Summary


PRSUBD20236555
Public Infrastructure
Final Acceptance
DEVELOPMENT COMPLETE
Streets of West Pryor, Lot 13A - Sanitary Sewer relocation for Lot 13A of Streets of West Pryor
12/15/2023
02/08/2024
09/10/2024
Locations
Contacts
Sam Malinowsky, Address:SM Engineering, Phone:(785) 341-9747  
Sam Malinowsky, Address:SM Engineering, Phone:(785) 341-9747  
Prosser Wilbert Construction Inc, Address:13730 W 108th Street  
Reviews
Review Type Outcome Est. Completion Date Completed
Engineering Record Drawing Review - Sanitary Accepted 08/30/2024 08/30/2024
Susan Nelson, P.E.
Engineering Review - Sanitary Approved with Conditions 01/12/2024 01/05/2024
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
01/05/2024

Contact Development Services Inspections at (816) 969-1200 to schedule a pre-construction meeting.
Miscellaneous Correction
Corrective Action Required
01/05/2024

Please submit two (2) paper copies (one full size and one 11”x17”) with the red Bluebeam authentication stamp to Ryan Heckman, City Hall, 220 SE Green St., Lee’s Summit, MO 64063. No work described by the plans shall be allowed until these plans have been submitted to the City, and a pre-construction meeting has been held between Ryan Heckman and the contractor.
Miscellaneous Correction
Corrective Action Required
01/05/2024

Any public improvements will require a set of Record Drawings prior to acceptance.
Miscellaneous Correction
Corrective Action Required
01/05/2024

All permanent off-site easements, in a form acceptable to the City, shall be executed and recorded with the Jackson County Recorder of Deeds prior to issuance of a Certificate of Substantial Completion. A certified copy shall be submitted to the City for verification.
Miscellaneous Correction
Corrective Action Required
01/05/2024

The Engineer’s Estimate of Probable Construction Costs has been accepted for this project and the Engineering Plan Review and Inspection Fee, which is calculated as 3% of the total infrastructure cost. These must be paid prior to issuance of an infrastructure permit. $1,359.00
Miscellaneous Correction
Corrective Action Required
01/05/2024

Note that any improvements installed over City utilities or within City easements will not be repaired or replaced if future utility maintenance is required, including, but not limited to, pavement, curbing and guttering, landscaping, trees, shrubs, or other items.
Engineering Review - Sanitary Corrections 01/03/2024 01/03/2024
Susan Nelson, P.E.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Submit an Engineer's Estimate of Probable Construction Costs.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Submit the SWPPP and a copy of the MDNR Land Disturbance Permit.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Update all standard details to show current (2023) revisions.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Add a note to plans that flowable fill backfill is required around all structures.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Label the existing manholes. The existing manhole to be removed is 21-129 and the existing manhole on the other side of the proposed connection is 21-130.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Show missing pipe segment in Sanitary Line A profile.
Miscellaneous Correction
Corrective Action Required
01/03/2024

Please note: With the proposed layout of the sanitary line, if it becomes necessary for the City to dig up this line in the future, there would be significant impact to the ADA parking which will cause inconvenience to the building user and require costly restoration for the property owner.
Fees
Paid Fees Amount Paid Owing Date Paid
91100C8-Sanitary Sewer Insp Fees $1,359.00 $1,359.00 Paid 01/31/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Sanitary Sewer Construction Inspection Partial 3/4/2024 3/4/2024 03/04/2024
Misc
Informational
03/04/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in
Grading/Excavation/Fill Inspection Partial 3/4/2024 3/4/2024 03/04/2024
Misc
Informational
03/04/2024
3-4-24 DP. Contractor Rock and Dirt is on site grading dirt. They have an extra 3' of fill that they weren't expecting they need to remove. This will be stored on a unused lot. They will need to put ESC measures around the dirt pile.
