Certificate of Occupancy
ACH DEVELOPMENT LLC
NEW SINGLE FAMILY
NEW HOUSE - UNFINISHED BASEMENT - COVERED PATIO
07/31/2020
08/10/2020
06/17/2021
Locations
Contacts
ACH DEVELOPMENT LLC, Address:3170 NE CARNEGIE DR STE 400  
CAPITAL CONSTRUCTION SERVICES LLC, Address:2642 NE HAGAN RD, Phone:(816) 875-0018  
UNITED HEATING & COOLING, Address:301 DUCK RD, Phone:(816) 761-5262  
INHOME SYSTEMS LLC, Address:510 MISSION RD SW, Phone:(816) 372-0483  
A BRIGHT PLUMBING LLC, Address:18107 E 18TH TER N, Phone:(816) 215-0730  
DROTHFUSS@CAPITALCONST.COM  
Reviews
Review Type Outcome Est. Completion Date Completed
Plot Plan Review Approved 08/04/2020 08/03/2020
Kim Brennan
Deck location
Corrective Action Required
07/31/2020

Deck location, with dimensions to property lines must be provided on the plot plan.
Residential Plan Review Approved 08/04/2020 07/31/2020
Kim Brennan
Fees
Paid Fees Amount Paid Owing Date Paid
9110078-Valuation Fee New Single Family $1,480.01 $1,480.01 Paid 08/10/2020
9110073-Right of Way Permit Fee $80.00 $80.00 Paid 08/10/2020
7232302-Residential License Tax Fee $1,077.12 $1,077.12 Paid 08/10/2020
8331507-Sewer Connection Fee $540.00 $540.00 Paid 08/10/2020
8331401-Water Tap Fee $3,581.00 $3,581.00 Paid 08/10/2020
8350015-Water Meter Fee $455.54 $455.54 Paid 08/10/2020
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


