Summary
PRRES20215472
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED PATIO STOP WORK ORDER generated on 03/24/2022 12:00 AM by username 'Mitchell Schwarz'. STOP WORK ORDER removed on 04/26/2022 12:00 AM by username 'Mitchell Schwarz'.
10/19/2021
10/27/2021
04/24/2022
04/28/2023
Locations
Contacts
SAB CONSTRUCTION INC, Address:PO BOX 942, Phone:(816) 524-3855  
Curtis Tate, Address:PO box 942   
TEAGUE ELECTRIC CONSTRUCTION INC, Address:12425 W 92ND ST, Phone:(913) 529-4600  
MIKE BRYANT HEATING & COOLING , Address:1711 E 123RD , Phone:(913) 441-7807  
GARRISON PLUMBING, Address:15430 S MAHAFFIE ST STE 102, Phone:(913) 768-1311  
CURTIS@SABHOMES.COM  
Zack Bryant, Address:200 NW Commerce Court  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
8331507-Sewer Connection Fee $480.00 $480.00 Paid 10/27/2021
9110073-Right of Way Permit Fee $85.00 $85.00 Paid 10/27/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 10/27/2021
9110078-Valuation Fee New Single Family $1,335.87 $1,335.87 Paid 10/27/2021
8331401-Water Tap Fee $3,655.00 $3,655.00 Paid 10/27/2021
8350015-Water Meter Fee $479.24 $479.24 Paid 10/27/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 09/02/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 11/24/2021 11/24/2021
Misc
Corrective Action Required
11/24/2021
Ufer above sump pump as stated in 3rd party inspection
Sewer Service Inspection - R Passed 11/29/2021 (1:00) 11/29/2021 11/29/2021
Water Service Inspection - R Passed 12/1/2021 (10:30) 12/1/2021 12/01/2021
Underslab Plumbing Inspection - Residential Failed 12/7/2021 12/7/2021 12/07/2021
Misc
Corrective Action Required
12/07/2021
Provide proper venting for basement bathroom see code section P3108.2.1 Horizontal wet vent
Underslab Plumbing Inspection - Residential Passed 12/10/2021 12/10/2021 12/10/2021
Misc
Resolved
12/10/2021
Provide proper venting for basement bathroom see code section P3108.2.1 Horizontal wet vent
Piers/Caissons Inspection - Residential Passed 12/20/2021 (9:00) 12/20/2021 12/20/2021
Erosion Control Inspection Residential Failed 3/15/2022 03/15/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
03/15/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Address erosion control around lot, back of lot has no erosion control
Erosion Control Inspection Residential Failed - Stop Work 3/24/2022 03/24/2022
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
03/15/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Address erosion control around lot, back of lot has no erosion control Still not in compliance stop work issued
Electrical Service Inspection Failed 4/14/2022 4/14/2022 04/14/2022
Misc
Corrective Action Required
04/14/2022
ufer ground needs to be connected to middle grounded bus bar
Gas Service Inspection - Residential Failed 4/14/2022 4/14/2022 04/14/2022
Misc
Corrective Action Required
04/14/2022
bond gas line
All Rough Inspection - Residential Failed 4/14/2022 4/14/2022 04/14/2022
Misc
Corrective Action Required
04/14/2022
-PFH nailing and strapping to be to plans /code -PFH sheathing breaks to be to plans and code -provide attic access above single car garage -anchor bolt within 12” of sill plate break in garage -fireblock ceiling line of hvac chase. -midway strap all dwv in stud space 2” in diameter or less -dbl lvl above owners entry to extend to stair wall per plans and be supported by 3 stud pac -3 studs under lvl per plans basement stairwell entry address plans call for stl beam -complete electrical at fire place -secure gas line at fireplace -complete electrical at fireplace -fireblock stud space into furr down at great room windows -install all doors -missing nails in hanger for lvls above kitchen -strap top plate where lapped weds than 24” dining room -protect pex and dwv at dining/pantry wall -address 2x6 wall at front entry not continuous -columns at front porch to plans -fire block bed 4 walls to ceiling space -seal top plate penetration in bed 4 -strap top plate lapped less than 24” at “Hollywood bath” -address roof supports landing on non load bearing wall bed 3 entry -stud shoe on dwv master bath W wall -seal top plate penetration right of master closet entry -address hip rafters over notched/cut throughout -ufer ground to connect to the middle grounded bus bar -protect service panel from dwv and pex above -bond gas line -plans call for 5 2x4 under steal beam at basement egress window -seal penetration under fireplace not being used -sold block above steel beam where accessible (some missing) -solid block under cantilever
