineering Review Approved with Conditions 01/25/2023 01/18/2023
Mike Weisenborn
DE Engineers Estimate
Corrective Action Required
01/18/2023

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $26,530.08.
DE Contact Field Eng. Inspector
Corrective Action Required
01/18/2023

Prior to the commencement of any construction activities, the Contractor shall contact Tom Taylor of Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference.
DE Commercial Detention Basin
Corrective Action Required
01/18/2023

The applicant shall submit and the City shall accept an “As-built / As-graded” detention basin plan prior to issuance of any occupancy permit for the proposed development.
Misc.
Corrective Action Required
01/18/2023

Two (2) full size paper copies of the Final Development Plan with the red Bluebeam authentication stamp shall be delivered to City Hall, Attn: Steve Robbins, 220 SE Green St., Lee's Summit, MO 64063 prior to any construction activities.
DE Future Repair Work
Corrective Action Required
01/18/2023

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Miscellaneous Correction
Corrective Action Required
01/18/2023

Detention basin detail sheet C5.0 shall be corrected during the as-built phase by providing the storage volume in cubic feet rather than sq. yards. It appears this was a minor typographical error when compared to the stormwater report.
Planning Review Corrections 11/16/2022 11/11/2022
Shannon McGuire
Corrective Action Required
11/11/2022

Parapet walls are required for the screening of rooftop mechanical equipment. On all the elevations please provide a dashed line indicating the roof line and rooftop mechanical equipment. The screening shall be at the height or tall then the mechanical equipment it is screening.
Corrective Action Required
11/11/2022

Please provide the manufacturer’s specification sheets for proposed mechanical equipment to be used.
Engineering Review Approved with Conditions 09/15/2021 09/15/2021
Gene Williams, P.E.
DE Engineers Estimate
Corrective Action Required
09/15/2021

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project, and the Engineering Plan Review and Inspection Fee (which is calculated as 3% of the total infrastructure cost plus a water test inspection fee(s)), and the water tap and meter setup fee have been included. These must be paid prior to the issuance of an infrastructure permit and/or the final processing of a building permit. $26,530.08.
DE Contact Field Eng. Inspector
Corrective Action Required
09/15/2021

Prior to the commencement of any construction activities, the Contractor shall contact Tom Taylor of Field Engineering Inspections at (816) 969-1200 to coordinate a preconstruction meeting / conference.
DE Commercial Detention Basin
Corrective Action Required
09/15/2021

The applicant shall submit and the City shall accept an “As-built / As-graded” detention basin plan prior to issuance of any occupancy permit for the proposed development.
Misc.
Corrective Action Required
09/15/2021

Two (2) full size paper copies of the Final Development Plan with the red Bluebeam authentication stamp shall be delivered to City Hall, Attn: Steve Robbins, 220 SE Green St., Lee's Summit, MO 64063 prior to any construction activities.
DE Future Repair Work
Corrective Action Required
09/15/2021

Please be aware that any future repair work to public infrastructure (e.g., water main repair, sanitary sewer repair, storm sewer repair, etc.) within public easements will not necessarily include the repair of pavement, curbing, landscaping, or other private improvements which are located within the easement.
Miscellaneous Correction
Corrective Action Required
09/15/2021

Detention basin detail sheet C5.0 shall be corrected during the as-built phase by providing the storage volume in cubic feet rather than sq. yards. It appears this was a minor typographical error when compared to the stormwater report.
Planning Review No Comments 09/15/2021 09/08/2021
Mike Weisenborn
Fire Review Approved with Conditions 09/15/2021 09/08/2021
Mike Weisenborn
Code Statement
Corrective Action Required
09/08/2021

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Building Codes Review No Comments 09/15/2021 09/08/2021
Mike Weisenborn
Traffic Review No Comments 09/15/2021 09/08/2021
Mike Weisenborn
Engineering Review Corrections 09/07/2021 09/07/2021
Gene Williams, P.E.
Corrective Action Required
09/07/2021

Freeboard between the 100% clogged/zero available storage is shown as 0.8 feet. Is a waiver being sought for the 1.0 foot of freeboard requirement? If so, please contact me for specific forms for the waiver request. Staff would support the waiver, but it must be submitted on forms provided by the City, along with justification for the waiver.
Building Codes Review No Comments 09/07/2021 09/03/2021
Joe Frogge
Miscellaneous Correction
Resolved
09/03/2021

