Permit Application Status

PRRES20213182


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20213182
Building Permit - Residential
Certificate of Occupancy
CMH PARKS INC
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - COVERED DECK STOP WORK ORDER generated on 09/01/2021 12:00 AM by username 'Patrick Schonfeldt'. STOP WORK ORDER removed on 09/02/2021 12:00 AM by username 'Patrick Schonfeldt'.
06/21/2021
06/22/2021
12/19/2021
06/23/2022
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
CMH PARKS INC, Address:5000 CLAYTON RD  
Summit Homes, Address:120 SE 30th St, Phone:(816) 434-5074 Ext:320  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
AJ@SUMMITHOMESKC.COM  
Reviews

There are no reviews for this permit application.

Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,033.81 $1,033.81 Paid 06/22/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 06/22/2021
7232302-Residential Excise Tax Fee $1,077.12 $1,077.12 Paid 06/22/2021
8331504-EFHB Middle Big Creek, Full $435.24 $435.24 Paid 06/22/2021
8331507-Sewer Connection Fee $390.00 $390.00 Paid 06/22/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 06/22/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 06/22/2021
9110080-Not Ready Inspection Fee $50.00 $50.00 Paid 06/09/2022
9110080-3rd and Subsequent Inspection Fee (Per Hour) $100.00 $100.00 Paid 06/09/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Underslab Plumbing Inspection - Residential Failed 9/1/2021 9/1/2021 09/01/2021
Misc
Corrective Action Required
09/01/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION, ENGINEER REPORT REQUIRED TO BE SUBMITTED TO PERMIT WITHIN 48 HOURS OF INSPECTION
Footing Inspection - Residential Failed - Stop Work 9/1/2021 9/1/2021 09/01/2021
Misc
Corrective Action Required
09/01/2021
INSPECTION DENIED FOOTING POURED WITHOUT INSPECTION, ENGINEER REPORT REQUIRED TO BE SUBMITTED TO PERMIT WITHIN 48 HOURS OF INSPECTION
Footing Inspection - Residential Passed 9/2/2021 9/2/2021 09/02/2021
Misc
Informational
09/02/2021
APPROVED PER BRADLEY HUXOL 7/30/21
Underslab Plumbing Inspection - Residential Failed 9/3/2021 9/3/2021 09/03/2021
Misc
Corrective Action Required
09/01/2021
UNABLE TO PERFORM INSPECTION WITH MUD WATER COVERING DWV FROM RAIN, RESCHEDULE WHEN CONDITIONS ALLOW FOR INSPECTION
Underslab Plumbing Inspection - Residential Passed 9/14/2021 9/14/2021 09/14/2021
Misc
Resolved
09/14/2021
Sewer Service Inspection - R Passed 1/5/2022 (9:15) 1/5/2022 01/05/2022
01/05/2022
Water Service Inspection - R Passed 1/11/2022 (10:30) 1/11/2022 01/11/2022
All Rough Inspection - Residential Not Ready 2/14/2022 2/14/2022 02/14/2022
Misc
Corrective Action Required
02/14/2022
INSPECTION DENIED MAINTAIN GRAVEL FILTER ON DRIVE, 6" LIFT REQUIRED NO CITY STAMPED PLANS ON SITE AT TIME OF INSPECTION
Erosion Control Inspection Residential Failed 2/14/2022 2/14/2022 02/14/2022
Misc
Corrective Action Required
02/14/2022
MAINTAIN GRAVEL FILTER ON DRIVE, MIN 6" LIFT REQUIRED
Electrical Service Inspection Failed 2/16/2022 2/16/2022 02/16/2022
Misc
Corrective Action Required
02/16/2022
-remove panel bonding screw at sub panel
Gas Service Inspection - Residential Failed 2/16/2022 2/16/2022 02/16/2022
Misc
Corrective Action Required
02/16/2022
-GAS PRESSURE 7 PSI, MUST MAINTAIN 10 PSI FOR TEST
All Rough Inspection - Residential Failed 2/16/2022 2/16/2022 02/16/2022
Misc
Corrective Action Required
02/14/2022