Fire Line Construction Inspection Partial 4/8/2024 4/8/2024 04/08/2024
Misc
Informational
04/08/2024
4/8/2024 DP. Crew was onsite and installed the fireline into the foundation and out 2 sticks. 6" C900 pipe with tracer wire.
Erosion Control Inspection Partial 4/8/2024 4/8/2024 04/08/2024
Misc
Informational
04/08/2024
4-8-24 DP. ESC is installed and is in good working order.
Sanitary Sewer Construction Inspection Partial 4/11/2024 4/11/2024 04/11/2024
Misc
Informational
03/04/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1.
Sanitary Sewer Construction Inspection Partial 4/12/2024 4/12/2024 04/12/2024
Misc
Informational
04/11/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs.
Sanitary Sewer Construction Inspection Partial 4/16/2024 4/16/2024 04/16/2024
Misc
Informational
04/12/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 Rieke is onsite today still working on breaking rock and moving towards A-2
Sanitary Sewer Construction Inspection Partial 4/17/2024 4/17/2024 04/17/2024
Misc
Informational
04/16/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet.
Erosion Control Inspection Partial 4/18/2024 4/18/2024 04/18/2024
Misc
Informational
04/08/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order
Sanitary Sewer Construction Inspection Partial 4/22/2024 4/22/2024 04/23/2024
Misc
Informational
04/17/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base.
Sanitary Sewer Construction Inspection Partial 4/23/2024 4/23/2024 04/23/2024
Misc
Informational
04/23/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base.
Sanitary Sewer Construction Inspection Partial 4/24/2024 4/24/2024 04/24/2024
Misc
Informational
04/23/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today.
Sanitary Sewer Construction Inspection Partial 4/25/2024 4/25/2024 04/25/2024
Misc
Informational
04/24/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today. 4-25-24 DP. Crew was on site this morning before the rain backfilling the sewer trench.
Erosion Control Inspection Partial 4/25/2024 4/25/2024 04/25/2024
Misc
Informational
04/18/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order 4-25-24 DP. ESC is in good working order. Welch fencing was onsite yesterday replacing down silt fence
Sanitary Sewer Construction Inspection Partial 4/30/2024 4/30/2024 04/30/2024
Misc
Informational
04/25/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today. 4-25-24 DP. Crew was on site this morning before the rain backfilling the sewer trench. 4-30-24 DP. Crew is onsite and exposing existing storm boxes for precision cut to come core in junctions
Site Visit Partial 05/02/2024
Misc
Informational
05/02/2024
5-2-24 Dustin A, No activity due to rain
Site Visit Partial 05/03/2024
Misc
Informational
05/02/2024
5-2-24 Dustin A, No activity due to rain 5-3-24 Dustin A, Nobody working on site
Erosion Control Inspection Partial 5/6/2024 5/6/2024 05/06/2024
Misc
Informational
04/25/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order 4-25-24 DP. ESC is in good working order. Welch fencing was onsite yesterday replacing down silt fence 5-6-24 DP. ESC is in good working order
Storm Sewer Construction Inspection Partial 5/8/2024 5/8/2024 05/08/2024
Misc
Informational
05/08/2024
5-8-24 DP. Crew is still working on storm. They have concrete coming tomorrow at 1 pm to pour two walls on storm junction boxes and collars.
Storm Sewer Construction Inspection Partial 5/14/2024 5/14/2024 05/14/2024
Misc
Informational
05/08/2024
5-8-24 DP. Crew is still working on storm. They have concrete coming tomorrow at 1 pm to pour two walls on storm junction boxes and collars. 5-14-24 DP. Crew is onsite today backfilling they have concrete coming tomorrow at 1:30 to pour the remaining collars on strom
Erosion Control Inspection Partial 5/15/2024 5/15/2024 05/15/2024
Misc
Informational
05/06/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order 4-25-24 DP. ESC is in good working order. Welch fencing was onsite yesterday replacing down silt fence 5-6-24 DP. ESC is in good working order 5-15-24 DP. ESC is in good working order.
