Permit Application Status

PRRES20210296


In order to schedule inspections, you need to be signed in.

 / 

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary
PRRES20210296
Building Permit - Residential
Certificate of Occupancy
NEW SINGLE FAMILY
NEW HOUSE - FINISHED BASEMENT - ROOF TRUSS
01/21/2021
02/03/2021
07/26/2021
09/29/2021
Locations
Contacts
CLAYTON PROPERTIES GROUP, INC, Address:120 SE 30TH ST, Phone:(816) 246-6700  
PERMITTING@SUMMITHOMESKC.COM  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
ARROW CIRCLE ELECTRIC, Address:1224 SE CENTURY DR, Phone:(816) 373-4888  
RELIABLE MECHANICAL SERVICES INC, Address:1025 W COUCHMAN DR, Phone:(816) 903-7674  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 02/04/2021 02/02/2021
Dylan Eppert
As-graded plot plan
Corrective Action Required
02/02/2021

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Drainage swales/berms
Corrective Action Required
02/02/2021

Drainage swales/berms: provide cross-section elevations as required to conform to the accepted "As graded" Master Drainge Plan (MDP), include cross-section detail from MDP. IT APPEARS THE MDP SHOWS A BERM IN THE REAR YARD PLEASE VERIFY AS IT SAYS TO SEE NOTE 7. IF SO PLEASE CALL OUT BERM.
Residential Plan Review Approved 02/04/2021 02/02/2021
Dylan Eppert
Plot Plan Review Rejected 01/29/2021 01/27/2021
Dylan Eppert
As-graded plot plan
Corrective Action Required
01/27/2021

A as-graded plot plan per Section 7-160, Code of Ordinances, is required prior to occupancy.
Drainage swales/berms
Corrective Action Required
01/27/2021

Drainage swales/berms: provide cross-section elevations as required to conform to the accepted "As graded" Master Drainge Plan (MDP), include cross-section detail from MDP. IT APPEARS THE MDP SHOWS A BERM IN THE REAR YARD PLEASE VERIFY AS IT SAYS TO SEE NOTE 7. IF SO PLEASE CALL OUT BERM.
Residential Plan Review Approved 01/29/2021 01/27/2021
Dylan Eppert
Residential Plan Review Approved 01/25/2021 01/26/2021
Dylan Eppert
03 Two (2) plot plans
Corrective Action Required
01/26/2021