-Anchor bolts required within 12” of plate breaks -min 30” clearance at attic access -Install front door and windows -Solid block all exterior sheathing breaks -secure all vertical DWV 2” or less at mid point -seal all top plate penetrations- see master bed, great room -solid block at all step flashing -shim all trimmer studs cut short of headers -fireblock between studs at great room fireplace lid -secure gas line at fireplace -seal floor penetrations at fireplace -land rafters to top plate and nail per code at covered front entry -update engineered plans to reflect added man door at garage -2x6 studs 16” oc at garage wall per plans -LIB bracing all locations per plans -(4) 2x4 stud packs all girder truss bearing ends per plans -ensure required proper slope of vent lines across trusses at attic -Truss hangers all locations per plans -all truss lateral bracing per plans -provide full bearing for dbl 2x10 at stair wall -provide bocca protection plate DWV bottom plate basement flex room -fireblock vertical to horizontal at furred down soffit ends, fb annular spaces around DWV, seal penetrations etc -Provide joist hangers at floor joists great room fireplace cantilever -solid block between joists at cantilevers -remove panel bonding screw at sub panel -fireblock vertical every 10’ between studs and foundation wall at basement -provide protection plate at DWV soffit line, see basement wet bar and bedroom -complete bath exhaust fan duct at basement bath -provide joists hangers at basement bath DWV headers -header bored for DWV less than 2” from end of header at basement bath -complete plumbing for basement wet bar -(3) 2x10 joists at fireplace cantilever per plans -solid block between joists every 48” oc for island per plans -CS-PF at great room windows, nail exterior sheathing per plans - -nail exterior sheathing per plans
All Rough Inspection - Residential Failed 2/24/2022 2/24/2022 02/24/2022
Misc
Corrective Action Required
02/16/2022
-Install front door and windows -Solid block all exterior sheathing breaks -seal all top plate penetrations- see great room -secure gas line at fireplace -seal floor penetrations at fireplace -update engineered plans to reflect added man door at garage -Truss hangers all locations per plans , no truss layout at reinspection -all truss lateral bracing per plans, no truss layout at reinspection -provide full bearing for dbl 2x10 at stair wall -solid block between joists at cantilevers -remove panel bonding screw at sub panel -complete bath exhaust fan duct at basement bath -header bored for DWV less than 2” from end of header at basement bath
Electrical Service Inspection Passed 3/1/2022 3/1/2022 03/01/2022
Misc
Resolved
03/01/2022
-remove panel bonding screw at sub panel
Gas Service Inspection - Residential Passed 3/1/2022 3/1/2022 03/01/2022
Misc
Resolved
03/01/2022
-GAS PRESSURE 7 PSI, MUST MAINTAIN 10 PSI FOR TEST
All Rough Inspection - Residential Failed 3/1/2022 3/1/2022 03/01/2022
Misc
Corrective Action Required
02/24/2022
-update engineered plans to reflect added man door at garage -Truss hangers all locations per plans , no truss layout at reinspection , PROVIDE TRUSS HANGER DETAIL , GRAGAE HANGERS ARE FOR 2X4. -all truss lateral bracing per plans, no truss layout at reinspection -provide full bearing for dbl 2x10 at stair wall ,WHERE WAS THIS ADDRESSED? -solid block between joists at cantilevers , NOT COMPELTE -complete bath exhaust fan duct at basement bath , NOT COMPLTE -header bored for DWV less than 2” from end of header at basement bath, NOT COMPLETE
All Rough Inspection - Residential Passed 3/3/2022 3/3/2022 03/03/2022
Misc
Resolved
03/03/2022
Driveway Inspection Partial 5/4/2022 05/04/2022
Misc
Informational
05/04/2022
On 5.4.2022 I performed a driveway inspection and pass the subgrade to pour concrete.
Sidewalk Inspection Partial 5/4/2022 05/04/2022
Misc
Informational
05/04/2022
On 5.4.2022 I performed a sidewalk inspection and pass the sub-grade to pour concrete.