$0.00
Inspections
Inspection Outcome Requested Scheduled Date Inspected
Footing Inspection - Residential Passed 8/13/2020 (8:00) 8/13/2020 at 8:00 AM 08/13/2020
Water Service Inspection - R Passed 8/27/2020 (9:45) 8/27/2020 08/27/2020
Sewer Service Inspection - R Partial 8/27/2020 8/27/2020 08/27/2020
Misc
Corrective Action Required
08/27/2020
Partial approval minus connection to public sewer
Underslab Plumbing Inspection - Residential Passed 8/27/2020 8/27/2020 08/27/2020
Sewer Service Inspection - R Passed 08/28/2020
Misc
Resolved
08/28/2020
Partial approval minus connection to public sewer
Piers/Caissons Inspection - Residential Passed 9/21/2020 (8:00) 9/21/2020 09/21/2020
Gas Service Inspection - Residential Failed 10/30/2020 10/30/2020 10/30/2020
Misc
Corrective Action Required
10/30/2020
-Provide min ten psi pressure for testing
Electrical Service Inspection Passed 10/30/2020 10/30/2020 10/30/2020
All Rough Inspection - Residential Failed 10/30/2020 10/30/2020 10/30/2020
Misc
Corrective Action Required
10/30/2020
FRAMING: -Install flashings above exterior wall trims -Nail garage portal brace wall sheathing per code; install straps -Anchor sill plate within 12” of break, min 2 per plate -Remove all osb sheathing debris from roof -Fb laundry/garage wall from ceiling/roof space -Provide full width bearing support for I beam at kitchen & dining -Support lvl hip above rear dining -Brace ends of lvl beams against rotation -Support hip rafters above entry door -Provide full support for beam above foyer hallway -Nail corner studs with 16d @12” oc or equivalent nailing -Fb triangular space at front dining; fb fireplace space from roof; fb all dead spaces from roof throughout -Install collar ties near ridge -Support hip rafters above front bedroom -Nail siding into studs at rear bedroom&bathroom roof step flashings. -The upset lvl beam above bedroom #3 must extend to lvl across the catwalk -Provide (2) lvl beam above doorway to front dining; provide support underneath point loaf ELECTRICAL: -Protect wiring within 6 ft of all attic access openings -Install dryer receptacle box -Protect SE cable at bottom wall plate; protect other wirings at bottom wall plate throughout -Provide a wall receptacle at foyer wall (with switch) wider than 3 ft -Provide minimum 12”x12” clear unobstructed opening for access to hydro tub motor. Receptacle cannot obstruct opening MECHANICAL: -Vent 2nd fl bath fan -Provide insulation shield for 2nd fl furnace b-vent **OK TO INSULATE
Gas Service Inspection - Residential Passed 11/6/2020 11/6/2020 11/06/2020
Misc
Resolved
11/06/2020
-Provide min ten psi pressure for testing
All Rough Inspection - Residential Failed 11/6/2020 11/6/2020 11/06/2020
Misc
Corrective Action Required
10/30/2020
FRAMING: -Nail garage portal brace wall sheathing per code **Nail the sheathing to the sill plate and to the lvl header (8d 3" grid pattern). Also instal the missing 2" washers and nuts for the south side -Fb fireplace space from roof; fb all dead spaces in master bath area from roof -The upset lvl beam above bedroom #3 must extend to lvl across the catwalk **nail all the hanger nail holes -lvl beam above doorway to front dining-provide support underneath point load **Please put a double 2x10 underneath the point load. The installed double 2x10 adjacent to the return air does not catch the point load ELECTRICAL: -Provide minimum 12”x12” clear unobstructed opening for access to hydro tub motor. Receptacle cannot obstruct opening **Framer/anyone please provide min. 12"x12" unobstructed pathway to the motor. How are you going to replace the motor when there are so many things in the way?
All Rough Inspection - Residential Failed 11/11/2020 11/11/2020 11/11/2020
Misc
Corrective Action Required
11/06/2020
FRAMING: -Garage portal brace wall-install the missing 2" washers and nuts for the south side -lvl beam above doorway to front dining-provide support underneath point load
All Rough Inspection - Residential Passed 11/12/2020 11/12/2020 11/12/2020
Misc
Resolved
11/12/2020
FRAMING: -Garage portal brace wall-install the missing 2" washers and nuts for the south side -lvl beam above doorway to front dining-provide support underneath point load
Driveway Inspection Partial 1/13/2021 (P.M.) 1/13/2021 01/13/2021
Misc
Informational
01/13/2021
1/13/21 Wednesday Driveway - forms and materials passed pre-inspection.
Sidewalk Inspection Partial 1/13/2021 (P.M.) 1/13/2021 01/13/2021
Misc
Informational
01/13/2021
1/13/21 Wednesday Sidewalk - forms and materials passed pre-inspection.
Driveway Inspection Passed 1/15/2021 1/15/2021 01/19/2021