Utility plan references sheet C9 for water meter installation detail (WAT-11) but it is actually on sheet 7.1. Installation of copper piping as designated on detail will be field verified.
Planning Review Corrections 09/07/2021 09/02/2021
Jennifer Thompson
Corrective Action Required
09/02/2021

During the PDP process approval was received for metal paneling for the principal structure. The trash enclosure didn't get approval for the use of metal paneling for the exterior of the enclosure (the walls). The exterior of the trash enclosure (besides the gate), is required to be of a masonry, stucco material. It seemed the call out for the exterior walls were metal paneling.
Fire Review Approved with Conditions 09/07/2021 08/31/2021
Jim Eden
Code Statement
Informational
08/31/2021

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Traffic Review No Comments 09/07/2021 08/30/2021
Mike Weisenborn
Planning Review Corrections 08/23/2021 08/23/2021
Jennifer Thompson
Corrective Action Required
08/23/2021

The exterior of the trash enclosure (besides the gate), is required to be of a masonry, stucco material. It seemed the call out for the exterior walls were metal paneling.
Engineering Review Corrections 08/23/2021 08/23/2021
Gene Williams, P.E.
Corrective Action Required
08/18/2021

Please refer to comment 14 within the previous applicant letter. We do not agree the detention basin is in a "cut" situation. Only a small portion of the basin is shown in this condition. An emergency spillway is warranted, and justification for its location to minimize risk shall be discussed within a revised stormwater report. According to the grading plan, there will be instances where the top of dam is 12 feet higher than existing ground. If the primary outlet works becomes clogged, the dam will overtop. This is not allowed by the Design and Construction Manual.
Corrective Action Required
08/18/2021

Further discussion was held between the applicant's design professionals and City staff concerning Port Dr./Lakewood Way ADA ramp design that was missing from the previous submittal (see comment 12 previous applicant letter). As discussed during an email to Jeff Skidmore and Ryan McGinnis Aug. 9, 2021, an ADA-accessible receiver ramp is required on the northwest corner of Port Dr. It shall be designed to receive pedestrian traffic from the opposite side of Port Dr. Please provide an ADA-accessible ramp on the west side of Port Dr. terminating at a turning space that is designed to be "flat" (as defined by no more than 1.5% slope in any direction). Ensure crosswalk between the two (2) ADA-accessible ramps is after the stop sign. Min. distance is 4 feet, maximum is 6 feet.
Corrective Action Required
08/23/2021

Please see previous applicant letter comment 12. Although an Port Dr./Lakewood Way ADA-accessible ramp detail has been provided on Sheet C1.0, it does not meet the standards set forth in Section 5305 of the City of Lee's Summit Design and Construction Manual in terms of slopes. In particular, ramp exceeds the max. longitudinal design slope of 7.5% from the truncated domes to the gutter when using the elevation callouts provided on this sheet. Cross slopes exceed 1.5% max. Turning space was not defined, and appears to exceed 1.5% in one or more directions. As a guide, Section 5304.8 of the Design and Construction Manual includes a list of items that are required within plans. Please review this list and provide the detailing necessary to construct the ramps in accordance with City of Lee's Summit standards.
Corrective Action Required
08/23/2021

Please see previous applicant letter comment 12. Cross slope at the stop controlled ADA-route across the intersection of Port Dr. and Lakewood Way appears to exceed the max. slope at the proposed crossing. Stop signs should be relocated to a point no further than the PC of the curb return. The relocated crosswalk at that location (i.e., 4 feet after the relocated stop sign) appears to meet the cross slope standards based on the elevation callouts. It would appear the ADA-route across the intersection was planned further north than shown, because the slopes appear compliant near the PC of the curb return.
Corrective Action Required
08/23/2021

Please eliminate the truncated domes from the ADA ramps shown at the commercial entrance. These are only required at public street intersections or other high volume entrances.
Corrective Action Required
08/23/2021

Please see comment 2 and 16 contained within the previous applicant letter. Although Sheet C5.0 was provided, and included some of the items listed, it did not include the grading plan in the form of contours within the detention basin, labeling of line 300 as "section view of dam at outlet structure" (or equivalent language), top of dam elevation in numeric format, emergency spillway in plan view and profile view, elevation of emergency spillway crest in plan and profile view, proposed storage for the 100 year event, slope callouts for dam face (e.g., 3:1), and slope within the bottom of the basin (the profile view shows "less than 1% min.", which does not appear to make sense).
Corrective Action Required
08/23/2021

