Summary


PRSITE20193330
Development - Site
Final Acceptance
Hannah Reese
DEVELOPMENT COMPLETE
FULL SITE DEVELOPMENT
11/12/2019
12/20/2019
01/26/2021
Locations
Contacts
Hannah Reese, Address:704 SE Oldham Ct  
CENTRIC CONSTRUCTION GROUP, Address:520 W PENNWAY STE 100, Phone:(816) 389-8300  
  
Reviews
Review Type Outcome Est. Completion Date Completed
Licensed Contractors Approved 11/12/2019 12/18/2019
Joe Frogge
Fees
Paid Fees Amount Paid Owing Date Paid
Right of Way Permit Fee $80.00 $80.00 Paid 12/18/2019
Sanitary Sewer Insp Fees $271.50 $271.50 Paid 12/18/2019
Water Insp Fee $667.50 $667.50 Paid 12/18/2019
Water Test Fee $400.00 $400.00 Paid 12/18/2019
Storm Sewer Inspection Fee $2,727.87 $2,727.87 Paid 12/18/2019
Paved Surface Inspection Fee $5,932.40 $5,932.40 Paid 12/18/2019
$5,932.38
Site Grading Fee $717.54 $717.54 Paid 12/18/2019
Water Tap Fee $23,180.00 $23,180.00 Paid 12/18/2019
Water Meter Fee $2,457.66 $2,457.66 Paid 12/18/2019
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Storm - Material Verification Partial 03/04/2020
Misc
Informational
03/04/2020
Storm - Material Verification all materials on site appear to meet Lee’s Summit specifications. 3/4/20
Storm Sewer Construction Inspection Partial 03/04/2020
Misc
Informational
03/04/2020
On 3/3/20 began installation of Storm Tech Underground Detention located on Lot #3 & Storm Box 2C. Picture will be add to inspection as project continues. See ADS Storm Tech Detention Plans sheet 3 of 6 & Storm Box 2C.
Storm Sewer Construction Inspection Partial 03/25/2020
Misc
Informational
03/04/2020
On 3/3/20 began installation of Storm Tech Underground Detention located on Lot #3 & Storm Box 2C. Picture will be add to inspection as project continues. See ADS Storm Tech Detention Plans sheet 3 of 6 & Storm Box 2C.
Misc
Informational
03/25/2020
3/24/20 Contractor began excavation for Storm Tech Underground Detention on Lot #2.
Misc
Informational
03/31/2020
Tom Taylor was given project as the presiding field inspector on 3-24-2020. Contractor began installing Storm Tech Detention Structure. Dirt excavation began.
Misc
Informational
03/31/2020
On 3-25-2020 contractor did not work because of on favorable weather. Rained, to wet to work.
Misc
Informational
03/31/2020
Contractor resumed installation of the Storm Tech Detention Structure. Water was pumped from location before rock and detention cells where placed and then covered with gravel. Contractor was showed that the plans I had showed 106.4LF of 8” HDPE would need to be installed to STR. 2C. This did not show on there specification plans.
Sanitary Sewer Construction Inspection Passed 04/09/2020
Misc
Informational
01/10/2020
DECEMBER 26, 2019 Crews were onsite installing Sanitary Sewer. Crews installed 4” schedule 40 . Cleanouts also were installed and verified by inspector. All pipe installed per plans. Crews were to install more gravel and back fill later in the day.
Miscellaneous Correction
Informational
04/07/2020
On Tuesday, 4-07-2020, Contractor completed 4”Sanitary Sewer tap to main and completed necessary building connection and back filled new service connection.
Misc
Informational
04/09/2020
On Thursday 4-09-2020. Rieke excavating preformed a vacuum test on the Sanitary Sewer. Sewer held air pressure for 20 minutes only losing 1 pound of air pressure. Contractor was told he needed to have on site with the machine a up dated cal. Sticker/tag date for the meter apparatus in the future. Vacuum test passed.