MISSING PLOT PLAN SUBMITTAL.
Plot Plan Review Rejected 01/25/2021 01/26/2021
Dylan Eppert
Planning Review (RES) Approved 01/25/2021 01/26/2021
Hector Soto Jr.
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $991.85 $991.85 Paid 02/03/2021
8331507-Sewer Connection Fee $360.00 $360.00 Paid 02/03/2021
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 02/03/2021
8350015-Water Meter Fee $455.54 $455.54 Paid 02/03/2021
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 02/03/2021
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 02/03/2021
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 09/28/2021
9110080-3rd and Subsequent Inspection Fee (Per Hour) $50.00 $50.00 Paid 09/28/2021
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 3/8/2021 (1:30) 3/8/2021 03/08/2021
Misc
Informational
03/08/2021
UFER FOUNDATION WALL REAR OF GARAGE
Underslab Plumbing Inspection - Residential Passed 4/1/2021 4/1/2021 04/01/2021
Erosion Control Inspection Residential Failed 05/25/2021
Misc
Corrective Action Required
05/25/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -Remove debris from storm water inlet -provide and maintain gravel filter -no further inspections until issues are resolved
Misc
Corrective Action Required
05/25/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -Remove debris from storm water inlet -provide and maintain gravel filter -no further inspections until issues are resolved
All Rough Inspection - Residential Failed 5/25/2021 5/25/2021 05/25/2021
Misc
Corrective Action Required
05/25/2021
-No gas lines installed -Provide vertical fire block & seal every 10' basement furr out -Fire block / insulate beam pocket above basement shower -Fire block vertical to horizontal at exhaust fan Basement bath -Unable to verify exterior sheathing fastening at portal opening -Two rows of 16D sinker nails 3” oc at braced wall panel top plates per plan, see section view of portal opening detail -Flash above both garage doors and address missing sheathing at corners -Install exterior doors and windows -Minimum 12” field 6” edge exterior sheathing fastening -Fireblock plate Penetrations throughout -Anchor bolt required within 12 inches of plates splice or end -Provide anchor bolt at third car -12” oc fastening, stud to stud and abutting studs at intersecting braced walls -Fireblock all through floor Penetrations -Provide engineered solution for repair of field altered trusses, South kitchen wall -Complete bath exhaust duct installation and address damaged flex duct, master bath -Secure supply duct in master bath -Provide attic access -Girder truss bearing per plan, front porch -truss hangers per plan -Truss lateral bracing per plan -Provide joist hangers at double joist connections to LVL in unfinished basement area -Address missing LVL over bedroom four and bedroom three -Provide full depth solid blocking above bedroom four and bedroom three per plan -Fireblock vertical to horizontal, bed three closet at drop ceiling level
Electrical Service Inspection Passed 6/2/2021 6/2/2021 06/02/2021
Gas Service Inspection - Residential Passed 6/2/2021 6/2/2021 06/02/2021
Piers/Caissons Inspection - Residential Passed 6/9/2021 (1:15) 6/9/2021 06/09/2021
Misc
Informational
06/09/2021
(2) 24 x 36 deck piers
All Rough Inspection - Residential Failed 6/15/2021 6/15/2021 06/15/2021
Misc
Corrective Action Required
05/25/2021
-Provide vertical fire block & seal every 10' basement furr out-SEAL STUD PENETRATIONS AT 10’ SEPARATION AND VERTICAL AT MARKED STUD NORTHEAST -Unable to verify exterior sheathing fastening at portal opening-SEAL PENETRATIONS IN MOISTURE BARRIER -Two rows of 16D sinker nails 3” oc at braced wall panel top plates per plan, see section view of portal opening detail -Install exterior doors and windows -Minimum 12” field 6” edge exterior sheathing fastening-NOT COMPLETE AT BACK WALL AND SOUTH CORNER SHEETS -Fireblock plate Penetrations throughout-SEAL TOP PLATE PENETRATION ABOVE RANGE, SOUTH GARAGE WALL AND THROUGHOUT BASEMENT -Anchor bolt required within 12 inches of plates splice or end-TIGHTEN THROUGHOUT -Provide engineered solution for repair of field altered trusses, South kitchen wall -Secure supply duct in master bath-FB AT BOTTOM PLATE -Provide attic access-30” MIN CLEARANCE REQUIRED -Girder truss bearing per plan, front porch -Address missing LVL over bedroom four and bedroom three -Fireblock vertical to horizontal, bed three closet at drop ceiling level-SEAL AT DWV AND BLOCK AT CEILING LINE BACK WALL
All Rough Inspection - Residential Failed 6/16/2021 6/16/2021 06/16/2021
Misc
Corrective Action Required
06/15/2021
-Install exterior doors and windows -Minimum 12” field 6” edge exterior sheathing fastening-NOT COMPLETE AT BACK NORTH AND SOUTH CORNER SHEETS -Fireblock plate Penetrations throughout-SEAL BASEMENT BEAM POCKETS / SOFFIT SE CLOSET -Provide engineered solution for repair of field altered trusses, South wall TRIPLE GIRDER & TRUSS TO WEST OF TRIPLE
All Rough Inspection - Residential Passed 6/17/2021 6/17/2021 06/17/2021
Misc
Resolved
06/17/2021
Sewer Service Inspection - R Passed 8/4/2021 8/4/2021 08/04/2021
Water Service Inspection - R Passed 8/5/2021 (10:30) 8/5/2021 08/05/2021
Driveway Inspection Partial 8/12/2021 8/12/2021 08/12/2021
Misc
Informational
08/12/2021
Forms were placed and aggregate was present and compacted. RP 8-12-21
Driveway Inspection Passed 8/20/2021 8/20/2021 08/20/2021
