Permit Application Status

PRRES20250106


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20250106
Building Permit - Residential
Issued
BELLAH HOMES LLC
NEW SINGLE FAMILY
NEW HOUSE. FINISHED/UNFINISHED BASEMENT. WALKOUT BASEMENT. COVERED DECK. SUSPENDED STOOP.
01/09/2025
01/31/2025
07/21/2025
Locations
Contacts
BELLAH HOMES LLC, Address:P O BOX 346, Phone:(816) 697-2870  
BELLAH HOMES LLC, Address:PO BOX 346  
Paul Miller, Address:P.O. Box 346, Phone:(816) 786-5050  
AFC HEATING AND COOLING, Address:824 NW MAIN ST , Phone:(816) 347-8388  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
TRI-COUNTY PLUMBING LLC, Address:PO BOX 234, Phone:(816) 720-3222  
PAUL@BELLAHHOMES.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
Right of Way Permit Fee $85.00 $85.00 Paid 01/31/2025
Residential Excise Tax Fee $1,022.72 $1,022.72 Paid 01/31/2025
Sanitary Sewer Development Fee $2,285.00 $2,285.00 Paid 01/31/2025
Valuation Fee New Single Family $2,186.19 $2,186.19 Paid 01/31/2025
Outstanding Fees Amount Paid Owing Date Paid
Not Ready Inspection Fee $75.00 $0.00 $75.00 Not Paid


$75.00    Add Fees to My Cart
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Plot Plan Inspection Pending
Occupancy Inspection - Codes Residential Pending
Driveway Inspection Pending
Misc
Informational
05/13/2025
5-13-25 NS Site visited and it appears that driveway and sidewalk have not been put in and will not be ready for a while.
Sidewalk Inspection Pending
Misc
Informational
07/08/2025
5-13-25 NS Site visited, and it appears sidewalk has not yet started. 7-7-25 NS site visited for a sidewalk inspection and it appears that crew had to tear out ADA ramp that was placed incorrectly by developer. After the new ada ramp they will do sidewalk and driveway
Erosion Control Inspection Residential Pending
DCM5 ESC INSP DENIED
Corrective Action Required
08/29/2025
Erosion control is in compliance
Misc
Corrective Action Required
08/29/2025
Cut down overgrown vegetation to city code requirement
Erosion Control Inspection Residential Failed 4/14/2025 04/14/2025
DCM5 ESC INSP DENIED
Corrective Action Required
04/14/2025
REQUESTED INSPECTION(S) DENIED DUE TO DEFICIENT EROSION CONTROL INSTALLATION. PROVIDE EROSION CONTROL AROUND DISTURBED AREA ON THE DOWNWARD SLOPE SIDE
Underslab Plumbing Inspection - Residential Not Ready 4/14/2025 4/14/2025 04/14/2025
Misc
Corrective Action Required
04/14/2025
Not ready for inspection. Inspection denied due to no erosion control
Erosion Control Inspection Residential Partial 4/21/2025 04/21/2025
DCM5 ESC INSP DENIED
Corrective Action Required
04/14/2025
Erosion control is in compliance
Underslab Plumbing Inspection - Residential Passed 4/21/2025 4/21/2025 04/21/2025
Misc
Resolved
04/21/2025
Not ready for inspection. Inspection denied due to no erosion control
Sewer Service Inspection - R Passed 5/7/2025 5/7/2025 05/07/2025
Driveway Inspection Partial 5/14/2025 05/13/2025
Misc
Informational
05/13/2025
5-13-25 NS Site visited and it appears that driveway and sidewalk have not been put in and will not be ready for a while.
Sidewalk Inspection Partial 5/14/2025 05/13/2025
Misc
Informational
05/13/2025
5-13-25 NS Site visited, and it appears sidewalk has not yet started.