Sanitary Sewer Construction Inspection Partial 5/15/2024 5/15/2024 05/15/2024
Misc
Informational
04/30/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today. 4-25-24 DP. Crew was on site this morning before the rain backfilling the sewer trench. 4-30-24 DP. Crew is onsite and exposing existing storm boxes for precision cut to come core in junctions 5-15-24 DP. We can begin sewer testing on 5-24-24
Storm Sewer Construction Inspection Partial 5/15/2024 5/15/2024 05/15/2024
Misc
Informational
05/14/2024
5-8-24 DP. Crew is still working on storm. They have concrete coming tomorrow at 1 pm to pour two walls on storm junction boxes and collars. 5-14-24 DP. Crew is onsite today backfilling they have concrete coming tomorrow at 1:30 to pour the remaining collars on strom 5-15-24 DP. Crew was pouring remaining collars today. All storm work will be complete after today.
Water Line - Construction Inspection Partial 5/15/2024 5/15/2024 05/15/2024
Misc
Informational
05/15/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in.
Water Line - Construction Inspection Partial 5/17/2024 5/17/2024 05/17/2024
Misc
Informational
05/15/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in. 5-17-24 DP. Crew laid water line 3 today. They haven't backfilled or poured kickers yet.
Site Visit Partial 5/20/2024 5/20/2024 05/21/2024
Misc
Informational
05/03/2024
5-2-24 Dustin A, No activity due to rain 5-3-24 Dustin A, Nobody working on site 5-20-24 DP. Rieke is onsite today but mostly working on installing electrical conduit for Evergy. They plan on pouring the final sewer invert today at 1 pm. Sewer testing is scheduled for Tuesday.
Erosion Control Inspection Partial 5/20/2024 5/20/2024 05/21/2024
Misc
Informational
05/15/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order 4-25-24 DP. ESC is in good working order. Welch fencing was onsite yesterday replacing down silt fence 5-6-24 DP. ESC is in good working order 5-15-24 DP. ESC is in good working order. 5-20-24 DP. ESC is in good working order.
Sanitary Sewer Construction Inspection Partial 5/21/2024 5/21/2024 05/21/2024
Misc
Informational
05/15/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today. 4-25-24 DP. Crew was on site this morning before the rain backfilling the sewer trench. 4-30-24 DP. Crew is onsite and exposing existing storm boxes for precision cut to come core in junctions 5-15-24 DP. We can begin sewer testing on 5-24-24 5-21-24 DP. Crew poured the final invert today on the daylight manhole.
Water Line - Construction Inspection Partial 5/21/2024 5/21/2024 05/21/2024
Misc
Informational
05/17/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in. 5-17-24 DP. Crew laid water line 3 today. They haven't backfilled or poured kickers yet. 5-21-24 DP. Crew poured a straddle block and a kicker at the blow off valve.
Sanitary Sewer Construction Inspection Partial 5/28/2024 5/28/2024 05/29/2024
Misc
Informational
05/21/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today. 4-25-24 DP. Crew was on site this morning before the rain backfilling the sewer trench. 4-30-24 DP. Crew is onsite and exposing existing storm boxes for precision cut to come core in junctions 5-15-24 DP. We can begin sewer testing on 5-24-24 5-21-24 DP. Crew poured the final invert today on the daylight manhole. 5-28-24 DP. Sewer testing did not happen today. Crew was having some trouble on pre testing. I'll follow up with them this morning. They are doing a private water tie in at 11 am
Sanitary Sewer - Mandrel Passed 5/30/2024 5/30/2024 05/31/2024
Misc
Informational
05/31/2024
5-30-24. Contractor completed mandrel testing today. A2-A1 - passed A2-A3 - passed
Sanitary Sewer - Air Test Passed 5/30/2024 5/30/2024 05/31/2024
Misc
Informational
05/31/2024
5-30-24 DP. Contractor complete Air pressure testing today A2-A3 - passed 7 min 34 seconds A2-A1 - passed 7 min 34 seconds
Sanitary Sewer - Vacuum Passed 5/30/2024 5/30/2024 05/31/2024
Misc
Informational
05/31/2024
5-30-24 DP. Contractor completed vacuum testing today. A-3- passed- 2 min A-2- passed- 2 min A-1- passed- 2 min
Erosion Control Inspection Partial 5/31/2024 5/31/2024 05/31/2024
Misc
Informational
05/21/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order 4-25-24 DP. ESC is in good working order. Welch fencing was onsite yesterday replacing down silt fence 5-6-24 DP. ESC is in good working order 5-15-24 DP. ESC is in good working order. 5-20-24 DP. ESC is in good working order. 5-31-24 DP. ESC is in good working order.