Misc
Informational
08/12/2021
Forms were placed and aggregate was present and compacted. RP 8-12-21
Misc
Informational
08/20/2021
Finished driveway meets LS specs. RP 8-20-21
Erosion Control Inspection Residential Failed 9/1/2021 09/01/2021
Misc
Corrective Action Required
05/25/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -Remove debris from storm water inlet -provide and maintain gravel filter -no further inspections until issues are resolved
Misc
Corrective Action Required
05/25/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -Remove debris from storm water inlet -provide and maintain gravel filter -no further inspections until issues are resolved
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
09/01/2021
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. - MAINTAIN SILT FENCE UNTIL SOD COMPLETE - - CLEAN STREET - - REMOVE SEDIMENT BUILD UP AT GUTTER BUDDY CURB INLET -
Occupancy Inspection - Codes Residential Failed 9/1/2021 9/1/2021 09/01/2021
Miscellaneous Correction
Corrective Action Required
09/01/2021
OBTAIN LAWN IRRIGATION PERMIT & submit back flow certification Submit as graded plot plan for review Remove sediment buildup at gutter buddy curb inlet Maintain silt fence until sod complete Clean street Remove Constuction debris from job site Provide final grade & sod Provide splash blocks Sump shall discharge 36" from foundation Seal top of exterior light fixtures, meter can, ac disconnect, low volt penetrations at meter can, gas line at meter, Complete stone work front of house A 4" sphere shall not pass through guardrails Provide guardrail or raise grade to less than 30" at front stoop Provide handrail garage stairs Provide self closing & latching door garage to dwelling Remove dust covers from smoke detectors Remove trash from window wells expose drain tiles Basement shower door not identified as tempered glass Provide (2) 3" screws in each exterior door hinge & strike plate Land sewer tracer wire in a box at grade
Erosion Control Inspection Residential Failed 9/13/2021 09/13/2021
Misc
Corrective Action Required
09/01/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -Remove debris from storm water inlet -provide and maintain gravel filter -no further inspections until issues are resolved
Misc
Corrective Action Required
09/01/2021
-Erosion control requires continuous maintenance. Repair damaged sections within 48 hours -immediate street cleanup required -Remove debris from storm water inlet -provide and maintain gravel filter -no further inspections until issues are resolved
DCM2 ESC DEFICIENT INSTALLATION
Corrective Action Required
09/01/2021
DEFICIENT EROSION CONTROL INSTALLATION. NO FURTHER INSPECTIONS UNTIL ADEQUATE EROSION CONTROL PROVIDED. - MAINTAIN SILT FENCE UNTIL SOD COMPLETE - - CLEAN STREET - - REMOVE SEDIMENT BUILD UP AT GUTTER BUDDY CURB INLET -
DCM6 ESC INSP DENIED STREET CLEAN UP
Corrective Action Required
09/13/2021
STREET CLEAN UP REQUIRED IMMEDIATELY, AND SHALL BE COMPLETED PRIOR TO REQUESTED INSPECTION(S) BEING PERFORMED.
Occupancy Inspection - Codes Residential Temporary C of O 9/13/2021 9/13/2021 09/13/2021
Miscellaneous Correction
Corrective Action Required
09/01/2021
OBTAIN LAWN IRRIGATION PERMIT & submit back flow certification Submit as graded plot plan for review Remove sediment buildup at gutter buddy curb inlet Clean street Land sewer tracer wire in a box at grade
Plot Plan Inspection Passed 9/22/2021 09/22/2021
Occupancy Inspection - Codes Residential Full C of O 9/29/2021 9/29/2021 09/29/2021
Miscellaneous Correction
Resolved
09/29/2021
Documents & Images
Date Uploaded File Type Document Name
01/21/2021 Application Form W2 #65 - Permit App
01/21/2021 2523941 RF SEALS 10282020
01/21/2021 W2 #65 - Juliette - Mediterranean - Sheets- signed
01/21/2021 65 WOODSIDE RIDGE ROOF LAYOUT- signed
01/26/2021 Drawing APPROVED ROOF TRUSS LAYOUT
01/26/2021 Specifications APPROVED ROOF TRUSS PACKAGE
01/27/2021 LOT 65 FINAL
01/26/2021 Letter Codes Residential Plan Review
01/27/2021 Letter Codes Residential Plan Review
01/27/2021 Plans APPROVED HOUSE PLAN
02/03/2021 Receipt Receipt for transaction:2021-000530
02/03/2021 Letter DS Building Permit
03/01/2021 Scope of Work Statement - W2 #65
03/01/2021 W2 #65 - Revised Juliette - Mediterranean - Sheets- signed
03/08/2021 Letter INSPECTION SUMMARY
03/22/2021 Approved Plans APPROVED PLANS
04/01/2021 Letter INSPECTION SUMMARY
05/25/2021 Letter INSPECTION SUMMARY
05/25/2021 Letter INSPECTION SUMMARY
06/02/2021 Letter INSPECTION SUMMARY
06/02/2021 Letter INSPECTION SUMMARY
06/09/2021 Approved Plans Approved Revised Truss Package
06/09/2021 Letter INSPECTION SUMMARY
06/15/2021 Letter INSPECTION SUMMARY
06/15/2021 Truss Repair
06/16/2021 Letter INSPECTION SUMMARY
08/04/2021 Letter INSPECTION SUMMARY
08/05/2021 Letter INSPECTION SUMMARY
08/12/2021 Letter INSPECTION SUMMARY
08/12/2021 Letter INSPECTION SUMMARY
08/20/2021 Letter INSPECTION SUMMARY
09/01/2021 Letter INSPECTION SUMMARY
09/01/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter INSPECTION SUMMARY
09/13/2021 Letter Codes Temporary Certificate of Occupancy
09/21/2021 Plot Plan APPROVED AS GRADED PLOT PLAN
09/22/2021 Letter INSPECTION SUMMARY
09/28/2021 Receipt Receipt for transaction:2021-007625
09/29/2021 Letter Codes Final Certificate of Occupancy
10/06/2021 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home