Misc
Informational
01/13/2021
1/13/21 Wednesday Driveway - forms and materials passed pre-inspection.
Misc
Informational
01/19/2021
1/19/21 Tuesday Driveway - passed inspection.
Sidewalk Inspection Passed 1/15/2021 1/15/2021 01/19/2021
Misc
Informational
01/13/2021
1/13/21 Wednesday Sidewalk - forms and materials passed pre-inspection.
Misc
Informational
01/19/2021
1/19/21 Tuesday Sidewalk - passed final inspection.
Occupancy Inspection - Codes Residential Failed 3/24/2021 3/24/2021 03/24/2021
Misc
Corrective Action Required
03/24/2021
-Obtain lawn irrigation permit and submit the backflow test report to city -Final grade, sod, downspout and sump pump extensions -Make sure that the sewer tracer wire and port are installed and available at grade level -Seal exterior wall penetrations, seal above AC disconnect, meter, etc -Screw the exterior door embedded jamb brace into studs -Install security strike plate for front entry door, the one that is designed to be installed behind the aluminum stripe -Isolate low voltage from 120V at fireplace switch -City amendment of the NEC requires all dedicated non-gfci receptacles in garage and unfinished basement to be identified (label, marking, etc) -Garage receptacles not gfci-protected; the gfci receptacle not tamper-resistant -Receptacles in half bathroom must be gfci-protected -Secure patio gfci receptacle -Fasten support to patio posts; cedar post shall not be embedded into concrete slab -Install cover plate for hydro tub receptacle -Install attic access cover -Tighten grounding connection to ufer
Occupancy Inspection - Codes Residential Temporary C of O 3/26/2021 3/26/2021 03/26/2021
Misc
Corrective Action Required
03/24/2021
-Final grade, sod, downspout and sump pump extensions -Make sure that the sewer tracer wire and port are installed and available at grade level -Seal exterior wall penetrations, seal above AC disconnect, meter, etc -Screw the exterior door embedded jamb brace into studs -Fasten support to patio posts; cedar post shall not be embedded into concrete slab
Occupancy Inspection - Codes Residential Full C of O 6/17/2021 6/17/2021 06/17/2021
Misc
Resolved
06/17/2021
-Final grade, sod, downspout and sump pump extensions -Make sure that the sewer tracer wire and port are installed and available at grade level -Seal exterior wall penetrations, seal above AC disconnect, meter, etc -Screw the exterior door embedded jamb brace into studs -Fasten support to patio posts; cedar post shall not be embedded into concrete slab
Documents & Images
Date Uploaded File Type Document Name
07/31/2020 Letter Permit Application and license tax form
08/03/2020 Letter Codes Residential Plan Review
08/03/2020 Drawing Approved Drawings
08/03/2020 Plot Plan Approved Plot Plan
08/10/2020 Receipt Receipt for transaction:2020-005075
08/10/2020 Letter DS Building Permit
08/13/2020 Letter INSPECTION SUMMARY
08/27/2020 Letter INSPECTION SUMMARY
08/27/2020 Letter INSPECTION SUMMARY
08/27/2020 Letter INSPECTION SUMMARY
08/28/2020 Letter INSPECTION SUMMARY
09/21/2020 Letter INSPECTION SUMMARY
10/30/2020 Letter INSPECTION SUMMARY
10/30/2020 Letter INSPECTION SUMMARY
10/30/2020 Letter INSPECTION SUMMARY
11/06/2020 Letter INSPECTION SUMMARY
11/06/2020 Letter INSPECTION SUMMARY
11/11/2020 Letter INSPECTION SUMMARY
11/12/2020 Letter INSPECTION SUMMARY
01/13/2021 Letter INSPECTION SUMMARY
01/13/2021 Letter INSPECTION SUMMARY
01/19/2021 Letter INSPECTION SUMMARY
01/19/2021 Letter INSPECTION SUMMARY
03/24/2021 Letter INSPECTION SUMMARY
03/26/2021 Letter Codes Temporary Certificate of Occupancy
06/17/2021 Letter Codes Final Certificate of Occupancy
06/17/2021 Letter Field Certificate of Occupancy
Upload Documents

Guidelines For Electronically Submitting Documents:

  • Submitted documents should be under 100MB in size.
  • Accepted file extensions:
    • pdf, jpg, xls, doc, xlsx, docx, dwg
  • All plans shall be to scale.
  • Recommended naming conventions:
    • Keep filename consistent.
    • Avoid the use of non-friendly filenames. (ex. k9dk38fj3.pdf)
    • Avoid inappropriate language in filenames.
  • Submitted documents will be stamped at the conclusion of the review.
    • The stamp will be placed in the upper right hand corner of the document. It is recommeded that this area, to the extent possible, be left blank so that no information is lost when the the stamp is applied.
Remember to click the Upload Document button. If you are applying for a New permit, make sure to click the "next step" button after you have completed the upload of documents

Select any documents you wish to provide:





Portal Home