Water Line - Construction Inspection Partial 5/30/2024 5/30/2024 05/31/2024
Misc
Informational
05/21/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in. 5-17-24 DP. Crew laid water line 3 today. They haven't backfilled or poured kickers yet. 5-21-24 DP. Crew poured a straddle block and a kicker at the blow off valve. 5-31-24 DP. Crew attempted to do the first tie in. Their plans just called for them to remove a plug and tie into a TEE. Turns out they have to remove a TEE and replace it with a CROSS. They put this together yesterday evening and had leaks. This is a private water main and no residential services are affected.
Sanitary Sewer Construction Inspection Passed 6/6/2024 6/6/2024 06/06/2024
Misc
Informational
05/29/2024
3-4-24 DP. Crew was on site and removed the sewer pipe out from the building pad. This Sewer had no flow on it. They capped it off for when they tie back in 4-11-24 DP. Rieke Construction is on site and began excavating down to the existing SS line. They got the base of MH A-1 set with the existing pipe laid into MH A-1. They are on a 5' rock shelf so are not able to move along very quick. When I left this afternoon they were getting ready to put their first piece of pipe out of A-1. The contactor also had ROMAC fittings to tie in the sewer service to the main. With input from Brent, I declined these and told them two places to find max adapters. Contractor is laying their pipe on adequate aggregate and covering 1'. They are also starting tracer wire on pipe coming out of A-1. 4-12-24 DP. Rieke construction is onsite today still breaking rock coming out of A-1 they had 3 pieces of pipe laid. I also provided the superintendent with design and construction manual details on backfilling around structures and the new KCMMB asphalt designs. 4-16-24 DP. Rieke is onsite today still working on breaking rock and moving towards A-2 4-17-24 DP. Still working on breaking rock. They realized they were about 8" off so had to rerun the pipe they did have in ground. Still not to A-2 yet. 4-22-24 DP. Contractor has made it to MH A-2 and has set the base. 4-23-24 DP. COntractor has pipe ran between A-2 and A-3. He is working on breaking rock out to set MH A-3 base. 4-24-24 DP. Crew has all public sewer pipe installed, and connected to the three Manhole bases. They are working on backfilling today. 4-25-24 DP. Crew was on site this morning before the rain backfilling the sewer trench. 4-30-24 DP. Crew is onsite and exposing existing storm boxes for precision cut to come core in junctions 5-15-24 DP. We can begin sewer testing on 5-24-24 5-21-24 DP. Crew poured the final invert today on the daylight manhole. 5-28-24 DP. Sewer testing did not happen today. Crew was having some trouble on pre testing. I'll follow up with them this morning. They are doing a private water tie in at 11 am 6-6-24 DP. All sewer testing passed. LS Water Dept. Bond inspection and camera test passed. Sewer is finished.
Sanitary Sewer - Mandrel Passed 6/3/2024 6/3/2024 06/06/2024
Misc
Informational
06/06/2024
6-3-24 DP. A2- A1 passed A2-A3 passed
Sanitary Sewer - Air Test Passed 6/3/2024 6/3/2024 06/06/2024
Misc
Informational
06/06/2024
6-3-24 DP. A2 to A3 passed A2 to A1 passed
Sanitary Sewer - Vacuum Passed 6/3/2024 6/3/2024 06/06/2024
Misc
Informational
06/06/2024
6-3-24 DP. A3- passed A2- passed A1- passed
Sanitary Sewer - Camera Test Passed 6/6/2024 6/6/2024 06/06/2024
Misc
Informational
06/06/2024
6-6-24 DP. Camera test passed. Bond inspection accepted by LS Water Dept.