Conclusions and Recommendations contained within the Stormwater Study: This section contained a statement concerning the emergency spillway being comprised of the grated top of the outlet structure. This does not meet the requirements contained in Section 5600 of the KC APWA, as adopted by the City of Lee's Summit. The top of an outlet structure may be used, provided it is not connected to the primary outlet works. In this case, the top of the grate is acting as a portion of the primary outlet works since the nominal 100 year water surface elevation is above the crest of the grated top. If it is desired to utilize the grated top for the emegency spillway, a minimum of 6 inches freeboard is required between the top of this grated inlet and the 100 year nominal water surface elevation within the basin. Additionally, any downstream pipe connection shall be able to manage the 100% clogged/zero available storage 100 year water surface elevation without overtopping the dam, and with a minimum 1.0 feet of freeboard. Discussion within the text of the report shall be provided, in addition to calculations in the appendix.
Corrective Action Required
08/23/2021

See comment 3 in the previous applicant letter. The response states that the receiving pipe shall be used to constrict flows, but unclear whether overtopping of the dam shall occur during the 100% clogged/zero available storage condition and still maintain a minimum 1.0 feet of freeboard. Please see above comments concerning the emergency spillway for additional clarification.
Corrective Action Required
08/23/2021

Previous submittal showed no casing carrier pipe for the fire line beneath Port Dr. The most recent submittal (utility sheet which was not included on the previous submittal) shows casing carrier pipe for the fire line. Please remove the casing carrier pipe since it is not desired by Water Utilities. It shall be bored, but a casing carrier pipe is not needed or desired.
Corrective Action Required
08/23/2021

Please label the gate valve on the west side of Port Dr. in addition to the label. See opposite side of Port Dr. for example.
Fire Review Approved with Conditions 08/23/2021 08/17/2021
Jim Eden
Code Statement
Informational
08/17/2021

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Knox Locks
Resolved
08/17/2021

IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official. Action required- Provide a Knox Box on the building above the FDC and knox key switches on the gates.
Building Codes Review Approved with Conditions 08/23/2021 08/16/2021
Mike Weisenborn
Miscellaneous Correction
Corrective Action Required
08/16/2021

Utility plan references sheet C9 for water meter installation detail (WAT-11) but it is actually on sheet 7.1. Installation of copper piping as designated on detail will be field verified.
Traffic Review No Comments 08/23/2021 08/16/2021
Mike Weisenborn
Planning Review Corrections 08/03/2021 08/03/2021
Jennifer Thompson
Corrective Action Required
08/03/2021

Provide elevations of the structure. This was not submitted as part of the final development plan submittal.
Corrective Action Required
08/03/2021

On Sheet C0.0 the call out for City of Lee's Summit Public Works replace Dena Mezger with Michael Park.
Corrective Action Required
08/03/2021

Provide a Photometric Sheet. Provide all manufacturer's specifications for the lighting and mechanical units.
Corrective Action Required
08/03/2021

Provide a detail for the trash enclosure.
Corrective Action Required
08/03/2021

The Unified Development Ordinance requires deciduous trees to be a minimum of 3" caliper and evergreen trees are a minimum of 8' in height. Please revise the landscape table.
Corrective Action Required
08/03/2021

Provide dimensions for the parking stalls: width and height. Provide dimensions for the north and south drive aisles.
Corrective Action Required
08/03/2021

Provide the oil/gas well note indicating whether there are any onsite.
Engineering Review Corrections 08/03/2021 08/03/2021
Gene Williams, P.E.
Corrective Action Required
08/03/2021

Retaining wall appears to be within a platted easement on the north side of the project. This is considered an "unallowed use" of the easement.
Corrective Action Required
08/03/2021

Highly recommend a separate sheet for the detention basin. An as-built drawing is required prior to occupancy, and the single sheet with the grading and outlet structure details makes the as-built requirement fairly straightforward. Items to include on this sheet, in addition to what has already been shown on the grading plan, include the storage volume for the 100 year event, the 100 year water surface elevation, the clogged condition/zero available storage 100 year water surface elevation, top of dam, bottom of basin, and slope of the basin. During the as-built phase, the as-built storage volume and as-built elevations shall be shown.
Corrective Action Required
08/03/2021