Storm Sewer Construction Inspection Passed 05/26/2020
Misc
Informational
03/25/2020
On 3/3/20 began installation of Storm Tech Underground Detention located on Lot #3 & Storm Box 2C. Picture will be add to inspection as project continues. See ADS Storm Tech Detention Plans sheet 3 of 6 & Storm Box 2C.
Misc
Informational
03/25/2020
3/24/20 Contractor began excavation for Storm Tech Underground Detention on Lot #2. Contractor began installation of 1A Storm 5X6 Baffle Curb Inlet. 9See detail on sheet 6 of 14.
Misc
Informational
03/26/2020
On 3-26-2020, I inspected the installation of ADS Storm Detention Structure located on the west side of the Aristocrat Motors building. Emergency Overflow box # 1A is located in this Detention Structure. Fill rock is being placed over the detention cells and if time allows fill dirt will be placed over the rock. Rieke Excavation is preforming the installation.
Misc
Partial Correction
03/26/2020
On 3-27-2020, Contractor found that rain the night before had caused the bank on the west side of the Detention structure to collapse onto the westerly detention ceil. Care had to be taken to remove fill dirt off of the cell and new filter fabric had to be place before rock and dirt fill could resume. Approximately 5ft. Of water had to be pump from the basin floor. Approximately 80 linear feet of rock fill was completed today with additional rain expected tonite. Rieke Excavation completed the work on site.
Misc
Informational
03/31/2020
On Monday 3-30-2020 I inspected the installation of the end sections to the ADS Storm Tech Detention Structure as it connects to the STR. #2 CI. All fabric and gravel where placed and dirt fill was started. Contractor was told that I am requesting soil density test for the sub-grade on tomorrow.
Misc
Informational
03/31/2020
On Monday 3-30-2020 I inspected the installation of the end sections to the ADS Storm Tech Detention Structure as it connects to the STR. #2 CI. All fabric and gravel where placed and dirt fill was started. Contractor was told that I am requesting soil density test for the sub-grade on tomorrow.
Misc
Informational
03/31/2020
On Tuesday 3-31-2020 contractor completed 90% of the dirt fill over the Detention Structure.
Misc
Informational
03/31/2020
Contractor also poured invert for 5’x3’ inlet STR. 2A
Miscellaneous Correction
Corrective Action Required
03/31/2020
Misc
Informational
04/02/2020
On Wednesday 4-02-2020 Contractor installed field inlets #1D, #1C, and #1B of the Storm Sewer System and laid 252.9 LF. Of 24” HDPE pipe between the (2) structures.
Misc
Informational
04/03/2020
On Thursday, 4-02-2020 contractor installed 86 LF of24” HDPE pipe between Str. #1B and Str. #1A and grouted all dog houses then back filled all pipe. Also completed grading at skate rink area.
Misc
Informational
04/06/2020
On Monday 4-06-2019 Reikie Grading installed 106LF of HDPE pipe coming from the Aristocrat Motors to Str. 1A and backfilled. Contractor also poured inverts for Str. 1A to 1D.
Miscellaneous Correction
Corrective Action Required
04/06/2020
Curb - Proof Roll Partial 06/01/2020
Misc
Informational
04/16/2020
On Thursday, 4-16-2020. Rieke Excavation completed proof rolling of the curb cuts at the entrance of Aristrocrats and The skate rink. Inspection passed inspection
Misc
Informational
06/01/2020
On Monday, 6-01-2019. A proof roll for the parking lot was completed and there where areas that were questionable. These areas will be rolled again and may need further treatment (shot rock) before approved for grid and AB3 sub-base.
Grading/Excavation/Fill Inspection Partial 06/03/2020
Misc
Informational
04/07/2020
On Tuesday, 4-07-2020. The contractor Rieke Grading back filled around Str. 1A.