Footing Inspection - Residential Passed 06/06/2025
Informational
06/06/2025
Footing approved by engineer
All Rough Inspection - Residential Failed 6/6/2025 06/06/2025
Misc
Corrective Action Required
06/06/2025
Garage portal framing only-OK
Piers/Caissons Inspection - Residential Passed 6/17/2025 6/17/2025 06/17/2025
Sidewalk Inspection Partial 7/8/2025 7/8/2025 07/08/2025
Misc
Informational
05/13/2025
5-13-25 NS Site visited, and it appears sidewalk has not yet started. 7-7-25 NS site visited for a sidewalk inspection and it appears that crew had to tear out ADA ramp that was placed incorrectly by developer. After the new ada ramp they will do sidewalk and driveway
Gas Service Inspection - Residential Passed 8/19/2025 08/19/2025
Erosion Control Inspection Residential Partial 8/19/2025 08/19/2025
DCM5 ESC INSP DENIED
Corrective Action Required
04/21/2025
Erosion control is in compliance
Electrical Service Inspection Failed 8/19/2025 08/19/2025
Misc
Corrective Action Required
08/19/2025
-Bond the service panel enclosure -Flip the lower half of grounding clamp for tight connection to rebar
All Rough Inspection - Residential Failed 8/19/2025 8/19/2025 08/19/2025
Misc
Corrective Action Required
06/06/2025
-Nail siding to sill plates and stud along edge @ 6” oc -Provide security blocking at side garage door per security code -Install tension straps at garage PFH walls -Secure nail plate to wall sole plate at half bathroom -Brace roof beams against rotation -Tie down rafters to wall top plate -Protect wiring adjacent&below left window of master bedroom -Fb pantry/kitchen double stud wall space from roof -Provide purlin support for rafters above stair -Seal off return air space from shower pan at bedroom 2 -Provide a receptacle at foyer guardrail wall space -Provide full stud support for LVL beam at foyer/hallway angled wall -Securely fasten NM cable above Rec area per code -Fb gap at top of the vertical fire blocking -Protect plumbing at basement half bathroom -Anchor basement sill plates within 12” of breaks -Install hangers in basement where required -Provide 3 king studs at basement slide door beam per plan -Toe nail joists to top plates -Provide 5-stud support for I beam at bedroom 3; 3-stud support for I beam at shower exterior wall -Provide engineer splice detail for the W 14”X74# I beam -Connect duct to bed 4 bathroom fan **DO NOT INSULATE
Erosion Control Inspection Residential Failed 8/25/2025 8/25/2025 08/25/2025
DCM5 ESC INSP DENIED
Corrective Action Required
08/19/2025
Erosion control is in compliance
Misc
Corrective Action Required
08/25/2025
Cut down overgrown vegetation to city code requirement
All Rough Inspection - Residential Failed 8/25/2025 8/25/2025 08/25/2025
Misc
Corrective Action Required
08/19/2025
-Nail siding to sill plates and stud along edge @ 6” oc **Nail to studs along edge @6” oc -Provide security blocking at side garage door per security code **block at strike plate height, 3 stud spaces out -Secure nail plate to wall sole plate at half bathroom -Brace roof beams against rotation -Fb pantry/kitchen double stud wall space from roof **Seal gap and penetrations -Seal off return air space from shower pan at bedroom 2 **Seal gap -Provide full stud support for LVL beam at foyer/hallway angled wall **Complete electrical to receptacle -Securely fasten NM cable above basement Rec area per code -Fb gap at top of the vertical fire blocking in basement -Install hangers in basement where required **Install hanger at lvl beam connection near the big I beam -Provide 3 king studs at basement slide door beam per plan **Complete electrical -Toe nail joists to top plates **4-8d or 3-10d. Toe nail joists into top plates -Provide 5-stud support for I beam at bedroom **Complete electrical; protect wiring where within 1.25” of stud surface -Provide engineer splice detail for the W 14”X74# I beam **First, the I beam splice is not per 6/S3.4 per email from engineer. Second, engineer did not specify where the splice is supposed to be located. The currently installed splice is located near the I beam column support **DO NOT INSULATE