Is a single 12 inch storm line exiting the basin sufficient for the 100 year event? According to our rough calculations, this primary outflow pipe will not meet the Design and Construction Manual in terms of being able to manage the 100 year event without surcharging.
Corrective Action Required
08/03/2021

A separate utility plan sheet showing the water and sanitary sewer shall be provided.
Corrective Action Required
08/03/2021

Utility plan sheet shall provide callouts for sizing of public water main on west side of Port Dr.
Corrective Action Required
08/03/2021

Material type and sizing shall be shown on utility sheet for the fire line. An additional valve shall be shown on the west side of Port Dr.
Corrective Action Required
08/03/2021

Fire line shall not be tapped, but rather, a cut-in tee shall be noted and shown.
Corrective Action Required
08/03/2021

The plans do not indicate if an irrigation system will be installed. Please provide additional information.
Resolved
08/04/2021

Is an existing sanitary sewer stub already provided for this lot? Mike Weisenborn 08/04/2021 9:03 AM - As stub is not shown on the as-built.
Resolved
08/04/2021

If using anything other than the original sanitary sewer wye and stub, it will need to be properly abandoned. Mike Weisenborn 08/04/2021 9:03 AM - As stub is not shown on the as-built.
Corrective Action Required
08/03/2021

Domestic water main material type shall be shown on the utility sheet. Please be aware of the requirements shown on the standard detail.
Corrective Action Required
08/03/2021

Plan set was missing the ADA-accessible ramps. Standard details shall not be used to construct ADA-accessible ramps, but rather, site-specific designs shall be used. Please be aware the method shown at Lakewood Way and Port Dr. is not going to be acceptable. Multi-directional ramps as shown in GEN-3A are not acceptable unless repairing an existing legacy ramp. New ramp design shall be a mono-directional ramp for each direction. Please ask for examples if needed.
Corrective Action Required
08/03/2021

Wings are shown in the overall site plan for the ADA-accessible ramps. The City does not desire the wings, but rather, grading no more than 3:1 to achieve a transition in the areas normally reserved for "wings".
Corrective Action Required
08/03/2021

Is an emergency spillway warranted for the basin? Is this basin in a cut situation? If not, an emergency spillway meeting the requirements contained in the Design and Construction Manual is required, including the 1.0 foot freeboard between the clogged/zero available storage condition and the top of dam, and 0.5 feet from the nominal 100 year water surface elevation and the crest of the emergency spillway.
Corrective Action Required
08/03/2021

What is the top width of the dam? It appears to be 1 foot, which does not appear adequate for long term integrity of the dam.
Corrective Action Required
08/03/2021

Recommend a typical section view of the dam, showing the emergency spillway, the slope of the dam, the top of the dam, the top width of dam, and the bottom of the basin elevation. This should be placed on the single sheet discussed elsewhere.
Corrective Action Required
08/03/2021

Low opening in the outlet structure appears to be at the flowline (in) elevation of the pipe entering the basin. In other words, it appears there is zero slope from the incoming pipe to the lowest opening in the outlet structure. Please evaluate and revise as appropriate.
Corrective Action Required
08/03/2021

KCMMB mix of a minimum 8 inches thickness shall be shown at the new driveway, from the sawcut in right of way, to the property line.
Corrective Action Required
08/03/2021

Backflow vault shall be moved outside the limits of the easement.
Corrective Action Required
08/03/2021

Discrepancies exist in the outlet structure. One version shows eleven (11) openings, while another shows (7) openings. Please reconcile, and consider that the report shows seven (7). If eleven (11) orifices are being installed, the report shall be updated.
Corrective Action Required
08/03/2021

An Engineer's Estimate of Probable Construction Costs is required prior to formal approval of the plans. The Engineering Plan Review and Inspection Fee is based on this estimate. Please include the following: 1) storm lines and storm structures, 2) sanitary lines and wyes, 3) water lines and fire lines, 4) pavement, 5) subgrade, including the area one (1) foot beyond the back of curb, 6) curb and gutter, 7) grading and compaction, 8) detention basin construction, 9) sidewalk and ADA-accessible ramp, 10) erosion and sediment control measures, and 11) final restoration, including sodding, seeding, fertilizer, mulch, and topsoil.
Traffic Review No Comments 08/03/2021 08/02/2021
Brad Cooley, P.E., RSPI
Building Codes Review Approved with Conditions 08/03/2021 08/02/2021
Joe Frogge
Miscellaneous Correction
Corrective Action Required
08/02/2021