Occupancy Inspection - Codes Residential Failed 6/8/2022 6/8/2022 06/08/2022
Misc
Corrective Action Required
06/08/2022
-resolve outstanding inspection fees -obtain lawn irrigation system permit -final sidewalk and driveway inspections required, contact development services to schedule -final grade and sod -gutters and downspouts -splash blocks -complete cover at covered front porch, exposed beams are not treated lumber -install windows master bed -provide security screws at back door and garage door, (2) 3” screws each hinge and strike -provide trim and flashing at exterior windows -landscaping maintain 6” clearance to siding -provide landing at garage exterior door
Erosion Control Inspection Residential Partial 06/08/2022
Misc
Resolved
06/08/2022
MAINTAIN GRAVEL FILTER ON DRIVE, MIN 6" LIFT REQUIRED
Driveway Inspection Passed 6/10/2022 6/10/2022 06/10/2022
Misc
Informational
05/04/2022
On 5.4.2022 I performed a driveway inspection and pass the subgrade to pour concrete.
Misc
Informational
06/10/2022
6.10.2022 Driveway appears to be in compliance
Sidewalk Inspection Passed 6/10/2022 6/10/2022 06/10/2022
Misc
Informational
05/04/2022
On 5.4.2022 I performed a sidewalk inspection and pass the sub-grade to pour concrete.
Misc
Informational
06/10/2022
6.10.2022 Sidewalk appears to be in compliance
Occupancy Inspection - Codes Residential Temporary C of O 6/13/2022 6/13/2022 06/13/2022
Misc
Corrective Action Required
06/08/2022
-SOD -SPLASH BLOCKS OK FOR TCO, TCO EXPIRES 6/27/22***
Erosion Control Inspection Residential Passed 06/16/2022
Plot Plan Inspection Passed 6/16/2022 6/16/2022 06/16/2022
Occupancy Inspection - Codes Residential Failed 6/16/2022 6/16/2022 06/16/2022
Misc
Corrective Action Required
06/13/2022
-SUMP PUMP DISCHARGE MIN 36" FROM FOUNDATION OK FOR TCO, TCO EXPIRES 6/27/22***
Occupancy Inspection - Codes Residential Full C of O 6/23/2022 6/23/2022 06/23/2022
Misc
Resolved
06/23/2022
Documents & Images
Date Uploaded File Type Document Name
06/21/2021 RR #90 - PERMIT APP
06/22/2021 Approved Plans Approved Drawings
06/22/2021 Approved Plans Approved Truss Layout
06/22/2021 Approved Plans Approved Truss Package
06/22/2021 Permit Codes Residential Plan Review
06/22/2021 Plot Plan Approved Plot Plan
06/22/2021 Permit Codes Residential Plan Review
06/22/2021 Permit DS Building Permit
06/22/2021 Receipt Receipt for transaction:2021-004782
09/01/2021 Letter INSPECTION SUMMARY
09/01/2021 Letter Stop Work Order
09/01/2021 Lot 90 Reserve at Stoney Creek Footing Inspection
09/01/2021 Lot 90 Manor at Stoney Creek Foundation Inspection
09/02/2021 Letter INSPECTION SUMMARY
09/03/2021 Letter INSPECTION SUMMARY
09/14/2021 Letter INSPECTION SUMMARY
01/05/2022 Letter INSPECTION SUMMARY
01/11/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/14/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/16/2022 Letter INSPECTION SUMMARY
02/24/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/01/2022 Letter INSPECTION SUMMARY
03/03/2022 90 reserve at stoney creek letter (002)
03/03/2022 Letter INSPECTION SUMMARY
03/03/2022 Letter INSPECTION SUMMARY
05/04/2022 Letter INSPECTION SUMMARY
05/04/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/08/2022 Letter INSPECTION SUMMARY
06/09/2022 Receipt Receipt for transaction:2022-004516
06/10/2022 Letter INSPECTION SUMMARY
06/10/2022 Letter INSPECTION SUMMARY
06/13/2022 Letter Codes Temporary Certificate of Occupancy
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/16/2022 Letter INSPECTION SUMMARY
06/23/2022 Letter Field Certificate of Occupancy
06/23/2022 Letter Codes Final Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home