Water Line - Construction Inspection Partial 6/7/2024 6/7/2024 06/10/2024
Misc
Informational
05/31/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in. 5-17-24 DP. Crew laid water line 3 today. They haven't backfilled or poured kickers yet. 5-21-24 DP. Crew poured a straddle block and a kicker at the blow off valve. 5-31-24 DP. Crew attempted to do the first tie in. Their plans just called for them to remove a plug and tie into a TEE. Turns out they have to remove a TEE and replace it with a CROSS. They put this together yesterday evening and had leaks. This is a private water main and no residential services are affected. 6-7-24 DP. Crew was onsite excavating for their second tie in (fire line)
Water Line - Construction Inspection Partial 6/11/2024 6/11/2024 06/11/2024
Misc
Informational
06/10/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in. 5-17-24 DP. Crew laid water line 3 today. They haven't backfilled or poured kickers yet. 5-21-24 DP. Crew poured a straddle block and a kicker at the blow off valve. 5-31-24 DP. Crew attempted to do the first tie in. Their plans just called for them to remove a plug and tie into a TEE. Turns out they have to remove a TEE and replace it with a CROSS. They put this together yesterday evening and had leaks. This is a private water main and no residential services are affected. 6-7-24 DP. Crew was onsite excavating for their second tie in (fire line) 6-11-24 DP. Crew is still working on water services. The meter pits will be 2.5 feet from the buildings, 2 pits will be in sidewalk and 1 in green space. Brent agreed for the contractor to run a couple feet of copper out of the meter and tie onto the poly that is stubbed out of the foundation of the building.
Fire Line - Hydrostatic Test Passed 6/14/2024 6/14/2024 06/14/2024
Misc
Informational
06/14/2024
6-14-24 DP. Crew completed a hydrostatic test on their fire line. 200psi for 2 houra
Water Line - Construction Inspection Passed 6/13/2024 6/13/2024 06/18/2024
Misc
Informational
06/11/2024
5-15-24 DP. Crew exposed the first water tie in location to see what they were dealing with. They are planning on laying all of the pipe and then doing the first tie in. 5-17-24 DP. Crew laid water line 3 today. They haven't backfilled or poured kickers yet. 5-21-24 DP. Crew poured a straddle block and a kicker at the blow off valve. 5-31-24 DP. Crew attempted to do the first tie in. Their plans just called for them to remove a plug and tie into a TEE. Turns out they have to remove a TEE and replace it with a CROSS. They put this together yesterday evening and had leaks. This is a private water main and no residential services are affected. 6-7-24 DP. Crew was onsite excavating for their second tie in (fire line) 6-11-24 DP. Crew is still working on water services. The meter pits will be 2.5 feet from the buildings, 2 pits will be in sidewalk and 1 in green space. Brent agreed for the contractor to run a couple feet of copper out of the meter and tie onto the poly that is stubbed out of the foundation of the building. 6-13-24 DP. Crew finished installing water pipe with tracer wire. All kickers and straddle blocks were poured.
Water Line - Hydrostatic Test Passed 6/14/2024 6/14/2024 06/18/2024
Misc
Informational
06/18/2024
6-14-24 DP. Crew performed hydrostatic test on the 8" water extension and also the 6" fire line. The 8" was tested at 150 psi for 2 hours and the 6" was tested at 200 psi for 2 hours. Both passed.
Fire Line Construction Inspection Passed 6/13/2024 6/13/2024 06/18/2024
Misc
Informational
04/08/2024
4/8/2024 DP. Crew was onsite and installed the fireline into the foundation and out 2 sticks. 6" C900 pipe with tracer wire.