Misc
Informational
04/14/2020
On Monday, 4-13-2020. The contractor completed parking lot grading at the front entrance of the project. Survey stakes were installed for the curb. Sawing was completed at front entrance for curb installation off of the off road of Hwy. 291
Misc
Informational
04/16/2020
On Thursday,4-16-2020. Rieke Excavation worked grading in front of the Land Mart Skate Rink.
Misc
Informational
06/03/2020
On Wednesday, 6-03-2020. The contractor began placement of the geo grid in the front parking lot. Placement of AB3 began.
Misc
Informational
06/22/2020
On Monday, 6-22-2020. Contractor Rieke Excavators completed grading and island backfill in front parking lot entrance
Misc
Informational
06/23/2020
On Tuesday, 6-23-2020. Rieke Excavating is performing dirt backfilling at front entrance of the property both sides of the street.
Misc
Informational
07/13/2020
On Monday 7-13-2020. Throne and Son Asphalt Paving complete sub-grade rock fill and compact AB3 for placement of Base lift of asphalt.
Curb - Proof Roll Passed 07/06/2020
Misc
Informational
06/01/2020
On Thursday, 4-16-2020. Rieke Excavation completed proof rolling of the curb cuts at the entrance of Aristrocrats and The skate rink. Inspection passed inspection
Misc
Informational
06/01/2020
On Monday, 6-01-2019. A proof roll for the parking lot was completed and there where areas that were questionable. These areas will be rolled again and may need further treatment (shot rock) before approved for grid and AB3 sub-base.
Misc
Corrective Action Required
06/03/2020
On Wednesday, 6-03-2020. A curb form inspection was completed and we determined the west side curb at the entrance was only 4” thick and should be 6”. The contractor was notified and inspection failed for the west side of the entrance.
Misc
Corrective Action Required
06/08/2020
Curb proof roll failed today. Monday 6-08-2020. Contractor did not have enough AB3 base placed or compacted.
Misc
Informational
06/08/2020
On Monday 6-08-2020. The contractor poured approx. 300 LF of CG-1 curb at entrance of project.
Misc
Resolved
06/10/2020
On 6-08-2020. The proof roll that failed due to not enough AB3 placement was corrected on Tuesday, 6-09-2020. AB3 was placed and compacted. Testing passed for easterly parking lot only.
Misc
Resolved
06/10/2020
On 6-08-2020, the sub grade at the entrance (west side) failed due to curb gutter not having the proper thickness. Contractor dug out sub grade and was able to pour curbing
Misc
Informational
06/10/2020
On Wednesday 6-10-2020, Bed Rock Concrete formed and poured inland curbing for the easterly parking lot. Sub grade and forms passed
Misc
Informational
06/12/2020
On Thursday 6-11-2020. Aristocrat Motor contractor Bed Rock concrete poured full depth patch in front entrance on east and west sides of street. They also formed approx. 40 LF of CG-1 curbing in front parking lot.
Misc
Informational
06/19/2020
On Thursday, 6-18-2020. BedRock concrete formed, graded and poured approx. 250 LF of CG-1 curb located at the front parking lot at the entrance of the Aristocrat Motors. Contractor also formed and poured (5) car pads located at the entrance in front of the landmark skate. And poured the trash dumpster post footing in the back parking lot.
Misc
Informational
07/06/2020
On Monday, 7-06-2020. Thorne and sons completed curb proof roll for the curb in the back and west side of the parking lot. Proof roll passed for curb placement.
Water Line - Construction Inspection Partial 07/06/2020
Misc
Informational
07/06/2020
On Monday, 7-06-2020. While trucking in AB3 one of the trucks hit the fire hydrant and broke it. Contractor will need to replace hydrant.
Pavement-Curb Construction Passed 07/13/2020
Misc
Informational
07/08/2020
On Wednesday, 7-08-2020. Bed Rock Concrete formed and poured approx. 500 LF of CG-1 curb for parking lot.
Misc
Informational
07/13/2020
On Thursday, 7-09-2020. Bed Rock Concrete formed and poured approx. 250 LF of CG-1 and CS curb through out project at various locations.