Erosion Control Inspection Residential Partial 4/26/2022 04/26/2022
DCM3 ESC REQUIRED 2 DAY
Resolved
04/26/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Address erosion control around lot, back of lot has no erosion control Still not in compliance stop work issued
Misc
Informational
04/26/2022
erosion control in compliance at time of inspection Mitchell Schwarz 04/26/2022 7:52 AM
Gas Service Inspection - Residential Passed 4/27/2022 4/27/2022 04/27/2022
Misc
Resolved
04/27/2022
bond gas line
Electrical Service Inspection Passed 4/27/2022 4/27/2022 04/27/2022
Misc
Resolved
04/27/2022
ufer ground needs to be connected to middle grounded bus bar
All Rough Inspection - Residential Failed 4/27/2022 4/27/2022 04/27/2022
Misc
Corrective Action Required
04/14/2022
-PFH sheathing breaks to be to plans and code -anchor bolt within 12” of sill plate break in garage -fireblock ceiling line of hvac chase. -midway strap all dwv in stud space 2” in diameter or less -dbl lvl above owners entry to extend to stair wall per plans and be supported by 3 stud pac -3 studs under lvl per plans basement stairwell entry address plans call for stl beam -fire block bed 4 walls to ceiling space -seal top plate penetration in bed 4 -strap top plate lapped less than 24” at “Hollywood bath” -seal top plate penetration right of master closet entry -address hip rafters over notched/cut throughout -ufer ground to connect to the middle grounded bus bar -protect service panel from dwv and pex above -seal penetration under fireplace not being used -sold block above steel beam where accessible (some missing) -solid block under cantilever
All Rough Inspection - Residential Failed 5/5/2022 5/5/2022 05/05/2022
Misc
Corrective Action Required
04/27/2022
Provide access to front stoop or open garage for inspection -fireblock ceiling line of hvac chase. -3 studs under lvl per plans basement stairwell entry address plans call for stl beam -fire block bed 4 walls to ceiling space -seal top plate penetration in bed 4 -seal top plate penetration right of master closet entry -address hip rafters over notched/cut throughout -ufer ground to connect to the middle grounded bus bar -protect service panel from dwv and pex above -seal penetration under fireplace not being used -sold block above steel beam where accessible (some missing)
All Rough Inspection - Residential Not Ready 5/10/2022 5/10/2022 05/10/2022
Misc
Corrective Action Required
05/05/2022
Provide access to front stoop or open garage for inspection -3 studs under lvl per plans basement stairwell entry address plans call for stl beam -fire block bed 4 walls to ceiling space -seal top plate penetration in bed 4 -address hip rafters over notched/cut throughout -protect service panel from dwv and pex above -sold block above steel beam where accessible (some missing)
All Rough Inspection - Residential Failed 5/12/2022 5/12/2022 05/12/2022
Misc
Corrective Action Required
05/10/2022
-3 studs under lvl per plans basement stairwell entry address plans call for stl beam *okay to insulate *
All Rough Inspection - Residential Passed 5/17/2022 5/17/2022 05/17/2022
Misc
Resolved
05/17/2022
-3 studs under lvl per plans basement stairwell entry address plans call for stl beam *okay to insulate *
Driveway Inspection Partial 7/19/2022 7/19/2022 07/19/2022
Misc
Informational
07/19/2022
On 7.19.2022 i conducted a driveway inspection and pass the subgrade to pour concrete.
Sidewalk Inspection Partial 7/19/2022 7/19/2022 07/19/2022
Misc
Informational
07/19/2022
On 7.19.2022 i conducted a sidewalk inspection and pass the subgrade to pour concrete.