Water Line - Construction Inspection Partial 6/14/2024 6/14/2024 06/18/2024
Misc
Informational
06/18/2024
6-14-24 DP. Both lines were Chlorinated.
Water Line - Construction Inspection Passed 6/17/2024 6/17/2024 06/18/2024
Misc
Informational
06/18/2024
6-14-24 DP. Both lines were Chlorinated. 6-17-24 DP. Both lines were dechlorinated.
Water Line - Coliform Test 1 Partial 6/18/2024 6/18/2024 06/20/2024
Misc
Informational
06/20/2024
6-18-24 DP. Took first sample on 8" and 6" to Blue Valley Lab.
Water Line - Coliform Test 1 Partial 6/19/2024 6/19/2024 06/20/2024
Misc
Informational
06/20/2024
6-18-24 DP. Took first sample on 8" and 6" to Blue Valley Lab. 6-19-24 DP. Fist sample on the 6" fire line passed. First sample on the 8" line failed TC+
Water Line - Coliform Test 2 Partial 6/19/2024 6/19/2024 06/20/2024
Misc
Informational
06/20/2024
6-19-24 DP. I took second sample of 6" and 8" water mains to Blue Valley Lab.
Water Line - Coliform Test 2 Partial 6/20/2024 6/20/2024 06/20/2024
Misc
Informational
06/20/2024
6-19-24 DP. I took second sample of 6" and 8" water mains to Blue Valley Lab. 6-20-24 DP. The second sample from the 6" main passed and can now be put in service. The second sample of the 8" passed making it the first passing sample of the 8". Still need 1 more passing sample before the 8" can be put into service.
Water Line - Coliform Test 2 Partial 6/20/2024 6/20/2024 06/20/2024
Misc
Informational
06/20/2024
6-19-24 DP. I took second sample of 6" and 8" water mains to Blue Valley Lab. 6-20-24 DP. The second sample from the 6" main passed and can now be put in service. The second sample of the 8" passed making it the first passing sample of the 8". Still need 1 more passing sample before the 8" can be put into service. 6-20-24 DP. I took the 3rd sample to Blue Valley Lab today for the 8" water main.
Erosion Control Inspection Partial 6/25/2024 6/25/2024 06/25/2024
Misc
Informational
05/31/2024
4-8-24 DP. ESC is installed and is in good working order. 4-18-24 DP. ESC is still in good working order 4-25-24 DP. ESC is in good working order. Welch fencing was onsite yesterday replacing down silt fence 5-6-24 DP. ESC is in good working order 5-15-24 DP. ESC is in good working order. 5-20-24 DP. ESC is in good working order. 5-31-24 DP. ESC is in good working order. 6-25-24 RH. ESC is good.
Water Line - Coliform Test 2 Passed 6/21/2024 6/21/2024 06/25/2024
Misc
Informational
06/20/2024
6-19-24 DP. I took second sample of 6" and 8" water mains to Blue Valley Lab. 6-20-24 DP. The second sample from the 6" main passed and can now be put in service. The second sample of the 8" passed making it the first passing sample of the 8". Still need 1 more passing sample before the 8" can be put into service. 6-20-24 DP. I took the 3rd sample to Blue Valley Lab today for the 8" water main. 6-21-24 DP. 3rd sample on 8" passed.