Utility plan references sheet C9 for water meter installation detail (WAT-11) but it is actually on sheet 7.1. Installation of copper piping as designated on detail will be field verified.
Fire Review Approved with Conditions 08/03/2021 07/29/2021
Jim Eden
Code Statement
Corrective Action Required
08/04/2021

All issues pertaining to life safety and property protection from the hazards of fire, explosion or dangerous conditions in new and existing buildings, structures and premises, and to the safety to fire fighters and emergency responders during emergency operations, shall be in accordance with the 2018 International Fire Code.
Knox Locks
Corrective Action Required
07/29/2021

IFC 506.1 - Where access to or within a structure or an area is restricted because of secured openings or where immediate access is necessary for life-saving or fire-fighting purposes, the fire code official is authorized to require a key box to be installed in an approved location. The key box shall be of an approved type listed in accordance with UL 1037, and shall contain keys to gain necessary access as required by the fire code official. 506.1.1 Locks. An approved lock shall be installed on gates or similar barriers when required by the fire code official. Action required- Provide a Knox Box on the building above the FDC and knox key switches on the gates.
Fees
Paid Fees Amount Paid Owing Date Paid
9110077-Final Development Plan fee $725.00 $725.00 Paid 07/20/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Hearings
Title Location Date Time
Documents & Images
Date Uploaded File Type Document Name
07/20/2021 Application Form Final Development Plans App
06/02/2021 Engineer Report/Study The Stormwater Report
06/03/2021 Plans Lakewood MDNR Permit
06/03/2021 Engineer Report/Study SWPPP
08/04/2021 Letter Applicant Letter - FDP (DFDP)
08/16/2021 Plans FDP Sheet Set Rev_ 1
08/16/2021 Engineer Report/Study Rev_1 Final Stormwater Management Plan
08/16/2021 Letter 20-261 - Response to comments - 8-04-2021
08/24/2021 Letter Applicant Letter - FDP (DFDP)
09/08/2021 Letter Response to Comments dated 9-7-21 for Lakewood Self Storage Commercial FDP
09/08/2021 Engineer Report/Study Final Stormwater Management Plan
09/08/2021 Engineer Report/Study 20210907_20-261-FDP Sheet Set-Rev_3
09/15/2021 Activity Document FeeWoksheetFDP
09/15/2021 Letter Applicant Letter - FDP (DFDP)
09/15/2021 Approved Plans Approved Lakewood Self Storage FDP Plan Set
11/09/2022 Email RE_ Lakewood - Building Permit Submittal from Strickland Construction
11/15/2022 Letter Applicant Letter - FDP (DFDP)
01/18/2023 Plans ARCH - LWS-20230103
01/18/2023 Plans ELEC - Updated 1-12-23
01/18/2023 Letter PermitResponseLetter20230103
01/18/2023 Plans PLUMB & MECH - Updated 1-12-23
01/18/2023 Specifications Submittal -MECH Cutsheets - 281890-Lakewood Storage (2)
01/24/2023 Letter Applicant Letter - FDP (DFDP)
12/18/2024 Plans DETENTION BASIN AS-BUILT_REV 0_PL2021278
12/23/2024 Accepted Record Drawings 20241218_20-261-3-FDP-STRM-C5.0 DETENTION BASIN ASBUILT Accepted
11/17/2022 Email Re_ Lakewood Self Storage
11/17/2022 Application Form FDP App, Affivavit - Signed
11/09/2022 Plans LWS-20221108-ARCHSET
09/07/2021 Letter Applicant Letter - FDP (DFDP)
08/30/2021 Plans 20210830_20-261-FDP Sheet Set-Rev_2
08/30/2021 Engineer Report/Study 2-20210826_Complete 20-261-Final Stormwater Management Plan
08/30/2021 Letter Response to Comments dated 8-23-21 for Lakewood Self Storage Commercial FDP-signed
08/16/2021 Engineers Estimate 20-261 Lakewood Business Park Lot 35 Cost Estimate
07/20/2021 Receipt Receipt for transaction:2021-005766
07/20/2021 Plans The FDP
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.