Driveway Inspection Passed 8/8/2022 08/08/2022
Misc
Informational
07/19/2022
On 7.19.2022 i conducted a driveway inspection and pass the subgrade to pour concrete. 8.8.2022 Driveway appears to be compliant
Sidewalk Inspection Passed 8/22/2022 08/08/2022
Misc
Informational
08/08/2022
Sidewalk appears to be in compliance
Erosion Control Inspection Residential Failed 10/26/2022 10/26/2022
Misc
Resolved
10/26/2022
erosion control in compliance at time of inspection Mitchell Schwarz 04/26/2022 7:52 AM
DCM3 ESC REQUIRED 2 DAY
Corrective Action Required
10/26/2022
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Mitchell Schwarz 10/26/2022 1:29 PM
Plot Plan Inspection Passed 04/13/2023
Occupancy Inspection - Codes Residential Failed 4/13/2023 4/13/2023 04/13/2023
Misc
Corrective Action Required
04/13/2023
-Bring water meter well lid to grade (ensure 14”-18” from meter lid to well lid -guard rail at front porch where more than 30” from ground 36” out -tamper caps at a/c compressor -properly support csst Above furnace -stairs between great room and dining room greater that 3/8 difference in rise
Erosion Control Inspection Residential Passed 04/28/2023
DCM3 ESC REQUIRED 2 DAY
Resolved
04/28/2023
EROSION CONTROL REQUIRED. EROSION CONTROL SHALL BE IN COMPLIANCE WITHIN TWO BUSINESS DAYS. Mitchell Schwarz 10/26/2022 1:29 PM
Occupancy Inspection - Codes Residential Full C of O 4/28/2023 4/28/2023 04/28/2023
Misc
Resolved
04/28/2023
-Bring water meter well lid to grade (ensure 14”-18” from meter lid to well lid -guard rail at front porch where more than 30” from ground 36” out -tamper caps at a/c compressor -properly support csst Above furnace -stairs between great room and dining room greater that 3/8 difference in rise
Documents & Images
Date Uploaded File Type Document Name
10/25/2021 hf02 rev_ permit app
10/25/2021 hf02 revised excise tax app
10/26/2021 Approved Plans approved plans
10/26/2021 Permit Codes Residential Plan Review
10/26/2021 Plot Plan APPROVED PLOT PLAN
10/27/2021 Permit Codes Residential Plan Review
10/27/2021 Permit DS Building Permit
10/27/2021 Receipt Receipt for transaction:2021-008315
11/23/2021 M L Crose 2034 SW Farm Field Ln LSMO Hook Farms Lot 2 SAB Permit 2021-5472 Foundation footing Inspection Report 11-4-21
11/24/2021 Letter INSPECTION SUMMARY
11/29/2021 Letter INSPECTION SUMMARY
12/01/2021 Letter INSPECTION SUMMARY
12/07/2021 Letter INSPECTION SUMMARY
12/10/2021 Letter INSPECTION SUMMARY
12/20/2021 Letter INSPECTION SUMMARY
03/15/2022 Letter INSPECTION SUMMARY
03/24/2022 Letter Stop Work Order
04/14/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/14/2022 Letter INSPECTION SUMMARY
04/20/2022 DW FRAMING ADDENDUM HF02 Redbud 2034 SW Farm Field Ln
04/26/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
04/27/2022 Letter INSPECTION SUMMARY
05/05/2022 Letter INSPECTION SUMMARY
05/10/2022 Letter INSPECTION SUMMARY
05/11/2022 DW FRAMING ADDENDUM HF02 Redbud 2034 SW Farmfield Ln 5-11-22
05/12/2022 Letter INSPECTION SUMMARY
05/17/2022 DW ENTRY HEADER LETTER HF02 Redbud 2034 SW Farmfield Ln 5-16-22
05/17/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
07/21/2022 Letter INSPECTION SUMMARY
09/02/2022 Receipt Receipt for transaction:2022-007226
10/26/2022 Letter INSPECTION SUMMARY
04/13/2023 Letter INSPECTION SUMMARY
04/13/2023 Letter INSPECTION SUMMARY
04/13/2023 Letter INSPECTION SUMMARY
04/13/2023 Letter INSPECTION SUMMARY
04/28/2023 Letter INSPECTION SUMMARY
04/28/2023 Letter Field Certificate of Occupancy
04/28/2023 Letter Codes Final Certificate of Occupancy
Upload Documents
  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:
Browse..





    Portal Home