Misc
Informational
07/13/2020
On Friday, 7-10-2020. Bed Rock Concrete formed and poured tie-in sections of curb through out project.
Sidewalk Inspection Passed 07/23/2020
Misc
Informational
07/23/2020
On Thursday, 7-23-2020. Bed Rock Concrete formed and poured 4” sidewalk under the canopy of the building. Approx. 1,000 sf of walk was poured.
Misc
Informational
07/25/2020
On Saturday, 7-25-2020 Bed Rock Concrete formed and poured concrete sidewalk in frt. of building adjacent curbing and are pouring curb island in back corner of building next to fire hydrant. Contractor also formed and poured 12’X 30’ trash pad.
Pavement-Surface Partial 07/25/2020
Misc
Informational
07/25/2020
On Tuesday, 7-21-2020. Thorne and son paved 1 st lift of base asphalt at front parking lot. Rain came early morning stoping all construction. Project shut down. Approx. 300 Tons were laid.
Misc
Informational
07/25/2020
On Friday, 7-24-2020. Thorne & Son Asphalt resumed base asphalt installation on front parking lot. Laid all of lot, approx. 500 tons.
Sidewalk Inspection Passed 09/01/2020
Misc
Informational
09/01/2020
Bed Rock Concrete poured 4” sidewalk up close to the building on Saturday, 7-25-2020
Misc
Informational
09/01/2020
On Monday, 8-10-2020. Bed Rock Concrete poured 135LF of 4” sidewalk out in the front entrance of the building.
Site Visit Partial 09/01/2020
Street - Wedge Lift Passed 09/15/2020
Misc
Informational
09/15/2020
On Friday 9-11-2020. Throne and Sons Asphalt completed asphalt patching for CG-1 curbing at entrance of project and also completed asphalt punchlist for temp. Occupies. They completed the parking lot repairs where there was ponding as well.
ESC - (Vegetation/Ground Cover) Passed 09/21/2020
Misc
Informational
09/21/2020
On Thursday 9-17-2020 the contractor completed sodding and installed ground cover for the completion landscaping for the project.
Install Street and Stop Signs Passed 09/21/2020
Misc
Informational
09/21/2020
All signage has been installed throughout project.
Sewer Service Inspection Passed 01/26/2021
Sewer Service Inspection Passed 01/26/2021
Misc
Informational
01/26/2021
Connction passed.
Documents & Images
Date Uploaded File Type Document Name
12/18/2019 Receipt Receipt for transaction: 2019-007753
12/19/2019 Letter DE-Permit
01/10/2020 Aristocrat Motors
01/10/2020 Sanitary Sewer and Cleanouts
01/10/2020 Sanitary Sewer and Cleanouts0
03/04/2020 Letter INSPECTION SUMMARY
03/04/2020 Letter INSPECTION SUMMARY
03/04/2020 20 # 1
03/04/2020 20 # 2
03/04/2020 20 # 3
03/04/2020 20 # 4
03/25/2020 Letter INSPECTION SUMMARY
03/25/2020 Letter INSPECTION SUMMARY
03/25/2020 Letter INSPECTION SUMMARY
04/09/2020 Letter INSPECTION SUMMARY
08/19/2020 approved 8.19.20 aristocrat FDP-GradingPlan-Detail-REVISION-20200731
08/17/2020 approved 8.17.20 BOL-RF-24-4_5_1_1
08/17/2020 approved 8.17.20 Resized_20200817_151655
09/16/2020 Letter DE-Punch List
09/16/2020 Letter DE-Certificate of Substantial Completion Multiple Lot
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
12/03/2020 Letter INSPECTION SUMMARY
01/26/2021 Letter DE-Daily Inspection Summary
01/26/2021 Letter DE-Certificate of Final Acceptance (Commercial)
01/26/2021 Letter INSPECTION SUMMARY
01/26/2021 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home