Water Line - Coliform Test 1 Passed 07/02/2024
Misc
Informational
06/20/2024
6-18-24 DP. Took first sample on 8" and 6" to Blue Valley Lab. 6-19-24 DP. Fist sample on the 6" fire line passed. First sample on the 8" line failed TC+
Documents & Images
Date Uploaded File Type Document Name
12/08/2023 Plans Streets of W Pryor Lot 13 SANITARY 11-29-23
12/10/2023 Plans Streets of W Pryor Lot 13 PERMIT 12-8-23
10/25/2023 Application Form Lot 13 FDP Ownership Affidavit
01/03/2024 Letter SUBD Comment Letter
01/04/2024 Engineer Report/Study Lot 7c thru 14 SWPPP
01/04/2024 Engineers Estimate Lot 13A Public Sanitary Cost Estimate 1-4-24_xls
01/04/2024 Letter Responses to SUBD Comment Letter dated 1-3-24
01/04/2024 Plans Streets of W Pryor Lot 13 SANITARY 1-3-24
01/05/2024 Activity Document PRSUBD20236555 Streets of West Pryor Lot 11 30 HOP & Lot 13 Waterway Sanitary CV Fee Worksheet FY24
01/05/2024 Letter SUBD Comment Letter
01/31/2024 Receipt Receipt for transaction:2024-000523
02/05/2024 Certificate/License Business License Certificate_Prosser Wilbert
02/08/2024 Approved Plans Streets of W Pryor Lot 13 SANITARY_approved plans_2.8.2024
02/08/2024 Letter Eng approval letter_SOWP Lot 13
03/04/2024 Letter INSPECTION SUMMARY
03/04/2024 Letter INSPECTION SUMMARY
03/04/2024 Letter INSPECTION SUMMARY
04/08/2024 Letter INSPECTION SUMMARY
04/08/2024 Letter INSPECTION SUMMARY
04/11/2024 Letter INSPECTION SUMMARY
04/12/2024 Letter INSPECTION SUMMARY
04/16/2024 Letter INSPECTION SUMMARY
04/18/2024 Letter INSPECTION SUMMARY
04/18/2024 Letter INSPECTION SUMMARY
04/23/2024 Letter INSPECTION SUMMARY
04/23/2024 Letter INSPECTION SUMMARY
04/24/2024 Letter INSPECTION SUMMARY
04/25/2024 Letter INSPECTION SUMMARY
04/25/2024 Letter INSPECTION SUMMARY
04/30/2024 Letter INSPECTION SUMMARY
05/02/2024 Letter INSPECTION SUMMARY
05/03/2024 Letter INSPECTION SUMMARY
05/06/2024 Letter INSPECTION SUMMARY
05/08/2024 Letter INSPECTION SUMMARY
05/14/2024 Letter INSPECTION SUMMARY
05/15/2024 Letter INSPECTION SUMMARY
05/15/2024 Letter INSPECTION SUMMARY
05/15/2024 Letter INSPECTION SUMMARY
05/15/2024 Letter INSPECTION SUMMARY
05/17/2024 Letter INSPECTION SUMMARY
05/21/2024 Letter INSPECTION SUMMARY
05/21/2024 Letter INSPECTION SUMMARY
05/21/2024 Letter INSPECTION SUMMARY
05/21/2024 Letter INSPECTION SUMMARY
05/29/2024 Letter INSPECTION SUMMARY
05/31/2024 Letter INSPECTION SUMMARY
05/31/2024 Letter INSPECTION SUMMARY
05/31/2024 Letter INSPECTION SUMMARY
05/31/2024 Letter INSPECTION SUMMARY
05/31/2024 Letter INSPECTION SUMMARY
06/06/2024 Letter INSPECTION SUMMARY
06/06/2024 Letter INSPECTION SUMMARY
06/06/2024 Letter INSPECTION SUMMARY
06/06/2024 Letter INSPECTION SUMMARY
06/06/2024 Letter INSPECTION SUMMARY
06/07/2024 Letter DE-Certificate of Substantial Completion Single Lot
06/07/2024 Letter DE-Punch List
06/10/2024 Letter INSPECTION SUMMARY
06/11/2024 Letter INSPECTION SUMMARY
06/14/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/18/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/20/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
06/25/2024 Letter INSPECTION SUMMARY
06/27/2024 Bond
07/02/2024 Letter INSPECTION SUMMARY
08/23/2024 Streets of W Pryor Lot 13 SANITARY 8-23-24 As Built
08/30/2024 PRSUBD20236555 Streets of W Pryor Lot 13 SANITARY 8-23-24 As Built Accepted
09/09/2024 Final Affidavit and Agreement 2
09/10/2024 Letter DE-Certificate of Final Acceptance (Commercial)
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home