Electrical Service Inspection Failed 8/25/2025 08/25/2025
Misc
Corrective Action Required
08/19/2025
-Bond the service panel enclosure -Flip the lower half of grounding clamp for tight connection to rebar
All Rough Inspection - Residential Failed 8/27/2025 8/27/2025 08/27/2025
Misc
Corrective Action Required
08/25/2025
-Nail siding to sill plates and stud along edge @ 6” oc **Nail along vertical edge of siding panel to studs @6” oc, not 8” or 12” -Brace roof beams against rotation **Brace the (2)2x12 roof beam above the master closet **OK TO INSULATE
Electrical Service Inspection Failed 8/27/2025 08/27/2025
Misc
Corrective Action Required
08/25/2025
-Bond the service panel enclosure -Flip the lower half of grounding clamp for tight connection to rebar
Electrical Service Inspection Passed 8/29/2025 08/29/2025
Misc
Resolved
08/29/2025
-Bond the service panel enclosure -Flip the lower half of grounding clamp for tight connection to rebar
All Rough Inspection - Residential Passed 8/29/2025 8/29/2025 08/29/2025
Misc
Resolved
08/29/2025
-Nail siding to sill plates and stud along edge @ 6” oc **Nail along vertical edge of siding panel to studs @6” oc, not 8” or 12” -Brace roof beams against rotation **Brace the (2)2x12 roof beam above the master closet **OK TO INSULATE
Erosion Control Inspection Residential Failed 8/29/2025 08/29/2025
DCM5 ESC INSP DENIED
Corrective Action Required
08/25/2025
Erosion control is in compliance
Misc
Corrective Action Required
08/25/2025
Cut down overgrown vegetation to city code requirement
Documents & Images
Date Uploaded File Type Document Name
01/09/2025 Lot 28 Tax Application
01/14/2025 Permit Codes Residential Plan Review
01/16/2025 Application Form PERMIT APPLICATION
01/22/2025 Approved Plans APPROVED PLANS
01/22/2025 Permit Codes Residential Plan Review
01/28/2025 Plot Plan APPROVED PLOT PLAN
01/28/2025 Permit Codes Residential Plan Review
01/31/2025 Permit DS Building Permit
01/31/2025 Receipt Receipt for transaction: 2025-000650
03/14/2025 Approved Plans 3-14-25 APPROVED PLOT PLAN
03/14/2025 Approved Plans 3-14-25 APPROVED PLANS
03/28/2025 3RD Party Insp Report M L Crose 1817 NE Lashbrook Cir LSMO 3rd Party Footing Inspection Report Pg 1 3-28-25
03/28/2025 3RD Party Insp Report M L Crose 1817 NE Lashbrook Cir LSMO 3rd Party Footing Inspection Report Pg 2 3-28-25
04/14/2025 Letter INSPECTION SUMMARY
04/14/2025 Letter INSPECTION SUMMARY
04/21/2025 Letter INSPECTION SUMMARY
04/21/2025 Letter INSPECTION SUMMARY
05/07/2025 Letter INSPECTION SUMMARY
05/13/2025 Letter INSPECTION SUMMARY
05/13/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/06/2025 Letter INSPECTION SUMMARY
06/17/2025 Letter INSPECTION SUMMARY
07/08/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/19/2025 Letter INSPECTION SUMMARY
08/22/2025 Email 1817 NE Lashbrook Cir All rough Inspection
08/25/2025 Letter INSPECTION SUMMARY
08/25/2025 Letter INSPECTION SUMMARY
08/25/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
08/27/2025 Letter INSPECTION SUMMARY
08/29/2025 Letter INSPECTION SUMMARY
08/29/2025 Letter INSPECTION SUMMARY
08/29/2025 Letter INSPECTION SUMMARY
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home